Greystones Harbour PPP - Civil & Maritime Works - … · 2014-11-12 · period –Design,...
Transcript of Greystones Harbour PPP - Civil & Maritime Works - … · 2014-11-12 · period –Design,...
2 Contents
Contents
1. History2. Bid Stage3. Preferred Bidder
Stage4. Detailed Design
Stage5. Construction Stage
Images from 1996
3
Location
• Design life: 100 years
• MHWS/MLWS: 1.5m / -1.5 m OD Malin
• Climate change: +0.9 m in 100 years
• 100 year return period at 2015
+2.5m OD Malin
. Hmo = 4.7 m
. Tp = 10.7 s
Dublin
Greystones
History
6
Coastal Erosion
Coastline
Old Landfill
Harbour Siltation
Storm Damage
Storm Damage1. Siltation of Harbour
2. Damage to
Breakwaters
3. Coastal Erosion
Problems
8
• Collapse of Structures
• Cavities within Breakwater
• Remedial Works
History
Damage to Breakwater
9
Coastal Erosion –Railway
• Route Selection – Earl of Meath
• Isombard Kingdom Brunel
• Bray Head – Pre-Cambrian rocks
• Tunnels and Bridges
History
12
Coastal Erosion – Cliffs
• Dynamic Coastal ‘Cell’• Erosion Process – waves• Erosion Process – rainfall• 0.5m/year average retreat
History
13
Coastal Erosion –Storm Events
• 1929/31 Storms• Houses Lost• Coastal Defences
destroyed
History
[Pictures]
16
Bid Stage
• 1999 - Greystones (and Delgany) Local Area Plan designated site for new
Harbour/Marina.
make safe and restore existing harbour,
Address coastal erosion, and;
provide new major public amenity.
• 2001 – Wicklow County Council decision to procure through a PPP model.
230 Berth Marina
360 Residential Units
6,000m² Commercial
16 acre public park
Public Harbour, Public Square
Coastal Protection Works
Bid Stage
17
Public Private Procurement (PPP) Model
• 30 year concession period – Design, Construction and Operation
• Award of Preferred Bidder status pre-planning
• EU Public Procurement• WCC provide land,
concessionaire provides public amenities
• Hand-back to WCC all public space
• Significant new facilities for local clubs
Bid Stage
18
Ground Conditions
• Desk Study• Ground Investigations• Ground Model• Made Ground
Bid Stage
Laminated Fluvio-
glacial Sands &
GravelsBeach Shingle
Brown Boulder Clays
Greywacke Bedrock
varies
-6m OD Malin
+10m OD Malin
0m OD Malin
19 Bid Stage
Reference Design and Outline EIS
• Refurbished Harbour• New Marina• Landslide Development• Public Amenities• Coastal Protection
20
Bid Design - Layout
Bid Stage
Coastal protection
02 Marina
03 North breakwater
04 Harbour
05 South breakwater
06 Public slipway
07 Coastguard
08 Yacht clubs
• Minimizing cut and fill • Buildings more protected
21
Bid Design – Harbour Entrance
• Simplify geometry (cost)• Retain dynamic ‘spending’ beach
Bid Stage
Bid design
N
Reference design
23
Bid Design –Breakwaters
• Height and Width constraints
• Structure options: Embankment Sheet-piled
Cofferdam Precast Caisson
(marine access) Precast Block
• Seaward Revetment
Bid Stage
24 Bid Stage
Assumes no interventions to existing coastline
Elevation NTS
Existing cliff top
Existing beach
Perspective View Section 1
Coastal Protection Existing Situation
Scheme Objectives:
• Protect landfill and heritage area
• Preserve coastal cliff walk
• Overall scheme should preserve or
enhance amenity value and minimise
adverse environmental impact
Key Constraint
Avoid increased erosion of coastline to
north of scheme.
