OPERATION MANUAL PART І
Installation of the Automatic Parking Bollard RB348
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Certified according toASTM F2656-07 M30
Page.
-2-
Формат А4
ROAD BLOCKING SYSTEMS
Contents:
1. General Guidelines ............................................................................................................. 3
2. Product Description ............................................................................................................ 6
3. Purpose .............................................................................................................................. 6
4.Technical Features .............................................................................................................. 8
5.Product Specification ...........................................................................................................9
6.Bollard Installation .............................................................................................................. 10
7.Connection of Bollard utilities ............................................................................................. 16
8.Precommissioning .............................................................................................................. 16
9. Operation Regulations ...................................................................................................... 18
10.Warranty Liabilities .......................................................................................................... 22
11. Hydraulic System ............................................................................................................ 23
12. Notes ............................................................................................................................... 25
The Manual is provided for joint use with the Operation Manual. Part II. Wiring of theRoad Blockers of RB series.
џ This Manual is an integral part of the product and shall be handed over to the customer. The manual shall be kept for future use and to be consulted, if appropriate.
џ If the Road Blocker is resold, handed over to another owner or transported to another place, make sure that this manual is enclosed to the product to be used by new owner and/or maintenance staff during installation and/or operation.
The following abbreviation are used in this Manual:
џ M - Maintenance;џ HU - Hydraulic Unit;џ HC - Hydraulic Cylinder;џ R.s.l. - Road surface level (reference point + 0.000)
Installation and Operation Manual Revision 1.0 01.2017
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-3-
General safety guidelines.
The Manual should be scrutinized prior to the equipment installation
and operation to ensure safety of people. Safety is not ensured in
case of improper operation or use.
џ The Company "TiSO" does its best to provide surety and accuracy of this Manual
and reflect substantial design modifications. Continuous improvement may cause
little differences between the equipment to be supplied the description herein.
џ The Manual to be kept for future use.
The personnel servicing operating electrical installations or
performing their adjustment, wiring, repair, maintenance and
installation shall be trained to handle the relevant model! Training
shall be performed by the product manufacturer or product
manufacturer's representatives!
џ Operating equipment to be beyond the reach children and outsiders. The manu-
facturer shall not be liable for violation of safety rules..
In case of improper operation and noncompliance with requirements
of instruction manuals the road blocker may constitute a danger to
life and health of people by presence of increased voltage in electric
circuits and movable parts!
The product to be transported in only down state!
џ Any actions that are not explicitly specified in this Manual are prohibited.
џ Safety devices provide security of potentially hazardous areas.
1.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-4-
1.1 Instructions to installer:
1. The equipment installation instructions shall be complied with for the purpose of safety.2. The bollard shall be installed according to the code of practice in compliance withsafety regulations for installation.3. The equipment shall be installed when it is deenergized.4. Packing materials are subject to disposal according to the applicable standards.5. The bollard installation procedure, specified in the Manual, shall be strictly observed.
џ It is forbidden to modify the equipment configuration and to use materials and components being outside the scope of delivery and not specified by this Manual.
џ It is forbidden to install equipment during thunderstorm, heavy rain or snowfall, in explosive environment and obscured conditions.
џ Installation area shall be prepared according to the applicable standards.
The bollard shall be installed, connected and precommissioned byqualified professionals.
6. When faults or defects are detected, the Supplier's service department shall be referred to;
7. The installer shall provide the user with the required information on operation of the system in manual mode in case of emergency;
8. The manufacturer shall not be liable for the equipment operation in the following events:
џ noncompliance with installation procedure;џ use of nonstandard materials and components;џ performance of work by unqualified personnel.
9. The manufacturer shall not be liable for compliance with safety measures during installa-tion of equipment by the personnel outside the Company's service department.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-5-
1.2 Instructions to user:
1. The operation regulations, prescribed by this Manual, shall be strictly observed.2. No modifications of the equipment components shall be made.3. The equipment shall be used for intended purposes, specified by the manufacturer.4. Don't try to repair or adjust the bollard on your own.The relevant servicedepartment shall be referred to. Breaking of seals shall cancel the manufacturer'swarranty liabilities.5. The bollard control units (panels) shall be beyond the reach of outsiders.6. The Company "TiSO" shall not be liable for improper operation of equipment andviolation of safety measures by the user.
