GROUNDWATER MONITORING SYSTEM …AA3/...2017/10/17 · GROUNDWATER MONITORING SYSTEM CERTIFICATION...
Transcript of GROUNDWATER MONITORING SYSTEM …AA3/...2017/10/17 · GROUNDWATER MONITORING SYSTEM CERTIFICATION...
GROUNDWATER MONITORING SYSTEM CERTIFICATION
U.S. EPA COAL COMBUSTION RESIDUAL RULE
DISPOSAL AREA NO. 3 MONTOUR STEAM ELECTRIC STATION
DERRY TOWNSHIP MONTOUR COUNTY, PENNSYLVANIA
Prepared For:
MONTOUR, LLC WASHINGTONVILLE, PENNSYLVANIA
Prepared By:
CIVIL & ENVIRONMENTAL CONSULTANTS, INC. PITTSBURGH, PENNSYLVANIA
CEC Project 132-065.1202
OCTOBER 2017
-i- Area 3, GMS Certification October 2017
TABLE OF CONTENTS
1.0 INTRODUCTION..............................................................................................................1 1.1 Purpose .................................................................................................................... 1
2.0 SITE OVERVIEW .............................................................................................................3 2.1 Background ............................................................................................................. 3 2.2 Geologic Setting...................................................................................................... 3 2.3 Hydrogeologic Setting ............................................................................................ 4
2.3.1 Conceptual Model ........................................................................................4 2.3.2 Hydrogeologic Characteristics .....................................................................4
3.0 GROUNDWATER MONITORING SYSTEM ...............................................................6 3.1 Monitoring Well Selection ...................................................................................... 6 3.2 Well Construction ................................................................................................... 7 3.3 Monitoring Well Development ............................................................................... 7
4.0 GROUNDWATER MONITORING CERTIFICATION ..............................................8
FIGURES
Figure 1 – Site Location Map – Area 3 Figure 2 –CCR Rule Groundwater Sampling Locations Figure 3 – Fourth Quarter 2015 Groundwater Contour Map
ATTACHMENTS
Attachment 1 – CCR Rule Boring Logs
-1- Area 3, GMS Certification October 2017
1.0 INTRODUCTION
1.1 PURPOSE
The United States Environmental Protection Agency (USEPA) issued 40 C.F.R. 257, Subpart D,
Disposal of Coal Combustion Residuals from Electric Utilities (CCR Rule) on April 17, 2015. The
CCR Rule regulates disposal of coal combustion residuals (CCR) in new and active landfills and
impoundments. CEC has prepared this report for Montour, LLC to meet the groundwater
monitoring system certification requirements for Disposal Area No. 3 at their Montour Steam
Electric Station, Derry Township, Montour County, Pennsylvania.
The CCR Rule states the following criteria for a groundwater monitoring system (40 C.F.R.
§257.91):
(a) Performance standard. The owner or operator of a CCR unit must install a groundwater
monitoring system that consists of a sufficient number of wells, installed at appropriate
locations and depths, to yield groundwater samples from the uppermost aquifer that:
(1) Accurately represent the quality of background groundwater that has not been
affected by leakage from a CCR unit. A determination of background quality may
include sampling of wells that are not hydraulically upgradient of the CCR
management area where:
(i) Hydrogeologic conditions do not allow the owner or operator of the CCR
unit to determine what wells are hydraulically upgradient; or
(ii) Sampling at other wells will provide an indication of background
groundwater quality that is as representative or more representative than
that provided by the upgradient wells; and
(2) Accurately represent the quality of groundwater passing the waste boundary of
the CCR unit. The downgradient monitoring system must be installed at the waste
boundary that ensures detection of groundwater contamination in the uppermost
aquifer. All potential contaminant must be monitored.
(b) The number, spacing, and depths of monitoring systems shall be determined based upon
site-specific technical information that must include thorough characterization of:
-2- Area 3, GMS Certification October 2017
(1) Aquifer thickness, groundwater flow rate, groundwater flow direction including
seasonal and temporal fluctuations in groundwater flow; and
(2) Saturated and unsaturated geologic units and fill materials overlying the
uppermost aquifer, materials comprising the uppermost aquifer, and materials
comprising the confining unit defining the lower boundary of the uppermost
aquifer, including, but not limited to, thicknesses, stratigraphy, lithology, hydraulic
conductivities, porosities and effective porosities.
