Hillingdon Towpaths
Page 1 of 56
June 2014
Hillingdon Towpaths
Hillingdon Towpaths
Page 2 of 56
Canal amp River Trust July 2014
London Waterways
Bow Back Rivers
Grand Union Canal
Paddington Arm of the Grand Union Canal
Slough Arm of the Grand Union Canal
Hertford Union Canal
Limehouse Cut
London Docklands
Regentrsquos Canal
River Lee
River Stort
Contact
Canal amp River Trust
The Toll House
Delamere Terrace
Little Venice
London
W2 6TT
0303 040 4040
enquirieslondoncanalrivertrustorguk
Hillingdon Towpaths
Page 3 of 56
1 SUMMARY 4
2 BACKGROUND 5
21 Better Towpaths for Everyone 5
22 Hillingdon Waterspace Strategy 6
23 Hillingdon Canals 7
24 Improvements so far 7
25 Opportunities 9
3 TOWPATH SPECIFICATION 10
4 COST ASSUMPTIONS 11
5 METHOD 12
6 ASSESSMENT CRITERIA 13
61 Design Guidance amp Standards 13
62 Criteria used in this report 14
63 Prioritisation 14
7 RESULTS 15
71 High Priority Towpath Sections 15
72 Medium Priority Towpath Sections 15
73 Low Priority Towpath Sections 16
74 Map of Priority Towpath Sections 17
Appendix 1 - Towpath estimator tool 18
Appendix 2 - Towpath assessment criteria scores 19
Appendix 3 ndash Towpath Survey Section Reports 20
Hillingdon Towpaths
Page 4 of 56
1 SUMMARY
Canal amp River Trust has produced this report to inform future investment priorities for
Hillingdon canal towpaths
The report was produced at the request of members of the Hillingdon Canals Partnership
and serves as a reference document for its work to promote and improve the boroughrsquos
waterways
It contains information for Hillingdon canal towpaths surveyed in 2013 covering
the Grand Union Canal (divided into 35 sections)
the Paddington Arm (1 section)
and Slough Arm (1 section)
For each section the general towpath condition levels of use and its function in connecting
people and places are considered
The result is a prioritised overview of borough towpaths for improvement which will support
funding applications and decisions
Hillingdon Towpaths
Page 5 of 56
2 BACKGROUND
21 Better Towpaths for Everyone
Sir Brian Fender chair of London
Waterways Partnership launched
Better Towpaths for Everyone in
spring 2014
The report was endorsed by the
Mayorrsquos Cycling Commissioner
Andrew Gilligan and sets out
proposals for 3 strategic cross-
borough Quietways along the Grand
Union Canal Paddington Arm and
River Lee responding to the Mayorrsquos
Cycling Vision
Hillingdon sits across 2 of these Quietways
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 2 of 56
Canal amp River Trust July 2014
London Waterways
Bow Back Rivers
Grand Union Canal
Paddington Arm of the Grand Union Canal
Slough Arm of the Grand Union Canal
Hertford Union Canal
Limehouse Cut
London Docklands
Regentrsquos Canal
River Lee
River Stort
Contact
Canal amp River Trust
The Toll House
Delamere Terrace
Little Venice
London
W2 6TT
0303 040 4040
enquirieslondoncanalrivertrustorguk
Hillingdon Towpaths
Page 3 of 56
1 SUMMARY 4
2 BACKGROUND 5
21 Better Towpaths for Everyone 5
22 Hillingdon Waterspace Strategy 6
23 Hillingdon Canals 7
24 Improvements so far 7
25 Opportunities 9
3 TOWPATH SPECIFICATION 10
4 COST ASSUMPTIONS 11
5 METHOD 12
6 ASSESSMENT CRITERIA 13
61 Design Guidance amp Standards 13
62 Criteria used in this report 14
63 Prioritisation 14
7 RESULTS 15
71 High Priority Towpath Sections 15
72 Medium Priority Towpath Sections 15
73 Low Priority Towpath Sections 16
74 Map of Priority Towpath Sections 17
Appendix 1 - Towpath estimator tool 18
Appendix 2 - Towpath assessment criteria scores 19
Appendix 3 ndash Towpath Survey Section Reports 20
Hillingdon Towpaths
Page 4 of 56
1 SUMMARY
Canal amp River Trust has produced this report to inform future investment priorities for
Hillingdon canal towpaths
The report was produced at the request of members of the Hillingdon Canals Partnership
and serves as a reference document for its work to promote and improve the boroughrsquos
waterways
It contains information for Hillingdon canal towpaths surveyed in 2013 covering
the Grand Union Canal (divided into 35 sections)
the Paddington Arm (1 section)
and Slough Arm (1 section)
For each section the general towpath condition levels of use and its function in connecting
people and places are considered
The result is a prioritised overview of borough towpaths for improvement which will support
funding applications and decisions
Hillingdon Towpaths
Page 5 of 56
2 BACKGROUND
21 Better Towpaths for Everyone
Sir Brian Fender chair of London
Waterways Partnership launched
Better Towpaths for Everyone in
spring 2014
The report was endorsed by the
Mayorrsquos Cycling Commissioner
Andrew Gilligan and sets out
proposals for 3 strategic cross-
borough Quietways along the Grand
Union Canal Paddington Arm and
River Lee responding to the Mayorrsquos
Cycling Vision
Hillingdon sits across 2 of these Quietways
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 3 of 56
1 SUMMARY 4
2 BACKGROUND 5
21 Better Towpaths for Everyone 5
22 Hillingdon Waterspace Strategy 6
23 Hillingdon Canals 7
24 Improvements so far 7
25 Opportunities 9
3 TOWPATH SPECIFICATION 10
4 COST ASSUMPTIONS 11
5 METHOD 12
6 ASSESSMENT CRITERIA 13
61 Design Guidance amp Standards 13
62 Criteria used in this report 14
63 Prioritisation 14
7 RESULTS 15
71 High Priority Towpath Sections 15
72 Medium Priority Towpath Sections 15
73 Low Priority Towpath Sections 16
74 Map of Priority Towpath Sections 17
Appendix 1 - Towpath estimator tool 18
Appendix 2 - Towpath assessment criteria scores 19
Appendix 3 ndash Towpath Survey Section Reports 20
Hillingdon Towpaths
Page 4 of 56
1 SUMMARY
Canal amp River Trust has produced this report to inform future investment priorities for
Hillingdon canal towpaths
The report was produced at the request of members of the Hillingdon Canals Partnership
and serves as a reference document for its work to promote and improve the boroughrsquos
waterways
It contains information for Hillingdon canal towpaths surveyed in 2013 covering
the Grand Union Canal (divided into 35 sections)
the Paddington Arm (1 section)
and Slough Arm (1 section)
For each section the general towpath condition levels of use and its function in connecting
people and places are considered
The result is a prioritised overview of borough towpaths for improvement which will support
funding applications and decisions
Hillingdon Towpaths
Page 5 of 56
2 BACKGROUND
21 Better Towpaths for Everyone
Sir Brian Fender chair of London
Waterways Partnership launched
Better Towpaths for Everyone in
spring 2014
The report was endorsed by the
Mayorrsquos Cycling Commissioner
Andrew Gilligan and sets out
proposals for 3 strategic cross-
borough Quietways along the Grand
Union Canal Paddington Arm and
River Lee responding to the Mayorrsquos
Cycling Vision
Hillingdon sits across 2 of these Quietways
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 4 of 56
1 SUMMARY
