Good neighbourly relations committee City of Brossard - May 4, 2016
Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
-
Upload
nouveau-champlain -
Category
Engineering
-
view
120 -
download
2
Transcript of Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee
![Page 1: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/1.jpg)
Meeting of the Verdun / Le Sud-Ouest Good Neighbourly Relations Committee New Champlain Bridge Corridor Project Centre communautaire Elgar – June 15, 2016
![Page 2: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/2.jpg)
New Champlain Bridge Corridor Project 2
Verdun Philippe Dubeau Hubert Fortin François Labelle Seraya Speer Vacant Billy Walsh – business community
Leanne Ruberry – business community Mario Langlois – community organizations Le Sud-Ouest Natacha Alexandroff Daniel Brasseur Sarah Chouinard Michael Ryan Wiseman – business community Marie-Josée Béliveau – business community Partners Dan Genest – Signature on the Saint Lawrence team Jean-François Parenteau – Verdun Borough
Benoît Dorais – Le Sud-Ouest Borough James Byrns – City of Montréal Vincent Jarry – Infrastructure Canada
Committee Members
![Page 3: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/3.jpg)
New Champlain Bridge Corridor Project
1. Present the favoured solution for anti-noise walls
2. Discuss the work completed, under way and to come from now until October 2016
3. Answer questions, identify potential solutions and discuss the issues
Meeting Objectives
3
![Page 4: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/4.jpg)
New Champlain Bridge Corridor Project
Agenda
4
Series Item Duration Time 1. Opening 10 min. 7:00 to 7:10 p.m.
2. Anti-noise walls 30 min. 7:10 to 7:40 p.m.
3. Question period for Committee members 10 min. 7:40 to 7:50 p.m.
4. Question period for general public 20 min. 7:50 to 8:10 p.m.
5. Work completed, under way and to come • Land sector • L’Île-des-Sœurs sector
30 min. 8:10 to 8:40 p.m.
6. Question period for Committee members 10 min. 8:40 to 8:50 p.m.
7. Question period for general public 10 min. 8:50 to 9:00 p.m.
8. Other business 10 min. 9:00 to 9:10 p.m.
9. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 p.m.
![Page 5: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/5.jpg)
New Champlain Bridge Corridor Project
Work Completed in the Last Months Verdun / Le Sud-Ouest
![Page 6: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/6.jpg)
New Champlain Bridge Corridor Project
• Prefabrication installations for the west jetty: 16 (of 38) footings poured
• Demolition of old L’Île-des-Sœurs bridge
• Creation of shipping lanes
• Partial demolition of Atwater, LaSalle / D'Argenson and L’Île-des-Sœurs overpasses
• Installation of water main at Gaétan-Laberge
Overview of Completed Work
6
![Page 7: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/7.jpg)
New Champlain Bridge Corridor Project
• More complaints: in connection with work intensification at jobsite
• Demolition of Atwater, LaSalle / D'Argenson and L’Île-des-Sœurs overpasses: no complaints
• Considerable road disruptions at L’Île-des-Sœurs over the weekend of June 3 to 5:
communications campaign and close coordination with all key stakeholders—there will be no surprises
• Public information meeting on May 25: over 90 people, which confirms interest in this type of event Future of bypass bridge Fourth northbound lane of new L’Île-des-Sœurs Bridge Impact of Gaétan-Laberge closure and other disruptions Permanent sound walls GHG offsetting Project of the Réseau électrique métropolitain (REM)
Completed Work: Observations
7
![Page 8: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/8.jpg)
New Champlain Bridge Corridor Project
Complaint Management (April 7 to June 10, 2016)
8
Topic Land L’Île-des-Sœurs
Total Closed Open Total Closed Open Total
Noise 2 2 4 4 - 4 8
Air quality 3 - 3 - - - 3
Traffic 3 - 3 2 - 2 5
Vibrations 3 2 5 - - - 5
Brightness - - - - - - -
Other 2 - 2 3 - 3 5
Total 13 4 17 9 - 9 26
Sector requiring special attention: south of A15 between LaSalle and Wellington
![Page 9: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/9.jpg)
New Champlain Bridge Corridor Project
Main Priorities for the Coming Months Verdun / Le Sud-Ouest
![Page 10: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/10.jpg)
New Champlain Bridge Corridor Project
1 2
10
Land
L’Île-des-Soeurs
Location of Sectors: Verdun / Le Sud-Ouest
![Page 11: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/11.jpg)
New Champlain Bridge Corridor Project
Construction of new A15S structures, walls and roads
Overall Plan: Spring 2016 to Fall 2017
Construction of Gaétan-Laberge urban
boulevard
11
Construction of new L’Île-des-Sœurs Bridge
Dismantling of existing A15S structures, walls and roads
![Page 12: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/12.jpg)
New Champlain Bridge Corridor Project
Description of work Approximate duration
Time frame
Legend: Work and Impacts
• Traffic: • Residential proximity: • Public transit: • Active transportation:
Minor Moderate
Major
Impact by colour code
12
![Page 13: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/13.jpg)
New Champlain Bridge Corridor Project
Design and planning under way so modifications are possible
Key Activities Under Way and to Come: Land
![Page 14: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/14.jpg)
New Champlain Bridge Corridor Project
Objective: Widening of A15S and reconfiguration of Atwater interchange and Gaétan-Laberge area
Current and upcoming work:
• Relocation of water mains between LaSalle and Wellington, and in the Atwater area • Partial demolition of Gibbons and Wellington overpasses, and part of A15S
• Reconstruction of A15S overpasses and roadbed
• Major reconfiguration of Atwater interchange and Gaétan-Laberge area
Approach:
• Daytime work especially when impact is major (e.g., noise level)
• Nighttime work when impact on daytime traffic is too significant
• Weekend work when necessary
Land
14
![Page 15: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/15.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: Land
Relocation of the water main between LaSalle and Wellington
Duration: 6 months Time frame: March to August
15
Some work 7 days a week, from 7 a.m. to 7 p.m. with workers
on-site at 6:30 a.m.
