Geotechnical Completion Report - Pokeno

69
J00113 | Lander Geotechnical Consultants Limited | 11 March 2021 Geotechnical Completion Report HITCHEN BLOCK STAGES 10E AND 10F For DFH JOINT VENTURE LIMITED

Transcript of Geotechnical Completion Report - Pokeno

Page 1: Geotechnical Completion Report - Pokeno

J00113 | Lander Geotechnical Consultants Limited | 11 March 2021

Geotechnical Completion

Report

HITCHEN BLOCK STAGES 10E AND 10F

For

DFH JOINT VENTURE LIMITED

Page 2: Geotechnical Completion Report - Pokeno

Lander Geotechnical Consultants Limited Level 3, 3 Osterley Way, P O Box 97 385, Manukau, Auckland 2241 Phone: (09) 262 1528; (09) 262 1526 Email: [email protected] www.landergeotechnical.co.nz

11 March 2021 Ref No: J00113

DFH Joint Venture Limited PO Box 302 877 North Harbour 1330

Attention: Mr R Parkinson

Dear Russell

RE: Geotechnical Completion Report for Hitchen Block Stages 10E & 10F, Pokeno

This report presents all supporting geotechnical data and our Suitability Statement in relation to land

development works undertaken at the above location.

It has been prepared in accordance with instructions received from DFH Joint Venture Limited and

forms part of the documentation required by Waikato District Council to achieve certification under

Section 224(c) of the Resource Management Act.

If you have any queries or you require any further clarification on any aspects of this report, please do

not hesitate to contact the undersigned.

For and on behalf of Lander Geotechnical Consultants Limited

S.G. Lander Principal Geotechnical Engineer CMEngNZ, CPeng, IntPE(NZ)

Page 3: Geotechnical Completion Report - Pokeno

TABLE OF CONTENTS

J00113 | 11 March 2021 i

1 INTRODUCTION AND DESCRIPTION OF SUBDIVISION 1

2 RELATED REPORTS 1

3 EARTHWORKS OPERATIONS 2

3.1 Plant 2

3.2 Construction Programme 2

4 QUALITY ASSURANCE AND CONTROLS 3

4.1 Inspections 3

4.2 Quality Control 3

4.2.1 Compaction Criteria 3

4.2.2 Compaction Assurance Testing 3

5 PROJECT EVALUATION 4

5.1 Bearing Capacity and Settlement of Building Foundations 4

5.2 Expansive Soils 4

5.3 Lot Gradients 5

5.4 Fill Induced Settlement 5

5.5 Stormwater Controls 5

5.6 Service Trenches 5

5.7 Underfill Drains 6

5.8 Topsoil 6

5.9 Contractor’s Work 6

6 STATEMENT OF PROFESSIONAL OPINION AS TO THE SUITABILITY OF LAND FOR BUILDING DEVELOPMENT 6

Tables

Table 1: CivilPlan Consultants Limited As-Built Plans

Table 2: Lander Geotechnical Consultants Geotechnical Completions Reports

Table 3: Suitability Summary Statement

Appendices

Appendix 1: CivilPlan Consultants Limited As-Built Drawings

Appendix 2: Field Density Summary Sheets

Appendix 3: Soil Classification Test Results

Appendix 4: Post-Construction Borehole Records

Appendix 5: Construction Observation Records

Page 4: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 1

1 INTRODUCTION AND DESCRIPTION OF SUBDIVISION

This Geotechnical Completion Report has been prepared for DFH Joint Venture Limited as part of the

documentation required to be submitted to the Waikato District Council following residential

subdivisional development.

It contains our Suitability Statement, relevant test data and the CivilPlan Consultants Limited as-built

plan set relating to Stages 10E and 10F of the Hitchen Block Residential Subdivision as follows:

Table 1: CivilPlan Consultants Limited As-Built Plans

Title Reference No. Date

As Built Contours 136701-10-AB210 February 2021

As Built Cut-Fill Contours 136701-10-AB211 February 2021

Stormwater As Built 136701-10-AB410 January 2021

Wastewater As Built 136701-10-AB411 January 2021

This report covers the construction period February 2018 to May 2018. It is intended to be used for

certification purposes as follows:

• 39 residential lots numbered 548 to 558, 564 to 568 and 570 to 592.

• 2 new roads named Clark Rise and Leathem Crescent (part).

• 2 jointly owned access lots that provide vehicle access to lots 564 to 568, 570 and 571.

This stage of the subdivision is located as shown on the attached CivilPlan Consultants Limited as-built

plans. As can be seen on the As Built Cut-Fill Contours plan, approximately three quarters of the lots

have been partly or totally affected by filling, to a maximum depth of approximately 6m.

2 RELATED REPORTS

A Geotechnical Investigation Report on the subject land was prepared by this Consultancy, reference

J00323 (Earthworks Stage 3), dated 30 June 2016. The conclusions and recommendations of that

report have been reviewed during the preparation of this document, along with the following

Geotechnical Completion Reports (prepared by Lander Geotechnical Consultants Limited) on adjacent

recently completed stages of the subdivision which are tabulated below:

Page 5: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 2

Table 2: Lander Geotechnical Consultants Geotechnical Completion Reports

Subdivision Title Reference No. Issue Date

Hitchen Block Stage 1 (Residential) J00113 23 December 2016

Gateway Industrial Part Stage 5 (Lots 28 and 29) J00022 27 February 2017

Hitchen Block Stage 2A and 2B (Residential) J00113 14 July 2017

Hitchen Block Stage 2C and 3A (Residential) J00113 27 October 2017

Hitchen Block Stage 3A2, 3B and 3C (Residential) J00113 20 December 2017

Hitchen Block Stage 5A (Residential) J00113 26 January 2018

Hitchen Block Stage 4A (Residential) J00113 23 March 2018

Hitchen Block Stage 6A and 6B (Residential) J00113 23 May 2018

Hitchen Block Stage 4B (Residential) J00113 28 August 2018

Hitchen Block Stage 7A & 7B (Residential) J00113 2 November 2018

Hitchen Block Stage 8A & 8B (Residential) J00113 9 May 2019

Hitchen Block Stage 6D (Residential) J00113 4 November 2019

Hitchen Block Stages 11, 12 and 14 (Residential) J00113 13 March 2020

Hitchen Block Stage 9 (Residential) J00113 24 June 2020

Hitchen Block Stages 6E & 10A to 10D (Residential) J00113 16 December 2020

3 EARTHWORKS OPERATIONS

3.1 Plant

The main items of plant used by the Contractor, Kerry Dines Limited were:

• 7 x bulldozers with scoops,

• 1 x elevating motorscraper,

• 3 x articulated dump trucks,

• 2 x 4WD sheepsfoot compactors,

• 4 x 20T hydraulic excavators,

• 1 x Tractor with disc ploughs.

3.2 Construction Programme

Earthworks operations for this stage commenced in February 2018 with topsoil stripping and the

muckout of the gully which runs beneath lots 568 and 570 to 573. Following this, underfill drainage

(comprising of 160mm perforated drain coils, covered with drainage aggregate and fully wrapped with

geotextile cloth) was installed along the gully invert and fill placement commenced.

Page 6: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 3

In the surrounding areas, topsoil stripping and fill placement progressed alongside similar earthworks in

the adjacent stages of the subdivision. Bulk filling operations were completed by late May 2018,

followed by infrastructure, roading construction and topsoiling of the lots through until early 2021.

4 QUALITY ASSURANCE AND CONTROLS

4.1 Inspections

During earthworks construction, engineering observations were undertaken on a near regular basis to

assess compliance with NZS 4431 and our project specific recommendations and specifications.

Project specific inspections were required on this stage of the development for:

• Topsoil stripping of earthworks areas;

• Removal of soft sediments in the gully inverts;

• Placement of the underfill drains;

• Fill placement and plant performance upon the subgrade periodically throughout the bulk filling

works.

4.2 Quality Control

4.2.1 Compaction Criteria

Due to the varying soil types being used as filling, the compaction control criteria of minimum allowable

shear strength and maximum allowable air voids were mainly used for quality assurance purposes.

Specification details were as follows for general fills:

Minimum Shear Strength and Maximum Air Voids Method

(a) Air Voids Percentage

(As defined in NZS 4402)

Average value less than 10%

Maximum single value 12%

(b) Undrained Shear Strength

(Measured by Pilcon shear vane - calibrated using NZGS 2001 method)

Average value not less than 140 kPa

Minimum single value 120 kPa

Note: The average value shall be determined over any ten consecutive tests

4.2.2 Compaction Assurance Testing

Regular insitu density, strength and water content tests were carried out on all areas of the filling at or in

excess of the frequency recommended by NZS 4431, and a series of hand auger boreholes were also

drilled at selected locations as an added check on quality control. The results of this testing (including

testing some testing undertaken on adjacent stages of the subdivision) are appended in Appendix 2.

Page 7: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 4

5 PROJECT EVALUATION

5.1 Bearing Capacity and Settlement of Building Foundations

Following the completion of earthworks operations, we returned to the site in February 2021 and drilled

a series of hand auger boreholes in order to determine representative finished ground conditions and

hence evaluate likely foundation options for future building development.

At current subgrade levels all filled and undisturbed natural ground has a geotechnical ultimate bearing

capacity of 300 kPa within the influence of conventional shallow residential building foundation loads.

Where any building platforms have been rutted by heavy machinery subsequent to this report, or

softened due to ponded rainwater, engineering advice should be sought with a view affected areas be

trimmed back to competent ground and reinstated with compacted hardfill to design subgrade level prior

to the commencement of building construction.

It should be noted that NZS 3604 only allows a maximum backfill depth of 600mm over the building

platform of a dwelling unless an Engineering design solution or endorsement is proposed, on account of

the risk of induced consolidation of the subsoils caused by the weight of the backfill.

5.2 Expansive Soils

Two sets of Atterberg Limit expansive soil tests and two Shrink-Swell Index tests were carried out on

samples selected from around the site and within the zone of likely influence of shallow building

foundations to inform the expansive Site Class for this stage of the subdivision. Our assessment has

taken into account both the Atterberg Limit and Shrink-Swell laboratory test results.

The Atterberg Limit tests were carried out in accordance with NZS 4402, "Methods of Testing Soils for

Civil Engineering Purposes" test section 2 and were primarily intended to assess the Expansive

Classes of the site materials as defined in AS 2870, "Residential Slabs and Footings – Construction".

The Shrink-Swell Index tests were carried out in accordance with AS 1289, "Methods of Testing Soils

for Engineering Purposes" test method 7.1.1 and were primarily intended to assess the Expansive

Classes of the site materials as defined in AS 2870, "Residential Slabs and Footings – Construction".

Based on the laboratory testing and visual tactile assessments of the soils observed in our post-

construction boreholes, the Expansive Site Classes for this stage of the subdivision are S (slight) for

residential lots 579 to 583, M (moderate) for residential lots 570 to 575 and H (high) for residential lots

548 to 558, 564 to 568, 576 to 578 and 584 to 592, as defined in MBIE Acceptable Solutions and

Verification Methods amendment 191.

The characteristic surface ground movement (ys) for Expansive Site Classes S, M and H is up to 22mm,

44m and 78mm, respectively. Details relating to these Expansive Site Classes are provided in

Appendix 3, and specific design alternatives for these Site Classes are presented in the Suitability

1 Ministry of Business, Innovation and Employment. Verification Methods and Acceptable Solutions Amendment 19 for NZ Building Code B1/AS1, Section 3 (as relevant to expansive soils and good ground). Effective 28 November 2019.

Page 8: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 5

Statement. These classifications may be re-addressed by end users during building consent if site

specific laboratory shrink-swell testing is undertaken, as recommended in the MBIE document attached.

For Class H soils, if slab on-grade floor slab construction takes place during a long dry summer,

exposed building platform soils may dry put and become highly desiccated. Over time the rehydration of

the soils below the floor slab can cause swelling and floor slab uplift. Floor slab uplift can cause distress

of tile floors and in garages where cracks are more apparent. It may also rack upper storeys and/or

rooflines if non-load bearing ground floor walls are lifted and act as struts. It is prudent to place hardfill

immediately upon completion of subgrade trimming, followed by thorough soaking of the hardfill prior to

concrete placement (e.g. for slab on-grade construction), all of which can help to limit the problem.

5.3 Lot Gradients

The appended as built contours plan shows areas having gradients steeper than 1(v) in 4(h) or being

immediately adjacent to land having such gradients. The extent of these areas has been determined by

the surveyed site gradients and our final walkover inspection, but there may be localised areas having

such gradients that have not been shown on the plans.

We are satisfied that these lots are not subject to the hazards described in section 71(3) of the Building

Act.

Details of resulting building and earthworks restrictions within the vicinity of these lots are presented in

the Suitability Statement.

5.4 Fill Induced Settlement

As a result of our pre-fill inspections, the installation of subsoil drainage, quality control testing and the

elapsed time since the placement of the majority of the filling (i.e. in excess of 12 months), we are of the

opinion that induced differential settlements beneath or within the certified filling due to its imposed

weight should be insignificant with respect to conventional NZS 3604 residential building development.