Canal amp River Trust has produced this report to inform future investment priorities for
Hillingdon canal towpaths
The report was produced at the request of members of the Hillingdon Canals Partnership
and serves as a reference document for its work to promote and improve the boroughrsquos
waterways
It contains information for Hillingdon canal towpaths surveyed in 2013 covering
the Grand Union Canal (divided into 35 sections)
the Paddington Arm (1 section)
and Slough Arm (1 section)
For each section the general towpath condition levels of use and its function in connecting
people and places are considered
The result is a prioritised overview of borough towpaths for improvement which will support
funding applications and decisions
Hillingdon Towpaths
Page 5 of 56
2 BACKGROUND
21 Better Towpaths for Everyone
Sir Brian Fender chair of London
Waterways Partnership launched
Better Towpaths for Everyone in
spring 2014
The report was endorsed by the
Mayorrsquos Cycling Commissioner
Andrew Gilligan and sets out
proposals for 3 strategic cross-
borough Quietways along the Grand
Union Canal Paddington Arm and
River Lee responding to the Mayorrsquos
Cycling Vision
Hillingdon sits across 2 of these Quietways
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 5 of 56
2 BACKGROUND
21 Better Towpaths for Everyone
Sir Brian Fender chair of London
Waterways Partnership launched
Better Towpaths for Everyone in
spring 2014
The report was endorsed by the
Mayorrsquos Cycling Commissioner
Andrew Gilligan and sets out
proposals for 3 strategic cross-
borough Quietways along the Grand
Union Canal Paddington Arm and
River Lee responding to the Mayorrsquos
Cycling Vision
Hillingdon sits across 2 of these Quietways
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 6 of 56
22 Hillingdon Waterspace Strategy
Canal amp River Trust works with key stakeholders brought together under the Hillingdon
Canals Partnership
The partnership is chaired by David Brough (of Hayes Town Partnership) and includes
representatives from Hillingdon Council Hayes Town Partnership GlaxoSmithKline Inland
Waterways Association Groundwork Thames 21 West Drayton Town Centre Action
Group and John McDonnell MP (Hayes amp Harlington)
In 2008 British Waterways produced a draft scoping report for a Hillingdon Waterspace
Strategy Good progress has been made on some initiatives identified in the Strategy and
this report will assist decisions on further work
An update of the Waterspace Strategy is planned during 201415 subject to funding
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 7 of 56
23 Hillingdon Canals
Canal amp River Trust cares for 2000 miles of historic inland waterways in England amp Wales
In the Capital Hillingdon has more towpaths than any other London Borough
London Borough km miles
1 Hillingdon 212 132 205
2 Ealing 156 97 151
3 Tower Hamlets 124 77 120
4 Enfield 90 56 87
5 Brent 83 52 81
6 Newham 78 49 76
7 Hackney 69 43 67
8 Westminster 55 34 54
9 Hounslow 36 23 35
10 Haringey 34 21 33
11 Camden 28 17 27
12 Islington 20 12 19
13 Kensington amp Chelsea 19 12 19
14 Hammersmith amp Fulham
17 10 16
15 Waltham Forest 13 08 13
Total 1034 642 100
Hillingdonrsquos 21km of traffic-free canal towpaths are split along the Grand Union Canal and
its Paddington and Slough Arms
Hillingdon Canals km miles
1 Grand Union Canal 175 109 829
2 Paddington Arm 29 18 132
3 Slough Arm 08 05 40
Total 212 132 100
Hillingdon towpaths are diverse in character condition and levels of use They connect the
town centres of Hayes West Drayton Uxbridge and Rickmansworth as well as bordering
the major employment site at Stockley Business Park
24 Improvements so far
In addition to the Canal amp River Trustrsquos programme of maintenance and improvement
works securing partner funding has been vital to delivering better access signs and
surfacing Towpaths have been improved in recent years with funding from Hillingdon
Council and Transport for London Other sections are now in more need of improvement
Some areas that have benefitted from investment such as to the west of and including
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 8 of 56
Hayes Town Centre are areas where we have long term aspirations for further improvement
given their strategic importance and high footfall
Hillingdon towpaths will also receive new Legible London signage during summer 2014
New towpath surface near Cowley New access ramp Uxbridge
Example of Legible London sign River Lee
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 9 of 56
25 Opportunities
There are some canal locations in Hillingdon that are not well used by local residents and
visitors or have large areas of redundant space often underneath road or rail bridges
Whilst these structures can create dark and sometimes intimidating spaces these locations
also present opportunities for improvement and increase in use
Hillingdon in partnership with Canal amp River Trust has submitted a funding application to
Transport for Londonrsquos Incubator Fund This includes installing the Sharkrsquos Canoe Club
underneath the Hayes By-pass and using the area under North Hyde Gardens as a
volunteer base and community space to promote activity and use of the canal We are in
discussions with the adjacent landowner about landscaping an upper towpath and installing
a Trim Trail (outdoor fitness trail) in the area
Hayes By-Pass (Section 1) and North Hyde Gardens (Section 2)
The by-pass is a large flyover with an access ramp from the A312 to the towpath There is a
large amount of redundant space underneath the road bridge As the bridge blocks out
light the space is dark and uninviting but could be used to install a climbing wall or outdoor
gym equipment
North Hyde Gardens has a vacant space at the base of the bridge on the towpath This
space has attracted antisocial behaviour in the past and has since been secured by the
local police and the landowners Legal and General
Shackles Dock Western View and Hayes Town Centre
These locations central to the town centre have suffered from littering and street-drinking
however Thames 21 and Sharkrsquos Canoe Club are in discussions with the landowners of
Shackles Dock about accessing the site for canoeing and there is also a wild flower
landscaping scheme proposed for Hayes Town Centre
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 10 of 56
3 TOWPATH SPECIFICATION
The photograph below shows a typical towpath in the borough which has been recently
improved It shows the preferred towpath specification and was taken in July 2013 on the
Grand Union Canal Paddington Arm
We aim to achieve these minimum specifications
18m wide surfaced path tarmac with tar spray and chip finish with timber edging
boards
Verges maintained either side of the path with a minimum of 600mm on the
waterside and 500mm at the back where possible