![Page 16: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/16.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: Land
16
Partial demolition of A15S overpasses and roadbed
Duration: 9.5 months Time frame: mid-March to December
Wellington closed Weekend of June 17 to 20
and nights beforehand
Demolition slated for August No closure required
![Page 17: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/17.jpg)
New Champlain Bridge Corridor Project
Closure of Wellington Street
Access ramp to A15N
17
![Page 18: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/18.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: Land
18
Partial construction of overpasses Duration: 7 months
Time frame: June to November
![Page 19: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/19.jpg)
New Champlain Bridge Corridor Project 19
• Drainage work • Earthwork • Retaining walls • Paving (spring 2017)
Work and Impacts: Land
Widening of A15S between LaSalle and Wellington
Duration: 1 year with limited work from November to May
Time frame: May 2016 to June 2017
• Drainage work • Earthwork • Retaining walls • Paving (spring 2017)
![Page 20: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/20.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: Land
BEFORE
AFTER
20
Reconfiguration of Atwater south interchange Duration: 1 year
Time frame: July 2016 to July 2017
AFTER
![Page 21: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/21.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: Land
Reconfiguration of Gaétan-Laberge Blvd. Duration: 12 months
Time frame: July 2016 to July 2017
21
![Page 22: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/22.jpg)
New Champlain Bridge Corridor Project
Chosen Rerouting Scenario: Gaétan-Laberge Area
22
Access ramp to A15N
Presentation of the 2016 traffic control and management plan – March 29, 2016 (CIGC)
22
A special communication effort will support the start of work and the impact on mobility
![Page 23: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/23.jpg)
New Champlain Bridge Corridor Project
Closure of Exit 60 on A15N: July 2016 to July 2017
Access ramp to A15N
Closure of Exit 60 on A15N for "Verdun / Rue Wellington"
23
Detour by Atwater
![Page 24: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/24.jpg)
New Champlain Bridge Corridor Project
Design and planning under way so modifications are possible
Key Activities Under Way and to Come: L’Île-des-Soeurs
![Page 25: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/25.jpg)
New Champlain Bridge Corridor Project
L’Île-des-Soeurs
25
Objective: Construction of the New Champlain Bridge's western approach, the new L’Île-des-Sœurs Bridge and the road connecting them
Current and upcoming work:
• Construction of new L’Île-des-Sœurs Bridge's southbound lane • Reconfiguration of overpass adjoining new L’Île-des-Sœurs Bridge • Construction of the New Champlain Bridge's western approach
Approach: • Daytime work especially when impact is major (e.g., noise level)
• Nighttime work when impact on daytime traffic is too significant
• Weekend work when necessary
![Page 26: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/26.jpg)
New Champlain Bridge Corridor Project
Work and Impacts: L’Île-des-Soeurs
Construction of new L’Île-des-Sœurs Bridge Duration: 19 months
Time frame: March 2016 to September 2017
26
• Pile caisson drilling and concreting (under way) • Piers and pier caps (under way) • Superstructure (first beams delivered)
![Page 27: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/27.jpg)
New Champlain Bridge Corridor Project
Overpass reconfiguration work Duration: 6 months
Time frame: April to September
Work and Impacts: L’Île-des-Soeurs
27
![Page 28: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/28.jpg)
New Champlain Bridge Corridor Project
Expected Impacts
![Page 29: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/29.jpg)
New Champlain Bridge Corridor Project
Expected Impacts
• Noise
• Air quality
• Traffic
• Vibrations
29
![Page 30: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/30.jpg)
New Champlain Bridge Corridor Project 30
M1: Sud-Ouest / D'Argenson M2: Sud-Ouest / Butler and Charlevoix M3: Verdun I1: Sax I2: Pointe-Nord I3: Cours des Fougères
Area
Activity
Time Exposed Sensitive
Area
Ambient Noise dBA
Criterion dBA
Estimated Noise dBA
Measures Required D / E / N
Land
