FOR Agricultural Produce Market Committee, Rahata ·  · 2018-01-16and to participate e-tendering...

129
Contractor APMC Rahata Rahata Agriculture Produce Market Committee 1 e-Tender Specification For Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar, FOR Agricultural Produce Market Committee, Rahata At. Sakuri, Tal. Rahata, Dist. Ahmednagar – 423107 Ph. No. (02423) 42319, e-mail: [email protected] Architect Ar. Sheetal C. Bhutada Bhutada Consultants Niwara Housing Society, Morage Wasti, Shrirampur, Dist. Ahemadnagar, Pin – 413 709 Tel. (02422) 210227, Fax. 210327 Mobile 9423160663 email: [email protected]

Transcript of FOR Agricultural Produce Market Committee, Rahata ·  · 2018-01-16and to participate e-tendering...

Contractor APMC Rahata

Rahata Agriculture Produce Market Committee 1

e-Tender Specification

For Proposed

Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar,

FOR

Agricultural Produce Market Committee, Rahata

At. Sakuri, Tal. Rahata, Dist. Ahmednagar – 423107 Ph. No. (02423) 42319, e-mail: [email protected]

Architect

Ar. Sheetal C. Bhutada

Bhutada Consultants Niwara Housing Society, Morage Wasti,

Shrirampur, Dist. Ahemadnagar, Pin – 413 709

Tel. (02422) 210227, Fax. 210327

Mobile 9423160663

email: [email protected]

Contractor APMC Rahata

Rahata Agriculture Produce Market Committee 2

e-Bid

For Proposed

Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar,

At Sakuri APMC, Tal. Rahata, Dist. Ahmednagar (Maharashtra)

e-BID REFERENCE : e-Tender/APMC RAHATA/Sakuri/2017-18

PUBLISHING OF ETENDER : 16/01/2018

PRE TENDER CONFERENCE : 25/01/2018 at 11.00 hours

LAST DATE OF SUBMISSION OF TENDER : 01/02/2018 up to 5.00PM

DATE & TIME OF OPENING( E1) OF

TENDER

: 05/02/2018 up to 12.00 Hrs

(If possible)

COST OF TENDER DOCUMENT : Rs. 1,180/- (Non Refundable) (Including

GST)

PLACE OF SUBMISSION & OPENING OF TENDER

Agricultural Produce Market Committee, Rahata

At. Sakuri, Tal. Rahata, Dist. Ahmednagar – 423107

Contractor APMC Rahata

Rahata Agriculture Produce Market Committee 3

I N D E X

SR. NO. C O N T E N T S PAGE NO.

1. Tender Notice / Invitation of Bids 1 to 19

2. Instructions to tenderers 20 to 26

3. Solvancy Certificate / Affidavit 27 & 28

4. Proforma for Furnishing Technical Particulars 29 to 33

5. Form of Bank Guarantee Bond 34

6. Declaration of Contractor 35

7. General Rules, directions for the Guidance for Contractors 36 to 38

8. Appendix of the Project 39

9. Tender for Works 40 to 41

10. Conditions of Contract 42 to 65

11. General Instruction to Tenderers 66 to 68

12. Additional General Instruction to Tenderers & Declaration 69 to 107

13. Undertaking 108

14. Miscellaneous 109 to 111

15. Schedule B 112 to 127

Contractor APMC Rahata

Rahata Agriculture Produce Market Committee 4

Tender Notice to be published in News Paper

Agricultural Produce Market Committee, Rahata

At. Sakuri, Tal. Rahata, Dist. Ahmednagar – 423107 Ph. No. (02423) 242319, e-mail: [email protected]

e-TENDER NOTICE APMC Rahata invites Percentage Rate B-1 Type-tenders for Civil Construction works of various projects from reputed & experienced contractors for the following works. Details are as follows:

No Name of the Project Estimated cost

(Rupees)

Type of Tender

1. Construction of Road Base Work, Internal Concrete Road

Rigid Pavement & Concrete Gutter in South side of

Sakuri Main Market, Tal. Rahata, Dist. Ahmednagar

3,24,32,187.00 B-1

2. Proposed Construction of Toilet Block, at Loni - Sheli

Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar 24,91,716.00 B-1

3 Proposed Construction of Toilet Block, at Sakuri Main

Market, Tal. Rahata, Dist. Ahmednagar 24,44,965.00 B-1

For Detail Tender notice please visit https://adf.maharashtra.etenders.in

Secretary

Contractor APMC Rahata

Rahata Agriculture Produce Market Committee 5

Detailed Tender Notice (Published on Web-Site)

Agricultural Produce Market Committee, Rahata

At. Sakuri, Tal. Rahata, Dist. Ahmednagar – 423107 Ph. No. (02423) 42319, e-mail: am_rahata@APMC RAHATA.com

e-TENDER NOTICE Agricultural Produce Market Committee (APMC), Rahata invites Percentage rate B-1 Type-tenders for Civil Construction work of various projects from reputed & experienced contractors for the following works. Details are as follows :

No. Name Of Work Estimated cost

(Rupees) EMD

Completion Period

Tender Cost in Rs.

1. Construction of Toilet Block, at Loni - Sheli

Mendhi Bazaar, Tal. Rahata, Dist.

Ahmednagar

24,91,716.00.00 1% of Estimated

Cost 25000.00

6 Months (Including

Rainy season)

1180/-

1. Blank Tender documents would be available on Government of Maharashtra site https://maharashtra.etender.in from 16/01/2018 to 01/02/2018 for downloading.

2. The cost of tender should be in the form of Online Payment mode only. 3. Last date of submission of tenders 01/02/2018 up to 17.00 Hrs. 4. Physical document (Envelope No.1) submission date is 01/02/2018 at 17.00 Hrs. 5. Technical Bid opening date is 05/02/2018 at 12.00 Hrs. 6. Commercial bid opening date will be conveyed separately. 7. EMD as above should be in the form of Online payment mode only. 8. Pre Tender conference will be held at 11.00 am of 25/01/2018 at APMC ’s office at Sakuri 9. Commercial bid opening date will be conveyed separately. 10. EMD as above should be in the form of Online payment mode only. 11. Pre Tender conference is not taken for this work. 12. The Tenderer should fulfill the following criteria: A. Attested copies of registration, GST certificates. B. Attested copy of Certificate as a registered contractor with the government of Maharashtra in PWD

in appropriate class is must. C. Tenderer should produce P.F. & ESIC registration after the tender allotment. D. Tenderer should have professional tax / GST registration. E. Single similar type of work for both civil done certificate in all the three year with minimum of single

work cost equal to estimated cost. F. Annual turnover must be equal to estimated cost for each individual work in every year of last three

years. G. Photo copy of Income Tax returns for the year of Annual year 2014-15, 2015-16, 2016-17. H. Corrigendum / Addendum, if any will be available only on website http://mahatenders.gov.in The rights to accept or reject any or all the tenders without assigning any reasons thereof are reserved by APMC.

Secretary

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 6

Additional Technical Details

Participating in the on‐line e‐Tendering process is required to regularly visit the website of

the Directorate for getting updates about the tender process.

1. The interested and qualified Authorization from manufacturer shall download e-tenders

and to participate e-tendering procedure, by using website portal

https//adf.maharashtra.etenders.in

2. The interested manufacturer shall have enrollment with above website and have digital

signature certificate. In this regard if there is any quarries, they may contact telephone number

of M/s. Sify Technologies Ltd. Nextender (India) Pvt. Ltd., Mumbai. On 020-

25315555/25315556 (Pune)

3. The manufacturer will have to pay Rs.1058.00 as downloading charges of e-tenders for

each work directly to the Sify Technologies Ltd. Nextender (India) Pvt. Ltd., Mumbai.

4. The interested contractors will have to submit all required documents Online i.e. copy of

authorization from manufacturer Income Tax, Sale Tax, VAT Registration, PAN No. and TIN

No. etc. with Earnest money Deposit, cost of blank tender for m (in Online Payment Mode)

Before last date of tender preparation, Otherwise he shall not consider f or online e-

tendering procedure.

5. The offer will be valid for 120 days from the opening of the tender.

6. The other terms and condition are available in e-tender form on above website.

7. The authority reserved the right to reject any all tenders so, received without assigning

any reason and no explanation can be demanded for the rejection of the offer by the

person/firm making tender.

8. The office is not responsible for postal delay if any.

9. No escalation will be paid.

10. Presence of the manufacture or his representative is essential for tender opening otherwise

there tender will not be considered.

11. The date of opening of commercial envelop is tentative and subject to change as per date

and time finalized by speaker, APMC, Rahata.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 7

Note:

* Realisation of NEFT/RTGS payment normally takes 2 to 24 hours, so it is

advised to make sure that NEFT/RTGS payment activity should be completed

well before time.

* NEFT/RTGS option will be depend on the amount of EMD.

* Help File regarding use of ePayment Gateway can be downloaded from

eTendering portal.

A) Terms and Conditions For Online-Payments

The Terms and Conditions contained herein shall apply to any person (“User”) using

the services of JCMC Maharashtra, hereinafter referred to as “Merchant”, for making

Tender fee and Earnest Money Deposit (EMD) payments through an online Payment

Gateway Service (“Service”) offered by ICICI Bank Ltd. in association with E Tendering

Service provider and Payment Gateway Service provider through JCMC Maharashtra

website i.e. http://pwd.maharashtra.etenders.in. Each User is therefore deemed to

have read and accepted these Terms and Conditions. Privacy Policy

The Merchant respects and protects the privacy of the individuals that access the

information and use the services provided through them. Individually identifiable

information about the User is not willfully disclosed to any third party without first

receiving the User's permission, as covered in this Privacy Policy.

This Privacy Policy describes Merchant’s treatment of personally identifiable

information that Merchant collects when the User is on the Merchant’s website. The

Merchant does not collect any unique information about the User (such as User's

name, email address, age, gender etc.) except when you specifically and knowingly

provide such information on the Website. Like any business interested in offering the

highest quality of service to clients, Merchant may, from time to time, send email to the

User and other communication to tell the User about the various services, features,

functionality and content offered by Merchant's website or seek voluntary information

fromThe User.Please be aware, however, that Merchant will release specific personal

information about the User if required to do so in the following cirumstances:

a) in order to comply with any valid legal process such as a search warrant, statute, or

court order, or available at time of opening the tender

b) if any of User’s actions on our website violate the Terms of Service or any of our

guidelines for specific services, or

c) to protect or defend Merchant’s legal rights or property, the Merchant’s site, or the

Users of the site or;

d) to investigate, prevent, or take action regarding illegal activities, suspected fraud,

situations involving potential threats to the security, integrity of Merchant’s

website/offerings.

Once a User has accepted these Terms and Conditions, he/ she may register on

Merchant’s website and avail the Services.

2. Merchant's rights, obligations, undertakings shall be subject to the laws in force in

India, as well as any directives/ procedures of Government of India, and nothing

contained in these Terms and Conditions shall be in derogation of Merchant's right to

comply with any law enforcement agencies request or requirements relating to any

User’s use of the website or information provided to or gathered by Merchant with

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 8

respect to such use. Each User accepts and agrees that the provision of details of his/

her use of the Website to regulators or police or to any other third party in order to

resolve disputes or complaints which relate to the Website shall be at the absolute

discretion of Merchant.

3. If any part of these Terms and Conditions are determined to be invalid or

unenforceable pursuant to applicable law including, but not limited to, the warranty

disclaimers and liability limitations set forth herein, then the invalid or unenforceable

provision will be deemed superseded by a valid, enforceable provision that most

closely matches the intent of the original provision and the remainder of these Terms

and Conditions shall continue in effect.

4. These Terms and Conditions constitute the entire agreement between the User and

Merchant. These Terms and Conditions supersede all prior or contemporaneous

communications and proposals, whether electronic, oral, or written, between the User

and Merchant. A printed version of these Terms and Conditions and of any notice

given in electronic form shall be admissible in judicial or administrative proceedings

based upon or relating to these Terms and Conditions to the same extent and subject

to the same conditions as other business documents and records originally generated

and maintained in printed form.

5. The entries in the books of Merchant and/or the Payment Gateway Service Providers

kept in the ordinary course of business of Merchant and/or the Payment Gateway

Service Providers with regard to transactions covered under these Terms and

Conditions and matters therein appearing shall be binding on the User and shall be

conclusive proof of the genuineness and accuracy of the transaction.

6. Refund For Charge Back Transaction: In the event there is any claim for/ of charge

back by the User for any reason whatsoever, such User shall immediately approach

Merchant with his/ her claim details and claim refund from Merchant alone. Such

refund (if any) shall be effected only by Merchant via payment gateway or by means of

a demand draft or such other means as Merchant deems appropriate. No claims for

refund/ charge back shall be made by any User to the Payment Gateway Service

Provider(s) and in the event such claim is made it shall not be entertained.

In these Terms and Conditions, the term “Charge Back” shall mean, approved and

settled credit card or net banking purchase transaction(s) which are at any time

refused, debited or charged back to merchant account (and shall also include similar

debits to Payment Gateway Service Provider's accounts, if any) by the acquiring bank

or credit card company for any reason whatsoever, together with the bank fees,

penalties and other charges incidental thereto.

8. Refund for fraudulent/duplicate transaction(s): The User shall directly contact

Merchant for any fraudulent transaction(s) on account of misuse of Card/ Bank details

by a fraudulent individual/party and such issues shall be suitably addressed by

Merchant alone in line with their policies and rules.

9. Server Slow Down/Session Timeout: In case the Website or Payment Gateway Service

Provider’s webpage, that is linked to the Website, is experiencing any server related

issues like ‘slow down’ or ‘failure’ or ‘session timeout’, the User shall, before initiating

the second payment,, check whether his/her Bank Account has been debited or not

and accordingly resort to one of the following options:

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 9

i. In case the Bank Account appears to be debited, ensure that he/ she does not make

the payment twice and immediately thereafter contact Merchant via e-mail or any other

mode of contact as provided by Merchant to confirm payment.

ii. In case the Bank Account is not debited, the User may initiate a fresh transaction to

make payment.

However, the User agrees that under no circumstances the Payment Gateway Service

Provider shall be held responsible for such fraudulent/duplicate transactions and hence

no claims should be raised to Payment Gateway Service Provider No communication

received by the Payment Gateway Service Provider(s) in this regard shall be

entertained by the Payment Gateway Service Provider.

Limitation of Liability

1. Merchant has made this Service available to the User as a matter of convenience.

Merchant expressly disclaims any claim or liability arising out of the provision of this

Service. The User agrees and acknowledges that he/ she shall be solely responsible

for his/ her conduct and that Merchant reserves the right to terminate the rights to use

of the Service immediately without giving any prior notice thereof.

2. Merchant and/or the Payment Gateway Service Providers shall not be liable for any

inaccuracy, error or delay in, or omission of (a) any data, information or message, or

(b) the transmission or delivery of any such data, information or message; or (c) any

loss or damage arising from or occasioned by any such inaccuracy, error, delay or

Commission, non-performance or interruption in any such data, information or message.

Under no circumstances shall the Merchant and/or the Payment Gateway Service

Providers, its employees, directors, and its third party agents involved in processing,

delivering or managing the Services, be liable for any direct, indirect, incidental, special

or consequential damages, or any damages whatsoever, including punitive or

exemplary arising out of or in any way connected with the provision of or any

inadequacy or deficiency in the provision of the Services or resulting from unauthorized

access or alteration of transmissions of data or arising from suspension or termination

of the Services.

1. The Merchant and the Payment Gateway Service Provider(s) assume no liability

whatsoever for any monetary or other damage suffered by the User on account of:

(I) the delay, failure, interruption, or corruption of any data or other information

transmitted in connection with use of the Payment Gateway or Services in connection

thereto; and/ or (ii) any interruption or errors in the operation of the Payment Gateway.

4. The User shall indemnify and hold harmless the Payment Gateway Service Provider(s)

and Merchant and their respective officers, directors, agents, and employees, from any

claim or demand, or actions arising out of or in connection with the utilization of the

Services.

The User agreethat Merchant or any of its employees will not be held liable by the

User for any loss or damages arising from your use of, or reliance upon the information

contained on the Website, or any failure to comply with these Terms and Conditions

where such failure is due to circumstance beyond Merchant’s reasonable control.

Miscellaneous Conditions :

Any waiver of any rights available to Merchant under these Terms and Conditions

shall not mean that those rights are automatically waived.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 10

1. The User agrees, understands and confirms that his/ her personal data including

without limitation details relating to debit card/ credit card transmitted over the Internet

may be susceptible to misuse, hacking, theft and/ or fraud and that Merchant or the

Payment Gateway Service Provider(s) have no control over such matters.