5.5 Stormwater Controls

It is important on all sloping lots that due care is paid to the design and construction of appropriate

stormwater disposal systems. These systems should serve to collect all runoff from roofs, decks and

paved areas, together with discharges from retaining wall drains and other subsoil drains and should

connect directly into the public stormwater drainage network.

Uncontrolled stormwater discharges onto the ground surface can cause erosion, scour and/or instability

on sloping land and should not be permitted under any circumstances where stability could be

compromised.

5.6 Service Trenches

As is normal on all subdivisions, building developments involving foundations within a 45° zone of

influence from pipe inverts will require Engineering input.

Page 9: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 6

5.7 Underfill Drains

The appended fill as-built cut-fill contour plans show the alignments of perforated underfill drains that

were placed in mucked out gully inverts prior to filling to tap groundwater seepages. These drains run

beneath portions of residential Lots 568 and 570 to 573.

These drains were intended to intercept localised groundwater seepages during earthworks and/or

allow engineered fill placement as required by the project specifications. The drains were installed as a

precautionary measure, not as remedial works for any existing instability, and they need no specific

maintenance.

Notwithstanding, it is recommended that future foundations or site development works preserve these

drains. In the event that they are compromised by any future development in any of the lots they should

be reinstated under geotechnical engineering observational guidance.

5.8 Topsoil

Topsoil depths in likely building platform areas were checked by the drilling of a borehole in the

approximate centre of lot. Our findings, which are indicative only and subject to variation at other

locations, show that likely topsoil depths are between 100 mm and 200 mm. Site specific findings are

presented in the Suitability Statement Summary.

5.9 Contractor’s Work

We have relied on the Contractor’s work practices and assume that the works have been carried out in

accordance with:

(i) The approved Contract drawings and design details,

(ii) The approved Contract specifications,

(iii) Authorised Variations to (i) and (ii) during the execution of the works,

(iv) The conditions of Resource, Earthworks and Building Consents where applicable,

(v) The relevant Lander Geotechnical Consultants Limited reports, recommendations and site

instructions,

and that all as-built information and other details provided to the Client and/or Lander Geotechnical

Consultants Limited are accurate and correct in all respects.

6 STATEMENT OF PROFESSIONAL OPINION AS TO THE SUITABILITY OF

LAND FOR BUILDING DEVELOPMENT

I, S.G. Lander, of Lander Geotechnical Consultants Limited, Auckland, hereby confirm that:

1. I am a Chartered Professional Engineer experienced in the field of geotechnical engineering as

defined in section 1.2.3 of NZS 4404 and was retained by the Owner/Developer as the Geotechnical

Engineer on Stages 10E and 10F of the Hitchen Block residential subdivision.

2. The extent of preliminary investigations carried out to date are described in Geotechnical

Investigation Report reference J00323, dated 30 June 2016, and the conclusions and

recommendations of that document have been re-evaluated in the preparation of this report. The

Page 10: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 7

results of all tests carried out under Lander Geotechnical Consultants Limited direction are

appended.

3. In my professional opinion, not to be construed as a guarantee, I consider that:

(a) The earth fills shown on the appended fill as-built plan have been placed in compliance with NZS

4431 and related documents.

(b) The completed earthworks give due regard to land slope and foundation stability considerations

within the residential lots, however, as shown on the appended contour as-built plan, lots 548 to

551, 564, 565, 568, 570 to 578 and 588 to 590 have gradients steeper than 1(v) in 4(h).

Any building development and/or earthworks proposals within the areas shown to be steeper

than 1(v) in 4(h) on the as-built contours plan are subject to specific geotechnical investigations

and/or foundation design.

(c) The function of the underfill drains should not be impaired by any building development or

landscaping works. In particular, any bored or driven piles must be positioned to avoid damaging

the underfill drains. The drains are shown pass under portions of residential Lots 568 and 570 to

573 at depths typically greater than 1m below existing ground level and therefore should not

adversely affect shallow foundation systems (dependant on final earthworks proposals). Further

comments relating to these drains is provided in the suitability statement summary.

(d) A geotechnical ultimate bearing capacity of 300 kPa may be assumed for foundation design on

all lots (except where specific geotechnical endorsement is required on account of sloping land

greater than 1(v in 4(h)).

Where a geotechnical bearing capacity greater than 300 kPa is required, (i.e. outside the limits of

NZS 3604, such as when piling is undertaken), further specific site investigation and design of

foundations should be carried out prior to building consent application.

(e) The backfilling and compaction of the stormwater and sanitary sewer trenches on this subdivision

has where possible been carried out to appropriate standards having regard for the prevailing

ground conditions and associated compaction induced pipe loadings.

(f) The assessed Expansive Site Class in terms of MBIE Acceptable Solutions and Verifications

Methods for NZ Building Code Clause B1 Structure, effective 28 November 2019, is S (slight) for

lots 579 to 583, M (moderate) for lots 570 to 575, and H (high) for lots 548 to 558, 564 to 568,

576 to 578 and 584 to 592. The characteristic surface ground movement for these Site Classes is

up to 22mm (Class S), 44mm (Class M) and 78mm (Class H), respectively in regard to the above

standard. Site specific laboratory testing may be undertaken by end-users to re-assess the

expansive site class during building consent stage.

(g) Subject to the geotechnical limitations, restrictions, recommendations and expansive soil

assessments associated with 3(b) to 3(f) above:

(i) The filled and undisturbed original ground within residential lot boundaries is generally

suitable for residential buildings constructed in accordance with NZS 3604 and related

documents.

(ii) On residential lots 579 to 583 foundation design may be carried out in accordance with Class

S (in terms of MBIE Acceptable Solutions and Verifications Methods for NZ Building Code

Clause B1 Structure, effective 28 November 2019) or alternatively, a specific foundation and

Page 11: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 8

structural design may be undertaken by a Chartered Professional Engineer who should allow

for expansive soil effects referenced above in the design.

For buildings having brittle exterior cladding appropriate control joints should also be

specifically designed depending on architectural specifications and structural form.

(iii) On residential lots 570 to 575 foundation design may be carried out in accordance with Class

M (in terms of MBIE Acceptable Solutions and Verifications Methods for NZ Building Code

Clause B1 Structure, effective 28 November 2019) or alternatively, a specific foundation and

structural design may be undertaken by a Chartered Professional Engineer who should allow

for expansive soil effects referenced above in the design.

For buildings having brittle exterior cladding appropriate control joints should also be

specifically designed depending on architectural specifications and structural form.

(iv) On residential lots 548 to 558, 564 to 568, 576 to 578 and 584 to 592 foundation design may

be carried out in accordance with Class H (in terms of MBIE Acceptable Solutions and

Verifications Methods for NZ Building Code Clause B1 Structure, effective 28 November

2019) or alternatively, a specific foundation and structural design may be undertaken by a

Chartered Professional Engineer who should allow for expansive soil effects referenced

above in the design.

For buildings having brittle exterior cladding appropriate control joints should also be

specifically designed depending on architectural specifications and structural form.

4. Road subgrades and lot accessway subgrades have been formed having due regard for slope

stability and settlement, available subgrade strengths are dependent on-site conditions and on

construction trafficking and variable results should be expected.

The professional opinion contained within this report is furnished to the Waikato District Council and

DFH Joint Venture Limited for their purposes alone, with respect to the particular brief given to us. It

may not be relied upon in any other context of for any other purpose without our prior review and

agreement. It does not remove the necessity for the normal inspection of site conditions at the time of

erection of any dwelling.

The appended table summarises the status of each residential lot covered by this Suitability Statement.

For and on behalf of Lander Geotechnical Consultants Limited

Prepared by: Reviewed By: Authorised by:

K. Meffan C.J. Edwards S.G. Lander Engineering Geologist Senior Engineering Geologist Principal Geotechnical Engineer MEngNZ CMEngNZ (PEngGeol) CMEngNZ, CPeng, IntPE(NZ)

Page 12: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 9

Table 3: Suitability Statement Summary

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

548 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

549 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

550 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

551 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

552 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

553 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

554 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

Page 13: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 10

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

555 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

556 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

557 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

558 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

564 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

565 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

566 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

567 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

Page 14: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 11

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

568 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

Function of underfill drains to be maintained (refer Section 5.7 and 6(3c) for further details). Any cuts deeper than 1m to be assessed by geotechnical engineer as underfill drain may be intercepted and require re-alignment under engineering direction, dependant on final development/earthworks proposals.

100 300 H

570 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

Function of underfill drains to be maintained (refer Section 5.7 and 6(3c) for further details).

200 300 M

571 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

Function of underfill drains to be maintained (refer Section 5.7 and 6(3c) for further details).

200 300 M

572 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

Function of underfill drains to be maintained (refer Section 5.7 and 6(3c) for further details).

200 300 M

Page 15: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 12

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

573 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

Function of underfill drains to be maintained (refer Section 5.7 and 6(3c) for further details).

200 300 M

574 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 M

575 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 M

576 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

577 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

Page 16: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 13

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

578 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

579 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 S

580 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 S

581 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 S

582 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 S

583 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 S

584 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

200 300 H

585 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

586 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

587 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

Page 17: Geotechnical Completion Report - Pokeno

Geotechnical Completion Report (this report must be read and/or reproduced in its entirety)

J00113 | 11 March 2021 14

Lot No.

Comments Topsoil Depth (mm)

Ultimate Bearing

(kPa)

Expansive Site

Class (B1/AS1)

588 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

589 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

590 Specific site investigation, foundation design and construction inspections required in area shown hatched on gradient as-built plan due to 1(v) in 4(h) gradient restrictions.

Elsewhere, Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

591 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

592 Foundation design in accordance with MBIE Acceptable Solutions and Verifications Methods for NZ Building Code Clause B1 Structure or engineer approved alternative foundation design.

100 300 H

Page 18: Geotechnical Completion Report - Pokeno

Appendix 1 CivilPlan Consultants Limited As-Built Plans

Page 19: Geotechnical Completion Report - Pokeno

10E10F

Harriet_Johnston_Drive

Hitc

hen_

Road

Leathem_Crescent

N

Hale_Court

Clark_Rise

NOTES1. ALL LEVELS ARE IN METRES AND IN TERMS OF THE LANDS& SURVEY DATUM (MEAN SEA LEVEL) AUCKLAND 1945.2. CONTOUR INTERVAL IS 1m3. CONTOURS ACCURACY IS + OR - 0.5m

LEGEND

MAJOR 5m CONTOURMINOR 1m CONTOURLAND STEEPER THAN 1:4

I, MICHAEL STEPHEN SMITH, CMENGNZ CPENG HEREBYBELIEVE ON ALL REASONABLE GROUNDS THAT THE CONTOURSSHOWN ARE ACCURATELY PLOTTED IN RELATION TOBOUNDARIES AS THIS INFORMATION HAS BEEN PROVIDED BYTHE CONTRACTOR OF THE WORKS - KERRY DINES LTD.

--------------- -----MICHAEL STEPHEN SMITH DATECMENGNZ CPENG

DRAWN:

APPROVED:DATE:

DATE:

DATE:PLOTTED: THIS DRAWING AND DESIGN REMAINS THE PROPERTYOF, AND MAY NOT BE REPRODUCED OR ALTERED,WITHOUT THE WRITTEN PERMISSION OF CIVILPLANCONSULTANTS LIMITED. NO LIABILITY SHALL BEACCEPTED FOR UNAUTHORISED USE OF THIS DRAWING.RJP 2-21

MSS 2-21

RJP 2-21

BY DATEREVISION DETAILSREVA ISSUED FOR 224C RJP 1-21

Filepath: P\APPDATA\LOCAL\AUTODESK\C3D 2020\ENU\TEMPLATE C:\DATA\POKENO\HITCHEN\STAGE 10\AS BUILTS\136701-10E-AB210.DWG

SHEET TITLE:

AS BUILT CONTOURS

PROJECT TITLE:

DFH JOINT VENTUREHITCHEN STAGES 10E,10F

POKENOLevel 9, Laidlaw House, 20 Amersham Way, Manukau, Auckland. Phone: 09 222 2445

CIVILPL NCONSUL TA TSN

DRAWING NUMBER: REV:

ISSUE STATUS:

136701-10-AB210 A

AS BUILT

0 10 20 30 40 50mSCALE BAR1:1000@A3

SCALE: (A1/A3) 1:500 / 1:1000

AutoCAD SHX Text
570
AutoCAD SHX Text
568
AutoCAD SHX Text
577
AutoCAD SHX Text
579
AutoCAD SHX Text
582
AutoCAD SHX Text
580
AutoCAD SHX Text
591
AutoCAD SHX Text
536
AutoCAD SHX Text
545
AutoCAD SHX Text
544
AutoCAD SHX Text
550
AutoCAD SHX Text
551
AutoCAD SHX Text
549
AutoCAD SHX Text
565
AutoCAD SHX Text
571
AutoCAD SHX Text
548
AutoCAD SHX Text
575
AutoCAD SHX Text
543
AutoCAD SHX Text
573
AutoCAD SHX Text
586
AutoCAD SHX Text
574
AutoCAD SHX Text
572
AutoCAD SHX Text
566
AutoCAD SHX Text
584
AutoCAD SHX Text
576
AutoCAD SHX Text
589
AutoCAD SHX Text
564
AutoCAD SHX Text
587
AutoCAD SHX Text
567
AutoCAD SHX Text
531
AutoCAD SHX Text
532
AutoCAD SHX Text
535
AutoCAD SHX Text
592
AutoCAD SHX Text
590
AutoCAD SHX Text
530
AutoCAD SHX Text
527
AutoCAD SHX Text
528
AutoCAD SHX Text
585
AutoCAD SHX Text
583
AutoCAD SHX Text
534
AutoCAD SHX Text
533
AutoCAD SHX Text
539
AutoCAD SHX Text
540
AutoCAD SHX Text
541
AutoCAD SHX Text
542
AutoCAD SHX Text
588
AutoCAD SHX Text
546
AutoCAD SHX Text
529
AutoCAD SHX Text
581
AutoCAD SHX Text
578
AutoCAD SHX Text
537
AutoCAD SHX Text
1
AutoCAD SHX Text
DP321866
AutoCAD SHX Text
2
AutoCAD SHX Text
DP176205
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
2
AutoCAD SHX Text
DP206719
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
556
AutoCAD SHX Text
555
AutoCAD SHX Text
552
AutoCAD SHX Text
558
AutoCAD SHX Text
553
AutoCAD SHX Text
554
AutoCAD SHX Text
557
AutoCAD SHX Text
DRAINAGE_RESERVE
AutoCAD SHX Text
55
AutoCAD SHX Text
50
AutoCAD SHX Text
54
AutoCAD SHX Text
53
AutoCAD SHX Text
52
AutoCAD SHX Text
51
AutoCAD SHX Text
50
AutoCAD SHX Text
49
AutoCAD SHX Text
48
AutoCAD SHX Text
47
AutoCAD SHX Text
46
AutoCAD SHX Text
45
AutoCAD SHX Text
44
AutoCAD SHX Text
55
AutoCAD SHX Text
55
AutoCAD SHX Text
54
AutoCAD SHX Text
53
AutoCAD SHX Text
52
AutoCAD SHX Text
51
AutoCAD SHX Text
50
AutoCAD SHX Text
58
AutoCAD SHX Text
59
AutoCAD SHX Text
60
AutoCAD SHX Text
61
AutoCAD SHX Text
62
AutoCAD SHX Text
63
AutoCAD SHX Text
64
AutoCAD SHX Text
65
AutoCAD SHX Text
66
AutoCAD SHX Text
67
AutoCAD SHX Text
68
AutoCAD SHX Text
48
AutoCAD SHX Text
49
AutoCAD SHX Text
50
AutoCAD SHX Text
60
AutoCAD SHX Text
59
AutoCAD SHX Text
58
AutoCAD SHX Text
57
AutoCAD SHX Text
57
AutoCAD SHX Text
56
AutoCAD SHX Text
56
AutoCAD SHX Text
55
AutoCAD SHX Text
56
Page 20: Geotechnical Completion Report - Pokeno

10E10F

Harriet_Johnston_Drive

Hitc

hen_

Road

Leathem_Crescent

N

Hale_Court

Clark_Rise

NOTES1. ALL LEVELS ARE IN METRES AND IN TERMS OF THE LANDS& SURVEY DATUM (MEAN SEA LEVEL) AUCKLAND 1945.2. CONTOUR INTERVAL IS 1m3. CONTOURS ACCURACY IS + OR - 0.5m

I, MICHAEL STEPHEN SMITH, CMENGNZ CPENG HEREBYBELIEVE ON ALL REASONABLE GROUNDS THAT THE CONTOURSSHOWN ARE ACCURATELY PLOTTED IN RELATION TOBOUNDARIES AS THIS INFORMATION HAS BEEN PROVIDED BYTHE CONTRACTOR OF THE WORKS - KERRY DINES LTD.

--------------- -----MICHAEL STEPHEN SMITH DATECMENGNZ CPENG

LEGENDUNDERFILL DRAINMAJOR 5m CONTOURMINOR 1m CONTOURFILL AREAS

3 21

4

-8 -9

-1

-2-3-4

-9

-9

-7-6-5-4-3-2-1

1234

5

6

-1-2

1

12

-1-2

-31

1

-1-2

-1

-5

-1

DRAWN:

APPROVED:DATE:

DATE:

DATE:PLOTTED: THIS DRAWING AND DESIGN REMAINS THE PROPERTYOF, AND MAY NOT BE REPRODUCED OR ALTERED,WITHOUT THE WRITTEN PERMISSION OF CIVILPLANCONSULTANTS LIMITED. NO LIABILITY SHALL BEACCEPTED FOR UNAUTHORISED USE OF THIS DRAWING.RJP 2-21

MSS 2-21

RJP 2-21

BY DATEREVISION DETAILSREVA ISSUED FOR 224C RJP 1-21

Filepath: P\APPDATA\LOCAL\AUTODESK\C3D 2020\ENU\TEMPLATE C:\DATA\POKENO\HITCHEN\STAGE 10\AS BUILTS\136701-10E-AB211.DWG

SHEET TITLE:

AS BUILT CUT-FILL CONTOURS

PROJECT TITLE:

DFH JOINT VENTUREHITCHEN STAGES 10E,10F

POKENOLevel 9, Laidlaw House, 20 Amersham Way, Manukau, Auckland. Phone: 09 222 2445

CIVILPL NCONSUL TA TSN

DRAWING NUMBER: REV:

ISSUE STATUS:

136701-10-AB211 A

AS BUILT

0 10 20 30 40 50mSCALE BAR1:1000@A3

SCALE: (A1/A3) 1:500 / 1:1000

AutoCAD SHX Text
570
AutoCAD SHX Text
568
AutoCAD SHX Text
577
AutoCAD SHX Text
579
AutoCAD SHX Text
582
AutoCAD SHX Text
580
AutoCAD SHX Text
591
AutoCAD SHX Text
536
AutoCAD SHX Text
545
AutoCAD SHX Text
544
AutoCAD SHX Text
550
AutoCAD SHX Text
551
AutoCAD SHX Text
549
AutoCAD SHX Text
565
AutoCAD SHX Text
571
AutoCAD SHX Text
548
AutoCAD SHX Text
575
AutoCAD SHX Text
543
AutoCAD SHX Text
573
AutoCAD SHX Text
586
AutoCAD SHX Text
574
AutoCAD SHX Text
572
AutoCAD SHX Text
566
AutoCAD SHX Text
584
AutoCAD SHX Text
576
AutoCAD SHX Text
589
AutoCAD SHX Text
564
AutoCAD SHX Text
587
AutoCAD SHX Text
567
AutoCAD SHX Text
531
AutoCAD SHX Text
532
AutoCAD SHX Text
535
AutoCAD SHX Text
592
AutoCAD SHX Text
590
AutoCAD SHX Text
530
AutoCAD SHX Text
527
AutoCAD SHX Text
528
AutoCAD SHX Text
585
AutoCAD SHX Text
583
AutoCAD SHX Text
534
AutoCAD SHX Text
533
AutoCAD SHX Text
539
AutoCAD SHX Text
540
AutoCAD SHX Text
541
AutoCAD SHX Text
542
AutoCAD SHX Text
588
AutoCAD SHX Text
546
AutoCAD SHX Text
529
AutoCAD SHX Text
581
AutoCAD SHX Text
578
AutoCAD SHX Text
537
AutoCAD SHX Text
1
AutoCAD SHX Text
DP321866
AutoCAD SHX Text
2
AutoCAD SHX Text
DP176205
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
2
AutoCAD SHX Text
DP206719
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
556
AutoCAD SHX Text
555
AutoCAD SHX Text
552
AutoCAD SHX Text
558
AutoCAD SHX Text
553
AutoCAD SHX Text
554
AutoCAD SHX Text
557
AutoCAD SHX Text
DRAINAGE_RESERVE
Page 21: Geotechnical Completion Report - Pokeno

10E10F

Harriet_Johnston_Drive

Hitc

hen_

Road

Leathem_Crescent

N

Hale_Court

Clark_Rise

NOTES1. ALL COORDINATES ARE IN METRES AND IN TERMS OFGEODETIC 2000 MT. EDEN

2. ALL LEVELS ARE IN METRES AND IN TERMS OF THE LANDSAND SURVEY DATUM (MEAN SEA LEVEL) AUCKLAND 1946

3. ALL LOT CONNECTIONS ARE 100NB PVC UNLESS SHOWNOTHERWISE.

4. MANHOLE INVERT LEVELS ARE LISTED CLOCKWISE FROMTHE OUTLET PIPE.

5. ALL MANHOLES ARE 1050NB WITH STANDARD DUTYLIDS AND COVERS UNLESS SHOWN OTHERWISE.ALL STORMWATER PIPES 225NB AND OVER ARE RCRRJ CLASS 2UNLESS SHOWN OTHERWISE EXCEPT FOR CATCHPIT LEADSWHICH ARE ALL CLASS 4. ALL CATCHPIT LEADS ARE 225NBUNLESS SHOWN OTHERWISE.

6. ALL CONCRETE PIPES AND STRUCTURES AREMANUFACTURED BY HYNDS PIPES. ALL PLASTIC PIPES AREMANUFACTURED BY MARLEY.

I, MICHAEL STEPHEN SMITH, CMENGNZ CPENG HEREBY BELIEVEON ALL REASONABLE GROUNDS THAT THE PIPE SIZES,FITTINGS, POSITIONS, COORDINATES AND LEVELS SHOWN AREACCURATELY PLOTTED IN RELATION TO BOUNDARIES AND ISCORRECT AS THIS INFORMATION HAS BEEN PROVIDED BY THECONTRACTOR OF THE WORKS - KERRY DINES LTD.

--------------- -----MICHAEL STEPHEN SMITH DATECMENGNZ, CPENG

LEGEND MANHOLE OUTLET CATCHPIT SW LINE

EX.MANHOLE EX.CATCHPIT EX.SW LINE

1.4

2.4

1.3

5.6

1.54.3

1.9

1.8

2.5

3.9

3.46.0

4.5

1.6

2.13.5

2.5

1.3

1.3 1.4

2.1

4.4

2.1

3.8

3.3

1.6

1.62.0

1.6

2.6

2.5

3.3

3.5

2.5

2.4

3.5

1.8

3.3

1.3

3.1

3.1

4.5

2.3

3.6

3.2

2.9

3.9

3.6

6.1

3.1

3.21.8

1.8

1.8

2.1

2.0

2.9

2.0

2.1

2.3

2.3

2.5

3.5

2.4

2.5

2.4

2.6

2.4

2.2 5.3

1.6

1.7

4.4

1.74.6

1.5

5.2

1.4

1.3

1.9

4.0

2.31.5

1.7

2.4

3.3

2.5

1.5

1.6

2.6

11.4

1.7

10.3

1.8

1.6

2.0

3.5DRAWN:

APPROVED:DATE:

DATE:

DATE:PLOTTED: THIS DRAWING AND DESIGN REMAINS THE PROPERTYOF, AND MAY NOT BE REPRODUCED OR ALTERED,WITHOUT THE WRITTEN PERMISSION OF CIVILPLANCONSULTANTS LIMITED. NO LIABILITY SHALL BEACCEPTED FOR UNAUTHORISED USE OF THIS DRAWING.RJP 1-21

MSS 1-21

RJP 1-21

BY DATEREVISION DETAILSREVA ISSUED FOR 224C RJP 1-21

Filepath: P\APPDATA\LOCAL\AUTODESK\C3D 2020\ENU\TEMPLATE C:\DATA\POKENO\HITCHEN\STAGE 10\AS BUILTS\136701-10E-AB410.DWG

SHEET TITLE:

AS BUILT STORMWATER DRAINAGE

PROJECT TITLE:

DFH JOINT VENTUREHITCHEN STAGES 10E,10F

POKENOLevel 9, Laidlaw House, 20 Amersham Way, Manukau, Auckland. Phone: 09 222 2445

CIVILPL NCONSUL TA TSN

DRAWING NUMBER: REV:

ISSUE STATUS:

136701-10-AB410 A

AS BUILT

0 10 20 30 40 50mSCALE BAR1:1000@A3

SCALE: (A1/A3) 1:500 / 1:1000

AutoCAD SHX Text
570
AutoCAD SHX Text
568
AutoCAD SHX Text
577
AutoCAD SHX Text
579
AutoCAD SHX Text
582
AutoCAD SHX Text
580
AutoCAD SHX Text
591
AutoCAD SHX Text
536
AutoCAD SHX Text
545
AutoCAD SHX Text
544
AutoCAD SHX Text
550
AutoCAD SHX Text
551
AutoCAD SHX Text
549
AutoCAD SHX Text
565
AutoCAD SHX Text
571
AutoCAD SHX Text
548
AutoCAD SHX Text
575
AutoCAD SHX Text
543
AutoCAD SHX Text
573
AutoCAD SHX Text
586
AutoCAD SHX Text
574
AutoCAD SHX Text
572
AutoCAD SHX Text
566
AutoCAD SHX Text
584
AutoCAD SHX Text
576
AutoCAD SHX Text
589
AutoCAD SHX Text
564
AutoCAD SHX Text
587
AutoCAD SHX Text
567
AutoCAD SHX Text
531
AutoCAD SHX Text
532
AutoCAD SHX Text
535
AutoCAD SHX Text
592
AutoCAD SHX Text
590
AutoCAD SHX Text
530
AutoCAD SHX Text
527
AutoCAD SHX Text
528
AutoCAD SHX Text
585
AutoCAD SHX Text
583
AutoCAD SHX Text
534
AutoCAD SHX Text
533
AutoCAD SHX Text
539
AutoCAD SHX Text
540
AutoCAD SHX Text
541
AutoCAD SHX Text
542
AutoCAD SHX Text
588
AutoCAD SHX Text
546
AutoCAD SHX Text
529
AutoCAD SHX Text
581
AutoCAD SHX Text
578
AutoCAD SHX Text
537
AutoCAD SHX Text
1
AutoCAD SHX Text
DP321866
AutoCAD SHX Text
2
AutoCAD SHX Text
DP176205
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
2
AutoCAD SHX Text
DP206719
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
556
AutoCAD SHX Text
555
AutoCAD SHX Text
552
AutoCAD SHX Text
558
AutoCAD SHX Text
553
AutoCAD SHX Text
554
AutoCAD SHX Text
557
AutoCAD SHX Text
563
AutoCAD SHX Text
562
AutoCAD SHX Text
DRAINAGE_RESERVE
AutoCAD SHX Text
STAGE_13
AutoCAD SHX Text
EX.MH13.4 LL46.38 IL43.54 IL45.06
AutoCAD SHX Text
EX.MH11.1
AutoCAD SHX Text
CON579 IL51.57
AutoCAD SHX Text
CON578 IL51.64
AutoCAD SHX Text
EX.MH10.1 LL52.46 IL49.08 IL49.10 IL49.84 IL49.23
AutoCAD SHX Text
CON580 IL51.28
AutoCAD SHX Text
EX.MH10.2
AutoCAD SHX Text
CON581 IL51.72
AutoCAD SHX Text
CON582 IL52.48
AutoCAD SHX Text
CON583 IL53.39
AutoCAD SHX Text
CON584 IL54.19
AutoCAD SHX Text
CON585 IL55.46
AutoCAD SHX Text
CON587 IL55.51
AutoCAD SHX Text
EX.MH10.3
AutoCAD SHX Text
CON588 IL55.86
AutoCAD SHX Text
CON589 IL55.88
AutoCAD SHX Text
CON590 IL56.29
AutoCAD SHX Text
CON591 IL57.39
AutoCAD SHX Text
CON592 IL57.22
AutoCAD SHX Text
MH12.1 LL IL52.08 IL53.43 IL52.16
AutoCAD SHX Text
375NB_RCRRJ 49.0m
AutoCAD SHX Text
DCP27 LL55.11 IL53.97
AutoCAD SHX Text
300NB RCRRJ 14.6m
AutoCAD SHX Text
MH13.5 1200 MHLL IL46.65 IL49.50 IL48.84 IL46.84
AutoCAD SHX Text
300NB_RCRRJ 131.3m
AutoCAD SHX Text
CON577 IL46.99
AutoCAD SHX Text
CON576 IL47.59
AutoCAD SHX Text
CON575 IL47.46
AutoCAD SHX Text
CON574 IL47.92
AutoCAD SHX Text
CON573 IL48.37
AutoCAD SHX Text
CON572 IL47.96
AutoCAD SHX Text
MH13.6 LL IL46.96 IL47.06
AutoCAD SHX Text
225NB RCRRJ 13.0m
AutoCAD SHX Text
375NB_RCRRJ 84.5m
AutoCAD SHX Text
MH12.2 LL IL53.72 IL53.83 IL54.79 IL53.90
AutoCAD SHX Text
CP26 LL56.09 IL54.94
AutoCAD SHX Text
CP25 LL56.09 IL54.99
AutoCAD SHX Text
225NB 10.2m
AutoCAD SHX Text
225NB 4.3m
AutoCAD SHX Text
375NB_RCRRJ 24.2m
AutoCAD SHX Text
MH12.3 LL IL54.13 IL54.54 IL54.27
AutoCAD SHX Text
225NB_RCRRJ 18.5m
AutoCAD SHX Text
BC586 IL55.40
AutoCAD SHX Text
CON586 IL55.64
AutoCAD SHX Text
375NB_RCRRJ 45.7m
AutoCAD SHX Text
MH12.4 LL IL55.04 IL55.77 IL55.62 IL55.12 IL56.08
AutoCAD SHX Text
CP21 LL57.26 IL56.12
AutoCAD SHX Text
CP22 LL57.28 IL55.83
AutoCAD SHX Text
225NB 6.8m
AutoCAD SHX Text
225NB 14.1m
AutoCAD SHX Text
CON558 IL56.33
AutoCAD SHX Text
CON556 IL57.78
AutoCAD SHX Text
CON555 IL58.39
AutoCAD SHX Text
CON554 IL59.00
AutoCAD SHX Text
300NB_RCRRJ 67.7m
AutoCAD SHX Text
CP19 LL59.95 IL58.80
AutoCAD SHX Text
CP20 LL59.92 IL58.81
AutoCAD SHX Text
225NB 6.6m
AutoCAD SHX Text
225NB 14.0m
AutoCAD SHX Text
MH12.5 LL IL57.80 IL58.59 IL58.60 IL57.92 IL58.82
AutoCAD SHX Text
225NB_RCRRJ 43.7m
AutoCAD SHX Text
CON553 IL60.10
AutoCAD SHX Text
MH12.6 LL IL60.17 IL60.30 IL60.25 IL60.66
AutoCAD SHX Text
CON552 IL60.92
AutoCAD SHX Text
225NB_RCRRJ 35.8m
AutoCAD SHX Text
CON551 IL61.10
AutoCAD SHX Text
CON550 IL61.02
AutoCAD SHX Text
BC550 IL60.51
AutoCAD SHX Text
225NB_RCRRJ 21.9m
AutoCAD SHX Text
MH12.7 LL IL62.33 IL63.27 IL63.69 IL63.60
AutoCAD SHX Text
CON710 IL63.91
AutoCAD SHX Text
BC549 IL63.51
AutoCAD SHX Text
CON549 IL64.41
AutoCAD SHX Text
150NB_PVC 21.1m
AutoCAD SHX Text
CON548 IL64.45
AutoCAD SHX Text
CON570 IL49.44
AutoCAD SHX Text
CON571 IL52.38
AutoCAD SHX Text
BC571 IL51.45
AutoCAD SHX Text
150NB_PVC_14.7m
AutoCAD SHX Text
MH13.7 LL IL47.24 IL47.34
AutoCAD SHX Text
MH13.8 LL IL48.90 IL49.63 IL49.03
AutoCAD SHX Text
225NB_RCRRJ 18.5m
AutoCAD SHX Text
CON566 IL48.49
AutoCAD SHX Text
CON563 IL49.93
AutoCAD SHX Text
CON562 IL49.66
AutoCAD SHX Text
225NB_RCRRJ 36.5m
AutoCAD SHX Text
BC13.9 IL49.33
AutoCAD SHX Text
150NB_PVC_22.4m
AutoCAD SHX Text
CON567 IL52.72
AutoCAD SHX Text
BC567 IL52.16
AutoCAD SHX Text
150NB_PVC_26.0m
AutoCAD SHX Text
MH14.1 LL43.90 IL42.23 IL42.43
AutoCAD SHX Text
OUT14.0 IL42.17
AutoCAD SHX Text
CON568 IL43.20
AutoCAD SHX Text
MH14.2 LL48.02 IL45.97 IL46.11
AutoCAD SHX Text
CON565 IL47.59
AutoCAD SHX Text
CON564 IL47.84
AutoCAD SHX Text
BC14.3 IL46.81
AutoCAD SHX Text
150NB_PVC_24.9m
AutoCAD SHX Text
150NB_PVC_23.9m
AutoCAD SHX Text
225NB RCRRJ 4.9m
Page 22: Geotechnical Completion Report - Pokeno

10E10F

Harriet_Johnston_Drive

Hitc

hen_

Road

Leathem_Crescent

N

Hale_Court

Clark_Rise

I, MICHAEL STEPHEN SMITH, CMENGNZ CPENG HEREBY BELIEVE ON ALLREASONABLE GROUNDS THAT THE PIPE SIZES, FITTINGS, POSITIONS,COORDINATES AND LEVELS SHOWN ARE ACCURATELY PLOTTED INRELATION TO BOUNDARIES AND IS CORRECT AS THIS INFORMATION HASBEEN PROVIDED BY THE CONTRACTOR OF THE WORKS - KERRY DINESLTD.

--------------- -----MICHAEL STEPHEN SMITH DATECMENGNZ CPENG

LEGEND MANHOLE WW LINE

EX.MANHOLE EX.WW LINE

NOTES

1. ALL COORDINATES ARE IN METRES AND IN TERMS OF GEODETIC 2000 MT. EDEN

2. ALL LEVELS ARE IN METRES AND IN TERMS OF THE LANDS AND SURVEY DATUM(MEAN SEA LEVEL) AUCKLAND 1946

3. ALL LOT CONNECTIONS ARE 100NB PVC UNLESS SHOWN OTHERWISE.

4. MANHOLE INVERT LEVELS ARE LISTED CLOCKWISE FROM THE OUTLET PIPE.

5. ALL MANHOLES ARE 1050NB WITH STANDARD DUTYLIDS AND COVERS UNLESS SHOWN OTHERWISE.

6. ALL PIPES ARE MANUFACTURED BY MARLEY AND MANHOLES BY HYNDS PIPES.

1.5

2.5

3.1

1.8

2.0

1.5

2.1

2.8

2.7 2.8

5.0

3.0

1.0

3.4

1.8

5.3

2.2

4.5

2.0

4.0

2.0

3.2

2.9

2.6

2.3

2.7

5.2

2.4

2.4

1.3

2.6 1.5

1.8 2.6

6.3

2.81.6

1.5 2.5

2.9

2.3

4.0

2.6

4.4

2.7

4.8

5.2

2.8

1.6

2.0

3.6

1.8

2.4

4.6

2.1

5.0

5.6

2.1

2.4

8.21.0

1.4

3.1

3.1

1.9

1.2

2.61.4

1.5 2.1

2.5

3.5

2.1

3.5

1.4

3.7

1.1

3.8

1.8

3.8

3.7 2.9

2.6 3.8

2.11.6

2.3

3.4

1.6

8.38.9 1.6

4.2

13.6

2.2

2.2

2.0

2.1

2.1

13.1

8.1

1.7

1.4

DRAWN:

APPROVED:DATE:

DATE:

DATE:PLOTTED: THIS DRAWING AND DESIGN REMAINS THE PROPERTYOF, AND MAY NOT BE REPRODUCED OR ALTERED,WITHOUT THE WRITTEN PERMISSION OF CIVILPLANCONSULTANTS LIMITED. NO LIABILITY SHALL BEACCEPTED FOR UNAUTHORISED USE OF THIS DRAWING.RJP 1-21

MSS 1-21

RJP 1-21

BY DATEREVISION DETAILSREVA ISSUED FOR 224C RJP 1-21

Filepath: P\APPDATA\LOCAL\AUTODESK\C3D 2020\ENU\TEMPLATE C:\DATA\POKENO\HITCHEN\STAGE 10\AS BUILTS\136701-10E-AB411.DWG

SHEET TITLE:

AS BUILT WASTE WATER DRAINAGE

PROJECT TITLE:

DFH JOINT VENTUREHITCHEN STAGES 10E,10F

POKENOLevel 9, Laidlaw House, 20 Amersham Way, Manukau, Auckland. Phone: 09 222 2445

CIVILPL NCONSUL TA TSN

DRAWING NUMBER: REV:

ISSUE STATUS:

136701-10-AB411 A

AS BUILT

0 10 20 30 40 50mSCALE BAR1:1000@A3

SCALE: (A1/A3) 1:500 / 1:1000

AutoCAD SHX Text
570
AutoCAD SHX Text
568
AutoCAD SHX Text
577
AutoCAD SHX Text
579
AutoCAD SHX Text
582
AutoCAD SHX Text
580
AutoCAD SHX Text
591
AutoCAD SHX Text
536
AutoCAD SHX Text
545
AutoCAD SHX Text
544
AutoCAD SHX Text
550
AutoCAD SHX Text
551
AutoCAD SHX Text
549
AutoCAD SHX Text
565
AutoCAD SHX Text
571
AutoCAD SHX Text
548
AutoCAD SHX Text
575
AutoCAD SHX Text
543
AutoCAD SHX Text
573
AutoCAD SHX Text
586
AutoCAD SHX Text
574
AutoCAD SHX Text
572
AutoCAD SHX Text
566
AutoCAD SHX Text
584
AutoCAD SHX Text
576
AutoCAD SHX Text
589
AutoCAD SHX Text
564
AutoCAD SHX Text
587
AutoCAD SHX Text
567
AutoCAD SHX Text
531
AutoCAD SHX Text
532
AutoCAD SHX Text
535
AutoCAD SHX Text
592
AutoCAD SHX Text
590
AutoCAD SHX Text
530
AutoCAD SHX Text
527
AutoCAD SHX Text
528
AutoCAD SHX Text
585
AutoCAD SHX Text
583
AutoCAD SHX Text
534
AutoCAD SHX Text
533
AutoCAD SHX Text
539
AutoCAD SHX Text
540
AutoCAD SHX Text
541
AutoCAD SHX Text
542
AutoCAD SHX Text
588
AutoCAD SHX Text
546
AutoCAD SHX Text
529
AutoCAD SHX Text
581
AutoCAD SHX Text
578
AutoCAD SHX Text
537
AutoCAD SHX Text
1
AutoCAD SHX Text
DP321866
AutoCAD SHX Text
2
AutoCAD SHX Text
DP176205
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
2
AutoCAD SHX Text
DP206719
AutoCAD SHX Text
NORTH_ISLAND_MAIN_TRUNK_RAILWAY
AutoCAD SHX Text
556
AutoCAD SHX Text
555
AutoCAD SHX Text
552
AutoCAD SHX Text
558
AutoCAD SHX Text
553
AutoCAD SHX Text
554
AutoCAD SHX Text
557
AutoCAD SHX Text
563
AutoCAD SHX Text
562
AutoCAD SHX Text
DRAINAGE_RESERVE
AutoCAD SHX Text
STAGE_13
AutoCAD SHX Text
MHU3 LL61.00 IL59.14 IL59.22 IL59.17
AutoCAD SHX Text
MHB39 LL52.98 IL50.03 IL50.22 IL50.17
AutoCAD SHX Text
EX.MHD3 LL46.69 IL44.11 IL44.18
AutoCAD SHX Text
150NB_PVC 21.1m
AutoCAD SHX Text
EX.MHV1 LL64.25 IL62.25 IL62.34 IL62.30
AutoCAD SHX Text
BCU4 IL59.50
AutoCAD SHX Text
CON550 IL60.13
AutoCAD SHX Text
CON551 IL60.38
AutoCAD SHX Text
MHV2 LL IL62.71
AutoCAD SHX Text
CON549 IL63.42
AutoCAD SHX Text
CON548 IL64.01
AutoCAD SHX Text
150NB_PVC 40.2m
AutoCAD SHX Text
MHD4 1500 MHLL50.94 IL45.02 IL49.65 IL45.18
AutoCAD SHX Text
CON577 IL45.50
AutoCAD SHX Text
CON576 IL45.66
AutoCAD SHX Text
CON575 IL48.07
AutoCAD SHX Text
CON574 IL48.18
AutoCAD SHX Text
CON573 IL48.26
AutoCAD SHX Text
150NB_PVC 131.6m
AutoCAD SHX Text
CON572 IL46.65
AutoCAD SHX Text
MHD5 1200 MHLL48.42 IL45.30 IL47.15 IL45.40 IL45.40
AutoCAD SHX Text
150NB_PVC 18.5m
AutoCAD SHX Text
CON580 IL51.34
AutoCAD SHX Text
MHX1 LL51.13 IL50.51 IL50.57
AutoCAD SHX Text
BCX2 IL51.00
AutoCAD SHX Text
150NB_PVC 32.8m
AutoCAD SHX Text
150NB_PVC 44.2m
AutoCAD SHX Text
CON579 IL51.44
AutoCAD SHX Text
CON578 IL51.62
AutoCAD SHX Text
MHB42 1200 MHLL IL54.80 IL56.25 IL54.83
AutoCAD SHX Text
MHB41 LL IL54.63 IL54.69
AutoCAD SHX Text
MHB40 LL56.83 IL54.23 IL54.32 IL54.25 IL55.46
AutoCAD SHX Text
MHB43 LL IL58.85 IL58.96 IL58.94
AutoCAD SHX Text
BCB44 IL59.20
AutoCAD SHX Text
150NB_PVC 90.0m
AutoCAD SHX Text
150NB_PVC 34.2m
AutoCAD SHX Text
150NB PVC 13.0m
AutoCAD SHX Text
MHA1 LL IL55.14
AutoCAD SHX Text
150NB_PVC 30.9m
AutoCAD SHX Text
150NB_PVC_71.9m
AutoCAD SHX Text
150NB_PVC 12.6m
AutoCAD SHX Text
150NB_PVC 80.6m
AutoCAD SHX Text
MHBZ1 LL58.40 IL56.13 IL56.48
AutoCAD SHX Text
CON581 IL51.87
AutoCAD SHX Text
CON582 IL52.68
AutoCAD SHX Text
CON583 IL53.41
AutoCAD SHX Text
CON584 IL54.41
AutoCAD SHX Text
CON585 IL55.65
AutoCAD SHX Text
CON586 IL55.94
AutoCAD SHX Text
CON587 IL55.55
AutoCAD SHX Text
CON588 IL55.74
AutoCAD SHX Text
CON589 IL55.70
AutoCAD SHX Text
CON590 IL56.03
AutoCAD SHX Text
CON591 IL57.02
AutoCAD SHX Text
CON593 IL57.20
AutoCAD SHX Text
CON552 IL59.80
AutoCAD SHX Text
CON553 IL59.91
AutoCAD SHX Text
CON554 IL59.01
AutoCAD SHX Text
CON555 IL58.46
AutoCAD SHX Text
CON556 IL57.49
AutoCAD SHX Text
CON557 IL57.14
AutoCAD SHX Text
CON558 IL55.93
AutoCAD SHX Text
CON571 IL51.96
AutoCAD SHX Text
CON570 IL48.14
AutoCAD SHX Text
CON568 IL46.77
AutoCAD SHX Text
CON566 IL48.44
AutoCAD SHX Text
CON565 IL47.90
AutoCAD SHX Text
CON564 IL48.82
AutoCAD SHX Text
CON563 IL49.91
AutoCAD SHX Text
CON562 IL49.12
AutoCAD SHX Text
MHD6 LL IL45.95
AutoCAD SHX Text
150NB_PVC 90.3m
AutoCAD SHX Text
MHF1 LL52.99 IL50.89 IL50.97
AutoCAD SHX Text
150NB_PVC 31.5m
AutoCAD SHX Text
150NB PVC 12.2m
AutoCAD SHX Text
CON567 IL52.35
AutoCAD SHX Text
BCF2 IL51.48
Page 23: Geotechnical Completion Report - Pokeno

Appendix 2 Field Density Test Summary Sheets

Page 24: Geotechnical Completion Report - Pokeno

Coffey Services NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103

PO Box 58877, Botany, Manukau, Auckland 2163

t +64 92723375 f +92723378

www.coffey.com

Client: Lander Geotechnical Consultants Limited PROJECT CODE: GENZETAM01177AA

Address PO Box 97 385, Manukau 2241 Page: 1 of 2

Attention: Chris Edwards

c.c: -

Project: J00113 - Hitchen Block - Stage 2 Pokeno

Approved Signatory:

Location: Pokeno Issue date:

Test Probe

Depth Comments

Oven Water

(mm) (FL = Finished level) Content (%)

24/11/2017 ETAM17W04199 AB 256 Fill Silty CLAY Fill L 1777814 5875272 - 150 0.4m to Subgrade level 141 154 154 134 1.73 38.1 1.25 2.7 6.0

24/11/2017 ETAM17W04199 AB 257 Fill Silty CLAY Fill L 1777829 5875274 - 150 0.2m to Subgrade level 168 141 141 UTP 1.77 45.4 1.21 2.7 0.0

Tested byField Shear Strength in kPa

UTP = Unable to penetrate

Cesar Pura

29/11/2017

Wet

Density

(t/m3)

Dry Density

(t/m3)

Solid

Density

Air Voids

(%)

Test method:

Date Work Order No: Easting NorthingTest

No.

Material

testedLocation

Test Methods in accordance with: Shear Strength (using field Shear vane in accordance with NZGS 2001):Nuclear Densometer Testing (in accordance with NZS 4407:2015 Test 4.2): Water Content Testing (in accordance with NZS 4402:1986 Test 2.1): Density Calculations (in

accordance with NZS 4402:1986 Tests 4.1.1.5(b)). Please note that Air Void calculations are not IANZ endorsed as part of this report.

Layer RL

This report must not be altered or reproduced except in full.

This report relates only to the positions tested.

IANZ Accredited Laboratory No:105LPS-07F11 Issue date 04072016

Page 25: Geotechnical Completion Report - Pokeno

Coffey Geotechnics NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103, New Zealand

PO Box 58 877, Botany, Manukau 2163, New Zealand

t+64 9 272 3375 f+64 9 272 3378 www.coffey.com

Work Order No: ETAM17W04199

Project:

Location: Tested by:

Date tested:

Fill L Area AB

24/11/2017

GENZETAM01177AASITE PLAN

NOT TO SCALE

Project No:

Page:

J00113 - Hitchen Block - Stage 2 Pokeno

2 of 2

256 257

Page 26: Geotechnical Completion Report - Pokeno

Coffey Services NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103

PO Box 58877, Botany, Manukau, Auckland 2163

t +64 92723375 f +92723378

www.coffey.com

Client: Lander Geotechnical Consultants Limited PROJECT CODE: GENZETAM01177AA

Address PO Box 97 385, Manukau 2241 Page: 1 of 2

Attention: Chris Edwards

c.c: -

Project: J00113 - Hitchen Block - Stage 2 Pokeno

Approved Signatory:

Location: Pokeno Issue date:

Test Probe

Depth Comments

Oven Water

(mm) (FL = Finished level) Content (%)

27/11/2017 ETAM17W04248 AB 258 Fill Silty CLAY Fill P 1777941 5875764 - 150 At Subgrade Level UTP UTP UTP UTP 1.86 27.2 1.46 2.7 5.9

27/11/2017 ETAM17W04248 AB 259 Fill Silty CLAY Fill L 1777632 5875546 - 150 1.8m to Subgrade level 168 131 161 154 1.84 34.1 1.37 2.7 2.6

Wet

Density

(t/m3)

Dry Density

(t/m3)

Solid

Density

Air Voids

(%)

Test method:

Date Work Order No: Easting NorthingTest

No.

Material

testedLocation

Test Methods in accordance with: Shear Strength (using field Shear vane in accordance with NZGS 2001):Nuclear Densometer Testing (in accordance with NZS 4407:2015 Test 4.2): Water Content Testing (in accordance with NZS 4402:1986 Test 2.1): Density Calculations (in

accordance with NZS 4402:1986 Tests 4.1.1.5(b)). Please note that Air Void calculations are not IANZ endorsed as part of this report.

Layer RLTested byField Shear Strength in kPa

UTP = Unable to penetrate

Cesar Pura

30/11/2017

This report must not be altered or reproduced except in full.

This report relates only to the positions tested.

IANZ Accredited Laboratory No:105LPS-07F11 Issue date 04072016

Page 1 of 2

Page 27: Geotechnical Completion Report - Pokeno

Coffey Geotechnics NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103, New Zealand

PO Box 58 877, Botany, Manukau 2163, New Zealand

t+64 9 272 3375 f+64 9 272 3378 www.coffey.com

Work Order No: ETAM17W04248

Project:

Location: Tested by:

Date tested:

Fill L and P, Refer to Plan AB

27/11/2017

GENZETAM01177AASITE PLAN

NOT TO SCALE

Project No:

Page:

J00113 - Hitchen Block - Stage 2 Pokeno

2 of 2

258

259

Page 28: Geotechnical Completion Report - Pokeno

Coffey Services NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103

PO Box 58877, Botany, Manukau, Auckland 2163

t +64 92723375 f +92723378

www.coffey.com

Client: Lander Geotechnical Consultants Limited PROJECT CODE: GENZETAM01177AA

Address PO Box 97 385, Manukau 2241 Page: 1 of 2

Attention: Chris Edwards

c.c: Michael Chan

Project: J00113 - Hitchen Block - Stages 1, 2 and 3, Pokeno

Approved Signatory:

Location: Pokeno Issue date:

6/04/2018 ETAM18W01401 SC 292 Fill Silty CLAY Fill L 1777756 5875262 - 150 At Finished Level 160 183 155 151 1.77 37.2 1.29 2.7 4.4

6/04/2018 ETAM18W01401 SC 293 Fill Silty CLAY Fill L 1777726 5875298 - 150 At Finished Level UTP UTP 183 178 1.90 43.1 1.33 2.7 0

Wet Density

(t/m3)

Dry Density

(t/m3)

Solid

Density

(t/m3)

Assumed

Air Voids

(%)

Test method:

Date Work Order No: Easting NorthingTest

No. Material tested Location

Test Methods in accordance with: *Shear Strength (using field Shear vane in accordance with NZGS 2001): Nuclear Densometer Testing (in accordance with NZS 4407:2015 Test 4.2): Water Content Testing (in accordance with NZS 4402:1986 Test 2.1): Moisture contents and dry

densities are corrected against oven dried moisture content testing.

Layer RL (m)Tested byField Shear Strength in kPa

UTP = Unable to penetrate

Cesar Pura

11/04/2018

Test Probe

Depth (mm) Comments

Oven Water

Content (%)

This report must not be altered or reproduced except in full.

This report relates only to the positions tested.

