www.energy.gov/EM 1 High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC February 25, 2015

Transcript of High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation...

Page 1: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 1

High Level Waste Relocation Project Update

Heatherly Dukes, High Level Waste Project

CH2M HILL B&W West Valley, LLC

February 25, 2015

Page 2: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 2

Milestone 1 – HLW Canister Relocation & Storage Project

Major 2014 Accomplishments • Constructed HLW Cask Storage Pad

• Procurement and delivery of equipment needed to package and relocate 278 canisters

• Fabrication of first 16 Vertical Storage Casks (VSC) and 8 overpack containers

• Developed canister decontamination process

• Performed numerous facility modifications

• Developed and submitted 10 CFR 71 (Packaging and Transportation of Radioactive Material) amendment for NRC approval

High Level Waste Storage Pad

Page 3: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 3

Automated Welding System (AWS) Delivered and Tested

Vertical Cask Transporter (VCT) and Tugger Delivered and

Tested

Equipment Delivery and Testing

Low Profile Rail Cart 80% Fabrication Complete

Load Testing in Mid-February Delivery in March

TL220 Delivery Complete

Page 4: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 4

8 Overpacks Fabricated and Fit Tested

16 Vertical Storage Casks Constructed, 8 Overpacks Loaded in VSCs

Vertical Storage Casks and Overpacks

Page 5: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 5

Chemical Process Cell (CPC)

• Fabricated Canister Decon System • Conducted proficiency training with the Canister Decon Unit • Two new cameras received for installation • Completed planning for decontaminating the CPC floor

Canister Decon Unit Proficiency Training

CPC Preparations

Page 6: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 6

Load-In Facility (LIF) Runway Installed

Facility Modifications

Load-In Facility

• Received two Aero-Go air pallet systems • Received cask preparation platform • Completed pavement saw cutting to allow

excavation for Cask Transfer Pad

(Aero-Go) Air Pallet for Load-In Facility

Equipment Decontamination Room (EDR)

• Grouted subsurface void spaces • Grouted the Soaking Pit and initiated installation of concrete cap • Completed planning for the subsurface soil strengthening • Completed electrical modifications for the transporters

Grouting Subsurface Void Space

Page 7: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 7

Road Upgrades

Conducted ~1600 linear feet of road widening

Mitigated overhead and underground utility interferences

Page 8: High Level Waste Relocation Project Update Meeting 2-25-2015/HLW...High Level Waste Relocation Project Update Heatherly Dukes, High Level Waste Project CH2M HILL B&W West Valley, LLC

www.energy.gov/EM 8

QUESTIONS?