(c) The groundwater monitoring system must include the minimum number of monitoring
wells necessary to meet the performance standards specified in paragraph (a) of this
section, based on the site-specific information specified in paragraph (b) of this section.
The groundwater monitoring system must contain:
(1) A minimum of one upgradient and three downgradient monitoring wells; and
(2) Additional monitoring wells as necessary to accurately represent the quality of
background groundwater that has not been affected by leakage from the CCR unit
and the quality of groundwater passing the waste boundary of the CCR unit.
The CCR Rule also outlines well installation, development, sampling, and decommissioning
requirements. The CCR Rule requires the owner or operator to obtain a certification from a
qualified professional engineer stating that the groundwater monitoring system has been designed
and constructed as outlined above. A record of the certification must be placed in the facility’s
operating record and the publicly accessible internet site and the state must be notified that the
information is available.
-3- Area 3, GMS Certification October 2017
2.0 SITE OVERVIEW
2.1 BACKGROUND
Disposal Area No. 3 (Area 3), located south of the main generation station (Figure 1), is a residual
waste landfill constructed and operated under Residual Waste Permit #300987 issued by the
Pennsylvania Department of Environmental Protection. The landfill is used for the disposal of
plant-generated residual waste, including scrubber wastewater treatment plant sludge (sludge is a
mixture of calcium sulfate solids and precipitated heavy metals), fly ash, mill rejects, and various
sump sludges. The disposal area also receives resins, filter bags and construction and demolition
wastes. The existing disposal area was constructed beginning in September 1987 and completed
in March 1990.
Area 3 consists of a western half and an eastern half. Only the eastern half has been constructed to
date. It is unlikely that the western half will ever be constructed. The eastern half is constructed
with a geomembrane liner and leachate collection system. Leachate from the eastern half is drained
through a piping network above the liner that directs the leachate into a leachate collection basin
located southeast of Area 3. The leachate collection basin is also lined with a geomembrane liner
and covered with onsite low permeability silt-clay soils.
Groundwater quality is monitored at Area 3 in accordance with the approved permit. Monitoring
points associated with the solid waste permit include: underdrains, monitoring wells, and surface
water locations. Wells associated with the permit are sampled quarterly. Results are summarized
in a Form 14R quarterly report submitted to the state.
2.2 GEOLOGIC SETTING
The site is situated on the northern limb of a regional anticline. The shallowest bedrock formation
underlying Area 3 is the Devonian Age Marcellus Shale. The Marcellus Shale has an approximate
orientation of N45°W with a dip to the northeast of 5 to 8°. The competent shale bedrock is overlain
by weathered bedrock that ranges in thickness from less than 1 foot to 10 feet. The weathered
bedrock is overlain by glacial till material consisting of silt, clay, and broken rock fragments.
-4- Area 3, GMS Certification October 2017
2.3 HYDROGEOLOGIC SETTING
2.3.1 Conceptual Model
Topographically, the site lies within a regional basin with the highland ridges consisting of the
more resistant rock formations of an anticline. There is potential for an upward hydraulic gradient
in the general area of the site. The water table is within 10 feet of the ground surface.
The water-bearing zone directly below the site is unconfined. The overburden and the bedrock
zones are hydraulically well connected. Groundwater monitoring wells in the area typically have
screen intervals that intercept both the overburden material and the underlying bedrock.
A small tributary of Mud Creek separates the two halves of Area 3. This southeastward-flowing
tributary is redirected into two subsurface 48-inch diameter pipe conduits installed within Area 3.
The flow enters piping on the northwestern side of Area 3 and exits the piping at the southeastern
side of Area 3 (Figure 2).
The groundwater underlying Area 3 is shallow (less than 10 feet below the ground surface) and
occurs within bedrock or at the bedrock/overburden interface. Groundwater underdrains were
installed under Area 3, below the geomembrane liner, to drain the groundwater during seasonal
high levels and maintain the regulatory 8 feet separation. The groundwater underdrains are
separate from the 48-inch diameter conduits, however both systems discharge into same area,
southeast of Area 3 (see Figure 2). Figure 3 provides an approximation of the groundwater
elevation contours that currently exist under Area 3. The general groundwater flow direction is to
the south.