2. Although all reasonable care has been taken towards guarding against unauthorized

use of any information transmitted by the User, Merchant does not represent or

guarantee that the use of the Services provided by/ through it will not result in theft

and/or unauthorized use of data over the Internet.

3. The Merchant, the Payment Gateway Service Provider(s) and its affiliates and

associates shall not be liable, at any time, for any failure of performance, error,

omission, interruption, deletion, defect, delay in operation or transmission, computer

virus, communications line failure, theft or destruction or unauthorized access to,

alteration of, or use of information contained on the Website.

4. The User may be required to create his/ her own User ID and Password in order to

register and/ or use the Services provided by Merchant on the Website. By accepting

these Terms and Conditions the User agrees that his/ her User ID and Password are

very important pieces of information and it shall be the User’s own responsibility to

keep them secure and confidential. In furtherance hereof, the User agrees to;

i. Choose a new password, whenever required for security reasons.

ii. Keep his/ her User ID & Password strictly confidential.

iii. Be responsible for any transactions made by User under such User ID and

Password.

The User is hereby informed that Merchant will never ask the User for the User’s

password in an unsolicited phone call or in an unsolicited email. The User is hereby

required to sign out of his/ her Merchant account on the Website and close the web

browser window when the transaction(s) have been completed. This is to ensure that

others cannot access the User’s personal information and correspondence when the

User happens to share a computer with someone else or is using a computer in a

public place like a library or Internet café.

Debit/Credit Card, Bank Account Details

1. The User agrees that the debit/credit card details provided by him/ her for use of the

aforesaid Service(s) must be correct and accurate and that the User shall not use a

debit/ credit card, that is not lawfully owned by him/ her or the use of which is not

authorized by the lawful owner thereof. The User further agrees and undertakes to

provide correct and valid debit/credit card details.

2. The User may make his/ her payment(Tender Fee/Earnest Money deposit) to Merchant

by using a debit/credit card or through online banking account. The User warrants,

agrees and confirms that when he/ she initiates a payment transaction and/or issues

an online payment instruction and provides his/ her card / bank details:

i. The User is fully and lawfully entitled to use such credit / debit card, bank account for

such transactions;

ii. The User is responsible to ensure that the card/ bank account details provided by him/

her are accurate;

iii. The User is authorizing debit of the nominated card/ bank account for the payment of

Tender Fee and Earnest Money Deposit

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 11

iv. The User is responsible to ensure sufficient credit is available on the nominated card/

bank account at the time of making the payment to permit the payment of the dues

payable or the bill(s) selected by the User inclusive of the applicable Fee.

Personal Information

3. The User agrees that, to the extent required or permitted by law, Merchant and/ or the

Payment Gateway Service Provider(s) may also collect, use and disclose personal

information in connection with security related or law enforcement investigations or in

the course of cooperating with authorities or complying with legal requirements.

4. The User agrees that any communication sent by the User vide e-mail, shall imply

release of information therein/ therewith to Merchant. The User agrees to be contacted

via e-mail on such mails initiated by him/ her.

5. In addition to the information already in the possession of Merchant and/ or the

Payment Gateway Service Provider(s), Merchant may have collected similar

information from the User in the past. By entering the Website the User consents to the

terms of Merchant’s information privacy policy and to our continued use of previously

collected information. By submitting the User’s personal information to us, the User will

be treated as having given his/her permission for the processing of the User’s personal

data as set out herein.

6. The User acknowledges and agrees that his/ her information will be managed in

accordance with the laws for the time in force.

Payment Gateway Disclaimer

The Service is provided in order to facilitate payment of Tender Fees/Earnest Money

Deposit online. The Merchant or the Payment Gateway Service Provider(s) do not

make any representation of any kind, express or implied, as to the operation of the

Payment Gateway other than what is specified in the Website for this purpose. By

accepting/ agreeing to these Terms and Conditions, the User expressly agrees that his/

her use of the aforesaid online payment service is entirely at own risk and responsibility

of the User.

10. EARNEST MONEY AND SECURITY DEPOSIT.

(i) Earnest money shall be paid via online using NEFT/RTGS or payment

gateway mode.

(ii) After Tender opening, the EMD of the unsuccessful bidder will be returned to

account provided by the bidder during the bid preparation as given in challan

under Beneficiary Account Number.

10.2 Earnest money in any other form or cash or cheque will not be accepted

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 12

D I S C L A I M E R

1. Detailed Time Table for the various activities to be performed in e-tendering process by the

Tenderer for quoting their offer is given in this Tender Document under Tender Schedule.

Contractor should carefully note down the cut-off dates for the carrying out each e-tendering

process / activity.

2. Every effort is being made to keep the Website up to date and running smoothly 24 x 7 by the

APMC RAHATA and the Service Provider. However, APMC RAHATA takes no responsibility, and

will not be liable for, the website being temporarily unavailable due to any technical issue at any

point of time.

3. In that event APMC RAHATA will not be liable or responsible for any damages or expenses

arising from any difficulty, error, imperfection or inaccuracy with this Website. It includes all

associated services or due to such unavailability of the Website or any part thereof or any

contents or any associated services.

4. Tenderers must follow the time table of e-tendering process and get their activities of e-

tendering processes done well in advance so as to avoid any inconvenience due to unforeseen

technical problem if any.

5. APMC RAHATA will not be responsible for any incomplete activity of e-tendering process of the

tenderer due to technical error/ failure of website and it cannot be challenged by way of appeal,

arbitration and in the Court of Law. Contractors must get done all the e-tendering activities well in

advance.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 13

DETAILS OF WORK

NAME OF WORK : Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar (Maharashtra)

Estimated cost of work : Total Civil Work : 24,91,716.00.00

Earnest Money 1% : Rs. 25,000/- (Rs Twenty Five Thousand only).

Term Deposit Receipt of Schedule Bank / Nationalized Bank / State Bank of India Challan (Not Allowed any E.SECRETARY Exemption Certificate). Total Security Deposit 5% ( Five Percent).

(i) Initial Security Deposit: Rs. 25,000/-

(ii) At the time of Acceptance of Tender Rs. 50,000/-

(ii) and Further Security Deposit to be deducted from bills.: Rs. 50,000/-

Total Security Deposit: Rs. 1,25,000/-

Registration Class of Contractor: Class VI(Civil) and above

Validity Period: 120 days from the date of opening.

Time limit for completion of work: 6 months (including monsoon)

Cost of Blank Tender Form: Rs. 1,180/-

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 14

TENDER SCHEDULE

Schedule of Dates

Seq No ADF Stage Vendor Stage Start Date & TimeExpiry Date & Time View Forms Envelops

1 Release Tender - 16-01-2018 10:00 16-01-2018 15:00 - -

2 - Tender Download 16-01-2018 15:01 01-02-2018 17:00 �

Commercial

Envelope

C1,Technical

Envelope T1

3 - Bid Preparation 16-01-2018 15:01 01-02-2018 17:00 �

Commercial

Envelope

C1,Technical Envelope T1

4 Close For Technical Bid - 01-02-2018 17:01 02-02-2018 17:00 - Technical

Envelope T1

5 Close For Price Bid - 01-02-2018 17:01 02-02-2018 17:00 - Commercial

Envelope C1

6 - Bid Submission 02-02-2018 17:01 04-02-2018 22:00 �

Commercial

Envelope C1,Technical

Envelope T1

7 Technical Bid Opening - 05-02-2018 10:01 05-02-2018 17:00 - Technical

Envelope T1

8 Price Bid Opening - 06-02-2018 10:01 06-02-2018 17:00 - Commercial Envelope C1

Pre Tender conference is not taken for this work

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 15

TO BE FILLED BY THE CONTRACTOR

I / We have quoted my / our offer in percentage rate in words as well as figures.

I/We further undertake to enter into contract in regular “B-1” Form of Public Works

Department.

Name and signature of Contractor :

Power of Attorney holder :

With complete Address :

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 16

Agricultural Produce Market Committee (APMC), Rahata INVITATION FOR TENDERS(Short Period)

DETAILED TENDER NOTICE TO CONTRACTOR NAME OF WORK : - Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar, 1.0) Online percentage rate tenders in 'B-1' Form are invited by the Agriculture Produce Market Committee (APMC ), Rahata. for the following work from Contractors. registered in appropriate class of the Public Works Department of Maharashtra State. The name of work, estimated cost, earnest money, security deposit, time limit for completion etc. are as under.

Sr.No Name of work

Name of work Estimated

Cost (Rupees)

Earnest Money

(Rupees)

Security Deposit

(Rupees)

Class of Contractor

Time limit in Tender (Calendar months)

1 Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar

24,91,716.00.00 25,000 Initial Rs. 25,000/- After Acceptance of Tender Rs. 50,000/- Through Bills Rs. 50,000/- Total Rs. 1,25,000/-

Class VI (Civil)

6 Calender Months including monsoon.

1.1 Tender form, conditions of contract, specifications and contract drawings can be downloaded from the e-tendering portal http://mahatenders.gov.in to the registered Contractors of appropriate category i.e. Class VI (Civil) after entering the details payment of Rs. 1,180/- (Rupees One Thousand, One Hundred & Eighty only.) in the form of Online Payment mode as per the Tender Schedule. Further information regarding the work can be obtained from the above office. 1.2 The Tender Fee in the form of Online payment mode as per the Tender Schedule. Bids will be opened as per the Tender Schedule, in the presence of such intending Tenderers or his/ their authorized representatives who may be present at that time. 1.3 The offer of the Contractor shall remain valid for acceptance for a minimum period of 120 days from the date fixed for opening of Envelope No. 2 (Main Tender) and thereafter until it is withdrawn by the Contractor by notice in writing duly addressed to the authority opening the tender and sent by Registered Post Acknowledgement Due. 1.4 The tender notice shall form a part of the contract agreement. 1.5 The tenders are invited on the Departmental design only 1.6 The tenderer if firm or company shall in their forwarding letter mention the names of all the partners of the firm or the company (as the case may be) and the name of the partner who holds the power attorney if any, authorizing him to conduct transaction on behalf of the Firm or Company. 1.7 Right is reserved to revise or amend the contract documents fully or part thereof prior to the date notified for the receipt of tender. Such deviations/ amendments if any shall be communicated in the form of corrigendum or by a letter as may be considered suitable.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 17

1.8 The tenderer shall enter his percentage rates in words and figures "below / above". In case there is difference between percentage written in figures and words, the lower offer will be taken as final. 1.9 No pages should be removed from, added in or replaced in the Tender. 1.10 Right is reserved to reject any or all tenders without assigning any reason thereof. 1.11 Tenders which do not fulfill all or any conditions or are incomplete in any respect are liable to summary rejection. 1.12 The Tenderer may, in the forwarding letter, mention any points he may wish to make clear but right is reserved to reject the same of the whole of the tenders if the same become conditional tender thereby.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 18

PRELIMINARIES Name of work:- 1. Proposed Construction of Toilet Block, at Loni - Sheli Mendhi

Bazaar, Tal. Rahata, Dist. Ahmednagar,

2.1 Name of Owner: Agriculture Produce Market Committee, At. Sakuri, Tal Rahata, Dist.

Ahmednagar – 423107

2.2 The site of the work is in Main market, At. Sakuri, Tal. Rahata, Dist. Ahmednagar are

invited by Agriculture Produce Market Committee (APMC RAHATA), Rahata.

2.3 The contractor is advised to visit and inspect the site (and existing premises, nature of work,

etc.) prior to tendering and no claim will have allowed on the grounds of ignorance of the

conditions under which works will be executed.

2.4 The work will consist of Proposed Construction of Toilet Block, at Loni - Sheli Mendhi

Bazaar,, Tal. Rahata, Dist. Ahmednagar.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 19

INVITATION OF BIDS

1.0 The Agriculture Produce Market Committee (APMC RAHATA) here in after referred to as

“APMC RAHATA” now invites sealed percentage rate tenders from having reputed &

experienced contractors register in appreciate class is must of PWD of Maharashtra for the

1. Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata,

Dist. Ahmednagar

2.0 Interested eligible tenderers / bidders may obtain further information from and inspect the

bidding documents at the office of Agriculture Produce Market Committee, At. Sakuri, Tal

Rahata, Dist. Ahmednagar – 423107

3.0 A complete set up of bidding documents may be purchased by any interested bidder upon

payment of a non-refundable fee as specified in tender notice.

4.0 Detailed terms and conditions as well as the technical specifications for all items as

indicated in the invitation to bid are contained in the bidding documents. Only one set of

document shall be sold to one bidder.

5.0 The APMC RAHATA shall not take the responsibility for any delay in receipt of the bidding

document if it is sent by post.

6.0 The bids will be opened in the presence of those bidders or their authorized representative

who choose to attend at the office of the APMC RAHATA, Rahata on the specified date and

time.

7.0 For any clarification please contact office of APMC RAHATA.

8.0 The APMC RAHATA at its sole discretion and without assigning any reasons there of

reserves the right to accept and /or reject any or all bids. APMC RAHATA also does not

bind to accept the lowest bid.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 20

Instructructions To Tenderers:-

GENERAL a) Time Limit :- The work is to be completed within time limit as specified in the Notice

inviting tender which shall be reckoned from the date of written order of commencing the

work and shall be inclusive of monsoon period.

b) Tender rate :- No alteration in the form of tender and the schedule of tender and no

additions in the scope of special stipulation will be permitted. Rates quoted for the tender

shall be taken as application to all leads and lifts.

c) Tender Units :- The tenderer’s should particularly note the unit mentioned in the Schedule

‘B’ on which the rates are based. No change in the units shall be allowed. In the case of

difference between rates written in figures and words, the correct rate will be the one, which

is lower of the two.

d) Correction :- No corrections shall be made in the tender documents. Any corrections that

are to be made shall be made by crossing the incorrect portion and writing the correct

portions above with the initials of the tenderer.

e) All pages of tender documents, conditions, specifications, corrections slips etc. shall be

initialed by the tenderer. The tender should bear full signature of the tenderer, or his

authorized power of attorney holder in case of firm.

f) The GST is shall be deducted from R.A. Bill amount Whether measured bill, advance

payment or secured advance as per Government of India, GST Council Rules and rates as

per applicable rate.

g) The Income tax @ 2% or percentage in force from time to time or at the rates as

intimated by the competent Income Tax authority shall be deducted from bill amount whether

measured bill, advance payment or secured advance.

h) Royalty :- Royalty shall be recovered from R.A. bills, if challans of revenue authority is

not submitted at the rates in force from time to time or at the rate as intimated by the

competent Revenue and Forest Department Authority.

2. EARNEST MONEY :- 2.1 Earnest money of Rs. 25,000/- (In words:- Rupees Twenty Five Thousand only) along with

the tender should be in the form of Online Payment mode.

2.2 Earnest Money Deposit exemption certificate shall not be accepted.

2.3 Tender of those who do not deposit earnest money in one of the above acceptable forms

shall be summarily rejected. Earnest money in any other form of cash or cheque will not

be accepted.

2.4

The amount of earnest money will be refunded to the unsuccessful tenderer on deciding

about the acceptance or otherwise of the tender or on expiry of the validity period

whichever is earlier. In case of the successful tenderer it will be refunded on his paying

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 21

the initial security deposit and completing the tender documents or will be transferred

towards a part of security deposit to be paid after awarding of the work. If successful

tenderer does not pay the security deposit in the prescribed time limit and complete the

agreement bond, his earnest money deposit will be forfeited to the APMC RAHATA.

2.5 Earnest money of the un-successful tenderers will be refunded on their application only

after an intimation of rejection of their tender is sent to them or on the expiry of the

validity period whichever is earlier.

3. TENDERING PROCEDURES:

3.1 Issue of blank tender forms :-

Blank Tender Form can be download from https://adf.maharashtra.etenders.in

3.2 Pre-tender Conference:-

3.2.1 Pre-tender conference is not taken for this tender.

3.2.2

3.2.3 3.2.4 3.3 3.3.1 3.3.2 3.3.3

The prospective tenderers are free to ask for any additional information or clarification either in writing or orally concerning the work, and the reply to the same shall be uploaded on https://adf.maharashtra.etenders.in and this clarification referred to as Common Set of Conditions/Deviations (C.S.D.), shall form part of tender documents and which will also be common and applicable to all tenderers. The point/points if any raised in writing and/or verbally/ online by the contractor in pretender conference and not finding place in C.S.D. issued after the pre- bid conference, is/are deemed rejected. In such case the provision in NIT shall prevail. No individual correspondence will be made thereafter with the contractor in this regard. The tender submitted by the tenderer shall be based on the clarification, additional facility offered (if any) by the Department, and this tender shall be unconditional. Conditional tenders shall be summarily REJECTED. All tenderers are cautioned that tenders containing any deviation from the contractual terms and conditions, specifications or other requirements and conditional tenders will be treated as non-responsive. The tenderer should clearly mention in forwarding letter that his offer (in envelope No. 1 & 2) does not contain any conditions, deviations from terms and conditions stipulated in the tender. Shortlisting of Contractors for Financial Bidding Process: The Tendering Authority will first open the Technical Bid documents of all Contractors and after scrutinizing these documents will shortlist the Contractors who are eligible for Financial Bidding Process. The shortlisted Contractors will be intimated by email. Opening of the Financial Bids: The Contractors may remain present in the Office of the Tender Opening Authority at the time of opening of Financial Bids. However, the results of the Financial Bids of all Contractors shall be available on the https://adf.maharashtra.etenders.in e-Tendering Portal immediately after the completion of opening process. Tender Schedule (Key Dates): The Contractors are strictly advised to follow the Dates and Times allocated to each stage in the Time Schedule in the Detailed Tender Notice for the Tender. All the online activities are time tracked and the Electronic Tendering System enforces time-locks that ensure that no activity or transaction can take place outside the Start and End Dates and Time of the stage as defined in the Tender Schedule.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 22

At the sole discretion of the Tender Authority, the time schedule of the Tender stages may be extended.