25
Coastal Protection Reference Design
• Highly engineered approach to halt
natural process over only part of
north beach
• Significantly increased erosion
forecast over northern section
threatening railway and impacting
on cliff walk
• Complete loss of much of north
beach and replacement with an
unsightly and inaccessible
shoreline, with loss of amenity,
natural cliffs and bird habitat
• Safety issue with regard to access
over and around revetments
• Given uncertainty in future
maritime conditions a highly
engineered approach is not sensible
as there is no flexibility in the
solution
Bid Stage
Perspective View
Section 1
Elevation
New cliff top
Rock Revetment
Engineered slope
26
Coastal Protection Design Development
• Solution is to work with nature rather than against it
• Managed Retreat solution• More sustainable solution for entire
north beach• Landfill protected with revetment
and groynes to create recreational beach area
• Single beach replenishment will supply material to the coastal system, reducing erosion behind berm and to lesser extent to the north by gradual shingle spread
• Existing north beach amenity preserved in its entirety
• Subject to detailed design and modelling off shore ‘reefs’ may be added to further reduce erosion over area protected.
• Reefs may be visually intrusive at low tide and potential safety issue
Bid Stage
Section 1 Showing Beach Replenishment Only Section 1 Showing Optional Reefs
27 Bid Stage
Coastal Protection Design Development
A: Perspective View Showing Beach Replenishment Only A: Elevation Showing Beach Replenishment Only
Existing cliff top
Shingle beach
28
Proposed Coastal Protection strategy
DO
NOTHING
MANAGED
RETREAT
HOLD THE
LINE
Railway
Archaeological
Site
Landfill site
Bid Stage
29
Preferred Bidder Stage
• Preliminary Design and EIA
• Planning Process
• Stakeholder Management
• Contractor Input
Preferred Bidder Stage
30
Preliminary Design and EIA
• Traffic and Access (Batching Plant)
• Protected Views• Ecology (sand-martins
and sea-kale) • Archaeology (St.
Crispin’s Cell and Rathdown Castle)
• Coastal Erosion• Old Landfill• Flooding
Preferred Bidder Stage
31
Planning Process
• WCC application to ABP• CPO included in
application• Foreshore Acquisition
included, Foreshore Lease/License not required
• Dredging and reclamation included in application
• Oral Hearing in March/April 2006
• Request for Further Information in August 2006. Submitted in October 2006
• 2nd Oral Hearing in March/April 2007
• Planning Granted in August 2007
Preferred Bidder Stage
32
Stakeholder Management –Harbour users
• OPW Coastguard Facilities
• Greystones Sailing Club (HUGs)
• Greystones Rowing Club
• Sea Scouts• Ridge Anglers• Diving Club• Moorings Licences• Public (adjoining
residents, local area, wider community)
Preferred Bidder Stage
33
Stakeholder Management
• Harbour residents with real impacts
• Resistance to change –‘Victorian Feel’
• Giving Public Amenity to Private Interests
• GPDA: GreystonesProtection and Development Association
• GUBOH: Give Us Back Our Harbour (twitter @guboh)
Preferred Bidder Stage
34
Contractor Input
• Construction Methodology (by land)
• Programme• Participation in
Planning Process• Value Engineering
Preferred Bidder Stage
35
Borrow Pit
• Materials Balance• Economics of
handling/processing• Granted as part of the
planning permission
Preferred Bidder Stage
36
Detailed Design
• Planning permission granted August 2007
• Concession Agreement signed December 2007
• Detailed Design:
Breakwater Structures
Harbour & Marina
Detailed Design Stage
1. Limited modelling for reference design
2. Hand calculations & limited modelling for
bid design
3. Numerical modelling completed
4. Physical modelling (in progress when
application made)
5. Hand calculations for revised layout
Design risk:
Planning
stage
Detailed
design stage
Bid stage
38
Detailed Design
• Sispar appointed Sisk – Lagan JV for ‘Civil and Marine Works Contract’• Fixed Price D&B Contract (largely designed already)• Arup both Employer’s (Sispar) Representative and Contractor (SLJV) designer!