Vegetation managed not to encroach and limit space for sharing the towpath but
still providing a habitat for nature and space for moored boats
The surface finish gives an audible crunch which lets others know yoursquore there
18 metres
surfaced width
Vegetation hedges
managed not to
encroach
Tarmac with edging boards
and tar spry and chip finish
Grass verge
retained and
grass seeded
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 11 of 56
4 COST ASSUMPTIONS
The Trust uses its Towpath Estimator Tool to generate costs (see Appendix 1)
Estimated construction costs in this report are based on the Trustrsquos national term
contract rates for the 201314 financial year and are subject to inflationary uplift
Costs exclude design contingency and other project related costs such as legal or
land
The individual surveyed section reports (see Appendix 3) also include estimates for
additional measures to enhance the canal such as improvements to access points
bridges or signage
The total cost for towpath and additional improvements is estimated at just under
pound5million with pound13million in the high priority category (see Section 7 for complete
breakdown)
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 12 of 56
5 METHOD
The boroughrsquos canal towpaths were considered as 37 discrete sections
The 35 sections of the Grand Union Canal have been surveyed and presented in
order from the Bulls Bridge canal junction (between Southall and Hayes) as far as
Rickmansworth divided where bridges cross the towpath or at locks
The Paddington Arm was not surveyed in detail for this report It has had recent
enhancement works however a small section of towpath requires resurfacing This
has been earmarked for improvement as part of the Southall Gasworks
Development
The Slough Arm is subject to wider discussions with other local authorities and is
considered high priority
Section No
Location Distance (m)
Section No
Location Distance (m)
1 North Hyde Gardens to Bullrsquos Bridge
351 20 Bridge 184 to Bridge 185 232
2 North Hyde Gardens to Railway Bridge
277 21 Bridge 183a to Bridge 184 887
3 Railway Bridge to Shackles Dock 185 22 Bridge 183 to Bridge 183a 105
4 Shackles Dock to Station Road 203 23 Denham Lock to Bridge 183 489
5 Station Road to Printing House Lane
510 24 Bridge 182 to Denham Lock 455
6 Printing House Lane to Dawley Road
496 25 Bridge 181 to Bridge 182 872
7 Dawley Road to Rigby Lane 292 26 Bridge 180 to Bridge 181 1161
8 Rigby Lane to Stockley Road 896 27 Bridge 179 to Bridge 180 682
9 Stockley Rd to Iron Bridge Road 245 28 Bridge 178 to Bridge 179 1136
10 Iron Bridge Road to Horton Bridge Road
796 29 Bridge 177a to Bridge 178 512
11 Horton Bridge Road to West Drayton High Street
622 30 Bridge 177 to Bridge 177a 393
12 West Drayton High Street to Trout Rd
372 31 Riverside Cottages to Bridge 177
370
13 Trout Rd to Roving Bridge 496 32 Bridge 176d to Riverside Cottages
718
14 Roving Bridge to Linden Doors Lock
352 33 Bridge 176 to Bridge 176d 725
15 Linden Doors Lock to Benbow Bridge
586 34 Hillingdon border to Bridge 176
512
16 Benbow Bridge to Iver Lane 518 35 Bridge 175 to Hillingdon border
617
17 Iver Lane to Cowley Mill Road 933 36 Paddington Arm 1000
18 Cowley Mill Road to Culvert Lane 221 37 Slough Arm 834
19 Culvert Lane to Rockingham Road 322
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 13 of 56
6 ASSESSMENT CRITERIA
61 Design Guidance amp Standards
Towpaths are multi-functional spaces shared by
everyone whether for boating angling walking or
cycling They provide an attractive traffic-free
experience particularly appealing to enjoyment of
leisure time and can attract new and novice cyclists
The Trust has its own Towpath Design Guide which
sets out the approach needed for waterways
Following national consultation on sharing Towpaths
in early 2014 the Trust will publish a new Towpath
Policy setting out its expectations and approach to
managing and improving towpaths for shared use
Elsewhere new London Cycling Design Standards
(LCDS) were released for consultation in June 2014
The LCDS includes a Cycling Level of Service (CLoS)
which enables assessment of the suitability of a route
for cycling The design standards provide guidance to
ensure cycle routes are delivered to the following
good design outcomes
1 Safe
2 Direct
3 Comfortable
4 Coherent
5 Attractive
6 Adaptable
The LCDS refers to shared space although mainly
between motorised vehicles cyclists and pedestrians
The design standards do not adequately analyse the
needs of pedestrians and cyclists in off-highway
environments such as parks and canal towpaths
Similarly the National Cycle Network - Guidance and
Practical Details document produced by Sustrans
doesnrsquot fully consider constraints limitations and
character of towpaths The minimum width of 2m is
not always achievable for example under bridges
However 18m is often sufficient width for towpaths in
areas with medium to low flows
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 14 of 56
62 Criteria used in this report
The criteria used for this report consider physical condition levels of use and connectivity to
people and places as follows
1 Width
2 Surface
3 Levels for drainage
4 Vegetation
5 Access
6 Signage
7 Traffic
8 Links to places and people
9 Antisocial behaviour
10 Community interest
The scoring for each of the 10 criteria is explained in more detail in Appendix 2
63 Prioritisation
Survey results for the 37 towpath sections have been grouped as high medium or low
priority as follows
High Priority red scores 1 to 5
Medium Priority yellow scores 6 to 10
Low Priority green scores 11 to 20
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 15 of 56
7 RESULTS
Full details for each surveyed section are at Appendix 3 of this report
71 High Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
5 Bridge 200 to Bridge 199 510 pound119719 pound2300 11 to 2 2
6 Bridge 199 to Bridge 198 496 pound116440 pound2190 12 ndash 15 5
7 Bridge 198 to Bridge 196 292 pound68561 pound1500 12 ndash 15 4
8 Bridge 196 to Stockley Rd 896 pound210337 pound3400 1 to 12 1
23 Denham Lock to Bridge 183 489 pound114781 pound52162 12 to 3 4
31 Riverside Cottages to Bridge 177
370 pound86855 pound1880 15 to 16 4
32 Bridge 176d to Riverside Cottages
718 pound168529 pound7710 15 to 16 4
35 Bridge 175 to Hillingdon border
617 pound144852 pound2470 1 to 16 5
37 Slough Arm 834 pound166800 NA 12 to 14 5
Sub total pound1196874 pound7361200 pound1270486
72 Medium Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
1 Bulls bridge to Bridge 200c 351 pound82403 pound3310 15 to 18 9
2 Bridge 200c to Bridge 200b 277 pound65040 pound1620 2 9
3 Bridge 200b to Bridge 200a 185 pound43427 pound1450 15 7
4 Bridge 200a to Bridge 200 203 pound47637 pound1475 15 7
9 Stockley Rd to Bridge 194a 245 pound57512 pound1570 15 ndash 18 6
10 Bridge 194a to Bridge 193 796 pound186863 pound3000 1 to 15 7