2.3.2 Hydrogeologic Characteristics
Hydraulic gradients calculated from 2015 water levels range from 0.003 to 0.008, with an overall
average of 0.006. Hydraulic conductivity values for the site have been obtained from site specific
-5- Area 3, GMS Certification October 2017
data collected as part of previous site evaluations. Hydraulic conductivities in soil range between
1.7xl0-6 cm/sec and 1.8xl0-8 cm/sec. Highly weathered fractured shale ranged from 2.2xl0-2 cm/sec
to 5.0xl0-3 cm/sec. Fractured competent bedrock range from 3.0xl0-3 cm/sec to l.0xl0-4 cm/sec.
Competent shale with very little to no fracturing ranged from 1.7x10-6 cm/sec to 5.0xl0-7 cm/sec.
-6- Area 3, GMS Certification October 2017
3.0 GROUNDWATER MONITORING SYSTEM
3.1 MONITORING WELL SELECTION
The groundwater monitoring system consists of a sufficient number of wells at appropriate
locations and depths to provide groundwater samples from the uppermost aquifer that accurately
represent background groundwater quality and the quality of groundwater passing the waste
boundary of the CCR unit.
There are numerous monitoring wells around Area 3 that were installed for the Pennsylvania
Residual Waste Permit and for past investigations. The CCR Rule Groundwater Monitoring
System consists of one existing well (PZ3-31) that was used in a previous investigation, and five
new wells installed to meet the requirements of the CCR Rule. The well locations are shown on
Figure 2. Table 1 summarizes the wells included as the CCR Rule Groundwater Monitoring
System to meet the CCR Rule groundwater monitoring performance standard.
TABLE 1. CCR RULE GROUNDWATER MONITORING SYSTEM
Location Relative Location
Well Diameter
(in.)
Bottom of Screen (ft-
bgs)
Screen Length (ft)
PZ3-31 Downgradient 2 17.7 9.5 MW-3-100 Downgradient 4 15 10 MW-3-101 Downgradient 4 15 10 MW-3-102 Downgradient 4 17 10 MW-3-103 Upgradient 4 15 10 MW-3-104 Upgradient 4 14 10
Based on existing groundwater contours, locations MW-3-103 and MW-3-104 will provide
upgradient water quality for groundwater flowing toward Area 3. The remaining wells, PZ3-31,
MW-3-100, MW-3-101, and MW-3-102, will provide downgradient groundwater quality.
-7- Area 3, GMS Certification October 2017
3.2 WELL CONSTRUCTION
The Area 3 monitoring wells were vertically placed to monitor the uppermost aquifer. Borings
were advanced through the overburden and weathered bedrock using hollow-stem augers. Each
monitoring well is constructed of two or four-inch diameter schedule 40 PVC casing with
approximately 10 feet of well screen and solid riser extended to a height of approximately 2.5 feet
above the ground surface. The annulus is filled with clean quartz sand to approximately 2 feet
above the screen. Wells installed in response to the CCR Rule (MW-3-100, MW-3-101, MW-3-
102, MW-3-103, and MW-3-104) contain a U-Pack screen, used in an effort to reduce turbidity.
U-Pack screens, manufactured by Campbell Monoflex, are double-walled screens that enable the
installation of the filter media (silica sand) along the length of the screen prior to lowering it into
the borehole. This eliminates installing filter sand through turbid water, which entrains sediment
in the filter pack. The remaining annulus above the filter pack is filled with hydrated bentonite.
Each well is completed with a locking steel protective cover and concrete pad. The protective
cover is marked with the well identification number. Each well is locked and durable well signs
are installed at each well location. Boring logs are provided in Attachment 1.
3.3 MONITORING WELL DEVELOPMENT
Following installation, each monitoring well was developed by surging, bailing, and/or
overpumping. Development was determined to be complete when the groundwater was visually
clear and at least 10 well volumes had been removed. Additionally for the recently installed wells,
development was determined complete when turbidity was at or less than 5 NTU.