џ The Bollard must be installed, precommissioned and serviced by certified professionals having the relevant qualification and being familiar with the product design and instruction manuals:
- installation and operation manual (Part І, Part ІІ);- datasheet;- instruction manuals for components..
џ Technical inspections, maintenance, adjustment and repair shall be per-formed only when bollard is deenergized.
џ The device, designed and manufactured in accordance with directives of the European Union, shall be marked according to CE standards
Installation and Operation Manual Revision 1.0 01.2017
*- See section "Bollard wiring diagram" of the Operation Manual.Part II. Wiring of the Road Blockers of RB series.
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Terminal block
Page.
-6-
2.1 The bollard is an automatic retractable pillar. In down position it is on the roadbedlevel and does not obstruct the traffic. In up position it blocks unauthorizedvehicle access.
2.2 The bollard can be controlled:
џ from wire or wireless remote contr;o l panelџ automatically via access control system;џ manually (manual sinking in case of power failure).
Control of two and more bollards indifferent operation modes (in parallel,sequentially, in cascade) is possible.
2.3 The bollard is equipped with light signals.
2.4 Additional options:џ bollard heating (for low winter temperature climatic regions);џ induction loops;џ alarm siren;џ auxiliary remote control devices..
2. Product Description.
800
Bollard
800
Layout of induction loops
3. Purpose.
3.1 The retractable bollards are used at public, commercial and private facilities forunauthorized vehicle access control, vehicular traffic management and regulation atdifferent sites and adjacent areas as well as for management of parking lots and parkingspaces.
3.2 The bollards are recommended for passenger transport facilities, approaches to sportsfacilities and government facilities, to be used in front of shops, hotels, shopping malls andoffice centers, health care facilities, at the approaches to cottages and cottage settlements,to be installed at central urban and historical sites, industrial and dedicated special facilities
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-7-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-7-
3.3 The product has been sucsessfully tested (crash test) within the certification system ASTM ASTM F 2656-07.
Page.
-8-
Технические характеристики.4.
Make sure of availability ofthe plate with manufacturer'sdetails:
Technical Features:
Model RB-348 Installation type submersible Actuator type/location hydraulic / external Overall dimensions (LxWxH) 620х620х1747 Weight 711 kg Actuator Hydraulic Operating pressure 4 MPa Power supply 220v / 380v, 50/60 Hz Power consumption 1,5 kW Retractable cylinder Ø 325. Steel 20 Cylinder coating (standard) Corrosion-resistant coating + RAL Height of cylinder lift 1000 mm Speed of cylinder lift 30 cm/s Cylinder raising time 3,6 sec Temperature range -40 С / +60 С Permissible load on the lid 10000 kg
Options: Light signal + (LED) RAL 3000 flame red Sound signal + Cylinder sinking manual mode + Remote control panel +
Additional options:
Cylinder coating according to chosen RAL
+
Bollard heating + Forced water discharge +
Scope of delivery specification:
Bollard assembly 1 Installation casing ( Formwork) 1 pc Transportation packing 1 kit Eye-bolt М16 2 pc
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-9-
5. Product Specification
General product appearance
Bollard assembly Installation casing(Formwork)
1000
1747
620
325
600
The Bollard is delivered
and installed in the assem-
bled condition (in installa-
tion casing). The Bollard
can be removed from
installation casing when
repair or adjustment are
required in case of mal-
function.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
1
4
52
3 1. Cylinder li�2. Casing3. Frame4. Plate front5. FormworkPB - Plug-in terminal blockHC - hydraulic cylinder
HCPTB
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Scope of Delivery
Page.
-10-
1500
6.1 Arrangement of installation site:
џ Arrangement of installation site must comply with requirements of the applicable regulations and standards.
џ Installation area shall be fenced along perimeter with temporary security fencing or caution tape at the distance of 3 meters from the installation site.
џ The appropriate warning signs ISO 7010: 2011 shall be installed in front of the entrance to the installation site.
џ Make sure that there are no underground utilities at the installation site!џ Keep outsiders away from the installation site!џ Safety regulations must be observed during installation!
6.2 Installation sequence:
џ Preparation of installation well (pit);џ Installation of bollard in the predesign position;џ Installation of reinforcement cage;џ Installation of bollard with reinforcement cage in pit;;џ Installation of utility conduits;џ Concreting of well (pit);џ Connection of utilities.
