Meeting of the Verdun / Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre-St-Charles – April 7, 2016 Gaétan Laberge sector mobility scenario
New Champlain Bridge Corridor Project
Presentation Plan
♦ Presentation of construction work and obstructions
♦ Selected mobility scenario
♦ Preliminary schedule
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee 2
New Champlain Bridge Corridor Project
Construction of new A15S structures, walls and roadbeds
Overall plan:
Spring 2016 through Fall 2017
Demolition of existing A15S structures, walls and roadbeds
Construction of Gaétan-Laberge Blvd.
3
Construction of new Nun’s Island Bridge
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
New Champlain Bridge Corridor Project
Gaétan-Laberge sector
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee 4
New Champlain Bridge Corridor Project
Presentation of Construction Work and Obstructions
5
Specific Gaétan-Laberge sector context
› Fast-track construction of Gaétan-Laberge Blvd. in 2016 / 2017 will
provide a very attractive option in terms of mobility during
construction of the western approach to the new Champlain Bridge in
2017 / 2018, in the Nun’s Island sector.
› The phasing-mobility concept is based on one unique scenario, in
place for one year.
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
New Champlain Bridge Corridor Project
Selected mobility scenario The Site
6
Bretelle d’accès vers l’A15 Nord
Présentation mobilité – Comité de bon voisinage Verdun/Le Sud-Ouest
AM Reserved Lane
PM Reserved Lane
Access to A15
Access to A10
New Champlain Bridge Corridor Project
Selected mobility scenario Overview
7
Bretelle d’accès vers l’A15 Nord
Présentation du plan de contrôle et de gestion de la circulation 2016 – 29 mars 2016 (CIGC)
CLOSED AREA PROPOSED DETOUR
ON RAMP TO A15 SOUTH
ON RAMP TO A15 NORTH
RESERVED BUSSES
RAMP TO A10 WEST (DOWNTOWN)
ENTRANCE TO A15 SOUTH
A15: LANES DETOURED NORTHWARD
A15 NORTH: WIDENED TO (3) LANES
New Champlain Bridge Corridor Project
Selected mobility scenario Overhead View – Toward Champlain
8
Bretelle d’accès vers l’ A15 Sud (Centre-Ville)
CLOSED AREA PROPOSED DETOUR
ON RAMP TO A15 SOUTH
RAMP TO A10 WEST (DOWNTOWN)
RESERVED BUSSES
ENTRANCE TO A15 SOUTH
New Champlain Bridge Corridor Project
Selected mobility scenario Specific View
Wellington Exit Closure (access to downtown)
9
Bretelle d’accès vers l’ A10-Ouest (Centre-Ville)
VRAM-PM
Movement from A15 South exit 60 onto A10 West will be transferred to a temporary ramp constructed on Nun`s Island
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
RESERVED BUSSES
RAMP TO A10 WEST (DOWNTOWN)
New Champlain Bridge Corridor Project
Selected mobility scenario Overview – toward Turcot
10
Bretelle d’accès vers l’ A15 Sud (Centre-Ville)
CLOSED AREA PROPOSED DETOUR
A15: LANES DETOURED NORTH
A15 NORTH: WIDENED TO (3) LANES
ENTRANCE TO A15 SOUTH
ON RAMP TO A15 NORTH
RESERVED BUSSES
New Champlain Bridge Corridor Project
Selected mobility scenario Special reserved lane treatment
11
VRAM-PM
Bretelle d’accès vers l’A15 Nord
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
RESERVED BUSSES
New Champlain Bridge Corridor Project
Selected mobility scenario Overview – toward Turcot
12
CLOSED AREA PROPOSED DETOUR
ON RAMP TO A15 NORTH
A15: LANES DETOURED NORTH
A15 NORTH: WIDENED TO (3) LANES
ENTRANCE TO A15 SOUTH
RESERVED BUSSES
New Champlain Bridge Corridor Project
Selected mobility scenario Specific View
Closure of Ramp V (Exit 60 from A15 North)
13
Bretelle d’accès vers l’A15 Nord
Closure of Exit 60 from A15 North Verdun / Wellington St.
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
New Champlain Bridge Corridor Project
Selected mobility scenario Closure of Ramp V (Exit 60 from A15 North)
14
Bretelle d’accès vers l’A15 Nord
Detour via Atwater
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
New Champlain Bridge Corridor Project
Preliminary Schedule Gaétan-Laberge Sector
15
Obstruction configuration Schedule Duration Phase 1 implementation – Gaétan-Laberge
Closure of Ramp S (A15 South for lane leading to A10 West) July 2016 12 months
Closure of Ramp V (A15 North for Verdun-Wellington) July 2016 12 months
PM reserved lane July 2016 Definitive
Closure of Ramp T (A10 East feeder for A15 Nord) July 2016 12 months
Closure of Ramp 1 (R13-Jacques-Le Ber St. for A10 West) July 2016 12 months
Closure of access to Via-Rail from A15 South July 2016 12 months
Mobility presentation – Verdun / Sud-Ouest Good Neighbourly Relations Committee
Question and comment period