11 Bridge 193 to Bridge 192 622 pound146026 pound18000 12 ndash 15 8
12 Bridge 192 to Bridge 191 372 pound87340 pound2000 12 to 18 7
13 Bridge 191 to Bridge 190b 496 pound116440 pound2950 15 ndash 18 9
14 Bridge 190b to Bridge 190a 352 pound82645 pound1810 12 to 18 9
15 Bridge 190a to Bridge 189 586 pound137567 pound2380 15 to 18 9
17 Bridge 188 to Bridge 187 933 pound218999 pound3140 12 to 15 10
18 Bridge 187 to Culvert Ln 221 pound51886 pound1530 15 to 18 10
19 Culvert Ln to Bridge 186 322 pound75603 pound1780 12 to 18 6
20 Bridge 184 to Bridge 185 232 pound54476 pound1550 12 to 15 7
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 16 of 56
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
21 Bridge 183a to Bridge 184 887 pound208233 pound3110 12 to 15 7
22 Bridge 183 to Bridge 183a 105 pound24648 pound1250 12 to 15 6
24 Bridge 182 to Denham Lock 455 pound106808 pound2100 12 to 15 7
25 Bridge 181 to Bridge 182 872 pound204711 pound103075 1 to 15 7
26 Bridge 180 to Bridge 181 1161 pound272544 pound3760 1 to 15 7
27 Bridge 179 to Bridge 180 682 pound160110 pound2620 15 to 2 8
28 Bridge 178 to Bridge 179 1136 pound266675 pound3700 15 to 2 9
29 Bridge 177a to Bridge 178 512 pound120204 pound2220 15 to 2 10
30 Bridge 177 to Bridge 177a 393 pound92238 pound1940 15 to 16 10
34 Hillingdon border to Bridge 176
512 pound120204 pound2220 12 to 16 9
Sub total pound3030239 pound173560 pound3203799
73 Low Priority Towpath Sections
Map Section
No
Location Distance (m)
Estimated towpath
cost
Estimated additional works cost
Width (m)
Priority Score
16 Bridge 189 to Bridge 188 518 pound121581 pound2200 15 to 2 11
33 Bridge 176 to Bridge 176d 725 pound170188 pound7725 15 to 16 12
36 Paddington Arm 1000 pound183020 NA Min 18 14
Sub total pound474789 pound992500 pound484714
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 17 of 56
74 Map of Priority Towpath Sections
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 18 of 56
Appendix 1 - Towpath estimator tool
Project Name
overall length of towpath (m) 000 input 000
width of towpath (m) 000 input 000
area of any brick sheeting (m2) 000 input 000
Terram and 75mm type 1 base construction Yes
Granular surfacing (limestone granitebrick dust etc) No
SBM DBM or Breedon gravel surfacing No
Bitumen emulsion spray amp chip finish No specification and estimating rate to be confirmed currently pro visio nal assumed contract specification
timber edgings to path No
Excavated material disposed off site No
Is general site clearance required No
Are the works being delivered in Scotland No
Are the works being delivered in London amp SE No
Description Quantity Unit Rate pound p Quantity Unit Rate pound p
PERMANENT WORKS
Insert significant items as appropriate - PC SUM 0 0
Additions to costs calculated above for works carried out due to
difficultwaterborne access
to value of Class E earthworks included above 000 14500 0 000 10000 0
to value of Class O timber included above 000 14500 0 000 10000 0
to value of Class RP and Q towpath amp piling 000 14500 0 000 10000 0
to value of Class U brickwork blockwork and masonry included
above
000 11000 0 000 10000 0
to value of Class X miscellaneous work included above 000 11000 0 000 10000 0
pound 0 pound 0
Addition to cover minor items not specifically identified above
Add to value of Permanent Works as calculated including additions
for working from water
000 015 000 000 015 000
pound pound
bf pound 0 bf pound 0
GENERAL ITEMS
General Items applicable to all projects
Contractor Set-up Site Management Supervision etc including
general plant instruments personnel transport out of hours
security general labour site compound and hard standing general
testing etc 6500
Of Total
Perman
ent
Works 0 6500
Of Total
Permanent
Works 0
Site Specific General Items (ie access tracks specific temp works
etc)
pound 0 pound 0
PRICE ADJUSTMENTS
Add Regional Adjustment 0 0
0 0
pound 0 pound 0
pound 0 0
Add Inflation adjustment
pound pound
RISK
Add Risk monies for Construction Phase
Insert items sums and probability of
their occurrence as appropriate
land agent and owner fee sum 0 sum 0
sum sum
sum sum
0 0
0 0
0 0
excludes contingency or other proejct related costs such as legal etc these to be added by Regeneration project manager as appropriate
excludes external design assumed schemes developed on BW standard details Contractor preparing BoQ etc
Note until estimator is developed further default answer Yes
Towpath Budget Estimator - DRAFT - Revision 1
Probability
age
Full cost Probabili
ty age
For all associated works (access improvements bank protection piling
etc) either include a PC sum below or include specific measures in bill
build up found click Measured WorksA1
Grand Total - BUDGET ESTIMATE
Project and contract management from British Waterways 115
Total of Estimate (inclusive of Contractors staff) pound
Waterborne andor difficult access Non-waterborneeasy towpath access circa 500m
Full cost
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 19 of 56
Appendix 2 - Towpath assessment criteria scores
1 Width
0 - Width less than 12 in places
1 - No serious issues but not optimised
2 - Optimised 16m ndash 18m minimum except at bridges structures
2 Surface
0 - Likely to prevent access when wet cause punctures or encourage fast cycling
1 - No serious issues but not optimised
2 - Optimised Constant hard wearing with a low speed surface
3 Levels
0 - Change in level which causes drainage issue
1 - No serious issues but not optimised
2 - Optimised Good drainage and level throughout
4 Vegetation
0 - Encroaching and diminishing usable width
1 - No serious issues but not optimised
2 - Optimised Well-kept and easy to manage whilst maintaining habitat value
5 Access
0 - A lack of access points or the towpath is hard to access
1 - No serious issues but not optimised
2 - Optimised Access points provide easy access
6 Signage
0 - No consistent way-finding system in need of advisory signs to guide visitors or there is damage to signs
1 - No serious issues but not optimised
2 - Optimised good visitors way finding information
7 Traffic
0 - High
1 - Med
2 - Low
8 Links to trip generators (such as population centres or employment sites)
0 - Part of population centre
1 - Near to population centre
2 - Far from population centre (Rural or connective route only)
9 Anti-Social Behaviour
0 - Regular graffiti crime or rough sleeping hot spot
1 - Occasional evidence of anti-social behaviour
2 - No apparent evidence of anti-social behaviour
10 Community Support
0 - Is too far away or unattractive to community groups
1 - There is good potential of community involvement
2 - There is an active adoption or friends group in the area
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 20 of 56
Appendix 3 ndash Towpath Survey Section Reports
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 21 of 56