6.3 Layout of installation well (pit):
6. Bollard Installation.
1. Wooden formwork;2. PVC drain pipe ø57;3. Geotextile;4. (10-20mm grain size) gravel 250 mm;5. Protective concrete layer 50 mm (C30/37 EN V 206);
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
SECTION 1-1SCALE 1 : 50
R.s.l.
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
1500
1500
1350 1050
700
250
Page.
-11-
6.4 Installation procedure:6.4.1 Preparation of installation well (pit):
1. The required marking according to the design solutions to be made;
2. The roadbed to be removed, if appropriate;
3. A pit with dimensions of 2400mm х 2400mm and depth of 700 mm to be dug;
4. A pit with dimensions of 1500mm х 1500mm and depth of 1350 mm to be dug;
5. Geotextile to be put on the pit bottom;6. The pit to be filled with gravel (10-20mm grain size) to the
height of 250 mm;7. A drain pipe of ø75mm to be installed at the depth of 50-100
mm;8. The pit shall be filled with concrete to the height of 50 mm; 9. A formwork to be installed along the pit perimeter;10.The pit size is determined by the installer in case of loose soil.
In case of insufficient soil permeability orabundant groundwater it is advised to usepumps of forced water discharge into theexisting sewage system or earth.
6.4.2 Bollard installation in the designed position:
1. The unit to be unpacked;2. Outside condition and configuration of bollard to be checked;3. Remove face plate;4. Eye-bolts face plate;5. Bollard to be installed in the predesign position.
џ Bollard to be installed by means of handling equipment;џ Safety regulations to be observed according to the
applicable standards during handling operations!џ Slinging must be performed by the properly qualified
slingers having the appropriate permit to work;џ Presence of unauthorized persons at the installation
site during handling operations is PROHIBITED!
1-3
4-5
6-7
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-12-
Bollard in the predesign position:
6. High pressure hoses (HRH) and power supply cable to be laid incorrugated utility conduit.
7. The forced water discharge hose to be connected to the bottom nozzle, ifappropriate.
Free ends of hydraulic hoses and electrical cables to be packed tightly toprevent dirt, water and foreign particles penetration into them!
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Attack direction
Attack direction
Page.
-13-
SECTION 2-2 SCALE 1 : 30
8. Bollard with reinforcement cage to be installed into the pit by means of handlingequipment.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
Page.
-13-
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Traffic direction
Tra
ffic
direct
ion
Traffic direction
HPH to Hydraulic Unit
Forced waterdischarge
Prior to concreting:• Front plate to be installed and covered with protective film.• HPH and water discharge corrugated hose to be brought out into utility trench
Tra
ffic
dire
ctio
n
Page.
-14-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
џ Concreting to be performed with vibrated shrinkage according to the applicable standards;
џ It is advised to use waterproof additives to obtain water-resistant concrete.
џ Take a close look at the hydraulic unit and power supply connection diagrams.
џ Make sure of the bollard installation accuracy and attachment security prior to its connection
џ Concreting shall be performed with vibrated shrinkage according to the applicable standards.
џ It is advised to use waterproof additives to obtain water-resistant concrete.
џ Complete drying of concrete foundation takes at least 28 days.
After concrete is dry the road surface around Bollard to be restored, the installation area(site) to be arranged and prepared for connection of Bollard utilities and its trial performance..
9. The pit shall be filled with concrete up to the level of roadbed base.
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
SECTION 3-3SCALE 1 : 20
Concrete С30/37R.s.l.±0.000
Page.
-15-
12. Recommended options of water discharge
The customer shall provide secured water discharge for normal bollardoperation.Options of water discharge are shown conventionally.
Storm waterdrainage system
When natural drainage of water into soil is impossible, then water discharge into a separate pit to be provided.
Drainage pump
Water discharge pipe
Water discharge pipe
Storm waterdrainage system
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
Option А
Option В
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-16-
7.1 Bollard connection to hydraulic unit .Hydraulic unit hoses to be connected to bollard by means of connection sleeve.
7.2 Bollard connection to control unit1. The relevant electrical cable ends of control unit and bollard to be connected and
soldered;2. Heat shrink sleeves (optional) to be used to connect cables;3. 50 cm cable length margin from each side to be left to ensure remedial
maintenance.4. Cable length margin to be folded inwards utility conduit.
