GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not...

16
g GE Nuclear Energy Update on Steam Dryer Activities Presentation to USNRC J.F. Klapproth D.C. Pappone July 25, 2003

Transcript of GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not...

Page 1: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

gGE Nuclear Energy

Update on Steam DryerActivities

Presentation to USNRCJ.F. KlapprothD.C. PapponeJuly 25, 2003

Page 2: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

Agenda

* QC2 dryer failure overview

* Failure Mode Analysis and Safety assessment

* Extent of Condition

* Screening Matrix Evaluation

* SIL Recommendations (Preliminary)

* Plans for EPU

July 25, 2003 Update on Steam Dryer Activities Slide 2

Page 3: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g QC2 Steam Dryer Failure & Root Causes

*2002 Event- June 7: Identified

degraded steam dryerconditions

- July 11: Plant shutdown.Cover plate failed.

- Root Cause: High cyclefatigue due to highfrequency acousticresonance (130 to 230Hertz)

.2003 Event- May 6: First indication of

degraded dryerperformance

- May 28: Power reduced topre-EPU level. Moisturecarryover steady at 0.2%June 10: Plant shutdown.Cracks in dryer hoodsRoot Cause:High cyclefatigue due to lowfrequency pressureloading (0 to 50 Hertz)*Operation with failed coverplate caused acceleratedfatigue in the hood area*increased load due to PORVopening (April 16)

*Increased loadingEPU operation

due to

July 25, 2003 Update on Steam Dryer Activities Slide 3

Page 4: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Function and Safety Considerations

* The function of the steam dryer is to remove moisture fromsteam exiting the reactor by vanes and perforated plates

* The steam dryer does not perform a safety function- The steam dryer is not required to prevent or mitigate the

consequences of accidents

* Failure Modes and Effects Analysis (FMEA) evaluated thelikelihood and consequences for bounding loose parts

* For a degraded dryer, structural integrity is adequate if thesafety consequences of any loose part that may be generatedis analyzed to be acceptable

- FMEA demonstrates that loose parts will not interfere with the ability toshutdown the reactor, provide adequate core cooling, or isolate themain steam lines

* Safe reactor operation is not compromised by a degradedsteam dryer

July 25, 2003 Update on Steam Dryer Activities Slide 4

Page 5: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g FMEA Example

I I , " I '11119 11sm"mmimm I Immilm- I II I I I I ''I I....,,. . :,'.b, ,,, I II i. of Fai,, lure, ' , P' i', '' i

I ... -rb ab I i I alueI I * I' ~~~~~~~~U1 PI -O;

o rnseque .,na..'.1 1 .5 .1 . o. I'f. ,,: , 7 S ',F.. .'...

<~~ bkgaibftv-'&i~kitiJ:Wi

~ Previous' aiue alueotntiOflr : . r g i~~~~~~~~~nt 0tj.S jil.s-?? lSSiFailure iS..ighIs q Low qFrne5,l~~> I mpact: .mpact: Largei~z

5 Drain Yes H M 9 Lor None L 1 L to M 5 45hannels _

16 rain Pipes & No L L 1 Lor None L 1 L 9 9__ Eib~ow s ._ _ _ ._ _ _ _ _ _ __ _ _ _ _ _ _ _

17 upportRing No L L 1 L L 1 M 5 518 ross Beams No L L 1 L L 1 L 9 919 wer Support Yes L L 1 None L I None 9 9

ing_20 Baffle Yes L M 5 L L I None 9 45

BetweenCenter Banks

21 ne Bars Yes L M 5 L. L 1 None 9 4522 hannel for No M M 5 L L 1 L 9 45

team Dryeruide Rod

23 ng Rod & Yes L M 5 L L 1 None 9 45ing Eye

24 anway No L L 1 M L 1 H 1 1_ vers _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

25 hannel for Yes L M 5 L L 1 M 5 25PV Suppt

__ 3rkt_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

*Failures will result in large loose parts that cannot enter the core shroud region. Somesmall loose parts that can enter the core shroud may also be generated. These small partshave been evaluated to have no significant safety consequences.**Risk Priority Number (RPN) value less than 125 is not risk significant.