IANZ Accredited Laboratory No:105LPS-07F11 Issue date 04072016

Page 29: Geotechnical Completion Report - Pokeno

Coffey Geotechnics NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103, New Zealand

PO Box 58 877, Botany, Manukau 2163, New Zealand

t+64 9 272 3375 f+64 9 272 3378 www.coffey.com

Work Order No: ETAM18W01401

Project:

Location: Tested by:

Date tested:

Fill L, As below SC

6/04/2018

GENZETAM01177AASITE PLAN

NOT TO SCALE

Project No:

Page:

J00113 - Hitchen Block - Stages 1, 2 and 3, Pokeno

2 of 2

293

292

Page 30: Geotechnical Completion Report - Pokeno

Coffey Services NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103

PO Box 58877, Botany, Manukau, Auckland 2163

t +64 92723375 f +92723378

www.coffey.com

Client: Lander Geotechnical Consultants Limited PROJECT CODE: GENZETAM01177AA

Address PO Box 97 385, Manukau 2241 Page: 1 of 2

Attention: Chris Edwards

c.c: Michael Chan

Project: J00113 - Hitchen Block - Stages 1, 2 and 3, Pokeno

Approved Signatory:

Location: Pokeno Issue date:

4/05/2018 ETAM18W02082 SC 294 Fill Silty CLAY Fill L 1777774 5875437 49.13 150 - 167 167 179 179 1.89 31.6 1.43 2.7 2

4/05/2018 ETAM18W02082 SC 295 Fill Silty CLAY Fill L 1777766 5875452 44.95 150 - 160 160 167 167 1.80 28.5 1.40 2.7 8

Tested byField Shear Strength in kPa

UTP = Unable to penetrate

Cesar Pura

23/05/2018

Test Probe

Depth (mm) Comments

Oven Water

Content (%)

Wet Density

(t/m3)

Dry Density

(t/m3)

Solid

Density

(t/m3)

Assumed

Air Voids

(%)

Test method:

Date Work Order No: Easting NorthingTest

No. Material tested Location

Test Methods in accordance with: *Shear Strength (using field Shear vane in accordance with NZGS 2001): Nuclear Densometer Testing (in accordance with NZS 4407:2015 Test 4.2): Water Content Testing (in accordance with NZS 4402:1986 Test 2.1): Moisture contents and dry

densities are corrected against oven dried moisture content testing.

Layer RL (m)

This report must not be altered or reproduced except in full.

This report relates only to the positions tested.

IANZ Accredited Laboratory No:105LPS-07F11 Issue date 04072016

Page 31: Geotechnical Completion Report - Pokeno

Coffey Geotechnics NZ Ltd

144A Cryers Road, East Tamaki, Auckland 2103, New Zealand

PO Box 58 877, Botany, Manukau 2163, New Zealand

t+64 9 272 3375 f+64 9 272 3378 www.coffey.com

Work Order No: ETAM18W02082

Project:

Location: Tested by:

Date tested:

Fill L, As below SC

4/05/2018

GENZETAM01177AASITE PLAN

NOT TO SCALE

Project No:

Page:

J00113 - Hitchen Block - Stages 1, 2 and 3, Pokeno

2 of 2

295

294

Page 32: Geotechnical Completion Report - Pokeno

Appendix 3 Soil Classification Test Results

Page 33: Geotechnical Completion Report - Pokeno

15c Amber Crescent, Judea, Tauranga | PO Box 317, Tauranga 3140

p +64 7 571 0280 | [email protected] | www.geotechnics.co.nz

Our Ref: 1009521.1125.0.0/Rep1 Customer Ref: J00113

19 February 2021 Lander Geotechnical Consultants Limited Level 3, 3 Osterley way Manukau Auckland 2104 Attention: Kyle Meffan Dear Kyle

Hitchen Road Stages 10E + F Pokeno

Laboratory Test Report

Samples from the above mentioned site have been tested as received according to your instructions and the results are included in this report. Results apply only to the sample(s) tested.

Descriptions are enclosed for your information, but are not covered under the IANZ endorsement of this report.

This report has been prepared for the benefit of Lander Geotechnical Consultants Limited , with respect to the particular brief given to us and it cannot be relied upon in other contexts or for any other purpose without our prior review and agreement.

This report may be reproduced only in full.

Samples not destroyed during testing will be retained for one month from the date of this report before being discarded. If we can be of any further assistance, feel free to get in touch. Contact details are provided at the bottom of this page.

GEOTECHNICS LTD

Report prepared by: ...........................….......…............... Tylah Wardrope Laboratory Technician

Authorised for Geotechnics by: ...........................….......…............... Paul Burton Project Director

Report checked by: ...........................….......…...............Ryan MilliganProject ManagerApproved Signatory

19-Feb-21 t:\geotechnicsgroup\projects\1009521\1009521.1125\20210219.hitchen road stages 10e + f pokeno .tywa.docx

Page 1 of 7

Our Ref: 1009521.1125.0.0/Rep1

P.P.

Page 34: Geotechnical Completion Report - Pokeno

Customer Project ID

SAMPLE

Top Depth 0.5m

Bottom Depth 1.0m

Date

Reference Lot548

Description Hitchen Road Stages 10E + F Pokeno

Determination of Liquid & Plastic Limit, Plasticity Index - NZS 4402: 1986 Tests 2.2 (4 Point), 2.3 & 2.4

Sampled By Others, Tested As Received

Approved Signatory Ryan Milligan

• The material used for testing was natural, fraction passing a 425um sieve. • This test result is IANZ accredited.•Date tested 18/02/2021

Description silty CLAY with trace rootlets; brown. moist to dry, very high plasticity.

N/A Depth N/A

Description

SPECIMEN Reference

19/02/2021

TEST RESULTS

Liquid Limit 83

Plastic Limit 34

Plasticity Index 49

Judea

Tauranga 3110

Data N/A

New Zealand

Geotechnics ID S21TG000068

QESTLab Work Order ID W21TG-0030

TEST REMARKS

N/A

Geotechnics Project Number 1009521.1125.0.0

TEST DETAILS

LOCATION

p +64 7 571 0280

15C Amber Crescent

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Pla

stic

ity

Ind

ex (

PI)

Liquid Limit (LL)

Plasticity Chart - BS 5930:1999

A Line

B Line

ML

CV

CI

MH

MV

MI

CL

SC

Soil TypeM - SiltC - ClayS - Sand

PlasticityL - LowI - IntermediateH - HighV - Very HighE - Extremely High

CHME

CE

SF

GEOTECHNICS LTD

NZS 4402 - Tests 2.2,2.3,2.4 (4 Point) Atterberg

Page 1 of 1

Version 4.0 - 19 July 2019

Page 2 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 35: Geotechnical Completion Report - Pokeno

LOCATION

0.5m

Sampled By Bottom Depth 1.0m

Geotechnics Project Number 1009521.1125.0.0

QESTLab Work Order ID

p +64 7 571 0280

Customer Project ID

W21TG-0030

15C Amber Crescent

Judea

Tauranga 3110

New Zealand

Determination of the Linear Shrinkage - NZS 4402:1986 Test 2.6

TEST DETAILS

Description Hitchen Road Stages 10E + F Pokeno

Data N/A

SPECIMEN Reference Depth

SAMPLE Geotechnics ID S21TG000068

Reference Lot548 Top Depth

Description silty CLAY with trace rootlets; brown. moist to dry, very high plasticity.

Others, Tested As Received

TEST REMARKS

Description

Linear Shrinkage 23%

Date 19/02/2021

• This test result is IANZ accredited.•Date tested 18/02/2021

Approved Signatory Ryan Milligan

GEOTECHNICS LTD

NZS 4402 - Test 2.6 Linear Shrinkage

Page 1 of 1

Version 4.0 - 19 July 2019

Page 3 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 36: Geotechnical Completion Report - Pokeno

accred:2

lab:515081E3-268E-408F-BBB4-A76200890924

sig:743099A4-02DD-4644-A4BF-A8230167EB4D

silty CLAY with trace rootlets; brown. Sample Descriptionmoist to dry, very high plasticity.

Sample DetailsHitchen Road Stages 10E + F PokenoLocationLot548Sample Reference

0.5mSample Depth1.0mBottom Depth

S21TG000068Geotechnics ID

Test Results

18/02/202127.6

Result

Moisture Content [NZS 4402:1986 Test 2.1]MethodDescription

Limits

Moisture Content (%)Date Tested

19/02/2021

Material Test ReportReport No: MAT:S21TG000068

Issue No: 1

Customer:

Date of Issue:Report Authorised By :

Project: Hitchen Road Stages 10E + F Pokeno

Tauranga 3110

TaurangaJudeaNew Zealandp +64 7 571 0280

15C Amber Crescent

Lander Geotechnical

Manukau, 2104 Level 3, 3 Osterley Way

Please reproduce this report in full when transmitting to others or including in internal reports.

Address:

Customer Reference No.:Project No.: 1009521.1125.0.0

Ryan Milligan

Approved By:(Development Manager)Ryan Milligan

Page 1 of 1© 2000-2018 QESTLab by SpectraQEST.comForm No: 18909, Report No: MAT:S21TG000068

CommentsThis test result is IANZ accredited.

If samples have been taken, and were not destroyed during testing, they will be retained for one month from the date of this report before being discarded.

Page 4 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 37: Geotechnical Completion Report - Pokeno

Customer Project ID

SAMPLE

Top Depth 0.5m

Bottom Depth 1.0m

Date

Reference LOT 581

Description Hitchen Road Stages 10E + F Pokeno

Determination of Liquid & Plastic Limit, Plasticity Index - NZS 4402: 1986 Tests 2.2 (4 Point), 2.3 & 2.4

Sampled By Others, Tested As Received

Approved Signatory Ryan Milligan

• The material used for testing was natural, fraction passing a 425um sieve. • This test result is IANZ accredited.•Date tested 18/02/2021

Description SILT with some sand and some clay; lights brown. Dry, intermediate plasticity.

N/A Depth N/A

Description

SPECIMEN Reference

19/02/2021

TEST RESULTS

Liquid Limit 37

Plastic Limit 20

Plasticity Index 17

Judea

Tauranga 3110

Data N/A

New Zealand

Geotechnics ID S21TG000069

QESTLab Work Order ID W21TG-0030

TEST REMARKS

N/A

Geotechnics Project Number 1009521.1125.0.0

TEST DETAILS

LOCATION

p +64 7 571 0280

15C Amber Crescent

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50 60 70 80 90 100 110 120 130

Pla

stic

ity

Ind

ex (

PI)

Liquid Limit (LL)

Plasticity Chart - BS 5930:1999

A Line

B Line

ML

CV

CI

MH

MV

MI

CL

SC

Soil TypeM - SiltC - ClayS - Sand

PlasticityL - LowI - IntermediateH - HighV - Very HighE - Extremely High

CHME

CE

SF

GEOTECHNICS LTD

NZS 4402 - Tests 2.2,2.3,2.4 (4 Point) Atterberg

Page 1 of 1

Version 4.0 - 19 July 2019

Page 5 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 38: Geotechnical Completion Report - Pokeno

accred:2

lab:515081E3-268E-408F-BBB4-A76200890924

sig:743099A4-02DD-4644-A4BF-A8230167EB4D

SILT with some sand and some clay; lights Sample Descriptionbrown. Dry, intermediate plasticity.

Sample DetailsHitchen Road Stages 10E + F PokenoLocationLOT 581Sample Reference

0.5mSample Depth1.0mBottom Depth

S21TG000069Geotechnics ID

Test Results

18/02/202118.7

Result

Moisture Content [NZS 4402:1986 Test 2.1]MethodDescription

Limits

Moisture Content (%)Date Tested

19/02/2021

Material Test ReportReport No: MAT:S21TG000069

Issue No: 1

Customer:

Date of Issue:Report Authorised By :

Project: Hitchen Road Stages 10E + F Pokeno

Tauranga 3110

TaurangaJudeaNew Zealandp +64 7 571 0280

15C Amber Crescent

Lander Geotechnical

Manukau, 2104 Level 3, 3 Osterley Way

Please reproduce this report in full when transmitting to others or including in internal reports.

Address:

Customer Reference No.:Project No.: 1009521.1125.0.0

Ryan Milligan

Approved By:(Development Manager)Ryan Milligan

Page 1 of 1© 2000-2018 QESTLab by SpectraQEST.comForm No: 18909, Report No: MAT:S21TG000069

CommentsThis test result is IANZ accredited.

If samples have been taken, and were not destroyed during testing, they will be retained for one month from the date of this report before being discarded.

Page 6 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 39: Geotechnical Completion Report - Pokeno

LOCATION

0.5m

Sampled By Bottom Depth 1.0m

Geotechnics Project Number 1009521.1125.0.0

QESTLab Work Order ID

p +64 7 571 0280

Customer Project ID

W21TG-0030

15C Amber Crescent

Judea

Tauranga 3110

New Zealand

Determination of the Linear Shrinkage - NZS 4402:1986 Test 2.6

TEST DETAILS

Description Hitchen Road Stages 10E + F Pokeno

Data N/A

SPECIMEN Reference Depth

SAMPLE Geotechnics ID S21TG000069

Reference LOT 581 Top Depth

Description SILT with some sand and some clay; lights brown. Dry, intermediate plasticity.