Partial demolition of overpasses D M1 / M2 66 / 64 75 69 / 65 No D M3 61 75 83 Yes
Collection of debris E / N M3 60 / 59 65 / 64 TBD TBD
Road demolition D M2 64 75 66 No D M3 61 75 87 Yes
Construction of overpasses D M1 / M2 66 / 64 75 69 / 65 No D M3 61 75 83 Yes
Widening preparation work D M2 64 75 66 No M3 61 75 87 Yes
Relocation of water mains D M3 61 75 90 Yes
Noise Management Ambient noise levels (May 2015) / estimated (March 2016)
![Page 31: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/31.jpg)
New Champlain Bridge Corridor Project 31
M1: Sud-Ouest / D'Argenson M2: Sud-Ouest / Butler and Charlevoix M3: Verdun I1: Sax I2: Pointe-Nord I3: Cours des Fougères
Area
Activity
Time Exposed Sensitive
Area
Ambient Noise dBA
Criterion dBA
Estimated Noise dBA
Measures Required
D / E / N
L’Île
-des
-Sœ
urs West jetty – Prefabrication of footings
D I2 / I3
64 / 57 75 64 Monitoring
required E 59 / 52 64 / 57 60 N 57 / 52 62 / 57 58
Construction of new L’Île-des-Sœurs Bridge D I1 57 75 63 No
Overpass reconfiguration work D I1 57 75 68 No
Noise management Ambient noise levels (May 2015) / estimated (March 2016)
![Page 32: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/32.jpg)
New Champlain Bridge Corridor Project
Air Quality Management
• Four stations for air quality readings
• No expected impact on sensitive areas
• Monitoring mainly required for demolition and earthwork • Dust allayed with water canons • Use of dust control liquid
32
![Page 33: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/33.jpg)
New Champlain Bridge Corridor Project
Traffic
• Narrowing of lanes and reconfiguration of A15 route
• Scheduled closure: Wellington from June 17 to 20 and nights beforehand
• Major changes to drivers' habits as of July 2016 in the Gaétan-Laberge area
33
![Page 34: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/34.jpg)
New Champlain Bridge Corridor Project
Vibration Management
34
• Ongoing monitoring with seismograph in key sensitive areas: if the criteria set for the infrastructures concerned are exceeded, a warning is received and work methods are adjusted to meet the criteria
• Protective cushions used at times to dampen debris impact
shocks during demolition
• Visual assessment prior to construction and re-assessment afterwards
![Page 35: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/35.jpg)
New Champlain Bridge Corridor Project
Follow-up on Actions and Measures from Last Meeting
![Page 36: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/36.jpg)
New Champlain Bridge Corridor Project
Follow-up on Actions and Measures
36
SSL • Location of sound wall: earlier presentation • Development of La Poudrière area: first parts of the answer in the
presentation earlier + presentation on landscaping at next Good Neighbourly Committee meeting
• Urban integration of overpasses: adjustments in progress • Brightness of west jetty worksite: adjustments made
INFC • Environmental offsetting for the entire project (i.e, GHG): discussions
under way with city of Montréal • Possibility of a fourth lane connecting L’Île-des-Soeurs to Verdun,
on the new L’Île-des-Sœurs Bridge: analysis in progress
![Page 37: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/37.jpg)
New Champlain Bridge Corridor Project
Follow-up on Actions and Measures
37
City of Montréal • Access to the L’Île-des-Sœurs Channel from Pointe Saint-Charles:
analysis in progress • Future of the L’Île-des-Sœurs bypass bridge: analysis in progress • Trucking and mobility in Pointe Saint-Charles: observation
Verdun Borough • One-way traffic on Gilberte-Dubé / Rushbrooke: observation
![Page 38: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/38.jpg)
New Champlain Bridge Corridor Project
Next Meeting
![Page 39: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/39.jpg)
New Champlain Bridge Corridor Project
• Good Neighbourly Relations Committee: October 5 (TBC) in Le Sud-Ouest Borough
Topic: landscaping
Next Meeting
39
![Page 40: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/40.jpg)
New Champlain Bridge Corridor Project
● Website: www.newchamplain.ca
● Newsletter: sign up online
● Email: [email protected]
● 24/7 phone line: 514-876-1020
Contact Us
40
@nouv_champlain
![Page 41: Meeting of the Verdun / Le Sud-Ouest - Good Neighbourly Relations Committee](https://reader035.fdocuments.us/reader035/viewer/2022062823/587312d81a28ab673e8b460b/html5/thumbnails/41.jpg)
New Champlain Bridge Corridor Project