4.0 MANNER OF SUBMISSION OF TENDER AND ITS ACCOMPANIMENTS: -

i) Tender to be submitted in two separate sealed envelopes.

ii) Tenderer shall submit the tender and documents in two sealed envelopes as below :-

4.1.1 Envelope No.1(Documents) :-

The first envelope clearly marked as “ENVELOPE NO.1” shall contained the following

documents.

a. Forwarding letter clearly including the documents attached therein submitted in the first

cover and invariably stating that the offer in envelope No. 2 is unconditional. Any

conditional offer in forwarding letter by any tenderer in envelope No. 1 will invalidate

the offer.

b. Online Payment for the cost of Tender Document as prescribed in detailed tender notice.

c. Tender Fee and EMD to be paid Via SBI MOPS Online Payment Gateway Mode Only.

And upload successful payment receipt in Envelope No.1 Technical Bid Documents.

d. Attested copy of acknowledged Income tax Return filed for the immediate preceding

financial year

e. Permanent Account Number of the tenderer issued by the Commissioner of Income Tax

f. Attested copy of valid GST Certificate form Maharashtra/ India Goods and Service Tax

Department.

g. Tenderer should have professional tax registration.

h. Attested copies single similar type of work done certificate in all the three year with

minimum of single work cost equal to estimated cost.

i. Details of the other works tendered for and in hand with the value of the work unfinished

on the last date of submission of tender (in Form No .I)

j. Details of works of similar type and magnitude carried out by the Contractor. ( in Form

No. III)

k. Details of technical personnel on the rolls of tender (in Form No. IV)

l. List of Tools, plant and machinery immediately available with the tenderer for use on this

work. (in Form No. II)

m. A valid Solvency Certificate of amount equal to estimated cost of work i.e. Rs. 25 lakhs

from any nationalized / scheduled bank as per format attached herewith in Tender

document. (Page no. 27)

n. Attested copy of Certificate as a registered contractor with the government of

Maharashtra in PWD in appropriate class is must.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 23

o. Annual Turnover certificate from the registered Chartered Accountant should be

attached. (Annual turnover must be equal to estimated cost for each individual work in

every year of last three year.)

p. Technical bid will contain all relevant documents as mentioned above & in the cover

details & other important document submitted online. Tender should be submitted online

as well as attested hard copies of the same should be submitted at the time of technical

bid opening.

Important Note:

1. Please note that omission to attach any documents is likely to invalidate the tender.

2. Also note that failure to enclose un-conditional forwarding letter in envelope No.1 is

likely to invalidate the tender.

3. The Contractor is requested to fill in the name of the firm with full postal address on

page No. 35 and affix signature. Signature of witness with full name & address on page

No. 35 is also compulsory.

4. Earnest Money Deposit exemption certificate shall not be accepted.

5. Unless and until Financial Bid will not be opened if Technical Bid is not satisfied

4.1.2 Envelope No.2 (Main Tender)

Envelope No. 2 (Financial Bid) must be submitted on-line only

The Contractor will have to sign the original copy of the tender papers and the drawing

according to which the work is to be carried out. He shall also have to give a declaration

to the effect that he was fully studied the plans, specifications, local conditions,

availability of labour and materials and that he has quoted his rates with the

consideration to all these factors.

The tenderer should quote his offer on Schedule ‘B’ of the tender as percentage of

estimated rates at the appropriate place of tender documents to be submitted only in

envelope No.2. He should not quote this offer anywhere directly or indirectly in envelope

No.1. The Contractor shall quote for the work as per details given in the main tender and

also based on the detailed set of conditions issued/additional stipulations made by the

Departments informed to his by a letter from APMC RAHATA after Pre-tender

Conference. This tender shall be unconditional.

Even though tenderers meet the above requirement they are subject to be disqualified if

they have made misleading or false representations in the forms statements and

attachments submitted in proof of the qualification requirements

AND/ OR

Record of proof performance such as abandoning the works, not properly completing the

contract, inordinate delay in completion or work litigation history or financial failures etc.

If the tenderer has quoted below to the estimated rates, the additional security deposit

(performance Security) shall be paid additionally as mentioned below.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 24

Rate Quoted to estimated rate Additional security Deposit

(Performance Security)

If the offer submitted is below

schedule ‘B’ rates by more than 1% but

less than 10% of the estimated cost put

to tender

1% of Estimated cost put to tender

If below by more than 10% of the

estimated cost put to tender

1% of the estimated cost put to tender

plus an amount equal to the percentage

by which the offer is below 10% of the

estimated cost put to tender. (e.g. if the

offer is 15.31% below, the performance

security will be 1%+ (15.31-10)= 6.31%

of the estimated cost put to tender.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 25

4.2 SUBMISSION OF TENDER

i. The sealed envelopes No.1 cover shall be marked on the left hand top corner “Proposed

Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist.

Ahmednagar”. should be submitted online as well as Physically and envelopes No. 2

should be submitted online.

Ii The full name and address of the Tenderer and the name of the authorized agent

delivering the sealed cover containing the tender shall be written on the bottom left hand

corner. If submitted by post, the sealed envelope marked as above, shall be enclosed in

another cover properly addressed and shall be sent by Registered Post

Acknowledgement Due. The date and time for receipt of envelope containing tender shall

strictly apply in all cases. The tenderers should ensure that their tender is received By the

Secretary, Agriculture Produce Market Committee, At. Sakuri, Tal Rahata, Dist.

Ahmednagar – 423107 before the expiry of date and time. No delays on account of

any cause will be entertained for the late receipt of tender. Tender offered or received

after the date and time is over will either not be accepted or if inadvertently accepted,

will not be opened and shall be returned to the tenderer unopened.

iii. All Xerox copies submitted in connection with tender shall be Self attested only.

Otherwise their tender will not be considered for further action and envelope No.2 will

not be opened.

4.3 OPENING OF TENDERS

On the date specified in the tender notice following procedure will be adopted for

Opening of the tender.

Envelope No.1 :- First of all, Envelope No.1 of the e-tender will be opened to verify its

contents as per requirements. If the various documents contained in this envelope do not

meet the requirements of the Department, a note will be recorded accordingly by the

tender opening authority and the said tenderer’s Envelope No.2 will not be considered

for further action but the same will be recorded.

The decision of the tender opening authority in this regard will be final and binding on

the contractors.

Envelope No. 2 :- This envelope shall be opened immediately after opening of Envelope

No.1 only if contents of Envelope No.1 are found to be acceptable to the Department,

the tendered rate in Schedule ‘B’ or percentage above/below the estimated rates of

agreement B-1 shall then be read out in the presence of bidders who remain present at

the time of opening of Envelope No. 2

4.4 ACCEPTANCE OF TENDER

4.4.1 The acceptance of tender may be communicated to the Contractor by e-mail or letter

otherwise either by the tender opening authority of APMC RAHATA.

4.4.2 The successful tenderer will be required to produce to the satisfaction of the specified

concerned authority, a valid and concurrent license issued in his favour under provision of

the Contract Labour (regulation and Abolition) Act, 1970 before starting the work. On

failure to do so, the acceptance of tender is liable to be withdrawn and earnest money

forfeited.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 26

4.4.3 The tenderer whose tender is accepted will have to give an undertaking in writing to the

effect that he/they will pay the labours engaged on the work, the wages as per

Minimum Wages Act, 1948, applied to the zone in which the work lies and act

accordingly.

4.4.4 The Contractor shall comply with the provisions of the payment of Wages Act, 1936,

Minimum Wages Act, 1948, Employee’s Liability Act, 1938, Workmen’s Compensation

Act, 1961, The Contract Labour (Regulation and Abolition) Act, 1979, and any

modification thereof or any law relating thereto, and rules made thereunder from time to

time.

4.4.5 The Contractor whose tender is accepted is required to note that no foreign exchange

will be released by the APMC RAHATA.

4.4.6 The Contractor will have to sign the original copy of the tender papers and the drawings

according to which the work is to be carried out. The Contractor shall also have to give a

declaration to the effect that he has fully studied the plans, specifications, local

conditions, and availability of labour and materials and that he has quoted his rates with

the consideration to all these factors.

4.5 SECURITY DEPOSIT

4.5.1

The EMD of successful tenderer shall be converted in to Security deposit, 2% at the time

of acceptance of the tender by way of DD in favour of Agriculture Produce Market

Committee, Rahata and balance 2% security deposit will be recovered from the R. A.

Bills, in total of 5% of the bill amount.

4.5.2

All compensation or other sums payable by the Contractor under the terms of this contract or any other contract or on any account may be deducted from his Security Deposit or from any sums which may be due to him or may become due to him by APMC RAHATA on any account and in the event of the security being reduced by reason of any such above noted deductions, the Contractor shall within 10 days of receipt of notice of demand from the Engineer-in-charge make good the deficit.

4.5.3

There shall be no liability on the APMC RAHATA to pay any interest on the Security Deposited by or recovered from the Contractor.

4.5.4 The Security Deposit shall be refunded after completion of defect liability period prescribed for this contract in accordance with the provisions in Clause1 and 20 of the contract.

4.6 LABOUR WELFARE FUND

4.6.1 The successful tenderer shall have to pay 1% of the tender value in cash as cess under

Labour Welfare Fund as per Government Circular No. BCA 2007 / Pr. No. 788 /

Kamghar – 7A dated 26/10/2009.

4.6.2 The above mentioned cess if not paid to the department before work order the same will

be deducted @ 1% each R.A. Bills & Final Bills for Labour Welfare Fund.

5.0 VALIDITY PERIOD The offer shall remain open for acceptance for minimum period of 120 days from the Date of opening of Envelope No.2 (Financial Bid) and thereafter until it is withdrawn by the contractor by notice in writing duly addressed to the authority opening the tender and sent by Registered Post Acknowledgment due. 6.0 After completion of the e-tendering process, the successful bidder will have to submit the hard copy of downloaded tender document and drawings duly signed on each page by the contractor or his authorised signatory. The tender should bear full signature of the tenderer, or his authorized power of attorney holder in case of Firm.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 27

(On Banks Letter Head)

Date: Private & Confidential ------------------------------------------

----------------------------------------- A/c to (Company Name)

Ref no.

SOLVENCY CERTIFICATE.

We the (Bank Name) do hereby certify that (Name of Contractor Unit

& Unit address) having their Registered office at (Registered Office Address)

is solvent to the extent of Rs. ----------- (Rs --------------------) as disclosed by

the information and records which are available with the aforesaid bank. It is further notified that this certificate is being issued at the request of

(Name of Unit) without attaching any risk and responsibility on our part in

any respect whatsoever more particularly either as guarantor or otherwise. For (Bank Name) .

Sign & Stamp of Bank Manager

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 28

100 Rs. Bond

नमुना स�यत�ा लेख

स�यत�ा (Affidavit)

मी ………………………………………………………………………….. वय………………… वष …………. राहणार

………………………………………………………………………….. या स�य��त�ा लेखा�वारे �लहून देतो क� मी -----

-------------------------------------- या कंपनीचा/फमचा �ो�ायटर/भागीदार असून “Proposed

Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar,, Tal. Rahata, Dist.

Ahmednagar” या कामासाठI �नJवदा सादर केलK आहे. Mया �नJवदेNया Envelope No.1

मSये जी कागदपU ेसादर केलK आहेत ती खरK, बरोबर व पुण आहेत. �यामSये कोणतीहK UुटK,

चुका नाहKत, असे शपथपुवक माZय करKत आहे. Mया कागदपUामंSये काहK चुक�ची [दशाभुल

करणारK, खोटK अपुण मा[हती आढळ^यास मी कायदेशीर कायवाहKस पाU आहे व राहKन.

कं�ाटदार

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 29

FORM NO. I List of works tendered for and in hand as on the date of submission of this tender

Name of the Tenderer:-

Sr.No. Name of work.

Place & Country

Work in hand Anticipated date of completion

Work tendered for Remarks Tendered

cost Cost of remaining

Work

Estimated Cost

Date when decision is expected

Stipulated date of period of completion

1 2 3 4 5 6 7 8 9 10

SPECIMEN FORM

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 30

FORM NO. II Details of plant and machinery immediately available with the tenderer for the work

Name of the Tenderer:-

Sr.No. Name of equipment. No. of

units Kind and make

Capacity Age and Condition

Present Location

Remarks

1 2 3 4 5 6 7 8

SPECIMEN FORM

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 31

FORM NO. III Details of works of similar type and magnitude carried out by the Contractor

Name of the Tenderer :- Sr.No. Name of work. Cost of work Date of starting Stipulated date of

period of completion

Actual date of completion

Remarks

1 2 3 4 5 6 7

SPECIMEN FORM

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 32

FORM NO. IV Details of Technical Personnel available with Contractor

Name of the Tenderer :-

Sr.No. Name of Person Qualifications Whether working

in field or in office Experience of execution of similar works

Period for which the person is working with the tenderer

Remarks

1 2 3 4 5 6 7

SPECIMEN FORM

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 33

IMPORTANT NOTE:

1. Before tendering for the work the contractor should fully study the requirements, site

situation, specifications and tender conditions for the work to be done. He shall study the

complete details given on the drawings and in the Schedule 'B' and specifications to

facilitate him in quoting the correct percentage rate in the tender.

2. If the tenderer is a firm or company, they will have to mention in their forwarding letter,

the names of all the partners of the firm of company and disclose the identity if the

partner who holds power of attorney to conduct the transactions on behalf of the firm or

company in respect of the tendered work.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 34

FORM OF BANK GUARANTEE BOND

In consideration of the Agriculture Produce Market Committee (herein after referred to as “APMC RAHATA”) having agreed to exempt ______________________ (hereinafter referred to as "The Contractor”) from depositing with the APMC RAHATA in cash the sum of Rs.____________(Rupees ___________________________________________________ only ) being the amount of security deposit payable by the Contractor to the APMC RAHATA under the terms and conditions of the agreement dated the ______ day of __________and made between the APMC RAHATA of the one part and the Contractor of the other part (hereinafter referred to as “the said agreement") for_________ as security for the observance and performance by the contractor of the terms and conditions of the said agreement, on the contractor furnishing to the APMC RAHATA a guarantee in the prescribed form of a scheduled bank in India being in fact these presents in the like sum of Rs._____________(Rupees __________________________________________________only). We_________________________________________________BANK/LIMITED registered in India under__________________ Act and having one of our local Head Office at _____________________________________________________ do hereby: 1. Guarantee to the APMC RAHATA:- a) Due performance and observance by the Contractor of the terms, covenants and conditions on the part of the Contractor contained in the said agreement and b) Due and punctual payment by the Contractor to the APMC RAHATA of all sums of money, losses, damages, cost charges, penalties and expenses payable to the APMC RAHATA by the Contractor under or in respect to the said agreement. 2. Undertake to pay to the APMC RAHATA on demand and without demur and notwithstanding any dispute or disputes raised by the Contractor(s) in any suit or proceeding filed in any court of tribunal relating thereto the said sum of Rs. __________ (Rupees __________only) or such less sum may be demanded by the APMC RAHATA from us our liability hereunder being absolute and unequivocal and agree that. 3. a) The guarantee herein contained shall remain in full force and effect during the subsistence of the said agreement and that the same will continue to be enforceable till all the dues of the APMC RAHATA under or by virtue of the said agreement have been duly paid and its claims satisfied or discharged and till the APMC RAHATA certifies that the terms and conditions of the said agreement have been fully, properly carried out by the Contractor. b) We shall not be discharged or released from the liability under this guarantee by reasons of i) any change in the constitution of the bank or the Contractor or; ii) any arrangement entered into between the APMC RAHATA and the Contractor with or without our consent; iii) any forbearance or indulgence shown to the Contractor; iv) any variation in the terms covenant or conditions contained in the said agreement; v) any time given o the Contractor or; vi) any other conditions or circumstances under which, in law, a surety would be discharged. c) Our liability hereunder shall be joint and several with that of the Contractor as if we were principal debtors in respect of the said sum of Rs._________________________ (Rupees____________________________only) valid upto / / 20__ and d) We shall not revoke this guarantee during its currency except with the previous consent in writing of the APMC RAHATA. IN WITNESS WHEREOF the common seal of ________________ has been hereunto affixed this ________________ day of _______ 20 __. The common seal of _____________ was pursuant to the resolution of the Board of Directors of the Company dated the __________ day of herein affixed in the presence of …………………………who, in token thereof, have hereto set their respective hands in the presence of - 1. __________________________ 2._______________________

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 35

Name of work:- Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar,, Tal. Rahata,

Dist. Ahmednagar

DECLARATION OF THE CONTRACTORS

I/We hereby declare that I/We have made myself/ourselves thoroughly conversant with the sub-soil

conditions, the local conditions regarding all materials (such as stone, murum, sand etc) and labour of

which I/we have based my/our rates for this work. The specifications, conditions, bore results and lead of

materials on this work have been carefully studied and understood by me/us before submitting this

tender. I/We undertake to use only the best materials approved by the Engineer-in-charge, Agriculture

Produce Market Committee, Rahata or his duly authorized assistant, before starting the work and to

abide by this decision.