Others, Tested As Received

TEST REMARKS

Description

Linear Shrinkage 7%

Date 19/02/2021

• This test result is IANZ accredited.•Date tested 00/01/1900

Approved Signatory Ryan Milligan

GEOTECHNICS LTD

NZS 4402 - Test 2.6 Linear Shrinkage

Page 1 of 1

Version 4.0 - 19 July 2019

Page 7 of 7

Our Ref: 1009521.1125.0.0/Rep1

Page 40: Geotechnical Completion Report - Pokeno

45a Parkhouse Road, Wigram, Christchurch | PO Box 13055, Armagh, Christchurch 8141p +64 3 361 0300 | [email protected] | www.geotechnics.co.nz

Our Ref: 1100674.0003.0.0/Rep1Customer Ref: J00113

24 February 2021Lander Geotechnical LimitedPO Box 97 385,Manukau, Auckland

Attention: Kyle Meffan

Dear Kyle

Hitchen Block, Pokeno

Laboratory Test Report

The samples we collected from the above mentioned site have been tested according to yourinstructions and the results are included in this report. Results apply only to the sample(s) tested.

Descriptions are enclosed for your information, but are not covered under the IANZ endorsement ofthis report.

This report has been prepared for the benefit of Lander Geotechnical Limited, with respect to theparticular brief given to us and it cannot be relied upon in other contexts or for any other purposewithout our prior review and agreement.

This report may be reproduced only in full.

Samples not destroyed during testing will be retained for one month from the date of this reportbefore being discarded. If we can be of any further assistance, feel free to get in touch. Contactdetails are provided at the bottom of this page.

GEOTECHNICS LTD

Report prepared by:

...........................….......…...............Jack SinghLaboratory TechnicianApproved Signatory

Authorised for Geotechnics by:

...........................….......…...............Paul BurtonProject Director

Page 1 of 4

Page 41: Geotechnical Completion Report - Pokeno

GEOTECHNICS LTDHitchen Block, Pokeno - Laboratory Test ReportLander Geotechnical Limited

24 February 2021Our Ref: 1100674.0003.0.0/Rep1

Customer Ref: J00113

Report checked by:

...........................….......…...............Corey Papu-GreadChristchurch Manager

24-Feb-21\\ttgroup.local\corporate\geotechnicsgroup\projects\1100674\1100674.0003\workingmaterial\20210224.jasi.1100674.0003.0.0.rep1.docx

Page 2 of 4

Page 42: Geotechnical Completion Report - Pokeno

Geotechnics Project Number

QESTLab Work Order ID

Customer Project ID

LOCATION Description

Data

SAMPLE Geotechnics ID BH No

Reference Top Depth

Sampled By Bottom Depth

SPECIMEN Reference Depth

(kPa)

Initial Water Content (%)

Bulk Density (t/m³)

Dry Density (t/m³)

Final Water Content (%)

Swelling Strain (%)

Initial Water Content (%)

Shrinkage Strain (%)

Inert Material Estimate in the Soil

Specimen(%)

Soil Crumbling During Shrinkage

Cracking of the Shrinkage Specimen

(%)

Approved Signatory Jack Singh

Date 24/02/2021

SHRINKAGE TEST

38.0

3.3

None

None

Major

SHRINK - SWELL INDEX 1.8

TEST REMARKS

• Estimates of inert material, soil cracking and soil crumbling are enclosed for your information, but are not covered under the IANZ endorsement of this report. • This test result is

IANZ accredited.•Date tested 15/02/2021

SWELL TEST

39.9

1.79

1.28

41.4

-0.08

Applied Pressure 25

Lot 583 0.6m

Geotechnics

DescriptionSILT with trace clay and minor sand, brown mottled black. Moist.

Description

TEST RESULTS

S21CH000074 Lot 583

45A Parkhouse Road

Wigram 1100674.0003.0.0

Christchurch 8042 W21CH-0018

New Zealand J00113

p +64 3 361 0300

Determination of the Shrink - Swell Index - AS 1289 Test 7.1.1 - 2003

TEST DETAILS

Hithchen Block, Pokeno - Stage 10E&F

N/A

Page 3 of 4

1100674.0003.0.0/Rep1

Page 43: Geotechnical Completion Report - Pokeno

Geotechnics Project Number

QESTLab Work Order ID

Customer Project ID

LOCATION Description

Data

SAMPLE Geotechnics ID BH No

Reference Top Depth

Sampled By Bottom Depth

SPECIMEN Reference Depth

(kPa)

Initial Water Content (%)

Bulk Density (t/m³)

Dry Density (t/m³)

Final Water Content (%)

Swelling Strain (%)

Initial Water Content (%)

Shrinkage Strain (%)

Inert Material Estimate in the Soil

Specimen(%)

Soil Crumbling During Shrinkage

Cracking of the Shrinkage Specimen

(%)

Approved Signatory Jack Singh

Date 24/02/2021

SHRINKAGE TEST

33.5

5.5

None

Minor

Moderate

SHRINK - SWELL INDEX 3.1

TEST REMARKS

• Estimates of inert material, soil cracking and soil crumbling are enclosed for your information, but are not covered under the IANZ endorsement of this report. • This test result is

IANZ accredited.•Date tested 15/02/2021

SWELL TEST

34.1

1.84

1.37

35.9

-0.04

Applied Pressure 25

Lot 572 0.6m

Geotechnics

DescriptionSILT with minor clay and trace sand, orange brown mixed with grey. Moist.

Description

TEST RESULTS

S21CH000075 Lot 572

45A Parkhouse Road

Wigram 1100674.0003.0.0

Christchurch 8042 W21CH-0018

New Zealand J00113

p +64 3 361 0300

Determination of the Shrink - Swell Index - AS 1289 Test 7.1.1 - 2003

TEST DETAILS

Hithchen Block, Pokeno - Stage 10E&F

N/A

Page 4 of 4

1100674.0003.0.0/Rep1

Page 44: Geotechnical Completion Report - Pokeno

23C

3.2 Slab-on-ground in expansive soils

3.2.1 NZS 3604 Clause 1.1.2 Buildings covered by this Standard

Amend 1.1.2(a) to read:

“Buildings founded on good ground or on expansive soils where the requirements of 1.1.5 are met”

3.2.2 NZS 3604 New Clause Add new: “Clause 1.1.5 Buildings on expansive soils

Buildings on expansive soils shall be supported on slab-on-ground foundations complying with 7.5.13 and in addition to 1.1.2 shall be limited as follows:

(a) single storey, stand-alone household unit, and

(b) maximum length or width of floor of 24.0 m including any attached garage, and

(c) simple plan shapes such as rectangular, L, T or boomerang, and

(d) concrete slab-on-ground with a minimum thickness of 100 mm and a minimum concrete compressive strength of 20 MPa, and

(e) simple roof forms, incorporating hips, valleys, gables or mono pitches, and

(f) maximum overall height of 7.0 m to roof apex from lowest cleared ground level, and

(g) maximum roof height of 3.0 m, and

(h) roof slope between 10° and 35° from the horizontal, and

(i) maximum span of roof truss 12.0 m, and

(j) external walls maximum of 2.4 m height studs, other than gable end walls and walls to mono-pitched roofs, which shall not exceed 4.0 m.

COMMENT:

Floor plans Where floor plans incorporate re-entrant corners then continuity of the exterior ground beam shall be maintained by continuing it as an internal beam, with the exterior beam details continued for a length of at least 1.0 m into the internal beam. This is only applicable where internal beams are specified in Tables 7.4A and 7.4B. This is aimed to bring the solution in NZS 3604 in line with Clause 5.3.8 of AS 2870:2011.

Ground movementProvision for the additional ground movement effects from trees near to foundations in expansive soils should be considered. Trees remove moisture from the soil for a radius equal to the height of the tree. This causes expansive soils to shrink to varying degrees, and when near houses leads to differential settlement occurring under foundations. Movement of the foundations may lead to cracks in the building and door jamming.

Where existing trees (including trees that have been recently removed) are located closer to the foundations than 1.5 times the mature height of a tree, then additional geotechnical advice should be obtained. Planting of new trees should be avoided near foundations of new buildings or neighbouring buildings on sites with expansive soils.

3.2.3 NZS 3604 Clause 7.5.1 Add the following paragraph at the end of Clause 7.5.1:

“Slabs on expansive soils for buildings meeting the requirements of 1.1.5 shall, in addition to meeting the requirements of 7.5.1 to 7.5.12, meet the requirements of 7.5.13. Where there is conflict the requirements of 7.5.13 shall apply.”

3.2.4 NZS 3604 New clause, tables and figures Add new: Clause 7.5.13 Slab-on-ground in expansive soils

7.5.13.1 Identification of expansive soils 7.5.13.1.1 Should reasonable enquiry as outlined in 3.1.3 show any signs of expansive soils, the expansive soil class, as defined in AS 2870, shall be established by one or all of:

(a) enquiry to the local territorial authority, and/or

(b) reference to the certificate of suitability issued in terms of NZS 4431, and/or

(c) a soil test undertaken by a suitably qualified soils engineer.

7.5.13.1.2 Expansive soil class shall be defined as:

(a) Slightly ‘S’, having an Iss range of 0–1.9%, and a 500 year design characteristic surface movement return (ys) of 22 mm, or

(b) Moderately ‘M’, having an Iss range of 2.0–3.7% and a 500 year design characteristic surface movement return (ys) of 44 mm, orAmend 19

Nov 2019 Amend 19 Nov 2019

2 8 N o v e m b e r 2 0 1 9 M I N I S T R Y O F B U S I N E S S , I N N O VAT I O N A N D E M P L O Y M E N T

S T R U C T U R E G E N E R A L Acceptable Solution B1/AS1

Page 45: Geotechnical Completion Report - Pokeno

23D

(c) Highly ‘H’, having an Iss range of 3.8–6.5%and a 500 year design characteristic surface movement return (ys) of 78 mm, or

(d) Extremely ‘E’, having an Iss range of 6.6–7.5% and a 500 year design characteristic surface movement return (ys) of 90 mm.

7.5.13.2 Maximum aspect ratio of concrete slabs The aspect ratio of the concrete slabs or bays of concrete slabs, such as in the case of L, T or boomerang concrete slab shapes, shall not exceed 5 to 1 (length to width).

7.5.13.3 Foundation details 7.5.13.3.1 For the identified expansive soil class the foundation details, external and internal thickenings shall be as follows.

(a) For light wall claddings refer to Table 7.4A and Figure 7.22.

(b) For medium wall or heavy wall claddings refer to Table 7.4B and Figure 7.23.

7.5.13.3.2 Situations where no internal thickenings shall be required are limited to a rectangular slab with long side not exceeding 17.0 m. Where this limit is exceeded, add additional internal thickenings across the slab with the same cross section dimensions and reinforcing as the external footing, so that the centre to centre spacing of thickenings is always less than 17.0 m.

COMMENT:

Design constraints:

a) The characteristic surface movements and the corresponding expansivity classifications have been calculated based on design for ultimate limit state (ULS) conditions for a 1 in 1000 year “extreme” drought event, and the serviceability limit state (SLS) conditions for a 1 in 500 year drought event.

b) Maximum soil movements are calculated to be based on a 500 year return period for SLS, and a 1000 year return period for ULS*;

(*NB: This differed from the recommendations contained within BRANZ Study Report 120A (BSR120A) which used a 300 year return period for the design level drought conditions)

c) Climate parameters adopted from BSR120A of u = 1.2 pF, Hs = 1.5 m, and a crack depth of 0.5 Hs

d) The Iss (soil stability index) ranges attributed to the expansivity classifications as defined in 3.2.4 above have been calculated using the parameters presented in BSR120A and Equation 2.3.1 of AS 2870:2011.

e) Sites subject to parameters that differ from those mentioned above, in particular sites where the crack depth is less than 0.75 m, such as cut natural ground or clay backfill, require specific engineering assessment to confirm their appropriate site classification.

f) The effects of nearby trees (whether existing, recently removed, or future planting) are not considered in these solutions. It is recommended that specific geotechnical engineering advice is obtained where a tree is within a lateral distance of 1.5 times its mature height of the foundations.

Maintenance of foundations in expansive soils

Normal maintenance is that work generally recognised as necessary to achieve the expected performance over time of the foundation located on expansive soils. Unless otherwise specified by the designer and noted on the drawings, basic normal maintenance tasks should ensure that:

a) the drainage and wetting of the site is controlled so that extremes of wetting and drying of the soils are prevented, and

b) the position and operation of gardens adjacent to the dwelling are controlled, and the planting of trees near to foundations is suitably restricted, and

c) any leaks which develop in plumbing, storm water or sanitary sewage systems are repaired promptly.

