GENERAL Castoro 12 + LAY + SPA (presentation)
Transcript of GENERAL Castoro 12 + LAY + SPA (presentation)
Castoro 12
Laying process and general dataLaying process and general data
eni.com PREPARED BY: C12 FIELD ENGINEERS
CASTORO 12 – PIPE LAY VESSEL
2
CASTORO 12 – PIPE LAY VESSEL
SWS
3
CASTORO 12 – GENERAL LAYOUTLINE UP
35t PEDESTAL CRANE
PIPE STACKING AREA
LINE UP ROLLERS No. 1 AND 2
PIPE PIPEPIPE LOWERING CRADLE
PIPE LONGITUDINAL CONVEYOR
TRANSVERSAL CONVEYOR
TENSIONER
STINGERABANDON & RECOVERY WINCH
4
WINCH
FIRING LINE WORK STATIONS
5
FIRING LINE
The firing line will consist of the following major components:
• Four fixed height pipe supports R1, R2, R3 and R4• Variable height track support R5, R7• Tensioner + additional support (R_T)• Roller support R8 and R9• Vertical rollers V1 and V2 (mounted respectively on track support R7 and
rollers support R8)• Firing line working stations
6
FIRING LINE STATIONS FUNCTION
7
CASTORO 12 – ACTIVITIES PERFORMED ON BOARD
The activities to be performed onboard Castoro-12 are:• Pipe joint storage and handling• Welding preparations (bevelling, pre-heating & line-up)• Firing line welding (3 stations)• Firing line welding (3 stations)• NDT and Welding Repair (1 station)• Field Joint Coating(3 stations)• Initiation, normal pipe laying, lay down & contingency
operations`operations
8
LOADING OF PIPES INTO THE PIPE LOWERING CRADLE
9
MOVING OF PIPES INTO LONGITUDINAL CONVEYOR
10
GRINDING OF PIPE SIDE BEFORE WELDING
11
BEVELING OF PIPES
12
PIPES ALIGNMENT
13
PIPES WELDING
PIPE WELDINGAll welding shall be performed as per approved WPS/Welding Book and by qualified welders.The pre‐heating of the welding area of each joint, as specified on approved WPS/Welding Book, will becompleted prior to clamping The temperature will be measured using Digital Pyrometer or Tempilsticcompleted prior to clamping. The temperature will be measured using Digital Pyrometer or Tempilsticbefore to confirm WPS requirement. The root and Hot pass will be completed at the 1st station internalline‐up clamp will be removed after completion of the required passes with reference to the approvedWPS. The remaining subsequent passes will be carried at the 2nd or 3rd welding stations.
NDT OPERATIONNDT examination will be performed in station no. 4 as per approved procedure
WELD REPAIRIn case of defects out of acceptance criteria, the repair will be carried out at Station No.4 or No. 5, inaccordance with approved repair welding procedure and weld repair analysis.In case that the weld repair will be longer than admissible limit identified by weld repair analysis, therepair can be split in two independent sections, each one within admissible limit and shall be performedin different time (one subsequent the other). This will assure the safe condition during groove repairexcavation. The repair is allowed to be performed one time only, no second repair to be allowed.If the repair results is not successful, the pipe joints until the defective weld will be cut and removed fromthe firing line while C12 is back laying, then both cut pipe ends shall be re‐beveled and the laying process
14
repeated.
ILUC
15
IPW
16
WELDING 1ST STATION – ROOT & HOT PASS
17
WELDING 2nd STATION
18
WELDING 3rd STATION
19
NDT-RX
20
SAND BLASTING
21
PHASE 11 – SAND BLASTING APPARATUS
22
PRE-HEATING AND EPOXY APPLICATION
23
STINGER SYSTEM - PICTURES
24
STINGER SYSTEM – OVERVIEW
25
PALFINGER CRANE
26
27
PIPE LAY DOWN – CASTORO 12 MAIN NORMAL LAYING CONFIGURATION
Scope of Work:PULLING OF 28’’ EXPORT OIL LINE PIPE STRING IN TRANSITION ZONE FROM KP40.5 TO KP50.5
Transition Zone is identified as a zone, b t KP40 5 d KP52 9 hbetween KP40.5 and KP52.9, where water depth varies from approximately 1m to 0m. Due to the limitation of barge draft, the C12 cannot install pipeline in
t d th l th 1 6 b
28
water depth lower than 1.6m by conventional S-lay method.
TRENCH
Prior to start installation works trench was excavated by dredging subcontractor up to the required design depth from KP40.5 to KP50.5 for burial requirement.
After shore‐pull completion the pipeline will be backfilled by dredging subcontractor in order to guarantee a burial depth of 1.0m TOP from KP40.5 to KP50.5.
29
HOLD BACK SYSTEM
The hold‐back cable composed of several wire rope sections with different diameters (38 mm, 52 mm and 56 mm) will be pre‐laid in trench which is connected to an hold‐back system. y
7sections of Ø38mm cable
10 sections of Ø52mm cable
26 sections of Ø56mm cable
The hold back cable anchors system consists of 2x2 piles of a suitable capacity
30
The hold‐back cable anchors system consists of 2x2 piles of a suitable capacity
PIPE STRING PULLING - INITIATION
• CASTORO 12 moored at KP40.5 • STORIONE 2 comes close to stinger (approx.12m)• STORIONE 2 connects the hold-back cable to Skagit Winch pilot cable at her bowg p• STORIONE 2 connected to pipe pulling head via load cell at her stern
31
STORIONE 2 PULLING PONTOON
32
STORIONE 2 PULLING PONTOON
33
FLOATERS
3.25 T FLOATER
Over 760 floaters equipped with quick release system will be installed on the pipe string.
9 5T FLOATER9.5T FLOATER
34
FLOATERS
35
LIFTERS
Lifters are dedicated floating platforms with 20T load capacity equipped with motorized winch and chain blocks utilized to hoist
the pipe
36
STRING FABRICATION AND PULLING
The string fabrication and pulling operation will consist of the following activities:will consist of the following activities:
• Set-up of C12• Fabrication of string• Installation of floaters• Pulling of stringPulling of string• Support during pulling operation
37
PULLING OF STRING
• The pipeline will be pulled only when welding, NDTand FJC of a pipe joint is completed in the FL andinstallation of the floater, if required, is completedover the stinger
• During string pulling operation the essentialparameters will be controlled to ensure that the stringis not subject to excessive stress or deflection outsidethe specified limits: rollers reaction, stinger angle,Tensioner tension, Winch pulling force, Barge draftTensioner tension, Winch pulling force, Barge draftand trim, Barge positioning, String Configuration.
38
TERMINATION OF PULLING
• Once the weld joint between the pulling head and thepipeline has reached the intended location at approx. KP50.5,the pipe string will be abandoned on the trench bottom bythe pipe string will be abandoned on the trench bottom byremoving the floaters after that the alignment of the pipestring has been properly checked.
• 300m of pipeline must be laid from C12 stinger (about 25floaters to be removed) to ensure a sufficient pipe stabilityb f th t t f C12 l l i tibefore the start of C12 normal laying operation.
• Pipeline alignment will be checked prior of removing thefl t St i b h d l t ll b f l ifloaters. String can be pushed laterally before releasingfloaters by work boat to make sure the installation tolerancesare respected.
39
40