FIGURES
www.cecinc.com333 Baldwin Road - Pittsburgh, PA 15205-9072
412-429-2324 800-365-2324
DRAWN BY:DATE:
APPROVED BY:PROJECT NO:
FIGURE NO: 1
MONTOUR, LLCCCR RULE GROUNDWATER MONITORING SYSTEMCERTIFICATION REPORTMONTOUR STEAM ELECTRIC STATIONWASHINGTONVILLE, PA
CBL4/24/2017 1 " = 4,000 '
SITE LOCATION MAP - AREA 3BSJ HTW*
132-065.1202CHECKED BY:SCALE:
0 4,000 8,000SCALE IN FEET
REFERENCEUSGS TOPOGRAPHIC MAP/ ARCGIS MAP SERVICE: HTTP://GOTO.ARCGISONLINE.COM/MAPS/USA_TOPO_MAPS, ACCESSED 4/24/2017
* Hand signature on file
Document Path: \\svr-pittsburgh\projects\2013\132-065\-GIS\Maps\Area3_CCR_Certification\132065_EN01_FIG1_SITE_LOC.mxd
SITE
+
+
+
+
+
+
!
!
!
!
!
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
DUAL 48" DIAMETER CONDUIT
AREA 3 - EAST
AREA 3 - WEST(NOT CONSTRUCTED)
UNNAMEDTRIBUTARY
MP-3-6
LD-3-1
MP-3-7MP-3-9
MP-3-8
P-3-18
MP-3-5
MW-3-1
P-3-17
MW-3-15
MW-3-16
MW-3-17
PZ3-30
P-3-20
P-3-21
PZ3-31
MW-3-102
MW-3-101
MW-3-100
MW-3-103
MW-3-104
www.cecinc.com333 Baldwin Road - Pittsburgh, PA 15205-9072
412-429-2324 800-365-2324
DRAWN BY:DATE:
APPROVED BY:PROJECT NO:
FIGURE NO: 2
MONTOUR, LLCCCR RULE GROUNDWATER MONITORING SYSTEMCERTIFICATION REPORTMONTOUR STEAM ELECTRIC STATIONWASHINGTONVILLE, PACBL
5/2/2017
CCR RULE GROUNDWATER SAMPLING LOCATIONS - AREA 3BSJ
132-065.1202CHECKED BY:SCALE: 1 " = 300 '
LEGEND! AREA 3 PADEP QUARTERLY MONITORING POINT! OTHER EXISTING MONITORING POINT+ CCR RULE GROUNDWATER MONITORING POINT
CREEKCONDUITAREA 3 BOUNDARY
REFERENCEGOOGLE EARTH PRO IMAGERYIMAGE DATE: 9/26/2014
0 300 600SCALE IN FEET
* Hand signature on fileHTW*
Document Path: P:\2013\132-065\-GIS\Maps\Area3_CCR_Certification\132065_EN01_FIG2_MONITORING_LOCS_CCR.mxd
www.cecinc.com333 Baldwin Road - Pittsburgh, PA 15205-9072
412-429-2324 800-365-2324
DRAWN BY:DATE:
APPROVED BY:PROJECT NO:
FIGURE NO: 3
MONTOUR, LLCCCR RULE GROUNDWATER MONITORING SYSTEMCERTIFICATION REPORTMONTOUR STEAM ELECTRIC STATIONWASHINGTONVILLE, PA
CBL5/2/2017
FORUTH QUARTER 2015 GROUNDWATER CONTOUR MAP - AREA 3BJH HTW*
132-065.1202CHECKED BY:SCALE:P:\2
013\13
2-065\
-GIS\M
aps\Ar
ea3_CC
R_Certi
fication
\13206
5_EN0
1_FIG3
_GRO
UNDW
ATER_C
ONTO
URS.m
xd 5/2
/2017
2:56 P
M (cla
ngley)
* Hand signature on file
NO DATE DESCRIPTION--
SUBMITTAL & REVISION RECORD
-- --
NORTH!a
N.T.S
ATTACHMENT 1
BORING LOGS
516.2
512.2512.0
505.2
DP1
DP2
AU3
AR4
Hole Plug
4" PVC Riser
BentonitePellets#1 CleanQuartz Sand
#0 CleanQuartz Sandwithin U-Pack
10' 4"x6"U-Pack PVC0.01-slotscreen
100
100
CL
CL
Brown CLAY, trace coal fragments, moist, soft, (RESIDUAL SOIL)
Brown and black CLAY, trace coal fragments, moist, soft to loose,(RESIDUAL SOIL)
Black highly weathered SHALE, moist, (WEATHERED ROCK)Black SHALE, highly weathered, soft, massive
Wet at 10'BGS. Auger refusal at 10' BGS.