Amend 19 Nov 2019

Amend 19 Nov 2019

M I N I S T R Y O F B U S I N E S S , I N N O VAT I O N A N D E M P L O Y M E N T 2 8 N o v e m b e r 2 0 1 9

S T R U C T U R E G E N E R A L Acceptable Solution B1/AS1

Page 46: Geotechnical Completion Report - Pokeno

23E

Table 7.4A Reinforced concrete foundations in expansive soils for light wall claddings Clause 7.5.13 and Figure 7.22

Expansive soil class Slightly ‘S’ Moderately ‘M’ Highly ‘H’ Extremely ‘E’

Soil embedment (De) 375 mm 525 mm 575 mm 625 mm

Top steel (As top) 2/D 16 2/ D16 2/ D16 2/ D16

Bottom steel (As bottom) 1/ D16 1/ D25 1/ D20 1/ D25

Stirrups R6/ 125 crs. R6/ 125 crs. R6/ 300 crs. R6/ 300 crs.

Maximum spacing of internal thickenings no internal thickening

no internal thickening

2.5 m crs. 2.5 m crs.

Depth of thickening (D1) – – 400 mm 450 mm

Base width (B1) – – 300 mm 350 mm

Top steel (As top) – – 2/ D20 2/ D20

Bottom steel (As bottom) – – 2/ D16 2/ D20

Stirrups – – R6/ 150 crs. R6/ 150 crs.

Table 7.4B Reinforced concrete foundations in expansive soils for medium wall and heavy wall claddings Clause 7.5.13 and Figure 7.23

Expansive soil class Slightly ‘S’ Moderately ‘M’ Highly ‘H’ Extremely ‘E’

Soil embedment (De) 500 mm 550 mm 775 mm 800 mm

Top steel (As top) 2/ D16 2/ D20 2/ D20 3/ D20

Bottom steel (As bottom) 2/ D16 2/ D16 2/ D20 2/ D20

Stirrups R6/ 125 crs. R6/ 250 crs. R6/ 300 crs. R6/ 300 crs.

Maximum spacing of internal thickenings – 2.5 m crs. 2.5 m crs. 2.5 m crs.

Depth of thickening (D1) – 350 mm 450 mm 500 mm

Base width (B1) – 300 mm 300 mm 350 mm

Top steel (As top) – 2/ D16 3/ D20 3/ D20

Bottom steel (As bottom) – 2/ D16 2/ D16 2/ D20

Stirrups – R6/ 125 crs. R6/ 150 crs. R6/ 150 crs.

2 8 N o v e m b e r 2 0 1 9 M I N I S T R Y O F B U S I N E S S , I N N O VAT I O N A N D E M P L O Y M E N T

Amend 19 Nov 2019

S T R U C T U R E G E N E R A L Acceptable Solution B1/AS1

Page 47: Geotechnical Completion Report - Pokeno

Appendix 4 Post-Construction Borehole Records

Page 48: Geotechnical Completion Report - Pokeno

548 & 550

1 8

PL 04.02.212784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

UTP

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 548

Lot 550

188+

188+

188+

177/102 1.7

158/83 1.9

132/94 1.4

132/97 1.4

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

silty CLAY with trace fine sand, orange and brown streaked orange. Very stiff, moist, medium to high plasticity, insensitive [NATURAL]

becoming orange and brown streaked light grey, high plasticity

becoming red and orange streaked light grey

becoming orange, light grey streaked red/brown

becoming medium plasticity

TOPSOIL

clayey SILT, orange, red and grey streaked brown. Very stiff, moist, low plasticity, with trace fine gravel [FILL]

silty CLAY, orange, white and red streaked brown. Very stiff, moist, medium plasticity, with trace fine gravel

silty CLAY, orange streaked grey/brown. Very stiff, moist, high plasticity [NATURAL]

becoming orange and brown streaked light grey

becoming red and orange streaked light grey

becoming medium plasticity

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 49: Geotechnical Completion Report - Pokeno

552 & 554

2 8

PL 04.02.212784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 552

Lot 554

188+

150/107 1.4

134/105 1.3

81/51 1.6

81/48 1.7

102/67 1.5

134/70 1.9

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOILsilty CLAY with trace fine sand, orange streaked orange/brown. Very stiff, moist, medium to high plasticity [NATURAL]

becoming orange and light grey streaked orange/brown, high plasticity

becoming red and light grey streaked orange/brown

becoming light grey and orange streaked red/brown, medium plasticity

becoming orange/brown streaked light grey

becoming insensitive

TOPSOIL

silty CLAY, red and orange streaked light grey. Stiff, moist, medium plasticity, insensitive [NATURAL]

becoming orange and light grey streaked red

becoming orange, black and orange/grey mottled, high plasticity

becoming very stiff

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 50: Geotechnical Completion Report - Pokeno

557 & 567

3 8

PL/NM 09.02.212784/1750

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 557

Lot 567

134/70 1.9

161/78 2.1

UTP

243/135 1.8

135/108 1.2

177/92 1.9

116/77 1.5

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

silty CLAY, light grey and orange streaked brown. Very stiff, moist, medium plasticity, with trace fine gravel [FILL]becoming red and white streaked orange/brown

becoming orange streaked dark grey

becoming light grey streaked orange, high plasticity, insensitive

becoming orange streaked dark grey

becoming red, white, orange, grey streaked orange/brown

becoming dark grey, moderately sensitive

TOPSOIL

clayey SILT, brown, red and light grey mottled. Very stiff, dry to moist, low to no plasticity [FILL]

clayey SILT with trace fine sand, red speckled light grey. Hard, moist, low plasticity, insensitive [NATURAL]

silty CLAY with trace fine sand, red/orange streaked light grey. Very stiff, wet, high plasiticity, insensitive

becoming white, medium to high plasticity, with trace medium sand

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 51: Geotechnical Completion Report - Pokeno

572 & 577

4 8

PL/NM 09.02.212784/1750

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 572

Lot 577

188+

188+

188+

188+

134/70 1.9

161/78 2.1

UTP

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

TOPSOIL

silty CLAY, orange, white and brown streaked red/brown. Very stiff, moist, medium plasticity, with trace fine gravel [FILL]

becoming orange, black, light grey and red/brown streaked, without fine gravel

with trace fine gravel

becoming orange and brown

becoming red, white, black and brown mottled

clayey SILT, light grey streaked grey/brown. Very stiff, moist, low plasticity

clayey SILT, orange/red and grey speckled brown. Very stiff, dry to moist, low plasticity [NATURAL]

becoming black streaked orange/red, grey and brown

fine SAND, orange/yellow. Medium dense, moist, no plasticity

becoming insensitive

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 52: Geotechnical Completion Report - Pokeno

579 & 581

5 8

NM/PL 09.02.211750/2784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

270+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 579

Lot 581

227/58 3.9

250/62 4.0

227/58 3.9

188+

UTP

UTP

UTP

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

fine SAND, orange/yellow. Medium dense, dry to moist, no plasticity [NATURAL]

becoming orange streaked grey

becoming moderately sensitive

becoming sensitive

at 2.0m, becoming moderately sensitive

TOPSOILslightly clayey SILT with trace fine sand, orange streaked light grey/orange. Very stiff, moist, no plasticity [NATURAL]

silty CLAY, light grey and orange streaked red. Very stiff, moist, medium to high plasticity

becoming orange and light grey streaked brown/orange

clayey SAND, orange streaked light grey. Hard, moist, no plasticity

becoming orange streaked brown

becoming orange streaked light grey

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 53: Geotechnical Completion Report - Pokeno

583 & 585

6 8

PL 04.02.212784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 583

Lot 585

97/59 1.6

137/94 1.5

188+

158/43 3.7

140/40 3.5

172/54 3.2

124/54 2.3

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

silty CLAY with trace fine sand, orange, white and brown streaked dark grey. Very stiff, moist, medium plasticity [NATURAL]at 0.3m, becoming orange and light grey streaked brown/orange

becoming high plasticity

becoming red/brown, orange and light grey streaked orange/brownbecoming medium plasticity

becoming stiff, insensitive

becoming very stiff

TOPSOIL

silty CLAY with trace fine sand, orange. Very stiff, moist, medium plasticity, moderately sensitive [NATURAL]

clayey SILT with minor fine sand, orange. Very stiff, moist, low plasticity, moderately sensitive

becoming red streaked light grey and orange

becoming yellow/orange

becoming orange steaked light grey

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 54: Geotechnical Completion Report - Pokeno

588

7 8

PL 04.02.212784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 588

188+

167/129 1.3

150/105 1.4

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

silty CLAY, red, white and orange streaked brown. Very stiff, moist, medium plasticity, with trace fine gravel [FILL]

silty CLAY, orange streaked light grey. Very stiff, moist, medium to high plasticity [NATURAL]

becoming high plasticity

becoming medium plasticity

becoming insensitive

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 55: Geotechnical Completion Report - Pokeno

590 & 592

8 8

PL 04.02.212784

HITCHEN BLOCK STAGE 2, POKENO

J00113

Refer to site plan

DFH JOINT VENTURE LIMITED

Groundwater not encountered.(unless noted)

188+

PL

UTP = unable to penetrate.

EOB = end of borehole.

Lot 590

Lot 592

188+

183/99 1.8

188+

188+

148/86 1.7

161/107 1.5

132/94 1.4

E.O.B. at 2.0m. Target Depth.

E.O.B. at 2.0m. Target Depth.

So

ilS

en

sitiv

ity

TOPSOIL

clayey SILT, orange, grey and red streaked brown/orange. Very stiff, moist, low plasticity, with trace fine gravel [FILL]

silty CLAY, light grey/orange streaked, black mottled, brown/orange. Very stiff, moist, medium plasticity, without fine gravel

silty CLAY, orange streaked brown/orange. Very stiff, moist, medium plasticity [NATURAL]

becoming orange streaked light grey/orange, high plasticity

becoming orange, red streaked light grey

becoming medium plasticity

becoming insensitive

TOPSOIL

silty CLAY, light grey streaked orange. Very stiff, moist, medium to high plasticity [NATURAL]

becoming orange, red streaked light grey, medium plasticity

becoming light grey, orange streaked red/brown

becoming high plasticity

becoming insensitive

KM

Project Location :

Job Number:

Auger Borehole Nos.

Sample andLaboratory / Other

TestDetailsSOIL DESCRIPTION

Sheet of

Checked:

Comments:

BoreholeLocation:

mN mE Ground R.L.

Description:

Vane Head: Date:

Client :

1.0

1.5

0.0

0.5

2.0

0.5

0.0

1.5

1.0

2.0

Borehole Diameter:

50mm

Topsoil

Fill

Clay

Silt

Sand

Gravel

Organic

Pumice

Sandstone

Siltstone

Limestone

Volcanic

Plutonic

No Core

Logged By: Processor :

Va

ne

Sh

ea

r(kP

a)

pea

k/

resid

ual

Sta

nd

ing

Wa

ter

Le

ve

l

Le

ge

nd

Dep

th (

m)

Page 56: Geotechnical Completion Report - Pokeno

Appendix 5 Construction Observation Records

Page 57: Geotechnical Completion Report - Pokeno

Site Inspection Record

Project # & Name: J00113 - Hitchen Block

Date & Time: 16/02/18 10am

Author: CE

Plant Operating:

Weather:

Site Observations and Instructions:Requested to site by Trevor to inspect topsoil strip of Fill area L.

Noted that the topsoil had been stripped adequately to expose stiff natural ground. Requested that an underfill drain is installed as per the picture below, the slope still needs to be benched.

Requested underfill drain in green.

16/02/18Friday, 16 February 2018 12:27 p.m.

Inspections Page 18

Page 58: Geotechnical Completion Report - Pokeno

Inspections Page 19

Page 59: Geotechnical Completion Report - Pokeno

Site Inspection Record

Project # & Name: J00113 - Hitchen Block

Date & Time: 19/02/18 9am

Author: CE

Plant Operating:

Weather: Fine

Site Observations and Instructions:Photos from Trevor of Fill L drainage installation. Installation appears to have occurred as per CAN that we issued on the matter.

19/02/18Monday, 19 February 2018 9:28 a.m.

Inspections Page 20

Page 60: Geotechnical Completion Report - Pokeno

Inspections Page 21

Page 61: Geotechnical Completion Report - Pokeno

Inspections Page 22

Page 62: Geotechnical Completion Report - Pokeno

Site Inspection Record

Project # & Name: J00113 - Hitchen Block

Date & Time: 19/03/18 1pm

Author: CE

Plant Operating:

Weather: Fine

Site Observations and Instructions:Observation of progress of works on site. They have only 2 scrapers and 1 compactor working (as rest of plant is on the Bridge and Hynds).

Cut to fill around the pond area in the western part of stage 3 is the focus currently. Have asked Mike to get in contact with Trevor to ensure the appropriate level of fill testing is taking place.

19/03/18Tuesday, 20 March 2018 3:02 p.m.

Inspections Page 23

Page 63: Geotechnical Completion Report - Pokeno

Inspections Page 24

Page 64: Geotechnical Completion Report - Pokeno

Inspections Page 25

Page 65: Geotechnical Completion Report - Pokeno

Inspections Page 26

Page 66: Geotechnical Completion Report - Pokeno

Inspections Page 27

Page 67: Geotechnical Completion Report - Pokeno

Inspections Page 28

Page 68: Geotechnical Completion Report - Pokeno

Inspections Page 29

Page 69: Geotechnical Completion Report - Pokeno

Inspections Page 30