It is advised to lay electrical cables in corrugated polyamide tube withwaterproof sealed connectors to protect them against mechanical damageand environmental harmful impact
џ Operation instructions to be scrutinized prior to connecting utilities to hydraulic unit MPP-195 and control unit!
џ Operation instructions to be scrutinized during connection!џ The bollard utilities to be connected only by the properly qualified
professionals!
8.1 Preparation for precommissioning::џ Make sure of compliance and reliability connections of the bollard hydraulic
hoses and electrical cables, hydraulic unit and control unit;џ The roadbed around bollard to be restored;џ The equipment power network to be checked;џ Reliability of connection with earth loop to be checked;џ Hydraulic oil level in hydraulic tank to be checked.
7. Connection of Bollard Utilities
Corrugated polyamide cable conduit Insulation coating
Separate insulated conductors
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
to hydraulic unit to bollard
High pressure hoseConnection sleeve (conventionally)
8. Precommissioning
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-17-
8.2 Precommissioning::
џ Hydraulic unit and control unit to be energized;џ Bollard trial operation to be conducted
The following to be checked while conducting trial operation::1. Hydraulic unit operation parameters;2. Control unit and remote control panel operation parameters;3. Bollard operation parameters.
џ The required equipment performance parameter setting to be set, if appropriate
џ Oil to be refilled after hydrauluc unit is actuated and air is removed from hydraulic cylinders;
џ If a fault is detected the trouble to be traced and remedied, if applicable.џ
Table 1. Fault Finding
ĒŐĿÑÔŇĿ Possiblecause Remedy Notes
Bollardisraisingbyfitsandstarts
5.Thereareforeignparticlesinguides6.Cylinderisjammed.
5.Guidestobecleanedandlubricated.6.Cylinderconditiontobecheckedandreplaced,ifappropriate.
Incompleteraisingandsinkingofbollard
Thereareforeignparticlesinguides
Guidestobecheckedandcleanedandlubricated,ifappropriate
Actuationofhydraulicunitisfartoooften
1.Oilleakage2.Airinleakage
5.Hydraulicconnectionstobechecked.6.Airtobeevacuatedfromhydraulicsystem.
Operationnoise1.High-viscosityhydrolicoil2.Pumpiswornout3.Airinleakage
1.Oiltobechanged2.Pumptobereplaced3.Airtobeevacuatedfromhydraulicsystem
Excessiveheatingofhydraulicoil
5.Contaminationofhydraulicsystem6.Continuousoperation.
5.Hydraulicsystemtobecleaned.6.Operationconditionstobeobservedaccordingtothedatasheet.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-18-
9. Bollard Operation Regulations
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
To ensure the bollard continuous and reliable operation it is necessary:џ to use bollard according to its intended purpose;џ all rules specified in this Manual shall be strictly observed during operation;џ to provide maintenance and repair of equipment in due time;џ to prevent bollard operation and maintenance to be performed by unauthorized
persons
It is forbidden:1. to prevent bollard raising/sinking;2. to touch the road blocker's moving parts during its operation;3. to initiate movement of vehicles prior to complete bollard sinking.
The area adjacent to bollard shall be free and clear of foreign items
9.2 Equipment Maintenance:9.2.1 The Road Blocker maintenance includes preventive measures to be taken accordingto the established frequency to maintain the Road Blocker in operational condition,decrease component wearing and prevent faults and malfunctions.
Equipment examination and maintenance shall be performed according toSchedule (See Table 2) and only by properly qualified professionals.
9.2.2 Recommended types of the road blocker maintenance (M):Daily inspection (each shift);M-1 (monthly);M-2 (semiannually);M-3 (annually);Major repair (MR) – after 20000 cycles.
Table 2. Road Blocker maintenance schedule
M type Frequency Scope of control/work 1 2 3
Daily inspection
each shift
Normally the daily maintenance is performed before commencement of work and includes visual inspection of the boom barrier and, if required, prompt mechanical troubleshooting, elimination of corrosion and surface pollution. The following control shall be conducted during daily maintenance:
� availability of all units and sensors in their proper locations and their fastening security
� performance of all sensors and cable integrity; � boom barrier normal operation without jerks and
abnormal noises, jamming of movable constructional elements;
� motor heating (over 70°C).
Page.