Jul 25, 2003 Update on Steam Dryer Activities Slide 5

Page 6: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g QC-2 Extent of Condition Scope of Evaluation

*Evaluated EPU changes to identify potentiallyimpacted components

- Core power, FW and steam flow, FW temperature, RIPD andcarryunder

*Components included in review- Reactor internals:

eComponents instrumented during startup testing*Components in steam path, FW flow path

- External steam path*Main steam line piping*Steam path components

*Considered experience from- Flow induced & acoustic vibration- Flow effect on pressure distribution

July 25, 2003 Update on Steam Dryer Activities Slide 6

Page 7: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g QC2 Extent of Condition Summary

*Additional analysis identified that componentsevaluated are acceptable at EPU conditions

*Considerations in EPU evaluation process-Included additional dryer components- Included additional analysis elements (component FEA model,

FIV loads, FIV stresses)

July 25, 2003 Update on Steam Dryer Activities Slide 7

Page 8: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Asset Management

*Completed dryer screening matrix and key attributesto analyze susceptibility across the BWR fleet

*Revise SIL 644*Develop scope for dryer analysis for EPU

- Incorporated lessons learned from QC2 into analysis

*BWROG Activities

July 25, 2003 Update on Steam Dryer Activities Slide 8

Page 9: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Basic Hood Types

Square hoods I Slanted hoods I I Curved hoodsj

eBWRI3 Style Dryer

*Earliest Design'Localized Top Hood Stress

*Early BWR/4 Style Dryer

-Improved

oBetter Steam Flow

,,Reduced StressConcentration

*BWR/4 and Later

*Optimized for Steam Flow

July 25, 2003 Update on Steam Dryer Activities Slide 9

Page 10: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

9 Relative Stress on Dryer Hood

Update on Steam Dryer ActivitiesJuly 25, 2003

Page 11: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Screening Matrix ResultsSteam Dryer Outer Hood Relative Susceptibility

a i�i

I I.�I*

am

.0

0.4,

(0

�tU�t -

51am .au.

11am .I4�1. .UL

I- q N............

-~~ -U -- QSccc'M 'fi q Tn

1Ja)

:3

a0a7

-

a0

a)

-4

I-R

'F

13~Co

a) a a M:3:3N:3:3:3:3

-u-U-u 41cccccf M ff If

:3

314

0a =)a a) a)

-Uh t 3 L

2n- 0 C

M U-:3 a3

(AiW)

NJ

-Ua1)

CL)

-U

CLO

'a

:3

-U

:3

L)a,

a1

4)

-U-U

W LA)

CC)w

q IFTI~ -"

I A_

Square Hood Slanted & Curve Hood

I BWR/3-Style Steam Dryer is susceptible to dryer failure |Jul 2S 03Udt nSemDre ciiisSie1

July 25, 2003 Update on Steam Dryer Activities Slide 11

Page 12: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Screening Matrix

* Steam Velocity from Plant Data- Pressure based on square of steam velocity- QC2 = Highest =10, Other plants: Based on velocity2

* Stress from Finite Element Analysis- Based on uniform unit pressure loading- Square = 10, Slanted =3, Curved = 2

Average PressureFlow Vel. / Load Hood Stress Relative

Plant Line (ftlsec) Score Type Score ScorePlant 4 202 10.00 Flat 10 100Plant 5 168 6.90 Flat 10 69Plant 17 141 4.87 Stepped 3 15Plant 20 134 4.43 Stepped 3 13Plant 22 172 7.23 Curved 2 14Plant 14 181 8.03 Curved 2 16

July 25, 2003 Update on Steam Dryer Activities Slide 12

Page 13: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g SIL Recommendations

eSIL 644 issued 2002- Recommendations based on the cover plate failure at QC2 in July

2002*Moisture carryover monitoringinspectionn

- For BWR plants with square hood steam dryer- Focuses on the cover plate of the steam dryer

*SIL 644 Rev. 1 will be issued August 2003- Expands the scope to all dryer components of all BWR dryers

July 25, 2003 Update on Steam Dryer Activities Slide 13

Page 14: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g SIL Recommendations- Preliminary

*Monitoring of main steam line moisture content:- Establish base line for moisture content- Periodic monitoring, and- Following any transient that may induce pressure loads on the

dryer

*Inspections- Baseline inspection for all high stress locations

July 25, 2003 Update on Steam Dryer Activities Slide 14

Page 15: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Steam Dryer Evaluation

*Generic- Perform representative full FEA for each dryer type

.Plant Specific Assessment- Perform inspection- Confirm applicability of representative dryer type- Consider extent of conditions

July 25, 2003 Update on Steam Dryer Activities Slide 15

Page 16: GE Nuclear Energy Update on Steam Dryer Activities · -FMEA demonstrates that loose parts will not interfere with the ability to shutdown the reactor, provide adequate core cooling,

g Conclusion

*No safety concern due to degraded steam dryer*Root cause of QC-2 dryer failure understood*Square hood dryer more susceptible to failure*Lessons learned incorporated in EPU evaluationprocess

*industry communication planned for August

July 25, 2003 Update on Steam Dryer Activities Slide 16