Towpath Section 1
North Hyde Gardens Road to
(Bridge 200c Nestles to
Bulls Bridge junction)
Priority 9
Length of Towpath 351m
Current Towpath Surface Some evidence of
the existing towpath construction potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
There is no public access
Estimated Costs
Towpath surfacing with timber Edgings pound69882
Towpath surfacing with concrete Edgings pound82403
Additional works
New Bridge PlatesSigns including road names
pound1000 (approx)
General site clearance and de-veg over full towpath
length pound810
Permanent fencing or parapet over back pound1500
Total pound3310
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 22 of 56
Towpath Section 2
North Hyde Gardens Bridge to Railway
Bridge
(Bridge 200c Nestles Bridge to 200b)
Priority 9
Length of Towpath 277m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Timber edgings
Width of Towpath 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There
are no public access points to the towpath along this
stretch
Estimated Costs
Towpath surfacing with timber Edgings pound55159
Towpath surfacing with concrete Edgings pound65440
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound620
Total pound1620
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 23 of 56
Towpath Section 3
Railway Bridge to Shackles Dock
(Bridge 200b to 200a Exchair Dock)
Priority 7
Length of Towpath 185m
Current Towpath Surface Some
evidence of the existing towpath
construction potholed and bad
drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m
Services in towpath Fibre optic
cable inspection chambers are
present
Access Issues Waterborne access
would be needed to carry out this
work There is no public access point along
this stretch
Estimated Cost
Towpath surfacing with timber Edgings
pound36828
Towpath surfacing with concrete Edgings
pound43427
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath
length pound450
Total pound1450
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 24 of 56
Towpath Section 4
200a Exchair Dock to 200)
Priority 7
Length of
Towpath 203m
Current Towpath
Surface There is
evidence of the
existing towpath
construction and generally in good condition Towpath
surfacing with timber edgings present
Current Width of Towpath 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to
carry out this work There is a public access point just after
bridge 200 this a set of steps with metal railings (see picture
below)
Estimated Cost
Towpath surfacing with timber edgings pound40395
Towpath surfacing with concrete edgings pound47637
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound475
Total pound1475
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 25 of 56
Towpath Section 5
Station Rd to Printing House Lane (Bridge 200 to 199)
Priority 2
Length of Towpath 510m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy potholed
and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 12m to 2m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work There is a
public access point adjacent to bridge 199 set of
brick steps with metal railings
Estimated Costs
Towpath surfacing with timber edgings pound101526
Towpath surfacing with concrete edgings
pound119719
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1300
Total pound2300
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 26 of 56
Towpath Section 6
Printing House Lane to Dawley Road
(Bridge 199 to 198)
Priority 5
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m ndash 15m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access points at bridge 198 a set of concrete and
timber steps with timber a channel for bicycles
wheels
Concept Estimated Cost
Towpath surfacing with timber edgings pound98747
Towpath surfacing with concrete edgings pound116440
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length pound1190
Total pound2190
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 27 of 56
Towpath Section 7
Dawley Road to Rigby Lane
(Bridge 198 to 196)
Priority 4
Length of Towpath 292m
Current Towpath Surface Some
evidence of the existing towpath
construction generally muddy
potholed and bad drainage
Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m
to 15m
Services in towpath Fibre optic
cable inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access on to the towpath from the end of Rigby
Lane
Estimated Costs
Towpath surfacing with timber edgings pound58145
Towpath surfacing with concrete edgings pound68561
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus possible removal of metal work to public
access pound1000
Total pound2000
Access from Rigby Lane
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 28 of 56
Towpath Section 8
Rigby Lane to Stockley Road
(Bridge 196 to 195a)
Priority 1
Length of Towpath 896m
Current Towpath Surface Muddy
potholed surface tree roots narrow
and bad drainage Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 1m to
12m
Access Issues The only way down to this section of
towpath is via a set of long sloping steps from an
office car park on the Stockley Business Park These
steps are not ideal for transport of construction
materials Waterborne access would be needed to
carry out this work
Services in towpath Fibre optic cable inspection
chambers are present
Estimated costs
Towpath surfacing with timber edgings
pound175566
Towpath surfacing with concrete edgings
pound210337
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full towpath
length plus tidy up of stepped access pound2400
Total pound3400
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 29 of 56
Towpath Section 9
Stockley Road to Iron Bridge Road
(Bridge 195a to 194a)
Priority 6
Length of Towpath 245m
Current Towpath Surface There is evidence
of the existing towpath constructionsurfacing
generally in good condition Towpath surfacing
with timber edgings present in parts
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a
public access points at Iron Bridge Rd This
access has a long low gradient
surfaced slope down to the towpath
(see picture below)
Concept Estimated Cost
Towpath surfacing with timber edgings
pound48772
Towpath surfacing with concrete
edgings pound57512
Additional works
New Bridge PlatesSigns including road names
pound1000
General site clearance and de-veg over full
towpath length pound570
Total pound1570
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 30 of 56
Towpath Section 10
Iron Bridge Road to Horton Bridge Road
(Bridge 194a to 193)
Priority 7
Length of
Towpath 796m
Current Towpath
Surface Some
evidence of the
existing towpath
construction
generally muddy
potholed and bad
drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 1m to 15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There are no
public access point on this stretch
Estimated Costs
Timber Edgings pound158469
Concrete Edgings pound186863