I/We hereby further declare that my/our tender is unconditional in every manner of whatsoever in

nature.

I/We hereby undertake to pay the labours engaged on the work as per Minimum Wages Act, 1948

applicable to the zone concerned.

Signature of Contractor(s)

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 36

PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS

FORM B -1

GENERAL RULES, DIRECTIONS FOR THE GUIDANCE FOR CONTRACTORS

1. All work proposed to be executed by contract shall be notified in a form of invitation to

tender as published in Tender Notice.

This form will state the work to be carried out as well as the date for submitting, and

opening tenders, the time allowed for carrying out the work, also the amount of earnest

money to be deposited with the tender and the amount of the security deposit to be

deposited by the successful tenderer and the percentage, if any, so be deducted from bills.

It will also state weather a refund of a quarry fees, royalties, dues and ground rents will

be granted. Copies of the specifications designs and drawings and estimated rates

schedule rates and any other documents required in connection with the work shall be sign

by the competent authority for the purpose of identification and shall also be open for

inspection by contractor at Agriculture Produce Market Committee (APMC RAHATA).

Where the works are proposed to be executed according to the specifications

recommended other than as mentioned in tender and approved by a competent authority

on behalf of the APMC RAHATA such specifications with designs and drawings shall form

part of the accepted tender.

2. A) In the event of the tender being submitted by a firm, it must be signed by each partner

thereof, and in the event of the absence of any partner, it shall be signed on his behalf by

a person holding a power of attorney authorising him to do so.

B) i) The contractor shall pay along with the tender the sum of Rs 25,000/-(Rupees Ninety

Two Thousand and Four Hundred Only) as and by way of earnest money. The said amount

of earnest money shall not carry any interest whatsoever.

ii) In the event of his tender being accepted, subject to the provisions of sub clause (iii)

below, the said amount of earnest money shall be appropriated towards the amount of

security deposit payable by him under conditions of general conditions of contract.

iii) Below, the said amount of earnest money shall be appropriated towards the amount of

security deposit payable by the tenderer as required under General Conditions of

Contract.

vi) If after submitting the tender the contractor withdraws his offer, or modifies the same or

if after acceptance of his tender the contractor fails or neglects to furnish the balance of

security deposit, without prejudice to any other right and powers of the APMC RAHATA

hereunder, or in law, the APMC RAHATA shall be entitled to forfeit the full amount of the

earnest money deposited by him."

v) In the event of his tender not being accepted, the amount of earnest money deposited by

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 37

the contractor shall unless it is prior thereto is forfeited under the provisions of sub-clause

(iii) above, be refunded to him after passing receipt therefore.

3. Any person who submits a tender shall fill up the usual printed form, stating at what

percentage above or below the rates specified in Schedule-B (memorandum showing items

of work to be carried out) or at the what rates for the items specified in the said schedule

notice inviting tenders shall specify whether the tenderer has to quote a percentage above

or below the rates indicated in the memorandum of items of work or quote rates for the

items mentioned in the said memorandum. He is willing to undertake the work only one

rate or percentage on all the Estimated Schedule Rates shall be named. Tenders which

propose any alterations in the works specified in the said form of invitation to Tender, or in

the time allowed for carrying out the work, or which contain any other conditions may be

liable to rejection. No printed form to tender shall include a tender for more than one

work, but if contractors wish to tender for two or more works, they shall submit a separate

Tender for each. Tenders shall have the name and number of the work they refer written

outside the envelope.

4. The Secretary of APMC RAHATA or their duly authorised representative will open tender in

the presence of contractors who have submitted tenders or their representative who may

be present at the time and he will enter the amounts of the several tenders in a

comparative statement in a suitable form. In the event of a tender being accepted, the

contractor shall therefore, for the purpose of identification sign copies of the specification

and other documents mentioned in Rule 1.

5. The authority to dispose of the tenders shall have the right of rejecting all or any of the

tenders.

6. The memorandum of work to be tendered for and the schedule of materials to be supplied

by the APMC RAHATA and their rates shall be filled in and completed by the Office of the

The Secretary of APMC RAHATA before the tender form is issued. If a form issued to an

intending tenderer has not been so filled in and completed he shall request the said office

to have this done before he completes and delivers his tender.

7. All work shall be measured net by standard measure and according to the rules and custom

of the APMC RAHATA and their rates shall be without any local custom. The measurements

of work will be taken according to the usual method in use in the P.W.D. and no proposal

to adopt alternative method will be accepted.

8. Under no circumstance shall any contractor be entitled to claim enhanced rates for any

items in this contract.

9. Every registered contractor should, produce along with his tender a Certificate of

Registration with the PWD of Government of Maharashtra as approved Contractor in the

appropriate class and renewal of such registration with date of expiry.

10. All corrections and additions or pasted slips should be initialed.

11. The measurements of work will be taken according to the usual methods in use in the

Department and no proposals to adopt alternative methods will be accepted. The APMC

RAHATA’s decision as to what is the usual method in use in the Department will be final.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 38

12.

The tendering Contractor shall furnish a declaration along with tender showing all works for

which he has already entered into contract and the value of the work that remains to be

executed in each case on the date of submitting tender.

13. Every tenderer shall submit along with the tender information regarding Income tax circle,

or ward of the district in which he is assessed to Income-tax the reference to the number of

the assessment and the assessment year, Permanent Account Number PAN No. _________

14. In view of the difficult position regarding the availability of foreign exchange no foreign

exchange would be released by the APMC for the purchase of plant and machinery

required for the execution of the work contracted for_____________________.

15. The contractor will have to construct shed for storing controlled and valuable material

issued to him under Schedule "A" of the agreement, at work site, having double locking

arrangement. The materials will be taken for use in the presence of that departmental

person. No Material will be allowed to be removed from the site of works.

16. The contractors shall also give a list of Machinery in their possession and which they

propose to use on the works.

Successful tenderer will have to produce to the satisfaction of the accepting authority a

valid and current license issued in his favour under the provision of contract Labour

(Regulation & Abolition Act 1973) before starting work failing which acceptance of the

tender will be liable for withdrawal and earnest money will be forfeited.

17. Every Registered Contractor Should Furnish along With Tender a statement showing

previous experience & technical staff employed by him, in the form of statement no. V

18. Successful tenderer will have to produce to the satisfaction of the accepting authority a

valid and current license issued in his favour under the provision of Contract Labour

(Regulation and Abolition) Act, 1973 before starting work, failing which acceptance of the

tender will be liable for withdrawal and earnest money will be forfeited to APMC

RAHATA. (Reference Government of Maharashtra, Irrigation and Power Department’s letter

No.LAB/1076/1181/(666E-17) dated 8/9/1976).

19. The contractor shall comply with the provisions of the Apprentices Act. 1961and the rules

and orders issued there under from time to time. If he fails to do so, his failure will be a

breach of contract and the Secretary, may, in his discretion cancel the contract. The

contractor shall also be liable, for any pecuniary liability arising on account of any

violation by him of the provisions of the Act.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 39

APPENDIX

Estimate / cost of work Rs. 24,91,716.00/-

Total amount of security deposit

(5% or whichever is more)

1% : EMD converted in to SD,

2% at the time of acceptance of the

tender by way of DD and 2% from

R.A. bills.

Earnest money deposit (1%)

(By way of online gateway)

Rs.25,000/- at the time of tender

submission.

Date of Commencement Within a week from date of work

order

Date of Completion 6 Months (Including Monsoon) from

date of work order.

Period of final measurement and

valuation

30 days from date of completion or

date of submission of bill whichever is

later

Defect liability period 1 year from the date of completion of

entire work.

Retention percentage on total value of

work (including extra items and

additional work if any )

5% of actual cost of executed work.

Limit of Retention fund 5% of actual cost of executed work

Installment after virtual completion Nil

Period of honoring certificate 30 days

Validity of tender 120 days

No Mobilization advance and no escalation against material or labour will

consider.

Deduction of all applicable taxes from R. A. and final bills shall be as per the

prevailing rules and regulations of State and Central Government.

Price Variation Clause Not Applicable.

I agree with the appendix and all conditions of the tender.

Name of the Contractor :

Address of the Contractor

:

Date:_________________

Place:_________________

Stamp and Signature of the Contractor

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 40

TENDER FOR WORKS

I/ we hereby tender for the execution, for the APMC RAHATA and of the work specified in the

underwritten memorandum at (in figures) _______________ as well as in words

____________________________________ percent below/ above the estimated rates entered in

schedule 'B' (Memorandum showing items of work to be carried out) and in accordance in all respect with

specifications, designs, drawings and instructions in writing referred to in Rule 1 hereof and in clause of

the annexed conditions of contract.

a) if Several sub-works

are included they should

be detailed in a

separate list.

A) General description: - Proposed Construction of Toilet Block, at Loni -

Sheli Mendhi Bazaar,, Tal. Rahata, Dist. Ahmednagar

B) Estimated cost Rs. 24,91,716.00/-

c) The amount of earnest

money to be deposited

shall be in accordance

with the provisions of

Para 207 PW Manual

Govt. of Maharashtra.

C) Earnest Money Deposit 1% Rs. 25,000/-

D) Security Deposit :- (2%) As per contract value.

i) Initial (not less than the amount of the earnest

money) (2%)

Rs. 50,000/-

ii) To be deducted from current bills. (2%) As per contract value. Total : 5% As per contract value.

d) This deposit shall be

in accordance with

paras 213 and 214 of

the P. W. Manual Govt.

of Maharashtra

Secretary of APMC

where not security

deposit is taken will

very from 5 percent to

10 percent according to

the requirements of the

case where security

deposit is taken:

see note to Clause

of conditions of

contract.

E) Percentage if any to be deducted from bills so as

to make up the total amount required as security

deposit by the time half the work, as measured by

the cost, is done 5 % percent.

3% up to

acceptance of the

tender & 2 % from

RA Bills.

F) Time allowed for the completion of work from

date fixed in written order to commence.

6 Months

f) Give schedule where

necessary showing dates

by which the various

items are to be

completed.

6 Months.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 41

Should this tender be accepted I/ we hereby agree to abide by and fulfill all

the terms and provisions of the conditions of contract annexed hereto so far as

applicable and in default thereof to forfeit and pay to the APMC RAHATA

the sum of money mentioned in the said conditions.

l/We agree that this offer shall remain open for a minimum period of 120

days from the date fixed for opening the same and thereafter until it is

withdrawn by me/us by notice in writing duly addressed to the authority

opening the tenders and sent by Registered post A.D. or otherwise delivered

at the office of such authority.

Tender Fee and EMD to be paid Via SBI MOPS Online Payment Gateway Mode Only. And upload successful payment receipt in Envelope No.1 Technical Bid Documents. The amount of earnest money shall not bear interest and shall be liable to be forfeited to the Corporation/ APMC. should I/ We fail to (1) abide by the stipulation to keep the offer open for the period mentioned above or (2) sign and complete the contract documents as required by the Secretary of APMC RAHATA and furnish the security deposit as specified in item (d) of Memorandum contained in paragraph I above within the time limit laid down in Clause (1) of the annexed General Condition of the Contract. The amount of earnest money may be adjusted towards the security deposit or refunded to me / us if so desired by me /us in writing unless the same or any part thereof has been forfeited as aforesaid. The earnest money will be released to the unsuccessful contractors only after issue of work order to the successful bidder.

Signature of

contractor for

before submission

of tender

Contractor ___________________________________________________

Address (Full) _________________________________________________

_____________________________________________________________

Signature of

witness

Contractors

signature.

Dated the ________________ day of ______________________ 2014

(Witness) _________________________________________________

(Occupation) ______________________________________________

Signature of the

Office by whom

accepted.

The above tender is hereby accepted by me on behalf of APMC RAHATA

Rahata.

APMC RAHATA

Dated the ________________ day of _______________ 2016.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 42

CONDITIONS OF CONTRACT

Security deposit

CLAUSE 1 : The person / persons, whose tender may be accepted (herein

after called the contractor which expression shall unless excluded by or

repugnant to the context include his / heirs executors, administrator, and

assignees) shall within one day for a contract of Rs.1000/- or less or two

days for contract of more than Rs. 1000/- but less than Rs.2000/- and so

on up to a limit of 10 days which may be extended up to fifteen days if

the Secretary thinks, if fit to do so for contract, of over Rs. 10,000/- of

the receipt by him the notification of the acceptance of his tender deposit

with the APMC RAHATA in (if deposited for more than 12 Months) a sum

sufficient which will make up the full security deposit specified in the

tender. Provided always that, in the event of the contractor depositing a

lump sum by way of security deposit as contemplated above, then and in

such case, if the sum so deposited does not amount to Five (5) percent of

the total estimated cost of the work is shall be lawful for Agriculture

Produce Market Committee at the time of making any payment to the

contractor for work done under the contract to make up the full amount of

Five (5) percent by deducting a sufficient sum form every such payment as

last aforesaid until the full amount of the security deposit is made up. All

compensation or other sums of money payable by the contractor to APMC

RAHATA under the terms of his contract may be deducted from, or paid

by the sale of a sufficient part of his security deposit or from the interest

arising there or from any sums which may be due or may become by

APMC RAHATA to the contractor under any other contract or transaction

of any nature, whatsoever and in the event of his security deposit being

reduced by reason of any such deduction or sale as aforesaid, the

contractor shall within ten days hereafter, make good in cash or

Government Securities endorsed as aforesaid any sum or sums which may

have been deducted from or raised by sale of his security deposit or any

part thereof. The security deposit referred to, when paid in cash may at

the cost of the depositor, be converted into interest bearing securities

provided that the depositor has expressly desired this in writing.

If the amount of Security Deposit to be paid in lump within period

specified at above is not paid the tender/contract already accepted

may be considered as cancelled and legal steps taken against the

contractor for recovery of the amounts. The amount of Security Deposit

lodged by the contractor shall be returned along with the payment of

the final bill, if the date up to which the contractor has agreed to

maintain the work in good order is over. The amount of the security

deposit retained by the APMC RAHATA shall be released after defect

liability period is over. The contractor has to maintain the work in good

order till passing of one year.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 43

Compensation for

delay. CLAUSE 2 :

The time allowed for carrying out the work as entered in the tender shall be

strictly observed by the contractor and shall be reckoned from the date on

which the order to commence work is given to the contractor. The work shall

throughout the stipulated period of the contract be proceeded with, all due

diligence (time being deemed to be of the essence of the contract on the part

of the contractor) and the contractor shall pay as compensation on amount

equal to 1 % or such smaller amount as the Secretary of APMC RAHATA

(whose decision in writing shall be final) may decide, of the amount of the

estimated cost of the whole work as shown by the tender for every day that

the work remains un-commenced or unfinished, after the proper dates, And

further ensure good progress during the execution of the work, the contractor

shall be bound, in all cases in which the time allowed for any work exceeds

one month to complete.

The programme for completion of work should be attached in form of bar

chart. the contractor is supposed to carry out the work and keep the progress

as per bar chart. The contractor should complete the work as per phase

period given below, which is arrived from the bar chart.