Bottom of boring at 15.0 feet.
4.0
8.08.2
15.0
KEY # Talen #119
BACKFILL 4" PVC Monitoring Well
WATER LEVELS
NOTES
WELL INSTALLED Yes
AT END OF DRILLING 3.1 ft / Elev 517.1 ft
BEFORE CORING ---
STICKUP 2.21 ft above
CASING ELEVATION 522.37 ft
Estimated Well Recovery Rate = <0.5 feet per minute
AFTER DRILLING 2.8 ft / Elev 517.3 ft
DRILLING METHOD Macrocore, HSA & Air Rotary
DRILLING CONTRACTOR Eichelbergers
OUTER CASING 6", Steel
DEVELOPMENT METHOD overpumpingCEC REP JLB
ELEVATION 520.16 ft
CORE SIZE
DATE STARTED 4/4/16 COMPLETED 4/5/16
DRILLER Shane Albert
WELL ON
EASTING 2268665.56
4/19/2016 8:21:00 AM 3.0 ft / Elev 517.2 ft
NORTHING 328700.179
DIAMETER 8.25" RESULTS clear
YIELD 45 gal
MONITORING EQUIPMENT None
DE
PT
H(f
t)
0
5
10
15
SA
MP
LE ID
SA
MP
LE T
YP
E
PAGE 1 OF 1WELL NUMBER MW-3-100
CLIENT Talen Generation, LLC
PROJECT NUMBER 132-065
PROJECT NAME Area 3
PROJECT LOCATION Washingtonville, PA
CE
C G
EN
ER
AL
BH
/ T
P /
WE
LL 1
32-
065
AR
EA
3.G
PJ
NE
W C
EC
.GP
J 4
/29/
16Civil & Environmental Consultants, Inc.333 Baldwin RoadPittsburgh, PA 15205
WELL DIAGRAM
RE
CO
VE
RY
%
U.S
.C.S
.
MATERIAL DESCRIPTION
GR
AP
HIC
LOG
NA
518.5
513.5
509.5
505.0
DP1
DP2
DP3
AR4
Hole Plug
4" PVC Riser
BentonitePellets#1 CleanQuartz Sand
#0 CleanQuartz Sandwithin U-Pack
10' 4"x6"U-Pack PVC0.01-slotscreen
100
100
100
CL
CL
Brown CLAY, and vegetation, moist, soft, (RESIDUAL SOIL)
Brown and black CLAY, some shale fragments, moist, soft, (RESIDUALSOIL)
Black weathered SHALE, moist, very soft, (WEATHERED ROCK)
Auger refusal at 10.5'BGSBlack SHALE, highly weathered, very soft, thinly laminated
Bottom of boring at 15.0 feet.
1.5
6.5
10.5
15.0
KEY # Talen #119
BACKFILL 4" PVC Monitoring Well
WATER LEVELS
NOTES
WELL INSTALLED Yes
AT END OF DRILLING 5.4 ft / Elev 514.7 ft
BEFORE CORING ---
STICKUP 2.03 ft above
CASING ELEVATION 522.07 ft
Estimated Well Recovery Rate = >1 feet per minute
AFTER DRILLING 5.2 ft / Elev 514.9 ft
DRILLING METHOD Macrocore, HSA & Air Rotary
DRILLING CONTRACTOR Eichelbergers
OUTER CASING 6", Steel
DEVELOPMENT METHOD overpumpingCEC REP JLB
ELEVATION 520.04 ft
CORE SIZE
DATE STARTED 4/4/16 COMPLETED 4/5/16
DRILLER Shane Albert
WELL ON
EASTING 2268909.435
4/19/2016 8:26:00 AM 5.0 ft / Elev 515.1 ft
NORTHING 328281.275
DIAMETER 8.25" RESULTS clear
YIELD 70 gal
MONITORING EQUIPMENT None
DE
PT
H(f
t)
0
5
10
15
SA
MP
LE ID
SA
MP
LE T
YP
E
PAGE 1 OF 1WELL NUMBER MW-3-101
CLIENT Talen Generation, LLC
PROJECT NUMBER 132-065
PROJECT NAME Area 3
PROJECT LOCATION Washingtonville, PA
CE
C G
EN
ER
AL
BH
/ T
P /
WE
LL 1
32-
065
AR
EA
3.G
PJ
NE
W C
EC
.GP
J 4
/29/
16Civil & Environmental Consultants, Inc.333 Baldwin RoadPittsburgh, PA 15205
WELL DIAGRAM
RE
CO
VE
RY
%
U.S
.C.S
.