Additional works
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full
towpath length pound2000
Total pound3000
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 31 of 56
Towpath Section 11
Horton Bridge Road to
West Drayton High Street
(Bridge 193 to 192)
Priority 8
Length of Towpath 622m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There are 2 public access points both adjacent to the
bridges The access adjacent to the High Street is a
tarmacked slope which is generally used for car parking by
locals this could be used for materials and plant if
necessary There is also an old cobbled traffic management
system laid in the towpath just after the access point The
access adjacent to Horton Road Bridge is a set of ad-hoc
unmaintained timberconcrete steps unsuitable for works
access
Estimated Cost
Timber Edgings pound123838
Concrete Edgings pound146026
Additional works
New Bridge PlatesSigns including
road names pound1000
General site clearance and de-veg
over full towpath length pound2000
Newupdated access at Horton Road
Bridge pound10000 - pound15000
Total pound13000-pound18000
Access from West Drayton High Street
StreStreetStreet
Access from Horton Road Bridge
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 32 of 56
Towpath Section 12
West Drayton High Street Bridge to
Trout Rd
(Bridge 192 to 191)
Priority 7
Length of Towpath 372m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy potholed
and bad drainage Towpath surfacing with timber edgings
present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would
be needed to carry out this work There is
a public access on to the towpath from
StStephens Road the access has very
narrow ramps and a tight gate system this
access is for abled-body people only
Estimated Costs
Timber Edgings pound74071
Concrete Edgings pound87340
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length plus
possible removal of metal work to public access pound1000
Total pound2000
Access from St Stephenrsquos Road
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 33 of 56
Towpath Section 13
Trout Rd Bridge to Roving Bridge
(Bridge 191 to 190b)
Priority 9
Length of Towpath 496m
Current Towpath Surface There is evidence of the existing
towpath constructionsurfacing generally in good condition
Towpath surfacing with timber edgings present in parts
Extensive towpath works done outside the new Tesco
supermarket creating seating areas and public access
Current Width of Towpath 15m ndash 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work Towpath assessment needs to be carried
out to allow any plant on this section of towpath There are
public access points from the Tesco supermarket car park and adjacent to Trout Road bridge this access has
a traffic management gated system in place
Towpath surfacing with timber edgings
pound98747
Towpath surfacing with concrete edgings
pound116440
Additional works New Bridge PlatesSigns
including road names pound1000 General site
clearance and de-veg over full towpath
length pound1200
Removal of traffic calming system pound750
Total pound2950
Trout Road Access
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 34 of 56
Towpath Section 14
Slough Arm junction Roving Bridge to
Linden Doors Lock
(Bridge 190b to 190a)
Priority 9 Length of Towpath 352m
Current Towpath Surface Some evidence of
the existing towpath construction generally
muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access would be
needed to carry out this work There is a public
access point adjacent to Roving Bridge this is a
well maintained set of steps two large concrete
steps at the top then shallow cobbled set steps
the rest of the way
Concept Estimated Cost
Timber Edgings pound70089
Concrete Edgings pound82645
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound810
Total pound1810
Access at Roving Bridge
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 35 of 56
Towpath Section 15
Linden Doors Dock (Packet Boat Lane) to
Benbow Bridge
Bridge 190a to 189
Priority 9
Length of Towpath 586m
Current Towpath Surface Some evidence of the
existing towpath construction generally muddy
potholed and bad drainage Towpath surfacing with
timber edgings present in parts
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath
There are public access points at bridge 189 and
midway through the towpath length the access at
bridge 189 is wide and of towpath construction The
access midway through the length is constructed of concrete steps and a steel hand rails Both are in good
condition
Estimated Cost
Timber Edgings pound116664
Concrete Edgings pound137567
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound1380
Total pound2380
Access off public footpath
Access from Benbow Bridge
Access adjacent to bridge
189
Acce
Access adjacent to bridge
189
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 36 of 56
Towpath Section 16
Benbow Bridge to Iver Lane (Cowley Shovel
Bridge)
(Bridge 189 to 188)
Priority 11
Length of Towpath 518m
Current Towpath Surface A section of this
towpath is tarmac from bridge 188 to the Lock
There is evidence of the existing towpath
construction generally in good condition Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection
chambers are present
Access Issues Waterborne access would be
needed to carry out this work as the towpath is un-
assessed Towpath assessment needs to be
carried out to allow any plant on this section of
towpath There are public access points at bridge
188 and bridge 189 At bridge 188 there is a large
gated tarmac access area in front of a pub and cafeacute leading down
to the lock but there is a traffic calming system at the end of this
area At bridge 189 there is a narrow sloped stepped access down
to the towpath generally in good condition but would need opening
up
Estimated Cost
Timber Edgingspound103103
Concrete Edgingspound121581
Additional works New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full
towpath length pound1200
Total pound2200
Iver Lane Access
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 37 of 56
Towpath Section 17
Iver Lane (Cowley Shovel Bridge) to
Cowley Mill Rd (Gas Works Bridge)
Bridge 188 to 187
Priority 10
Length of Towpath 933m
Current Towpath Surface There is
evidence of the existing towpath
constructionsurfacing generally in good
condition Towpath surfacing with timber
edgings present in parts
Current Width of Towpath 12m to
15m
Services in towpath Fibre optic cable
inspection chambers are present
Access Issues Waterborne access
would be needed to carry out this work
as the towpath is un-assessed Towpath
assessment needs to be carried out to
allow any plant on this section of towpath There is a public access
point at Cowley Mill Rd Bridge this is a block paved ramp with one
half cobbled steps There is a public access points at Iver Lane
bridge this access is a large vehicular concrete ramp with gated
