Sisk's latest plan for Greystones Harbour, with phasing

download Sisk's latest plan for Greystones Harbour, with phasing

of 13

description

Plan for construction phasing at Greystones Harbour prepared for Sisk or their architects

Transcript of Sisk's latest plan for Greystones Harbour, with phasing

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    1/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 1Month 1 - Month 14

    36 Houses and Block O, Club Buildings and Part1 of the Public Square

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    2/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 2Month 12 - Month 24

    (PHASE 1 complete)

    21 Houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    3/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 3Month 16 - Month 28

    (PHASE 2 complete)

    53 Houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    4/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 4Month 19 - Month 32

    (PHASE 4 ongoing)

    28 Apartments, Public Square Part 2 and Public Park

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    5/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 4Month 19 - Month 32

    (PHASE 4 complete)

    28 Apartments, Public Square Part 2 and Public Park

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    6/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 5Month 18 - Month 42

    (PHASE 3 complete)

    49 Apartments and 4 houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    7/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 6Month 29 - Month 44

    (PHASE 5 complete)

    39 Apartments and 4 houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    8/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 7Month 41 - Month 55

    (PHASE 6 complete)

    41 Apartments and 6 houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    9/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 8Month 45 - Month 61

    (PHASE 7 complete)

    52 Apartments and 6 houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    10/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 9Month 38 - Month 51

    (PHASE 8 complete)

    19 houses

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    11/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    COMPLETION

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    12/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 1a5 Aug 2014 - 17 Sept 2015

  • 5/21/2018 Sisk's latest plan for Greystones Harbour, with phasing

    13/13

    architectural visualisation

    15 hazelbrook road terenure dublin 6w tel 01 4965340project:Phasing Development, Greystones

    PHASE 1b5 Aug 2014 - 17 Sept 2015