MATERIAL DESCRIPTION
GR
AP
HIC
LOG
NA
510.5
501.3
DP1
DP2
AU3
AR4
Hole Plug
4" PVC Riser
BentonitePellets#1 CleanQuartz Sand
#0 CleanQuartz Sandwithin U-Pack
10' 4"x6"U-Pack PVC0.01-slotscreen
100
100
CL
Brown and black CLAY, some shale fragments, moist, soft, (RESIDUALSOIL)
Black SHALE, highly weathered, soft, laminated
Auger refusal at 8.5'BGS
Bottom of boring at 17.0 feet.
7.8
17.0
KEY # Talen #119
BACKFILL 4" PVC Monitoring Well
WATER LEVELS
NOTES
WELL INSTALLED Yes
AT END OF DRILLING ---
BEFORE CORING 5.6 ft / Elev 512.7 ft
STICKUP 2.07 ft above
CASING ELEVATION 520.36 ft
Estimated Well Recovery Rate = 0.5 feet per minute
AFTER DRILLING 5.4 ft / Elev 512.9 ft
DRILLING METHOD Macrocore, HSA & Air Rotary
DRILLING CONTRACTOR Eichelbergers
OUTER CASING 6", Steel
DEVELOPMENT METHOD overpumpingCEC REP JLB
ELEVATION 518.29 ft
CORE SIZE
DATE STARTED 4/4/16 COMPLETED 4/7/16
DRILLER Shane Albert
WELL ON
EASTING 2269399.482
4/19/2016 8:31:00 AM 5.6 ft / Elev 512.7 ft
NORTHING 327692.877
DIAMETER 8.25" RESULTS clear
YIELD 190 gal
MONITORING EQUIPMENT None
DE
PT
H(f
t)
0
5
10
15
SA
MP
LE ID
SA
MP
LE T
YP
E
PAGE 1 OF 1WELL NUMBER MW-3-102
CLIENT Talen Generation, LLC
PROJECT NUMBER 132-065
PROJECT NAME Area 3
PROJECT LOCATION Washingtonville, PA
CE
C G
EN
ER
AL
BH
/ T
P /
WE
LL 1
32-
065
AR
EA
3.G
PJ
NE
W C
EC
.GP
J 4
/29/
16Civil & Environmental Consultants, Inc.333 Baldwin RoadPittsburgh, PA 15205
WELL DIAGRAM
RE
CO
VE
RY
%
U.S
.C.S
.
MATERIAL DESCRIPTION
GR
AP
HIC
LOG
NA
528.6
526.6
520.7
514.6
DP1
DP2
AR3
Hole Plug
4" PVC Riser
BentonitePellets#1 CleanQuartz Sand
#0 CleanQuartz Sandwithin U-Pack
10' 4"x6"U-Pack PVC0.01-slotscreen
100
100
CL
CL
Brown CLAY, and organics, moist, soft, (RESIDUAL SOIL)
Brown CLAY, trace iron staining, moist, soft, (RESIDUAL SOIL)
Brown and black weathered SHALE, moist, soft, (WEATHERED ROCK)
Trace of iron staining 5.0'-7.0' BGS
Wet
Auger refusal at 8.9'BGS.Black SHALE, highly weathered to moderately weathered, soft to mediumhard, trace of iron staining
Bottom of boring at 15.0 feet.