-19-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-19-
1 2 3
M-1 monthly
M-1 is performed monthly and includes the following measures:
� measures in the scope of daily inspection; � elimination of dust from the boom barrier body
and components;
� cleaning of actuators, sensors and drive; � verification of sensors fixation reliability and their
performance; � verification of good condition and fastening
security of cable connections to actuators and sensors;
� check of availability and integrity of protective fences and devices.
М-2 semiannually
M-2 maintenance is performed semiannually including the following types of work: measures in the scope of M-1; verification of fastening security of units and devices.
М-3 annually
M-3 maintenance is performed annually including the following types of work:
� measures in the scope of M-2; � check of status of bearings, sealing cups and
lubrication; � blowing and cleaning of terminal boxes; � tensioning of screw joints of terminal boxes; � check of reliability and quality of cable
connections and earthing; � check of insulation resistance; � recovery of paint coatings.
The hydraulic unit maintenance shall be performed according to theguidelines specified in the hydraulic unit instruction manuals,combining them with M-2 or M-3.
Major repair is recommended to be performed by the manufacturer or dedicated repairservice according to the manufacturer’s documentation with the use of the manufacturer’sspare parts as well as restored or manufactured by special repaire facilities according tothe manufacturer's documentation.Mean lifetime between major repair is at least 20000 hours
џ The time of maintenance and major repair can be increased or decreased depending on actual parameters of the road blocker operation and fixed by the company operating this equipment.
џ All types of maintenance should be recorded in maintenance and repair work sheet.
9 .3 Safety regulations: 9.3.1 The appropriate safety measures shall be observed during operation and maintenance of the Road Blocker
Continued Table 2
Page.
-20-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-20-
IT IS FORBIDDEN TO USE DEFECTIVE APPLIANCES, TOOLS,INSTRUMENTATION THE SERVICE LIFE OF WHICH EXPIRED.
9.3.2 Installation and operation of electrical equipment should be performed at the factory according to the Regulations for Operation of Consumer Electrical Installations, Safety Rules for Operation of Customers' Electrical Installations complied with the Occupational Safety Standards System (GOST 12.3.003, GOST 12.3.019 and GOST 12.3.032).
9.3.3 The road blocker must be repaired by the persons being over 18, having at least level III of electrical safety qualification, relevant permit to work with electrical facilities up to 1000V, be safety briefed at workplace and scrutinized the product instruction manuals.9.3.4 It shall be the responsibility of the owner to ensure safety measures.9.3.5 Hazardous characteristics during the road blocker operation are:џ mechanical impact of raising/sinking dynamic part;џ electric shock by 220V/380V.9.3.6 Service and repair shall be performed only when equipment is deenergized, a forbidding safety sign according to GOST 12.4.026 with notation “DO NOT SWITCH ON MEN WORKING!” is put on initiator. After completion of works safety signs should be removed and equipment should be actuated only upon authorization of the work superintendent
The road block is deenergized by switch К1 (S1) in the control unitbox.
9.3.7 The road blocker electrical equipment should be earthed. Resistance between earthing bus and each accessible metal non-current-carrying part of the road blocker electrical equipment housing should not exceed 4 Ohm
It is forbidden:џ to perform maintenance and repair works when the road blocker
electrical equipment is energized.џ to perform maintenance and repair works when equipment is in
operation.
9.3.8 The regulations specified in the documents listed below should be observed when using the Road Blocker:џ "Regulations for Operation of Consumer Electrical Installations";џ "Interbranch rules on labor safety during operation of electricity generating equipment";џ "Electrical Installations Code";џ GOST 12.0.004-90; GOST 12.1.019-85; GOST 12.3.019-80.
Switch К-1
Page.
-21-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-21-
9.3.9 General safety requirements accepted in the particular company should be in effect during installation and operation of the road blocker. The safety requirements according to GOST 9.014-78 should be observed during preservation and depreservation.
9.3.10 Fire safety regulations should be observed when paraffin oil for rinsing of units and parts is used.
9.3.11 The safety instructions specified in instruction manuals for purchased products and control system should be additionally governed by.
