GAS FREE PROCEDURES FOR PAINTING OPERATIONS Lesson Topic 3.3.
GAS FREE PROCEDURES FOR PAINTING OPERATIONS
-
Upload
heather-noble -
Category
Documents
-
view
43 -
download
5
description
Transcript of GAS FREE PROCEDURES FOR PAINTING OPERATIONS
GAS FREE PROCEDURES FOR GAS FREE PROCEDURES FOR PAINTING OPERATIONSPAINTING OPERATIONS
Lesson Topic 3.3Lesson Topic 3.3Lesson Topic 3.3Lesson Topic 3.3
INTRODUCTIONINTRODUCTION
As Gas Free Engineering Personnel you will be required to know the procedure and safety precautions involved during painting operation in a confined space.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
ENABLING OBJECTIVESENABLING OBJECTIVES
Describe gas freeing and safety precautions/procedures to be followed before, during, and after painting operations in accordance with NSTM Chapter 074 Vol. 3, Gas Free Engineering, NSTM Chapter 631 Vol. 1, Preservation of Ships in Service - General, NSTM Chapter 631 Vol. 2, Preservation of Ships in Service - Surface Preparation and Painting, and OPNAVINST 5100.19, series.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
PAINTING OPERATIONSPAINTING OPERATIONS
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
General safety measures
Potential hazards that exists in all painting operations make a continuing and enforced safety program essential.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
General safety measures
WORKING ENVIROMENT: Shall be studied before painters are sent into any work area.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Spray Painting
Performed to preserve and protect the ship’s interior spaces
Principal hazard is the paint, its components, and the form in which it is applied
Spray gun produces airborne contaminants Vapors, mists,
and aerosolsOSHA regulates
worker exposure and the PPE standard
More hazardous than brush application due to: Volume of material being applied Flammable residue deposited by
spraying which might spontaneously combust
Harmful toxic mists created by spraying
Spray Painting
What does the GFE have to What does the GFE have to do with Spray Painting?do with Spray Painting?
Ensure you are notified of any interior spray painting prior to the operation
This allows you to: Ensure operating personnel set up
ventilation properly and keep it running Ensure space is monitored for CO during
and after completion Consider LEL/Vapor Volume of solvents
involved per 074 Vol. 3 page 21-10
SAFETY IS YOUR NUMBER ONE
PRIORITY
Safe Painting Operations Two most important factors:
Responsibility of Supervisors and Operating Personnel Obtain Gas Free
Engineer’s Approval prior to commencing painting
Ensure GFE is advised when ventilation is secured after painting is completed
Gas Free Engineer provides technical assistance (ventilation set up, PPE) as needed in addition to gas free testing
Training
PRIOR TO PRIOR TO PAINTINGPAINTING
“For contaminating operations…withina confined or enclosed space, the
(GFE) certificate shall specify applicablerequirements such as ventilation, PPE,
respiratory protection, explosion proof andsparkproof equipment and suitable fire
protection equipment.”
NSTM 074 VOL 3
Basic Safety Guidelines
Always protect your crew against the three major hazards:
Mishaps Fire Toxicity
General safety measures
Hazards to be considered, include: Poor Ventilation Noxious Fumes High Temperatures Type of material and how applied Type of space
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Ensure the work supervisor uses a safety checklist
An example is provided in NSTM 631 Vol. 1 “Preservation of Ships in Service”
Basic Safety Guidelines
PG 34-35
General safety measures
BUDDY SYSTEMCOMMUNICATIONSAFETY OBSERVERWORK ENVIRONMENTVENTILATION REQUIREMENTSPPE REQUIREMENTS
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Personnel shall never work alone in hazardous areas
Communications should be maintained
Operation should be supervisedEnsure you state on the Gas Free
Certificate:“Observe Two Man Rule”
Buddy System - Communications -
Supervision
VENTILATION Requirements
Required to control the toxic and flammability hazard
Use dilution-type ventilation to protect adjacent areas Ensures vapor
concentrations remain below 10% of the LEL
Run ventilation continuously
Continue ventilation for at least one hour after painting is completed
Ventilation requirements / procedures
Outside air shall be provided at a minimum rate of 1 air change every 3 minutes, but not less than that required to provide a safe, life - supporting atmosphere.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Ventilation requirements / procedures
Use outside (fresh) air for supply, and exhaust directly to outside air.