1/4th of the work in ---------------- ** 1/4 of the time

1/2th of the work in ---------------- ** 1/2 of the time

3/4th of the work in ---------------- ** 3/4 of the time full work to be completed in 6 calendar months (including monsoon)

Note:- The quantity of the work to be done within a particular time to be

specified above shall be fixed and inserted in the blank space kept for the

purpose by the officer competent to accept the contracts after taking into

consideration the circumstances of each case and abide by the programme of

detailed progress laid down by Secretary of APMC RAHATA

In the event of the contractor failing to comply with these conditions he shall,

be liable to pay as compensation an amount equal to one percent or such

smaller amount as the Secretary of APMC RAHATA (whose decision in writing

shall be final) may decide of the said estimated cost of the whole work for

every day that the due quantity of work remains incomplete. provide always

that the total amount of the compensation to be paid under the provisions of

this clause shall not exceed 10 percent of the estimated cost of the work as

shown in the tender. Secretary should be the final authority in this respect. Action when whole of

security deposit is

forfeited.

CLAUSE 3 :

In any case in which under any clauses or clause of this contract the contractor

shall have rendered himself liable to pay compensation amounting to the

whole of his security deposit whether paid in one sum or deducted by

installments or in the case of abandonment of the work owing to serious illness

or death of the contractor or any other cause the Secretary of APMC RAHATA

shall have power to adopt any of the following courses, as forfeited he may

deem best suited the interest of APMC RAHATA.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 44

a) To rescind the contract (of which recession notice in writing to the contractor

under the hand of Secretary of APMC RAHATA shall be conclusive evidence),

and in that case the security deposit of the contractor shall stand forfeited

and be absolutely at the disposal of APMC RAHATA

b) To carry out the work or part of the work departmentally debiting the

contract or with the cost of the work, expenditure incurred on tools and plant,

and charges on, additional supervisory staff including the cost of work-

charged establishment employed for getting the unexecuted part of the work

completed and crediting him with the value of the work done departmentally

in all respects in the same manner and at the same rates as if it had been

carried out by the contractor under the terms of his contract. The certificate of

the Secretary of APMC RAHATA as to the costs and other allied expenses so

incurred and as to the value of the work so done departmentally shall be final

and conclusive against the contractor.

c) To order that the work of the contractor be measured up and to take such

part thereof as shall be unexecuted out of his hands and to give it to another

contractor to complete in which case all expenses incurred on advertisement

for fixing a new contracting agency, additional supervisory staff including the

cost of work charged establishment and cost of the work executed by the new

contract agency will be debited to the contractor and cost of work done or

executed through the new contractor shall be credited to the contractor in all

respects and in the same manner and at the same rates as if it had been

carried out by the contractor under terms of his contract. The certificate of the

Secretary of APMC RAHATA as to all the most of the work and other

expenses incurred as aforesaid for or in getting the unexecuted work done by

the new contractor and as to the value of the work so done shall be final and

conclusive against the contractor.

In case of contract shall be rescinded under clause (a) above, the contractor

shall not be entitled to recover or be paid any sum for any work therefore

actually performed by him under this contract unless and until the Secretary of

APMC RAHATA shall have certified in writing the performance of the such

work and the amount payable to him in respect thereof and he shall only be

entitled to be paid the amount so certified. In the event of either of the

courses referrers to in clause (b) or (c) being adopted and the cost of the work

executed. departmentally or through a new contractor and other allied

expenses exceeding the value of such credited to the contractor, the amount

of excess shall be deducted from any money due to the contractor by the

corporation under the contract of otherwise howsoever or from his security

deposit or the sale proceeds thereof, provided, however, that the contractor

shall have no claim against at the corporation even if the certified value of

the work done departmentally through a new contractor exceeds the certified

cost of such work and allied expenses provided always that whichever, of the

three courses mentioned in clause (a), (b) or (c) is adopted by the Secretary of

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 45

APMC RAHATA the contractor shall have no claim to compensation for any loss

sustained by him by reason of his having purchased, or procured any

materials, or entered into any engagements, or made any advance on

account of or with a view to the execution of the work or the performance or

the contract.

Action when the

progress of any

particular portion of

the works is

unsatisfactory.

CLAUSE 4:

If the progress of any particular portion of the work is unsatisfactory the

Secretary of APMC RAHATA shall not withstanding that the general progress

of the work is satisfactory, in accordance with clause 2 be entitled to take

action under clause 3 (b) after giving the contractor 10 days’ notice in writing

and the contractor will have to claim for compensatory for any loss sustained

by him owing to such action. Contractor remains

liable to pay

compensation if

action not taken

under clause 3 & 4

CLAUSE 5 :

In any case which any of the powers conferred upon the Secretary of APMC

RAHATA by clause 3 and 4 hereof shall have become exercisable and the

same shall not have been exercised the non-exercise thereof shall not

constitute a waiver of any of the conditions hereof and such powers

notwithstanding be exercisable in any future case of default by the contractor

for which by any clause or clauses hereof he is declared liable to pay

compensation amounting to the whole of his security deposit and the liability

of the contractor for past and future compensation shall remain unaffected In

the event of the Secretary of APMC RAHATA taking action Power to take

possession of or sell

contractor’s plant.

under sub-clause (a) or (c) of clause 3, he may, if he so desires, take

possession of all or any tools plants, materials and stores, in or upon the works

of the site here of or belonging to the contractor or procured by him and

intended to be used for execution of the work or any part thereof, paying or

allowing for the same in account at the contract rates, of in the case of

contract rates not being applicable at current market rates, to be certified by

the The Secretary of APMC whose certificate thereof shall be final. In the

alternative the Secretary of APMC RAHATA may, by notice in writing to the

contractor, or his clerk of works foreman or other authorised agent require him

to remove such tools, plant, materials or stores from the premises within a time

to be specified in such notice, and in the event of the contractor falling to

comply with and such requisition The Secretary of APMC. may remove at the

contractor's expense of any such removal, and the amount of the proceeds

and Expense of any such sale shall be final and conclusive against the

contractor. Extension of time.

CLAUSE 6 : If the contractor shall desire an extension of the time for

completion of the work on the ground of his having been unavoidably

hindered in its execution or on any other ground, he shall apply in writing to

the Secretary of APMC RAHATA before the expiration of the period

stipulated in the tender or before the expiration of 30 days from the date on

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 46

which he was hindered as aforesaid or on which the cause for asking for

extension occurred whichever is earlier, and the Secretary of APMC. May, if

in his opinion there are reasonable grounds for granting an extension grant

such extension as he thinks necessary or proper The decision of the Secretary

of APMC RAHATA in this matter shall be final. Final certificate. CLAUSE 7 : On completion of the work the contractor shall be furnished with a

certificate by Secretary of APMC RAHATA of such completion but no such

certificate shall be given for shall the work be considered to be complete until

the contractor shall have removed from the premise on which the work shall

have been executed all scaffolding, surplus materials and rubbish and shall

have cleaned off the dirt from all wood work it doors, windows walls floor or

other part of any building, in or upon which the work has been executed or of

which he may have had possession for the purpose of executing the work nor

until the work shall have been measured by the Engineer-in- charge or where

the measurements have been taken by the sub-ordinate until they have

received the approval of the Engineer-in-charge the said measurements being

binding and conclusive against the contractor, If the contractor shall fail to

comply with the requirements of the clause as to the removal of scaffolding

surplus materials and rubbish, and cleaning off dirt on or before the date

fixed for the completion of the work, the Engineer-in-charge may at the

expense of the contractor, remove such scaffolding, surplus materials and

rubbish and dispose of the same as he think fit and clean off such dirt as

aforesaid and the contractor shall forthwith pay the amount of all expenses so

incurred, but shall have no claim in respect of any such scaffolding or surplus

materials as aforesaid except for any sum actually realized by the sale

thereof. Payments on

intermediate

certificate to be

regarded as

advances.

CLAUSE 8 : No payment shall be made for any work, estimated to cost than

rupee one thousand till after the whole of the said work shall have been

completed and a certificate of completion given, But in the case of works

estimated to cost more than rupees one thousand, the contractor shall on

submitting a monthly bill therefore be entitled to receive payment

proportionate to the part of the work then approved and passed by the

Engineer-in-charge, whose certificate of such approval and passing of the sum

so payable shall be final and conclusive against contractor, All such

intermediate payments shall be regarded as payments by way of advance

against the final payments only and not as payments for work actually done

and completed and shall not preclude the Engineer-in-charge from requiring

bad, unsound, imperfect or unskillful work to be removed and taken away

and reconstructed or re-erected, nor shall any such payment be considered as

an admission of the due performance of the contract or any part thereof in

any respect or the accruing of any claim nor shall it conclude determine or

effect in any way the powers of the Engineer-in-charge as to the final

settlement and adjustment of the accounts or otherwise or any other way very

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 47

or affect the contract. The final bill is submitted by the contractor within one

month or the date fixed for the completion of the work otherwise the

Engineer-in-charge's certificate of the measurement and of the total amount

payable for the work shall be final and binding on all parties. Payment at reduced

rates on account of

items of work not

accepted as

completed to be at

the discretion of the

Engineer-in-charge.

CLAUSE 9: The rates or several items of works estimated to cost more than

Rs. 1000 agree to within, shall be valid only when the item concerned is

accepted as have been completed full in accordance with the sanctioned

specifications. In cases where the items of work are not accepted as so

completed the Engineer-in-charge may make payment on account of such

items at such reduced rates as he may consider reasonable in the preparation

of final or on account bills.

Bill to be submitted

monthly. CLAUSE 10: A bill shall be submitted by the contractor each month on or

before the date fixed by the Engineer-in-charge for all work executed in the

previous month and the Engineer-in-charge shall take or cause to be taken the

requisite measurement for the purpose of having the same verified and the

claim, so far as it is admissible, shall be adjusted if possible within 10 days

from the presentation of the bill. If the contractor, does not submit the bill

within the time fixed as aforesaid the Engineer-in-charge may depute a

subordinate to measure up the said work in the presence of the contractor or

his duly authorized agent whose countersignature to the measurement list shall

be sufficient, warrant, and the Engineer-in-charge may prepare a bill from

such list which shall be binding on the contractor in all respects. Bills to be on printed

forms. CLAUSE 11: If contractor shall submit all bills on the printed form to be had

on application at the office of the Secretary of APMC RAHATA The charges to

be made in the bills shall always be entered at the rates specified in the

tender or in the case of any extra work ordered in pursuance of these

conditions and not mentioned or provided for in the tender, at the rates

hereinafter provided for such work. Store’s supplied by

APMC RAHATA CLAUSE 12 : If the specification or estimate of the work provides for the use

any special description of material to be supplied from the APMC RAHATA

store or if it is required that the contractor shall use certain stores to be

provided by the Engineer-in-charge (such material and stores, and the prices

to be charge therefore, as hereinafter mentioned being so far as practice-

able for the convenience of the contractor but not so as in way to control the

meaning or effect of this contract specified in the schedule or memorandum

hereto the contractor shall be supplied with such materials and stores as may

be required from time to time to be used by him for the purpose of the

contract only, and the value of the full quantity of materials and stores so

supplied shall be set off deducted from any sums then the security deposit, of

the proceeds of sale there of: If the deposit is held in APMC RAHATA

Securities, the same or a sufficient portion thereof shall in that case be sold for

purpose. All material supplied to the contractor shall remain the absolute

property of APMC RAHATA And shall on no account be removed from the site

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 48

of the work, and shall at all times be open to inspection by the Engineer-in-

charge. Any such materials unused and in perfectly good condition at the time

of completion or determination of the contract shall be returned to the APMC

RAHATA stores, if the Engineer-in-charge so requires by a notice in writing

given under his hand but the contractor shall not be entitled to return any such

materials except with such consent and he shall no claim for compensation on

account of any such material supplied to him as aforesaid but remaining

unused by him or for any wastage in or damage thereto. CLAUSE 12 (A): All stores of controlled materials such as cement, steel etc.

supplied to the contractor by the APMC RAHATA should be kept by the

contractor under double lock and key and they will released in accordance

with the instructions of the Secretary of APMC RAHATA in this behalf and be

accessible for inspection by The Secretary of APMC RAHATA or his agent at

all the times. Works to be

executed in

accordance with

specification,

drawing, orders etc.

CLAUSE 13: The contractor shall execute the whole and every part of the

work in the most substantial and work-men like manner, and both as regards

materials and in every other respect in strict accordance with the

specifications. The contractor shall also confirm exactly, fully and faithfully to

the designs and inspections in writing relating to the work signed by Engineer-

in-charge and lodged in his office and to which the contractor shall be entitled

to have access for the purpose of inspection at such office or on the site of the

work during office hours. The contactor will be entitled to receive three sets of

contract drawing and working drawing as well as one certified copy of the

accepted tender doing with the work order free of cost. Further copies of the

contract drawings if required by him will be supplied at the rate of Rs. 10/-

per set of contract drawings and Rs. 1 /- per working drawing except where

otherwise specified. Alteration in

specification and

design not to

invalidate contract.

Rates for work not

CLAUSE 14 : The Engineer-in-charge shall have power to make any

alterations in/or additions to the original specifications, drawings, design and

instructions that may appear to him to be necessary or advisable during the

progress of the work, and the contractor shall be bound to carry out of the

work in accordance with any instructions in this connection which may be given

to him in writing signed by the Engineer-in-charge or his authorised assistant

and such alteration shall not invalidate the contract and any additional work

which the contractor may be directed to do in the manner above specified as

part of the work shall be carried out by the contractor on the same conditions

in all respect on which he agreed to do the main work, and at the same rates

as are specified in the tender for the main work. And if the additional and

altered work includes any class of work for which no rates is specified in this

contract, then such class of work shall be carried out of the rates entered in

the Schedule of Rates of the Division or at the rates mutually agreed upon

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 49

entered in estimate

or schedule of rates

the district.

between the Engineer-in-charge and the contractor, whichever are lower. If

the additional or altered work for which no rate is entered in the Schedule of

Rate of the Division is ordered to be carried out before the rates are agreed

upon, then the contactor shall within seven days of the date of receipt by him

of the order to carry out the work, inform the Engineer-in-charge the rate

which it is his intention to charge for such class of work, and if the Engineer-in-

charge does not agree to this rate, he shall by notice in writing, be at liberty

to cancel his order to carry, if out in such manner as he may consider

advisable, provided always that if the contractor shall commence work or

incur any expenditure in regard there to before the rates shall have been

determined as lastly herein before mentioned, then in such case he shall only

be entitled to be paid in respect of the work carried out or expenditure

incurred by him prior to the date of the determination of the rate as

aforesaid according to such rate or rates as shall be fixed by the Engineer-in-

charge in the event of dispute the decision of the SECRETARY of the APMC

will be final.

Where, however, the work is to be executed according to the designs,

drawings and specifications recommended by the contractor and accepted by

competent authority the alterations above referred to shall be within the

scope of such designs, drawings and specifications appended to the tender. Extension of time in

consequence of

additions or

alterations.

The time limit for completion of the work shall be extended in the proportion

that the increase in its cost occasioned by alterations or additions bear to the

cost of the original contract work, or according to the necessity of the work

and the certificate of the Engineer-in-charge as to such proportion shall be

conclusive. No claim to any

payment of

compensation for

alterations in or

restriction of work.

CLAUSE 15 :

1. If at any time after the execution of the contract documents, the

Engineer-in-charge shall for any reason whatsoever (Other than default

on the part of the compensation for contractor for which the APMC

RAHATA is entitled to rescind the contract) desire that, the whole or any

part of the work specified in the tender should be suspended for any

period or that the whole or part of the work should not be carried out

at, he shall give to the contractor a notice in writing of such desire and

upon the receipt of such notice the contractor shall forth with suspend or

stop the work wholly or in part as required after having due regard to

the appropriate stage at which the work should be stopped or

suspended so as not to cause any damage or injury to the work already

done or endanger the safety hereof provided that the decision of the

Engineer-in-charge as to the stage at which the work or any part of it

could be could have been safely stopped or suspended shall be final

and conclusive against the contractor. The contractor shall have no claim

to any payment or compensation whatsoever by reason of or in

pursuance of any notice as aforesaid, account of any suspension,

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 50

stoppage or curtailment expect the specified herein after.

2. Where the total suspension of work ordered as aforesaid continues for

a continuous period exceeding 90 days the contractor shall be at liberty

to withdraw from the contractual obligations under the contract so far as

it pertains to the unexecuted part of the work by giving a ten days prior

notice in writing to the Engineer-in-charge within thirty days of the said

prior of 90 days of such intention and requiring the Engineering-in-

charge to record the final measurements of the work already done and

to pay the final bill upon giving such notice the contractor shall be

deemed to have been discharged from his obligation to complete the

remaining unexecuted work under this contract on receipt of such notice

the Engineer-in-charge shall proceed to complete the measurement and

make such payment as may be finally due to the contractor within a

period of 90 days from the receipt of such notice in respect of the work

already done by the contractor, such payment shall not in any manner

prejudice the right of the contractor to any further compensation under

the remaining provisions of this clause.