9.3.12 The Road Blocker operating in conjunction with other technological equipment should have common locking with it.
It is strictly forbidden:џ to allow the persons being unfamiliar with operation and safety rules to
service the road blocker;џ to operate the road blocker unearthed;џ to touch current carrying elements;џ to touch movable parts of the road blocker during operation;џ to operate the road blocker when protective devices and switches are
removed;џ to prevent the road bl ocker raising and sinking;џ to use metalwork of the road blocker for connection of neutral wire of
electric welder;џ to perform welding works near the road blocker without noncombustible
material protection to avoid its burning.џ
Important!џ Prior to operation of the road blocker make sure that all units providing
safety of works are in good condition and properly installed;џ It should be taken into account that the product could be damaged
during transportation;џ Don’t disconnect the elements providing safety of works and don’t try to
modify them;џ In case of any faults or defects, inform the person in charge of the
product service.
Page.
-22-
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-22-
The warranty period is 1 year.The warranty period is effective from the date of bollard sale.The warranty is valid only subject to compliance with operation regulations and safety measures.The warranty repair shall not be performed in the following cases:- expiration of the warranty period;
- improper operation;
- the product bears the traces of tampering or attempt of unauthorized repair;
- damage resulted from the use of inappropriate accessories;
- damage caused by environment;
- damage resulted from the use of nonstandard or incompatible equipment;
- damage caused by exceeding of maximum permissible loads.In all cases, when the product is not subject to warranty repair, a paid repair maybe considered.
Warranty repair shall be performed upon availability of:• Product datasheet;• Warranty coupon with stamped date of sale.
10. Warranty Liabilities
Page.
-23-
11.1 The bollard hydraulic actuation is provided by hydraulic unit МРР-195. МРР-195.
Table 3. Basic specifications of hydraulic unit.
11.2 Hydraulic unit fluid:
Hydraulic oil at the ambient temperature of -10 to +40: Shell Tellus S2M32/Shell Tellus S2V32;Hydraulic oil at the ambient above-zero temperature: Shell Tellus S2M46/Shell Tellus S2V46;Hydraulic oil contamination class must be at least 10 class according to ISO 8573.1.
11.3 Hydraulic Diagram:
11. Bollard Hydraulic System
Maximum capacity of pump l/min 27
Operation pressure МPа 5
Motor
Pump
Shaft speed rpm 1500
Alternate current V 220/380
Motor capacity W 3000
АК1 - Hydropneumatic accumulator;Б - Hydraulic unit;ГЦ1.1 - Hydraulic cylinder of device;ГЗ1 - Hydraulic lock;ДР1 - Throttle;КО1 - Inverted spring-controlled valve;К02, К03 - Inverted valve;КП - Safety valve;Кр1.1- Кр1.5 - Two-way manually-operated valve;М - Motor;Мн - Manometer;Н - Pump;НР - Manually-operated pump;РД1 - Pressure relay;Р1.1 - Hydraulic distributor 4/3;Р1.2 - Hydraulic distributor 2/2;ФВ - Suction filter;ФС - Discharge filter;
Legend:
осbasic hydrophilies and hydraulic devices
devices assembled in one box
additional (optional) hydraulic lines and hydraulic devices
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-24-
950
12
00
HU БЭУ 550
Release tap
Control cabinet:
11.4 Bollard appearance.
џ Only recommended types of hydraulic oil to be used in hydraulic unit;џ Hydraulic oil level shall be between the upper and lower marks of gage rod;џ Hydraulic oil to be changed at least every 2000 hours of hydraulic unit opera-
tion.џ Every 1500-1700 hours are recommended;џ Safety valve to be set to at most 90 bar;џ The valve setting is forbidden to be changed by unqualified person; Oil leakage
is not permissible during hydraulic unit operation;џ Bending and jamming of hydraulic hoses are not permissible during pump unit
operation;џ Motor to be phased so that rotation of rotor consists with pointer on motor
housing;џ Motor to be protected by thermal relay and grounded.
Electronic control unit
Hydraulic unit
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-25-
12. Notes
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-26-
QR-code to be used to download the Operation Manual via Internet.
Installation and Operation Manual Revision 1.0 01.2017
ROAD BLOCKING SYSTEMS
HIGH SECURITY Bollard RB-348
Office: 71 Yamska str., 03150, Kyiv, Ukraine Tel.: +380 (44) 291-21-11· Production site: 14 Promyslova str., 02088, Kyiv, Ukraine, Fax: +380 (44) 291-21-12 E-mail: [email protected] www.tiso.global
Page.
-26-