access at the bottom
Concept Estimated Cost
Timber Edgingspound185717
Concrete Edgingspound218999
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2140
Total pound2140
Access at Cowley Mill Road
Access at Iver Lane
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 38 of 56
Towpath Section 18
Cowley Mill Bridge (Gas Works Bridge) to
Culvert Lane
Bridge 187 to 186
Priority 10
Length of Towpath 221m
Current Towpath Surface Some evidence of the existing towpath
construction generally in good condition some potholes and
bad drainage Towpath surfacing with timber edgings present
Current Width of Towpath 15m to 18m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to
carry out this work There are no public access points along
this stretch
Estimated Cost
Timber Edgings pound44003
Concrete Edgings pound51886
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound530
Total pound1530
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 39 of 56
Towpath Section 19
Culvert Lane to Rockingham Road (Dolphin
Bridge)
(Bridge 186 to 185)
Priority 6
Length of Towpath 322m
Current Towpath Surface Some evidence of the existing towpath
construction generally muddy potholed and bad drainage Towpath
surfacing with timber edgings present in parts
Current Width of Towpath 12m to 18m
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment needs
to be carried out to allow any plant on this section of towpath There
is a public access points at the end of Culvert Lane There is a hard
standing area that would be good for storage of materials
Estimated Cost
Timber Edgings pound64117
Concrete Edgings pound75605
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound780
Total pound1780
Access at Culvert Lane
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 40 of 56
Towpath Section 20
Uxbridge Lock Bridge to Uxbridge Bridge (Oxford Rd)
Bridge184 (Turnover) to Bridge 185
Priority 7
Length of Towpath 887m
Current Towpath Surface Worn patchy tarmac Timber
edgings
Current Width of Towpath 12m to 15m
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry out this work as
there is no suitable access to this section of towpath There are two public access
points along this stretch both are from the Swan and Bottle pub carparks
Estimated Cost
Timber Edgings pound46201
Concrete Edgings pound54476
Additional Suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound550
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 41 of 56
Towpath Section 21
Bridge 183a (A40) to Bridge 184 (Turnover)
Priority 7
Length of Towpath 887m
Current Towpath Surface Dusty rocky levels vary turning into worn
patchy tarmac Timber edgings
Current Width of Towpath 12m to 15m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work as there is no suitable access to this section of towpath
Concept Estimated Cost
Timber Edgings pound176592
Concrete Edgings pound208233
Suggested Additional works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound2110
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 42 of 56
Towpath Section 22
Bridge 183 (White Bridge) to Bridge 183a (A40)
Priority 6
Length of Towpath 105m
Current Width of Towpath 12m to 15m
Current Towpath Surface Muddy rocky
levels vary potholes poor drainage No Timber
edgings
Public access points
Construction Notes There are services in
towpath in this section Fibre optic cable
inspection chambers are present Waterborne
access would be needed to carry out this work
as there is no suitable access to this section of
towpath
Estimated costs
With Timber Edgings pound20902
With Concrete Edgings pound24648
Additional works
Signage (Bridge plates road names) pound1000
Vegetation management pound250
Above Site plan Below Satellite View
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 43 of 56
Towpath Section 23
Denham Lock to Bridge 183 White Bridge
Priority 4
Length of Towpath 489m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 12m to 3m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is a public access point which leads to and from
Colne Valley Park visitors centre
Estimated Cost
Timber Edgings pound97338
Concrete Edgings pound114781
Additional Towpath works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound1162
Works to bridge 183 ndash re-grading of exit ramp Partial reconstruction of parapet wall pound50000
Access from Colne Valley Park visitors centre
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 44 of 56
Towpath Section 24
Bridge 182 (turnover) to Denham Lock
Priority 7
Length of Towpath 455m
Current Towpath Surface Gravel rocky levels vary Timber edgings in
parts
Current Width of Towpath 12m to 15m
Public access points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried
out to allow any plant on this section of towpath There is no public access
point along this stretch
Estimated Cost
With Timber Edgings pound90577
With Concrete Endings pound106808
Non-Towpath works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound1100
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 45 of 56
Towpath Section 25
Bridge 181 (railway) to Bridge 182
(turnover)
Priority7
Length of Towpath 872m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any
plant on this section of towpath There is no public access point along this stretch
Estimated Cost
With Timber Edgings pound173606
With Concrete Edgings pound204711
Additional suggested works (these costs to be added to the concept estimate
cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound2075
Works to bridge 182 ndash Option 1 (resurface bridge painting of metal work) pound50000
Works to bridge 182 ndash Option 2 (redesign of lead-in ramps) pound100000
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 46 of 56
Towpath Section 26
Bridge 180 (Wide Water bridge) to Bridge
181 (Railway Bridge)
Priority 7
Length of Towpath 1161m
Current Towpath Surface Gravel rocky levels vary Timber
edgings in parts There is no public access point along this stretch
Current Width of Towpath 1m to 15m
Public Access Points
Construction Notes
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath
Estimated Costs
With Timber Edgings pound231130
With Concrete Edgings pound272544
Additional works
New Bridge PlatesSigns including road names pound1000
General site clearance and de-veg over full towpath length pound2760
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 47 of 56
Towpath Section 27
Bridge 179 to Bridge 180 Wide Water Bridge
Priority 8
Length of Towpath 682m
Current Towpath Surface Muddy rocky potholes and bad drainage
Timber edgings in parts Towpath level is low in places falling under wall
level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work
as the towpath is un-assessed Towpath assessment needs to be carried out
to allow any plant on this section of towpath There is a public access point