3. Where the Engineer-in-charge requires the contractor to suspend the

work for a period in excess of 30 days at any time or 60 days in the

aggregate the contractor shall be entitled to apply to the Engineer-in-

charge within 30 days of the resumption of work after such suspension

for payment of compensation to the extent of pecuniary loss suffered by

him in respect of working machinery rendered idle on the site of on

account of his having had to pay the salary or .wages of labour

engaged by him during the said period of suspension provided always

that the contractor shall not be entitled to any claim in respect of any

such working machinery salary or wages for the first 30 days whether

consecutive or in the aggregate of such suspension or in respect of any

suspension whatsoever occasioned by unsatisfactory work or any other

default, on his part. The decision of the Engineer-in-charge in this regard

shall be final and conclusive against the contractor. No claim to

compensation on

account of loss due

to delay in supply of

material by APMC

RAHATA

4. In the event of -

i) Any total stoppage of work on notice from the Engineer under Sub

clause (1) in that behalf.

ii) Withdrawal by the contractor from the contractual obligations to

complete the remaining unexecuted work under sub-clause (2) on

account of continued suspension of work for a period exceeding 90

days. Or

iii) Curtailment in the or quantity of items originally tendered on account of

any alteration, omission or substitutions in the specifications, drawings

designs or instructions under clause 14 (I) where such curtailment exceeds

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 51

25 % in quantity and the value of quantity curtailed beyond 25 % of

the rates for the item specified in the tender is more that Rs. 5000/- it

shall be open to the Contractor within 90 days from the service of (i) the

notice of stoppage of work or (ii) the notice of withdrawal from the

contractual obligation under the contract on account of the continued

suspension of work or (iii) notice under clause 14(i) resulting in such

curtailment to produce to the Engineer-in-charge satisfactory

documentary evidence \ that he had purchased or agreed to purchase

material for use in the contracted work before receipt by him of the

notice of stoppage suspension or curtailment and require the APMC

RAHATA to take over, on payment such material at the rates determined

by the Engineer the APMC RAHATA shall thereafter take over the

material so offered, provided the quantities offered, are not in excess

of the requirement of the unexecuted work as specified tender and are

of quality and specification approved by the Engineer. No claim to

compensation on

account of loss due

to delay in supply of

materials by APMC

RAHATA

CLAUSE 15 (A) :

The contractor shall not be entitled to claim any compensation APMC RAHATA

for the loss suffered by him on account of delay by APMC RAHATA in the

supply of materials entered in Schedule A where such delay is caused by

i) Difficulties relating to the supply of railway wagons.

ii) Force majeure.

iii) Act of God.

iv) Act of enemies of the state or any other reasonable cause beyond the

control of APMC RAHATA.

In the case of such delay in the supply of materials, APMC RAHATA shall grant

such extension of time for the completion of the works as shall appear to the

Secretary to be reasonable in accordance with the circumstances of the case.

The decision of the Secretary as to the extension of time shall be accepted as

final by the contractor.

Time limit for

unforeseen claim. CLAUSE 16 : Under no circumstances whatever shall be the contractor is

entitled to any compensation from APMC RAHATA on any account unless the

contractor shall have submitted a claim in writing to the Engineer-in-charge

within one month of the cause of such claim occurring. Action and

compensation

payable in case of

bad work.

CLAUSE 17 : If at any time before the security deposits is refunded to the

contractor, it shall appear to the Engineer-in-charge or his subordinate in

charge of the work, that any work has been executed with unsound, imperfect

or unskillful workmanship or with material of inferior quality, or that any

materials or articles provided by him for execution of the work are unsound,

or if a quality inferior to the contracted for or are otherwise not in accordance

with the contract, it shall be lawful for the Engineer-in-charge intimate this fact

in writing to the contractor and then notwithstanding the fact that the work,

materials or articles complained of may have been inadvertently passed,

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 52

certified and paid for the contractor shall be bound forthwith to rectify, or

remove and reconstruct the work so specified in whole or in part, as the case

may require or if so required shall remove the materials or articles so

specified and provide other proper and suitable materials or articles at his

own charge and cost and in the event of his failing to do so within a period to

be specified by the Engineer-in-charge in the written intimation aforesaid, the

contractor shall be liable to pay compensation at the rate of one percent on

the amount of the estimate for every day not exceeding ten days during which

the failure so continues and in the case of any such failure the Engineer-in-

charge may rectify or remove and execute the work or remove and replace

the materials or articles complained of as the case may be at the risk and

expense in all respects of the contractor. Should the Engineer-in-charge

consider that, any such inferior work or materials as described above may be

accepted or made use of it shall be within his discretion to accept the same at

such reduced rates as he may fix therefore. Works to be open to

inspection

Contractor or

responsible agent to

be present.

CLAUSE 18 : All the works under or in course of execution or executed in

pursuance of the contract at all times be open to the Inspection an supervision

of the engineer-in-charge and his subordinates, and the contractor shall at all

times during the usual working hours and at all other times at which

reasonable notice of the intention of the Engineer-in-charge and his

subordinates, to visit the works shall have been given to Contractor either

himself be present to receive orders and instructions or have a responsible

agent to be responsible agent duly accredited in writing present for that

purpose. Orders given to the contractor’s duly Authorized agent shall be

considered to have the same force and effect as if they had been given to the

contractor himself.

Notice to be given

before work is

covered up.

CLAUSE 19 : The contractor shall give not less than five day’s notice in writing

to the Engineer-in-charge or his subordinate in charge of the work before

covering up or otherwise placing beyond the reach of measurement any work

in order that the same may be measured, and correct dimensions thereof

taken before the so covered up or placed beyond the reach of measurement,

and shall not cover up or place beyond the reach of measurement any work

without the consent in writing of the Engineer-in- charge or his subordinate in

charge of the work, and if any work shall be covered up or placed beyond

the reach of measurement without such notice having been given or consent

obtained, the same shall be uncovered at the contractor’s expense and in

default thereof no payment or allowance shall be made for such work or for

the materials with which the same was executed. Contractor liable for

damage done and

for imperfection for

twelve months after

certificate.

CLAUSE 20 : If during the period of 12 Months from the date of completion as

certified by the Engineer-in-charge pursuant to clause 7 of the contract, in

opinion of Engineer-in-charge the said work is defective in any manner

whatsoever, the contractor shall forthwith on receipt of notice in that behalf

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 53

from the Secretary of APMC RAHATA duly commence execution and

completely carry out at his costs in every respect all the work that may be

necessary for rectifying and setting right the defects specified therein strictly

in accordance with and in the manner prescribed and under the supervision of

the Secretary of APMC RAHATA In the event of the contractor failing or

neglecting to commence execution of the said rectification work within the

period prescribed therefore in the said notice and or to complete the same as

aforesaid as required by the said notice, the Secretary of APMC RAHATA

may get the same executed and carried out departmentally or by any other

agency at the risk on account and at the cost of contractor. The contractor

shall forthwith on demand pay to the APMC RAHATA the amount of such costs,

charges and expenses sustained or incurred by the APMC RAHATA of which

certificate of the Secretary of APMC RAHATA shall be final and binding on

the contractor, such costs, charges and expenses shall be deemed to be

arrears of land revenue and in the event of the contractor failing or neglecting

to pay the same on demand as aforesaid without prejudice to any other rights

and remedies of the APMC RAHATA the same may be recovered from the

contractor as arrears of the revenue. The APMC RAHATA shall also be entitled

to deduct the same from any amount which may then be payable or which

may thereafter become payable by the APMC RAHATA. To the contractor

either in respect of the said work or any other work whatsoever or from the

amount of the security deposits retained by APMC RAHATA. The defect

liability period in particular for waterproofing treatment shall be 10 years

and contractor have to provide the bank guarantee of this work value for 10

years. Contractor to supply

plant ladders scaffolding etc.

And is liable to pay

damages arising

from non provision of

lights etc.

CLAUSE 21 : The contractor shall supply at his own cost all material (except

such special materials, if any, as may be supplied from the APMC RAHATA

stores) in accordance with the contract, plant, tools appliances, implements,

ladders, cordage tackle, scaffolding and any temporary works, which may be

required for the proper execution of work, in the original, altered or

substituted from and whether included in the specification or other documents

forming part of the contract or referred to in these conditions or not and which

may be necessary for the purpose of satisfying or complying with the

requirements of the Engineer-in-charge as to any matter of which under these

conditions he is entitled to be satisfied or which he is entitled to required

together with carriage therefore, to and from the work. The contractor shall

also supply without charge the requisite number of persons with the means and

materials necessary for the purpose of setting out works, and counting,

weighting and assisting in the measurement or examination at any time and

from time to time of the work or materials, Failing this the same may be

provided by the Engineer-in-charge the expense of the contractor and the

expenses may be deducted from any money due to the contractor under the

contract from his security deposit or the proceeds of sale thereof, or of a

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 54

sufficient portion thereof. The contractor shall provide all necessary fencing

and light required to protect the public from accident, and shall also be bound

to bear the expenses of defense of every suit, action or other legal

proceedings at law, that may be brought by any person for injury sustained

owing to neglect of the above precautions and to pay any damages and cost

which may be awarded in any such suit, action or proceedings to any such

person or which may with the consent of the contractor be paid in

compromising any claim by any such person.

List of machinery in contractor's possession and which they propose to use on

the works should be submitted along with the tender.

CLAUSE 21(A) The contractor shall provide suitable scaffolds and working

platforms gangways, stairways, and shall comply with the following

regulations in connection there with

a) Suitable scaffolds shall be provided for workmen for all work that cannot

be safely done from a ladder or by other means

b) A scaffolds shall not be constructed, taken down, or substantially altered

except.

i) Under the supervision of a competent and responsible person, and

ii) As far as possible by competent workers possessing adequate

experience in this kind of work.

c) All scaffolds and appliances connected herewith and all ladders shall,

i) Be of sound materials,

ii)

Be of adequate strength having regard to the loads and strains to

which they will be subjected and,

iii) Be maintained in proper condition.

d) Scaffolds shall be so constructed that no part thereof can be displaced in

consequence of normal use.

e) Scaffolds shall not be over loaded and so far as practicable the load shall

be evenly distributed.

f) Before installing lifting gear or scaffolds special precaution shall be taken

to ensure the strength and stability of the scaffold.

g) Scaffolds shall be periodically inspected by a competent person.

h) Before allowing scaffold to be used by his workmen the contractor shall

whether the scaffold has been erected by his workmen or not, take steps to

ensure that it complies fully with the regulations herein specified.

i) Working platforms, gangways and stairways shall.

i) be so constructed that no part thereof can sag unduly or unequally.

ii) be so constructed and maintained, having regard to the prevailing

conditions, as to reduce as far as practicable risks of persons tripping

or sleeping and

iii) be kept free from any unnecessary obstruction.

j) In the case working platforms, gangways, working place and stairways at

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 55

height exceeding 3 meters

i) Every working platform and every gangway shall be closely

boarded unless other adequate measures are taken to ensure safety.

ii) every working platform, and gangway, shall have adequate width

and

iii) Every working platform, and gangway, working place and stairway

shall be suitably fenced.

k) Every opening in the floor of a building or in a working platform shall

except for the time and to the extent required to allow to access of persons or

the transport or shifting or material be provided with suitable means to

prevent the fall of persons or material.

l) When the persons are employed on a roof where there in danger of failing

from a height exceeding 3 meters’ suitable precautions shall be taken to

prevent the fall of persons or materials.

(To be prescribed)

m) Suitable precautions shall be taken to prevent persons being struck by

articles which might fall from scaffolds or other working places.

n) Safe means of access shall be provided to all working platforms and other

working places.

o) The contractor/(s) will have to make payments to labourers as per Minimum

Wages Act 1948.

CLAUSE 21 (B) :

The contactor shall comply with the following regulations as regards the

hoisting Appliances to be used by him -

a) Hoisting machines, and tackle, including their attachments, anchorages and

supports shall.

i) be of good mechanical construction, sound material adequate strength

and free from patent defect, and

ii) be kept in good repairs and in good working order

b) Every rope used in hoisting or lowering materials or as means of suspension

shall be of suitable quality and adequate strength and free from patent

defect.

c) Hoisting machines and tackle shall be examined and adequately tested

after erection on the site and before use and be re-examined in position at

intervals to be prescribed by the APMC RAHATA.

d) Every chain, ring hook, shackles swivel and pulley block used in hoisting or

lowering materials or as means of suspension shall be periodically examined.

e) Every crane driver or hoisting appliance operator shall be properly

qualified.

f) No person who is below the age of fourteen years shall be in control of any

hoisting machine including any scaffolds which or given signals to the operator.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 56

g) In the case of every hoisting machine and of every chain, ring, hook, shackle

swivel and pulley block used in hoisting or lowering as a means of suspension

the safe working load shall be ascertained by adequate means.

h) Every hoisting machine and all gear referred to in the preceding regulation

above shall be plainly worked with the safe working load.

i) In the case of a hoisting machine having a variable safe working load each

safe working load and the conditions under which its applicable shall be

clearly indicated.

j) No part of any hoisting machine or any gear referred to in regulation

above shall be loaded beyond the safe working load except for the purpose

of testing.

k) Motors gearing transmission electric and other dangerous parts of hoisting

appliance shall be provided with efficient safe guards.

l) Hoisting appliances shall be provided with such means as will reduce to

minimum the risk of the accidental descent of the load.

m) Adequate precaution shall be taken to reduce to minimum the risk of any

part of suspended load becoming accidentally displaced. Measures for

prevention to fire

CLAUSE 22: The contactor shall not set fire to any standing jungle, trees,

brushwood or grass without written permit from the General Manager. When

such permit is given and also in all cases when destroying, cut or dug up trees,

brush wood grass etc. by fire the contractor shall take necessary measures to

prevent such fire spreading to or otherwise damaging surrounding property.

The contractor shall make his own arrangements for drinking water for the

labour employed by him and provide sanitary and other arrangements. Liability of

contractors for any

damage done in or

outside work area

CLAUSE 23 : Compensation for all damage done intentionally or

unintentionally by contractor’s labours whether in or beyond the limits of

APMC RAHATA property including any damage caused by the spreading of

fire mentioned in clause 22 shall be estimated by the Engineer-in-charge or

such other officer as he may appoint and the estimated by the Engineering-in-

charge subject to the decision of the Secretary of APMC. on appeal shall be

final and the contractor shall be bound to pay the amount of the assessed

compensation on demand failing which the same will be recovered from the

contractor as damage in the manner prescribed in clause 1 or deducted by

the Engineer-in-charge from any sums that may be due to or become due from

APMC RAHATA to the contractor under this contract or otherwise.

The contractor shall bear the expenses of defending any action or other legal

proceedings that may be brought by any person for injury sustained by him

owing to neglect of precautions to prevent the spread of fire and he shall also

pay any damages and cost that, may by awarded by the court in

consequence. Employment female

labour.

CLAUSE 24: The employment of female labours on works In the neighborhood

soldiers, barracks should be avoided as for as possible.

Work on Sunday CLAUSE 25: No work shall be done on a Sunday weekly off without the

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 57

sanction of the Engineer-in-charge. Work not be sublet

Contract may be

rescinded and

security deposit

forfeited for

subletting if without

approval or for

bring a public officer

or if contractor

becomes insolvent

CLAUSE 26: The contractor shall not be assigned or sublet without the written

approval of the Engineer-in-charge and if the contractor shall assign or sublet

his contract, or attempt to so or become insolvent or commence any

proceeding to be adjudicated an insolvent or make any composition with his

creditors or attempt so to do, the Engineer-in-charge may, by notice in writing,

rescind the contract, Also if any bribe gratuity, Gift, loan, perquisite, reward

or offered by the contractor of any of his servants or agents to any public

officer or person in the employ of APMC RAHATA in any way relating to his

office or employment, or if any such officer or person shall become in any

way directly or indirectly interested in the contract the Engineer-in-charge

may there upon by notice in writing rescind the contract and the security

deposit of the contractor shall thereupon stand forfeited and be absolutely at

the disposal of APMC RAHATA and the same consequence shall ensue as if

the contract had been rescinded under Clause 3 hereof and in addition the

contractor shall not be entitled to recover or be insolvent. Paid for any work

therefore actually performed under the contract. Sum payable by way

of compensation to be

considered as

reasonable

condensation without

reference to actual

loss.

CLAUSE 27: All sums payable by a contractor by way of compensation under

any of these conditions shall be considered as a reasonable compensation to

be applied to the use of APMC RAHATA without reference to the actual loss or

damage sustained, and whether any damage has or has not been sustained.

Charges in the

constitution of firm to

be notified.

CLAUSE 28: In the case of a tender by partners any change In the

constitution of a firm shall be forthwith notified by the contractor to the

Engineer-in-charge for his information.