Carefully consider the number, placement and capacity of blowers, number and size of flexible ducts, size and shape of space.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Ventilation requirements / procedures
Point of exhaust shall be as far as practical from point of supply.
Place ducts in areas where vapors may collect.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Ventilation requirements / procedures
Selection of supply or exhaust ventilation shall be based on: Internal configuration of the space Location of openings Blower availability Staging distribution and other
considerations
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Ventilation requirements / procedures
Safety Precautions Rope off and post DANGER AREA signs Prohibit smoking, hot work, and open
flame in the area. All electrical leads shall be sealed. All equipment requiring grounding shall
be grounded. Fire extinguishing equipment shall be in
the ready condition.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Protective EquipmentProtective Equipment
Respirators: All devices shall be approved by NIOSH and Mining Safety and Health Administration (MSHA).
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Protective EquipmentProtective Equipment
SUPPLIED AIR RESPIRATORS: Used in closed areas where ventilation cannot be supplied.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Protective EquipmentProtective Equipment
Respiratory care Equipment shall be cleaned
immediately after use.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
Protective EquipmentProtective Equipment
Eye Protection Must be worn in areas where there
is a possibility of particles, mists or vapors entering eyes
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
NOTE: Emergency eyewash stations shall beavailable at the site or portable eyewash stations available if fixtures are not installed.
Protective EquipmentProtective Equipment
Personnel shall wear adequate clean clothing and gloves to prevent skin contact with painting and cleaning materials.
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
GAS FREE GAS FREE ENGINEER ENGINEER INSPECTIONINSPECTION
APPLICATION OF PAINT IN A CONFINED SPACE
Conduct periodic gas free testsGFE conducts
the initial testGFEA/GFEPO
conduct retesting
Conduct testing during work breaksExhaust side of
portable ventilation
Air intakes
CHECK FOR OR STATE THE FOLLOWING:
Type of ventilation to be used
How you want ventilation set up Spell this out on
your Gas Free Chit Ensure all DC
numbers and plates are covered or numbers & location are recorded
Type of respiratory protection Spell this out on
your Gas Free ChitType of PPE to
use Spell this out on
your Gas Free Chit
Gas Free Testing Requirements
Oxygen test 19.5 - 22 percent
Explosive test Remain below 10 percent of the LEL
Toxic tests Remain below their PELs
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
DURING PAINT DURING PAINT OPERATIONSOPERATIONS
Never test levels at the nozzle of spray gun Receive inaccurate readings Ruin GFE equipment
Only one day’s paint can be in a space at any one time
DURING PAINT OPERATIONS
POST PAINT ING POST PAINT ING CONCERNSCONCERNS
POST PAINTING CONCERNS
Ventilation should run for 1 hour after job completion
Ensure DC labels & plates are restored correctly!!!
Clean respirators & dispose of hazardous material properly
10 minutes after ventilation shutdown, 10 minutes after ventilation shutdown, ensure space is gas freeensure space is gas free
Requirement from OPNAVINST 5100.19C (C18)
“Wear supplied air respirators when engaged in
spray painting operations internal to the ship
or in confined external areas…”
(Realize that 631 and 5100.19C differ on this
issue. NSTM 631 only requires supplied air for
Vinyl and Epoxy paints.
Always err on the side of
SAFETY!!
“VENI, VIDI, VENTILATE!!!”
Loosely translated means
“Ventilate, Ventilate, Ventilate!!!”