1.0
3.0
8.9
15.0
KEY # Talen #119
BACKFILL 4" PVC Monitoring Well
WATER LEVELS
NOTES
WELL INSTALLED Yes
AT END OF DRILLING 3.9 ft / Elev 525.6 ft
BEFORE CORING ---
STICKUP 2.17 ft above
CASING ELEVATION 531.73 ft
Estimated Well Recovery Rate = 0.2 feet per minute
AFTER DRILLING 3.3 ft / Elev 526.3 ft
DRILLING METHOD Macrocore, HSA & Air Rotary
DRILLING CONTRACTOR Eichelbergers
OUTER CASING 6", Steel
DEVELOPMENT METHOD overpumpingCEC REP JLB
ELEVATION 529.56 ft
CORE SIZE
DATE STARTED 4/11/16 COMPLETED 4/12/16
DRILLER Chris Brennenman
WELL ON
EASTING 2268933.966
4/19/2016 8:15:00 AM 4.1 ft / Elev 525.5 ft
NORTHING 329515.568
DIAMETER 8.25" RESULTS clear
YIELD 112 gal
MONITORING EQUIPMENT None
DE
PT
H(f
t)
0
5
10
15
SA
MP
LE ID
SA
MP
LE T
YP
E
PAGE 1 OF 1WELL NUMBER MW-3-103
CLIENT Talen Generation, LLC
PROJECT NUMBER 132-065
PROJECT NAME Area 3
PROJECT LOCATION Washingtonville, PA
CE
C G
EN
ER
AL
BH
/ T
P /
WE
LL 1
32-
065
AR
EA
3.G
PJ
NE
W C
EC
.GP
J 4
/29/
16Civil & Environmental Consultants, Inc.333 Baldwin RoadPittsburgh, PA 15205
WELL DIAGRAM
RE
CO
VE
RY
%
U.S
.C.S
.
MATERIAL DESCRIPTION
GR
AP
HIC
LOG
NA
532.4
529.8
522.4
DP1
DP2
AR3
Hole Plug
4" PVC RiserBentonitePellets#1 CleanQuartz Sand
#0 CleanQuartz Sandwithin U-Pack
10' 4"x6"U-Pack PVC0.01-slotscreen
Cave-in
100
100
CL
Light brown to brown CLAY, some iron staining, trace shale fragments,moist to moist-, soft, (RESIDUAL SOIL)
Auger refusal at 5'BGS
Black and gray highly weathered SHALE, soft, some iron staining,(WEATHERED ROCK)
Black and gray SHALE, highly weathered, soft
Bottom of boring at 15.0 feet.
5.0
7.6
15.0
KEY # Talen #119
BACKFILL 4" PVC Monitoring Well
WATER LEVELS
NOTES
WELL INSTALLED Yes
AT END OF DRILLING 5.8 ft / Elev 531.6 ft
BEFORE CORING ---
STICKUP 2.57 ft above
CASING ELEVATION 539.97 ft
Estimated Well Recovery Rate = 0.2 feet per minute
AFTER DRILLING 6.2 ft / Elev 531.2 ft
DRILLING METHOD Macrocore, HSA & Air Rotary
DRILLING CONTRACTOR Eichelbergers
OUTER CASING 6", Steel
DEVELOPMENT METHOD bailingCEC REP JLB
ELEVATION 537.4 ft
CORE SIZE
DATE STARTED 4/7/16 COMPLETED 4/8/16
DRILLER Shane Albert
WELL ON
EASTING 2269433.448
4/19/2016 8:34:00 AM 7.1 ft / Elev 530.3 ft
NORTHING 329351.825
DIAMETER 8.25" RESULTS clear
YIELD 120 gal
MONITORING EQUIPMENT None
DE
PT
H(f
t)
0
5
10
15
SA
MP
LE ID
SA
MP
LE T
YP
E
PAGE 1 OF 1WELL NUMBER MW-3-104
CLIENT Talen Generation, LLC
PROJECT NUMBER 132-065
PROJECT NAME Area 3
PROJECT LOCATION Washingtonville, PA
CE
C G
EN
ER
AL
BH
/ T
P /
WE
LL 1
32-
065
AR
EA
3.G
PJ
NE
W C
EC
.GP
J 4
/29/
16Civil & Environmental Consultants, Inc.333 Baldwin RoadPittsburgh, PA 15205
WELL DIAGRAM
RE
CO
VE
RY
%
U.S
.C.S
.
MATERIAL DESCRIPTION
GR
AP
HIC
LOG
NA