Direction of control

of the SECRETARY CLAUSE 29 : All works to be executed under the contract shall executed

under the and subject to the approval in all respects of Secretary of APMC

RAHATA for the time being, who shall be entitled to direct at what point or

points and in what manner they are to be commenced and from time to time

carried on. Decision of

SECRETARY to be

final

CLAUSE 30 (1) Except where otherwise specified in the contract and subject

to the powers delegated to him by APMC RAHATA then in force the decision

of the Secretary of APMC. for the time being shall be final, conclusive, and

binding on all parties to the contract upon all questions relating to the

meaning of the specifications, designs, drawings, and instructions herein

before mentioned and as to the quality of workmanship or material used on

the work or as to any other question claim, right, matter or thing whatsoever in

any way arising out of or relating to the contract, designs, drawings,

specifications, estimates, instructions, orders or these conditions, or otherwise

concerning the works, or the execution or failure to execute the same, whether

arising, during the progress of the work or after the completion or

abandonment thereof.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 58

CLAUSE 30 (2) The contractor may within thirty days of receipt by him of any

order passed by the Engineer-in-charge of the project as aforesaid appeal

against it to the SECRETARY concerned with the contract.

Clause 30 (3) If the contractor is not satisfied with the order passed by the

Secretary as aforesaid, the contractor may within 30 days of receipt by him

of any such order , appeal against it to the concerned APMC RAHATA Office

who, if convinced that Prima-facia the contractor’s claim rejected by Secretary

is not frivolous and that there is some substance in the claim of the contractor

as would merit a detailed examination and decision by the Board of Directors

at APMC RAHATA level for suitable decision.

Stores of European

or American

manufacture to be

obtained from the

Govt

CLAUSE 31 : The contractor shall obtain from the Departmental stores, all

stores & articles of European or American manufacture which may be required

for the work, or any part thereof or in making up any articles required

therefore or in connection therewith unless he has obtained, permission in

writing from the Engineer-in-charge to obtain such stores & articles elsewhere.

The value of such stores &articles as may be supplied to the contractor by the

Engineer-in-charge will be debited to the contractor in his account at the

rates shown in the said schedule, in Form A attached to the contract & if they

are not entered in the said schedule they shall be debited to him at cost price

which for purpose of this contract shall include the cost of carriage and other

expenses whatsoever which shall have been incurred in obtaining delivery of

the same at the stores aforesaid. Lump sum in

estimates.

CLAUSE 32 : When the estimate on which a tender is made includes lump sum

in respect of parts of the work, the contractor shall be payment in respect of

items of work involved or the part of the work in question at the same rates as

are payable under this contract for such items, or if the part of the work in

question is not in the opinion of the Engineer-in-charge capable of

measurement, the Engineer-in-charge may at his discretion pay the lump sum

amount entered in the estimate, and the certificate in writing of the Engineer-

in-charge shall be final and conclusive against the contractor with regard to

any sum or sums payable to him under the provisions of this clause. Actions where no

specifications CLAUSE 33: In the case of any class of work for which there is no such

specification as is mentioned in Rule 1 such work shall be carried out in

accordance with the Divisional specifications and in the event of there being

no Divisional specification then in such case the work shall be carried out in all

respects in accordance with the instructions and requirements of the Engineer-

in-charge. Definition of work.

CLAUSE 34 : The expression “work” or “Works” where used in these

conditions shall unless there be something in the subject or context repugnant

to such construction be construed to mean the work or the works contracted to

be executed under or in virtue the contract, whether temporary or permanent

and whether original altered, substituted or additional.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 59

Contractors percentage Whether applied to net or gross amount of bill.

CLAUSE 35: The percentage referred to in the tender shall be deducted from

/ added to the gross amount of the bill before deducting the value of any

stock issued.

Payment of quarry

fees and royalties.

CLAUSE 36: All quarry fees, royalties Octroi, dues and ground rent for

stocking materials, if any should be paid by the contractor.

Compensation under

workman’s

compensation Act.

CLAUSE 37: The contractor shall be responsible for and shall pay any

compensation to his workmen payable under the Workmen’s Compensation

Act, 1923 (VIII of 1923) (hereinafter called the said act) for injuries caused to

the workmen, If such compensation if paid by APMC RAHATA as principal

under Sub-section (1) of Section 12 of the said Act on behalf of contractor, it

shall be recoverable by APMC RAHATA from the contractor under sub-Section

(2) of the said Section. Such compensation shall be recovered in the manner

laid down in Clause 1 above. CLAUSE 37: (A)

A) The contractor shall be responsible for and shall pay the expenses of

providing medical aid to any workman who may suffer bodily injury as a

result of an accident. If such expenses are incurred by APMC RAHATA, the

same shall be recoverable from the Piece worker Contractor forthwith and be

deducted without prejudice to any other remedy of APMC RAHATA from any

amount due or that may become due to the Piece worker Contractor.

CLAUSE 37: (B)

B) The contractor shall provide all necessary personal safety requirement and

first aid apparatus available for the use of the persons employed on the site,

shall maintain the same condition suitable for immediate use at any time and

shall comply with the following regulations in connection therewith:-

a) The workers shall be required to use the equipment so provided by the

contractor and the contractor shall take adequate steps to ensure proper use

of the equipment by those concerned.

b) When work is carried on in proximity to any place where there is a risk of

drawing all necessary equipment shall be provided and kept ready for use

and all necessary steps shall be taken for the prompt rescue of any person in

danger.

c) Adequate provision shall be made for prompt first-aid-treatment of all

injuries likely to be sustained during the course of the work. CLAUSE 37: (C) C) The contractor shall duly comply with the provisions of 'The

Apprentices Act, 1961' (III of 1961) the rules made there under and the

orders that may be issued from time to time-under the Act the said rules and

on his failure or neglect to do so, he shall be subject to all the liabilities and

penalties provided by the said Act and said Rules.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 60

claims for quantities

entered in the tender

or estimate

CLAUSE 38 :

1) Quantities in respect of the several items shown in the tender are

approximate and no revision in the tendered rate shall be permitted in

respect of any of the items so long as, subject to any special provision

contained in the specifications prescribing a different percentage of

permissible variation the quantity of the item does not exceed the tender

quantity by more than 25 % and so long as the value of the excess quantity

beyond this limit at the rate of the item specified in the tender is not more

than Rs. 5000/-. 2) The contractor shall if ordered in writing by the APMC RAHATA so to do,

also carry out any quantities in excess of the limit mentioned in sub-clause (1)

hereof on the same conditions as and in accordance with the specifications in

the tender and at the rates.

i) derived from the rates entered in the current schedule of rates and in the

absence of the such rates.

ii) at the rate prevailing in the market, said rates being increased or

decreased as the case may be by the percentage which the total tendered

amount bears to the estimated cost of the work as put to tender based upon

the schedule of rates applicable to the year in which the tenders are invited. 3) Claims arising out of reduction in the tendered quantity of any item beyond

25% will be governed by the provision of clause 15 only when the amount of

such reduction beyond 25 percent at the rate of the item specified in the

tender is more than Rs. 5000/- 4) The clause is not applicable to extra items. 5) There is no change in the rate of the excess is more than 25% of the

tendered quantity, but the value of the excess work at the Tendered rates

does not exceeds Rs. 5000/-. 6) The quantities to be paid at tendered rate shall include:-

a) Tendered quantity plus.

b) 25% excess of the Tendered quantity or the excess quantity of the value

of Rs. 5000/- at the Tendered rates whichever is more. employment of

famine etc. labour.

CLAUSE 39: The contractor shall employ any famine, convict or other labour

or particular kind or class if ordered in writing to do so by the Engineer-in-

charge. Claim for

compensation for

delay in starting the

work

CLAUSE 40: No compensation shall be allowed for any delay caused in the

starting of the work on account of any acquisition of land or in the case of

clearance work on account of for any delay in according sanction to

estimates.

Claim for

compensation for

delay in the

execution of the

work.

CLAUSE 41: No compensation shall be allowed for any delay in execution of

the work on account of water, standing in borrows pits or compartments. The

rates are inclusive for hard of cracked soil, excavation in mud, sub-soil water

or water in borrows pits and no claim for an extra rate shall be entertained,

unless otherwise expressly specified.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 61

Entering upon or

commencing any

portion of work.

CLAUSE 42: The contractor shall not enter upon or commence any portion of

work except with the written authority and instruction of the Engineer-in-

charge or of his sub-ordinate in charge of the work. Failing such authority the

contractor shall have no claim to ask for measurements of or payment for the

work. Minimum age of

persons employed

the employment of

donkeys and other

animals and the

payment of fair

wages.

CLAUSE 43 : i) No contractors shall employ any person who is under the age

of 12 years.

ii) No contractors shall employ donkeys or other animals with breechings of

string or thin rope. iii) No animal suffering from sores, lameness or which is

immature shall be employed on, the work.

iv) The Engineer-in-charge or his Agent is authorized to remove from the work

any person or animal found working which does not satisfy these conditions

and no responsibility shall be accepted by APMC RAHATA for any delay

caused in the completion of the work by such removal.

v) The Contractor shall pay fair and reasonable wages to the workmen

employed by him in the contract undertaken by him. In the event of any

dispute arising between the contract and his workmen on grounds that the

wages paid are not fair and responsible the dispute shall be referred without

delay to the Secretary of APMC. who shall decide the same. The decision of

the Secretary of APMC. shall be conclusive and binding on the contractor. But

such decision shall not in any way affect the condition in the contract

regarding the payment to be made by APMC RAHATA at the sanctioned

tender rates.

vi) The contractor shall provide drinking water facilities to the workers.

Sanitary amenities shall be provided to the workers, engaged on large works

in urban areas.

vii) Contractor to take precautions against accidents which takes place on

account of labours using loose garments while working near machinery.

viii) All facilities provided in the Contract Labour (Regulation and Abolition Act

1970) the Maharashtra Contract Labour Regulation and Abolition Rule 1971

should be provided. Method of payment

CLAUSE 44: Payment to contractors shall be made by cheques drawn on a

bank at Rahata in account with the APMC RAHATA provided the amount

exceeds Rs.10/-, amounts not exceeding Rs.10/- will be paid in cash.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 62

Acceptance of

condition compulsory

before tendering for

work.

CLAUSE 45: Any contractor who does not accept these conditions shall not be

tender for work.

Employment of

scarcity labour CLAUSE 46 : If Government declares a state of scarcity or famine to exist in

any village situated within 10 miles of the work, the contractor shall employ

upon such parts of the works, as are suitable for unskilled labour, any person

certified to him by the Secretary of APMC. or be any person to whom The

Secretary of APMC. may have delegated this duty in writing to be in need of

relief and shall be bound to pay such persons wages not below the minimum

which APMC RAHATA may have fixed in this behalf. Any dispute which may

arise in connection with implementation of this clause shall be decided by the

Secretary of APMC. whose decision shall be final and binding on the

contractor. CLAUSE 47: The price quoted by the contractor shall not in any case exceed

the control price, if any fixed by APMC RAHATA or reasonable price which it

is permissible for him to charge a private purchases for the same class and

description the controlled price or the price permissible under hoarding and

profiteering ordinance 1943, as amended from time to time. If the price

quoted exceeds the controlled price or the price or the price permissible

under H. and P. P. ordinance the contractor will specifically mention this fact in

his tender along with the reasons for quoting such higher prices. The purchase

at his description will in such case exercise the right of revising the price at

any stage so as to conform with the controlled price on the permissible under

the Hoarding and Profiteering Preservation ordinance. The discretion will be

exercised without prejudice to any other action that may be taken against the

contractor. CLAUSE 47(A): The tendered rates shall be inclusive of all taxes, rates and

cases and shall also be inclusive of the tax leviable in respect of works

contract under the provision of the Maharashtra Sales tax on transfer of

property in goods involved in the execution of works Contract Act, 1985

(Maharashtra Act No. XIX of 1985)." CLAUSE 48: The rates to be quoted by the contractor must be inclusive of all

Taxes, Royalties & ceases & shall also be inclusive of the Tax Levi-able in

respect of work Contract & all other Local Municipal Corporation Taxes

applicable etc. The Tax liability shall be entirely on the part of Contractor

and no reimbursement on this account shall be made. CLAUSE 49: In case of materials that may remain surplus with the contactor

from those issued for the work contracted for, the date of ascertainment of the

materials being surplus will be taken as the date of sale for the purpose of

sales tax will be recovered on such sale. CLAUSE 50 : A) The contractor shall employ at least 80 percent of the total

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 63

number of unskilled labour to be employed by him on the said work from out

of persons ordinarily residing on the district in which site of the said work is

located.

Provided however, that if the required number of unskilled labour from that

district is not available, the contractor shall in the first instance employ such

number of person as is available and thereafter any with the previous

permission in writing of the Engineering-in-charge of the said work, obtain the

rest of his requirement of unskilled labour from outside the district. CLAUSE 51: Wages to be paid to the skilled and unskilled labours engaged

by the contractor.

The contractor shall pay the labours, skilled and unskilled, according to the

wages contract prescribed by the minimum wages act applicable to the area

in which the work of the contractor is in progress. CLAUSE 52 : All amounts whatsoever which the contractor is liable to pay to

the APMC RAHATA in connection with the execution of the work including the

amount payable in respect of (i) material and / or stores / supplied / issued

hereunder by the APMC RAHATA to the contractor (ii) hire charges in respect

of heavy plant, machinery and equipment given on hire by the APMC

RAHATA to the contractor for execution by him of the work and / or on which

advances have been given by the APMC RAHATA to the contractor may be

deemed to be arrears of land revenue & the APMC RAHATA through

Government may without prejudice to any other rights and remedies of the

APMC RAHATA recover same from the Contractor as arrears of revenue. P.W. Dept. No.

CAT/1284

(120) / Bullding-2

dated

14-8-65

CLAUSE 53: The contractor shall duly comply with all the provisions of the

Contract Labour (Regulation and Abolition) Act, 1970 (37 of 1970) and the

Maharashtra Contract Labour (Regulation and Abolition) Rules, 1971 as

amended from time to time and all other relevant statutes and statutory

provisions concerning payment of wages particularly to workmen employed

by the contractor and working on the site of the work. In Particular the

contractor shall pay wages to each worker employed by him on the site of the

work at the rates prescribed under the Maharashtra Contract Labour

(Regulation and Abolition) Rules 1971. If the contractor fails or neglects to

pay wages at the said rates or makes short payment and the Government

makes such payment of wages in full or part thereof less paid by the

contractor as the case may be, the amount so paid by the Government to such

workers shall be deemed to be arrears of Land Revenue and the Government

shall be entitled to recover the same as such from the contractor or deduct

same from the amount payable by the Government to the contractor

hereunder of from any other amount payable by the Government to the

contractor hereunder or from any other amounts payable to him by the

Government. CLAUSE 54: The contractor shall engage apprentices as bricklayer,

carpenter, wiremen, plumber as well as blacksmith as recommended by the

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 64

State Apprenticeship advisor, director of Technical Education. on the

construction works. (As per Government of Maharashtra, Education

Department No. TSA-5170/T-56689, dated 7-7-1972). CLAUSE 55: Condition for Malaria Eradication Govt. of Maharashtra P.WD.

Resolution No. CAT 1086/CR-243 K/Bldg/32 Bombay dt. 11-8-87.

A) The anti-malaria and other health measures shall be as directed by the

Joint Director (Malaria and Filaria) of Health Services, Rahata.

B) Contractor shall see that mosquitogenic conditions are not created so as to

keep vector population to minimum level.

C) Contractor shall carry out anti malaria measures in the area as per

guidelines prescribed under National Malaria Eradication programme and as

directed by the Joint Director (M & F) of Health Services, Rahata.

D) In case of default in carrying out prescribed anti-malaria measures

resulting in increase In Malaria incidence. Contractor shall be liable to pay to

Government the amount spent by Government on anti-malaria measures to

control the situation in addition to fine.

E) The contractor shall make sufficient arrangements for draining away the

sewerage water as well as water coming from the bathing and washing

places and shall dispose of this water in such a way as not to cause any

nuisance. He shall also keep the premises clean by employing sufficient

number of sweepers. The contractor shall comply with ail rules, regulations

bye-laws and directions given from time to time by any local or public

authority in connection with this work and shall pay fees or charges which are

leviable on him without any extra cost to Government. CLAUSE 56: Conditions Relating to Insurance of Contract Work.