Detailed Design Stage
39
Breakwaters - Stability
• Design for sliding, overturning, settlement
• Granular (porous) base – Goda Equations
• ‘Free standing’ Stacks to take out differential settlements
• Grout ‘socks’ with in-situ slab
Detailed Design Stage
44
Harbour Entrance
• Reflected waves – turbulence and water depth
• ‘Porous’ roundheads
• Uplift pressures – anchor piles
Detailed Design Stage
Wave disturbance in the harbour: A solid vs a porous harbour entrance
Difference compared to original design
45
Harbour/Marina Wave Climate• Seiching (reflected standing wave) within Marina
• Sloped revetments around Marina under boardwalk
Detailed Design Stage
46
Breakwater – Design Development
• Breakwater crest height
• Curved seaward – facing wave-wall
• Wider base blocks (with voids to manage weight)
• Antifer sizes and underlying rock fill sizes
Detailed Design Stage
49
Construction Stage
• Demolitions
• Batching Plant
• Breakwater Construction
• Dredging and Reclamation
• Piling Works
• Old Landfill
• Beaches and Erosion Protection
• Value Engineering
• Statistics
Construction Stage
50
Demolitions
• Pier, Kish base, north breakwater
• Gap Bridge (cut-stone retained)
Construction Stage
51
Batching Plant (S.M. Morris)
• Agreed early and part of planning as Contractor on-board
• Flexibility in materials (concrete) delivery to site
• Tolerance on 5m x 3m x 1m blocks of 1mm
• Maximised design using pre-cast elements
• Continuous environmental monitoring
Construction Stage
52
Breakwater Construction Plan
• General Approach –land based operation
• Temporary Causeway to allow breakwater construction on 3 fronts
• Bed preparation using frames (minimize divers required)
• Work out with block stacks, return with slab
Construction Stage
54
Breakwater Construction - Reality• Issue with leading edge of Temporary Causeway
• Bed preparation – levelling frame and divers
• Vulnerability of ‘free-standing’ stacks
Construction Stage
55
Storm Damage
• September 2008• Gusting Force 9 gale• Significant damage
over 9 rows of blocks• Temporary support to
stacks inadequate• Scour protection
around base inadequate
Construction Stage
58
Storm Protection
• Timber spacer blocks• End-frame• Levelling Frame for 6
stacks• Scour protection slabs• Revetment as close as
deemed safe behind
Construction Stage
59
Breakwater Tolerances
• Diver checked
formations
• Precise levelling of bed
• Diver assisted crane
placement of blocks
• Very tight tolerances on
block placement
• Visual impact (client and
architect)
60
Dredging
• Need for floating plant• Temporary load-out
quay• Hopper barges for
transfer• Machine excavation of
boulder clay (GPS on bucket)
Construction Stage
63
Landside Earthworks
• Marine Works delay impact on sequencing
• Compaction of fill• Use of lime on wet• boulder clays
Construction Stage
64
Piling Works
• Tubular Steel Piles• Driven to set (+
minimum penetration)• Hydraulic Hammer• Anticipate Driven
Precast Piles for buildings
Construction Stage
66
Old Landfill
• No CH4, traces CO2, granular curtain
• Above water table with porous capping –all mobile containments long-since leached to sea
• Risk Assessment to leave in-situ as parkland
• Approved by WCC and ABP
Construction Stage
68
Beaches and Erosion
• Where reclaimed, shingle removed for re-use
• 10,000m3 imported shingle at start of construction
• Predicted movement pattern
Construction Stage
69
Beaches and Erosion
• Observed pattern during construction
• 6,000m3 accreted shingle relocated in 2009
• 4,500m3 accreted shingle relocated in 2012
Construction Stage
83
Statistics
• Concrete Volume 125,000 cu meters, greater than Dundrum SC
• 5,100 breakwater blocks
• 3,900 antifers
• 90,000 tons of 3-6 ton imported rock armour
• 115,000 cu metres dredging /excavation
• 203,000 cu metres reclamation fill
• Contract Value approx. €50m, €1m over tender
• Total spend on development to date circa €70million
Construction Stage
84
ConstructionCompletion
Civil & MarineWorks contractStarted March 2008Completed Feb 2011
Construction Stage
85
Acknowledgements
• Wicklow County Council – Sean Quirke
• Employer’s Rep Jacobs (now Leigh Fisher)
• Sispar – John Sisks & Park Developments
• Sisk Lagan JV (and subcontractors)
• Design Team (OMP, Broadway Malyan, Terry Durney)
• Subconsultants (COWI, DHI)
• Arup Staff (office and site)
• Greystones Public Representatives
• Greystones people
• Jimmy Quinn photography and Derek Paine books
Acknowledgements