adjacent to Bridge 180 this is a long slope with bollards to stop vehicular access
Concept Estimated Cost
With Timber Edgings pound135783
With Concrete Edgings pound160110
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1620
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 48 of 56
Towpath Section 28
Bridge 178 Black Jacks to Bridge 179
Priority 9
Length of Towpath 1136m
Current Towpath Surface Muddy rocky potholes and bad
drainage Timber edgings in parts Towpath level is low in places
falling under wall level
Current Width of Towpath 15m to 2m
Public access points
Services in towpath Fibre optic cable inspection chambers are
present
Access Issues Waterborne access would be needed to carry out
this work as the towpath is un-assessed Towpath assessment
needs to be carried out to allow any plant on this section of
towpath There is no public access point along this stretch
Estimated Costs
With Timber Edgings pound226153
With Concrete Edgings pound266675
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting
for a firm cost)
General site clearance and de-veg over full towpath length pound2700
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 49 of 56
Towpath Section 29
Bridge 177a over Troy arm to Bridge
178 Black Jacks
Priority 10
Length of Towpath 512m
Current Towpath Surface Breedon type surface generally in
good condition Timber edgings
Current Width of Towpath 15m to 2m
Services in towpath Fibre optic cable inspection chambers
are present
Public access points
Access Issues Waterborne access would be needed to carry
out this work as the towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at Bridge 178
which leads to the Lock
Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Additional suggested works (these costs to be added to the
concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still
waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 50 of 56
Towpath Section 30
Bridge 177 Copper Mill Lane to Bridge 177a over Troy
arm
Priority 10
Length of Towpath 393m
Current Towpath Surface Dusty Rocky surface tree routes Large
potholes due to vehicular use in part Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Public access points
Construction Notes
Fibre optic cable inspection chambers are present Access Issues
Towpath assessment needs to be carried out to allow any plant on this
section of towpath There is a large vehicular access point at Bridge
177 which could be used for plant access
Estimated Costs
With Timber Edgings pound78219
With Concrete Edgings pound92238
Additional suggested works
Signage pound1000
Vegetation management pound940
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 51 of 56
Towpath Section 31
Riverside Cottages to Bridge 177 Copper Mill Lane
Priority 4
Length of Towpath 370m
Current Towpath Surface Dusty Rocky Large potholes due to vehicular use
Timber edgings visible in parts
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as
the towpath is un-assessed Towpath assessment needs to be carried out to
allow any plant on this section of towpath
Concept Estimated Cost
Timber Edgings pound73656
Concrete Edgings pound86855
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a
firm cost)
General site clearance and de-veg over full towpath length pound880
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 52 of 56
Towpath Section 32
Bridge 176D Stinkhole bridge to Riverside
Cottages
Priority 4
Length of Towpath 718m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this work as the
towpath is un-assessed Towpath assessment needs to be carried out to allow any plant
on this section of towpath
Estimated Cost
With Timber Edgings pound142917
With Concrete Edgings pound168529
Non-Towpath works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1710
Surface over Bridge 176DD pound5000 (investigate ownership of bridge)
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 53 of 56
Towpath Section 33
Bridge 176 Springwell Ln to Bridge 176D Stinkhole Bridge
Priority 12
Length of Towpath 725m
Current Towpath Surface Breedon gravel type surface Timber edgings
Current Width of Towpath 15m to 16m
Services in towpath Fibre optic cable inspection chambers are present
Access Issues Waterborne access would be needed to carry out this
work There is a public access point just after bridge 176 this is gives
access to the towpath from Springwell Lane and is the public access point
for a nearby carpark
Estimated Cost
Timber Edgings pound144327
Concrete Edgingspound170188
Additional Suggested works (these costs to be added to the concept
estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm
cost)
General site clearance and de-veg over full towpath length pound1725
Create a wheel channel over Bridge 176D pound5000
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 54 of 56
Towpath Section 34
Hillingdon area boundary to Bridge 176 Springwell Lane
Priority 9
Length of Towpath 512m
Current Towpath Surface Dusty
rocky potholed narrow in places and
bad drainage Timber edgings are
present in parts
Current Width of Towpath 12m to
16m
Public access points
Services in towpath Fibre optic cable inspection chambers
are present
Access Issues Waterborne access would be needed to carry
out this work as 335m of towpath is un-assessed Towpath
assessment needs to be carried out to allow any plant on this
section of towpath There is a public access point at bridge
176 this is gives access to the towpath from Springwell Lane
and is the public access point for a nearby carpark
Concept Estimated Cost
With Timber Edgings pound101941
With Concrete Edgings pound120204
Suggested additional works (these costs to be added to the concept estimate cost)
New Bridge PlatesSigns including road names pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1220
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 55 of 56
Towpath Section 35
Bridge 175 Stockers Farm to Hillingdon boundary
Priority 5
Length of Towpath 617m
Current Towpath Surface Dusty rocky
potholed narrow in places and bad drainage
Timber edgings are present in parts
Current Width of Towpath 1m to 16m
Public Access Points
Access Issues Waterborne access would be needed to carry out this work as the towpath is un-assessed
Towpath assessment needs to be carried out to allow any plant on this section of towpath There is a public
access point at bridge 175 this is a set of concrete
steps Boaters have well established gardens along
this stretch which may create conflict when trying to
achieve the 18m desired width
Estimated Costs
With Timber Edgings pound122843
With Concrete Edgings pound144852
Additional Suggested works (these costs to be
added to the concept estimate cost)
New Bridge PlatesSigns including road names
pound1000 (still waiting for a firm cost)
General site clearance and de-veg over full towpath length pound1470
Hillingdon Towpaths
Page 56 of 56
Hillingdon Towpaths
Page 56 of 56