REVIEW AND SUMMARYREVIEW AND SUMMARY
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
REVIEW AND SUMMARYREVIEW AND SUMMARY
Painting Operations
Lesson Topic 3.3, Gas Free Procedures For Painting Operations
THE ENDTHE ENDTHE ENDTHE END
GAS FREE MISHAPS“DEATH IN A COFFERDAM”
BACKGROUND
East Coast Amphib has leak in a MOGAS tank and contracts job to civilians to clean, inspect and fix tank
MOGAS tank located underneath the well deck
XO puts out at O-Call that no contractors will be working in tanks/voids that day
CDO present at O-Call
BACKGROUND
Contractor comes on board and informs CO that he will be “going in and out of the” MOGAS tank all day
OOD, CDO never notifiedCDO unfamiliar with Gas Free
Engineering - didn’t even know what IDLH stood for
TIMELINE
0805
“C” fire
- “C” fire in 1 of 4 shore power cables
- Base Fire Dept. called to secure cable
- Ship remains on shore power
TIMELINE
0805
“C” fire
- 1315 Contractor dons an electrically powered SAR with no back-up air supply to search for leak
- Space not gas freed
- 1320 Contractor enters the cofferdam
1320
Contractor Enters
TIMELINE
0805
“C” fire
- 1330 Ship goes from Shore to Ship’s Power while Public Works changes out bad cable
- Word is passed over 1MC
- Power interruption stops the Contractor’s SAR
1320
Contractor Enters
1330
Power Secured
TIMELINE
0805
“C” fire
- 1335 New cable in place and Shore Power restored
- Power surge shuts down several breakers, to include the one that powers the Contractor’s SAR
1320
Contractor Enters
1330
Power Secured
Shore Power Restored
1335
TIMELINE
0805
“C” fire
- 1342 Power restored to compressor but by this time Contractor was without air for 7 minutes
- R & A called away
- Drop test conducted at entrance and space is determined to be in the UEL
1320
Contractor Enters
1330
Power Secured
Shore Power Restored
1335
1342
Power Restored
TIMELINE
0805
“C” fire
- 1355 Ship calls Base Medical to report “unknown illness”
- 1400 Ship calls Base Fire Dept. and reports “Man down at quay wall”
1320
Contractor Enters
1330
Power Secured
Shore Power Restored
1335
1342
Power Restored
Fire Dept Called
1400
Firefighters arrive on scene and determine that it is a Rescue vice Recovery
Fire Chief and Firefighter enter space with SCOTT SCBA and no back-up air supply
Holes in swash plates 15 in x 22 in
TIMELINE
0805
“C” fire
- 1415 Asst. Fire Chief calls Trench and Rescue Team to be brought in
1320
Contractor Enters
1330
Power Secured
Shore Power Restored
1335
1342
Power Restored
Fire Dept Called
1400
1415
Trench & Rescue Called
Trench and Rescue Team arrives and asks to see ship’s drawings for another possible entrance
Positive Pressure ventilation and atmospheric monitoring ordered
TIMELINE
0805
“C” fire
- 1517 Two man Rescue Team enters cofferdam for recovery
- Max 25 minute stay time due to atmosphere
1320
Contractor Enters
1330
Power Secured
Shore Power Restored
1335
1342
Power Restored
Fire Dept Called
1400
1415
Trench & Rescue Called
1517
2 Man Team Enters for Recovery
Took 7 teams of two to three personnel more than 4 hours to recover the bodies of the Contractor and the Fire Chief
Final Analysis
Contracting company charged with 30 violations of 29 CFR, to include not providing a Marine Chemist to perform a Gas Free test and inadequate respiratory protection
CO, CDO, Air Officer, Fuels Officer and DCA all went to Admiral’s Mast
Final Analysis Cont.Final Analysis Cont.The CO was charged with overall responsibility for the safety and health of all people on his ship and 2 people died. The CO went on to 2 other major commands.
The CDO was charged with a violation of the SORM “The CDO shall keep himself informed of all events onboard the ship.” Charges eventually were dismissed.
The DCA was charged for numerous violations of NSTM 074.
The Air Officer and Fuels Officer were charged with failure to clean the MOGAS tank and cofferdam IAW NSTM’s