The Contractor shall take necessary Insurance Policy/Policies ( viz. Contractors

all risk insurance Policy, Erection all Risk Insurance Policy etc. as decided by

the Directorate of Insurance) so as to provide adequate insurance cover for

execution of the awaited contract work for total contract value and complete

contract period COMPULSORILY form the “Directorate of Insurance,

Maharashtra State, Mumbai only. Its postal address for Correspondence is

“264 MHADA, First Floor, Opposite Kalanagar, Bandra (East), Mumbai-

400 051, Similarly all workmen’s appointed to complete the contract work are

required to insure under workmen’s compensation Insurance policy. Insurance

Policy/ Policies taken out form any other company will not be accepted. If

any contractor has not taken out the insurance policy from the Directorate of

Insurance, Maharashtra State, Mumbai or has effected insurance with any

insurance company, the same will not be accepted and 1% of the te4nder

amount or such amount of premium calculated by the Government Insurance

Fund will be recovered directly from the amount payable to the Contractor

for the executed contract work and paid to the Directorate of Insurance Fund,

Maharashtra State Mumbai. The Director of Insurance reserve the right to

distribute the risk of insurance among the other insurers.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 65

CLAUSE 57: BUILDING AND OTHER CONSTRUCTION WORKERS WELFARE

CESS : As per government of Maharashtra, Industry, Energy & Labour

Department G. R. No. BLA 2009/Pr. Kra. 108/Kamgar-7A dated

17/06/2010 and Public Works Department Circular NO. BDG-2010/Pra.

Kra 277/Building-2, dated 28/09/2010, Building and other Construction

Workers Welfare cess at one percent or at the rates amended from time to

time as intimated by the competent authority under Building and other

Construction Workers Welfare Act 1996 will be deducted from the bill

amount whether measured Bill, Advance payment or Secured Advance. CLAUSE 58:

The price variation Clause is NOT applicable as in force in the APMC RAHATA

during the period of execution of this work and as modified and revised from

time to time.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 66

GENERAL INSTRUCTIONS TO TENDERERS :-

ADDITIONAL CONDITIONS FOR MATERIALS :-

CEMENT M. S. /H. Y. S. D. & T.M.T BARS, ASPHALT, R.C.C. PIPES ETC.) BROUGHT BY CONTRACTOR 1. All the materials such as Asphalt, Cement etc. shall be procured by the Contractor from approved Government Institutions or as directed by Engineer-in-charge only. The material shall be brought at the site of work well in advance by the Contractor. The gate pass of the Asphalt, invoice of Cement etc. shall be examined by the authorised representative of the Engineer-in-charge. 2. The Contractor shall submit periodically as well as on the completion of work, an account of all materials used by him on the work. In addition, a separate register shall be maintained on site for recording daily item wise Asphalt, Cement consumption and also item wise consumption of other materials. This shall be signed daily by Contractor or his representative and authorised representative of the Engineer-in-charge. 3. All the materials such as Asphalt, Cement etc. shall be procured by the Contractor from approved Government Institutions or as directed by Engineer-in-charge only. The materials from any other source in lieu of the approved Institutions shall be allowed except under written permission from the Engineer-in-charge. In such case, Certificate for its quality shall be produced by the Contractor and samples of materials shall be tested from any Government Laboratory by the Contractor at his own cost and the test results be supplied to the APMC RAHATA. The materials not confirming to the required standard shall be removed at once from the site of work by the Contractor at his own cost. All the materials such as Asphalt, Cement etc. required for use in the work shall be confirming to the concerned I.S. / M.O.S.T specifications. The Contractor shall get necessary tests carried out to the frequency specified for each material in the specification and submit the test results to the Engineer-in-Charge or his authorised representative. These materials shall be used on work by the Contractor, only if the test thereof is found satisfactory to the results Engineer-in-Charge or his authorised representative. For the purpose of daily testing of material, such as metal, sand, rubble etc. The Contractor shall make his own arrangements to install a well equipped Laboratory at the site of work at his own cost. The Contractor shall employ qualified personnel at the site of work at his own cost. The responsibility of carrying out tests to the frequency specified for each material shall rest with the Contractor. The extract of register shall be submitted to the Engineer-in-charge with each bill. Copy of register for the entire period shall be submitted along with the final bill. 4. The Contractor shall construct at his own cost shed/sheds as per direction of the Engineer-in-charge of the work for storing the materials and provide double locking arrangements. The Store shed such constructed shall be removed on completion of work. The Contractor shall take all necessary steps to guard the Materials brought by him. 5. The Contractor shall make his own arrangement for the safe custody of the materials brought by him on site of work.

6. The charges for conveying of materials from the place of purchase by the Contractor to the

site of work and the actual spot on work site shall be entirely borne by the Contractor. No claims on this

account shall be entertained.

7. Separate registers shall be maintained by the Contractor on the site for recording detailed item wise

Asphalt, Cement and Steel consumption on the work. These registers shall be signed by Contractor or his

authorised representative and got signed from the representative of Engineer-in-charge.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 67

8. The material required only for this work shall be kept in the godawn at site. No material shall be

shifted out side of the godawn except for the work for which this agreement is entered, without prior

approval of the Engineer-in-charge.

9. The Contractor shall produce sufficient documentary evidence i.e. bill for the purchase, octroi receipts

etc. for the purchase of material brought on the work site at once if so requested by the Department.

10. All these material i.e. cement, steel etc. shall be protected from any damages rains etc. by

the contractor at his own cost.

11. The Contractor will have to erect temporary shed of approved specifications storing of above

materials at work site at contractors cost having double lock arrangements (By Double lock it is meant

that godawn shall always be locked by two locks, one lock being owned & operated by Contractor &

other by Engineer-in-charge of his authorized representative & the door shall be openable only after

both locks are opened.)

12. If required, the weighment of cement bags / steel / bulk asphalt bouzers etc. brought by the

contractor shall be carried out by the contractor at his own cost.

13. The contractor shall not use cement and other material for the item to be executed outside the scope

of this contract except for such ancillary small item as are connected and absolutely necessary for

execution of this work as may be decided by the Engineer in charge.

14. The APMC RAHATA shall not be responsible for the loss in cement, steel, bulk asphalt etc. during

transit to work site. The cement brought by the contractor at the work site store shall mean 50 kg.

equivalent to 0.0347 cubic meter per bag by weight. The rate quoted should correspond to this method

of reckoning. In case of ordinary / controlled concrete, if cement is found short, the shortage / shortages

will be made good by the contractor at his cost.

15. INDEMNITY :- The condition regarding indemnity as defined on Page No. 64 at Sr. No. 4 will apply

mutatis mutandis in case of material brought by contractor at the site for the execution of the work being

executed under this contract.

16. In case the material brought by the Contractor become surplus owing to the change in the design of

the work the material should be taken back by the Contractor at his own cost after prior permission of

Engineer-in-charge.

17. Empty asphalt drums shall be the property of the Contractor and the same shall be removed

immediately after completion of work.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 68

Arrangement of Materials

1. The Contractor shall make his own arrangement for supply of materials including bitumen 60/70

grade, and 30/40 grade cement and steel , RCC pipes / Collars. The Contractor shall be

responsible for all transportation and storage of the materials at the site and shall bear all the

related costs. The Engineer shall be entitled at any time, to inspect or examine all such materials.

The Contractor shall provide reasonable assistance for such inspection or examination as may be

required.

2. The Contractor shall keep as accurate record of use of materials like bitumen, cement and steel used in

the works in a manner prescribed by the Engineer.

3. If there is any doubt regarding the material received, the same should be get tested from the

Government laboratory at the cost of the Contractor, and if the results are substandard, the material or

the work executed with such material will be rejected.

4. The day to day record of the receipt /utility/ balance of material should be kept by the Contractor at

plant site / site of work / store and same will be checked by the Engineer-in-charge or authorised

Engineer at any time.

5. The procurement of cement/ steel etc. should be from the authorised manufacturing company

and the vouchers regarding purchase thereof shall be submitted to Engineer-in-charge.

6. The testing charges shall be entirely borne by the Contractor.

Arrangement of Materials

1. The Contractor shall make his own arrangement for supply of materials including bitumen 60/70

grade, and 30/40 grade cement and steel , RCC pipes / Collars. The Contractor shall be

responsible for all transportation and storage of the materials at the site and shall bear all the

related costs. The Engineer shall be entitled at any time, to inspect or examine all such materials.

The Contractor shall provide reasonable assistance for such inspection or examination as may be

required.

2. The Contractor shall keep as accurate record of use of materials like bitumen, cement and steel

used in the works in a manner prescribed by the Engineer.

3. If there is any doubt regarding the material received, the same should be get tested from the

Government laboratory at the cost of the Contractor, and if the results are substandard, the material or

the work executed with such material will be rejected.

4. The day to day record of the receipt /utility/ balance of material should be kept by the Contractor at

plant site / site of work / store and same will be checked by the Engineer-in-charge

or authorised Engineer at any time.

5. The procurement of cement/ steel etc. should be from the authorised manufacturing company

and the vouchers regarding purchase thereof shall be submitted to Engineer-in-charge.

6. The testing charges shall be entirely borne by the Contractor.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 69

ADDITIONAL GENERAL INSTRUCTION TO TENDERERS

1. These are to apply as additional conditions and specifications unless otherwise already provided

for contradictorily elsewhere in this contract.

2. CONTRACTOR TO STUDY SITE CONDITIONS:-

The contractor shall be deemed to have carefully examined the work and site conditions including labour,

the general and the special conditions, specifications, schedules and drawings and shall be deemed to

have visited the site of the work and to have fully informed himself regarding the local conditions and

carried out his own investigations to arrive at rates quoted in the tender. In this regard, he will be given

necessary information to the best of knowledge of Department but without any guarantee about it.

If he shall have any doubt as to the meaning of any portions of these general conditions or the special

conditions, or the scope of work or the specifications and drawings, or any other matter concerning the

contract, he shall in good time, before submitting his tender, set forth the particulars thereof and submit

them to the SECRETARY in writing in order that such doubts may be clarified authoritatively before

tendering. Once a tender is submitted, the matter will be decided accordingly to tender conditions in the

absence of such authentic pre-clarification.

3. DECLARATION OF THE CONTRACTOR :-

The contractor should sign the declaration form attached herewith on page no 29.

4. INDEMNITY :-

The contractor shall indemnify the APMC RAHATA against all action, suits, claims and demands brought

or made against him in respect of anything done or committed to be done by the contractor in execution

of or in connection with the work of this contract and against any loss or damage to the APMC RAHATA

in consequence of any action or suit being brought against the contractor for anything done or omitted to

be done in the execution of the work of this contract. The APMC RAHATA may at its discretion and

entirely at the cost of the contractor defend such suit, either jointly with the Contractor or single in case

the latter choices not to defend the case.

5. DEFINITIONS :-

Unless excluded by or repugnant to the context.

a)The expression “Engineer” or “Engineer -in-charge” as used in the tender papers shall mean the

Engineer-in-charge of the work for the time being.

b)The expression “Contractor” used in the tender papers shall mean the successful tenderer whose

tender has been accepted, and who has been authorized to proceed with the work.

c)The expression “Contract” as used in tender papers shall mean the deed of contract together with its

original accompaniments and those latte incorporated in it by mutual consent.

d)The expression “Plant” as used in the tender papers shall mean every temporary and necessary or

considered necessary by the Engineer to execute, construct, complete and maintain the works and used

in, altered, modified, substituted and additional work ordered in the time and the manner herein

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 70

provided and all temporary materials and special and other articles of appliances of every sort, kind

and description whatsoever intended or used therefor.

e) ”Drawing” shall mean the drawings referred to in the specifications and any modifications of such

drawings approved in writing by Engineer and such other drawings as may from time to time be

furnished or approved in writing by the Engineer.

f) “Engineer’s representative” shall mean an assistant of the Engineer notified in writing to the

Contractor by the Engineer.

g) The “Site” shall mean the lands and/or other places, on under, in or through which the work is to be

executed under the contract including any other lands or places which may be allotted by MSA

MB or used for the purpose of contract.

m) The “Work” shall mean the works to be executed in accordance with the contract or part(s) thereof as

the case may be and shall include all extra or additional, altered or substituted works as required for

performance of the Contract.

n) The “Accepting Authority” shall mean the officer competent to accept the tender.

o) The “Day” shall mean a day of 24 hours from midnight to midnight irrespective of the number of

hours worked in any day in that week.

p) “Temporary works” shall mean all temporary works of every kind required in our about the

execution, completion, or maintenance of the works.

q) ”Urgent works” shall mean any measure which, in the opinion of the Engineer-in-charge, become

necessary during the progress of the works to obviate any risk or accident or failure or which become

necessary for security of the work or the persons working, thereon.

Where the context so requires, words importing the singular only also include the plural and vice-versa.

Heading and marginal notes, if any, to the general conditions shall not be deemed to form part thereof

or be taken in to consideration in the interpretation or construction thereof of the contract.

Wherever there is mention of “Schedule of Rates” of the division or simply D.S.R. in this Tender, it will be

taken to mean as “The Schedule of the rates of the Division in whose jurisdiction the work lies”.

6. ERRORS, OMISSIONS AND DISCREPANCIES: -

a) In case of errors, omissions, and/or disagreement between written and scaled dimensions on the

drawing or between drawings and specifications etc. the following order of preference shall apply.

i) Between actual scaled and written dimensions or descriptions on a drawing the latter shall be adopted.

ii) Between the written or shown description or dimensions in the drawing and corresponding one in the

specifications, the latter shall apply.

iii) Between the quantities shown in schedule of quantities and those arrived at from the drawings, the

latter shall be preferred.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 71

iv) Between the written description of the item in the schedule of quantities and the detailed description

in the specifications of the same items, the latter shall be adopted.

b) In case of discrepancy between percentage rate quoted in figures and words, the lowest of the two

will be considered for acceptance of tender.

c) In all cases of omissions and/or doubts or discrepancies in the dimensions or description of any item or

specifications, a reference shall be made to the APMC RAHATA Engineer, whose elucidation, elaboration

or decision shall be considered as authentic. The contractor shall be held responsible for any errors that

may occur in the work through lack of such reference and precaution.

d) The special provision in detailed specifications and wording of any item shall gain precedence over

corresponding contradictory provision (if any) in the Standard Specifications of Public Works Department

Hand Book where reference to such a specification is given without reproducing the details in contract.

7.1 PROGRAMME OF WORK : -

The work is required to be completed within a stipulated period of 4 Months (including the mansoon

period). The tentative programme may be as per the Bar -Chart.

7.2 a) METHODOLOGY OF CONSTRUCTION AND CONSTRUCTION EQUIPMENTS :-

Contractor shall furnish at least 15 days in advance his programme of commencement of item of work,

the details of actual methods that would be adopted by the contractor for the execution of the various

items of work such as well sinking, cast-in-situ, superstructure for bridgework and earthwork, W.B.M.,

black topping items etc. for road work supported by necessary detailed drawings and sketches including

those of the plant and machinery that would be used, there locations, arrangement for covering and

handling materials etc. and obtain prior approval of the Engineer-in-charge well in advance of starting

of such item of work. The Engineer-in-charge reserve the rights to suggest modifications or make

complete changes in the method proposed by the contractor, whether accepted previously or not at any

stage of the work, to obtain the desired accuracy, quantity and progress of the work which shall be

binding on the contractor, and no claim on account of such change in method of execution will be

entertained by the APMC RAHATA so long as specifications of the item remain unaltered. The sole

responsibility for the safety and the adequacy of the methods adopted by the Contractor, will however,

rest on the contractor, irrespective of any approval given by the Engineer.

In case of slippage from the approved work programme at any stage, the Contractor shall furnish

revised programme to make up the slippage within the stipulated time schedule and obtain the approval

of the Engineer to the revised programme.

b) CONSTRUCTION EQUIPMENT AND LOCATION :-

The Contractor shall be required to give a trial run of the equipments for establishing their capability to

achieve the laid down specifications and tolerance to the satisfaction of the Engineer before

commencement of the work. All equipment provided shall be of proven efficiency and shall be operated

and maintained at all times, in a manner acceptable to the Engineer and no equipment or personnal will

be removed from the site without permission of the Engineer.

c) PROGRESS SCHEDULE :-

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 72

The Contractor shall furnish within the period of one month of the order to start the work, the programme

of work in CPM/PERT charts in quadruplicate indicating the date of actual start, the monthly / progress

expected to be achieved and the anticipated completion date of each major item of work to be done by

him, also including dates of procurement and setting up of materials, plant and machinery. The schedule

is to be such as is practicable of achievement towards the completion of whole work in the time limit, the

particulars items, if any, on the due dates specified in the contract as shall have the approval of the

Engineer-in –charge. No revised schedule shall be operative without such acceptance in writing. The

Engineer is further empowered to ask for more detailed schedule or schedules say ; week by week for

any item or items, in case of urgency of work as will be directed by him and the Contractor shall supply

the same as and when asked for.

The Contractor shall furnish sufficient plant, equipment and labour as may be necessary to maintain the

progress of schedule. The working and shift hours restricted to one shift a day for

operations to be done under the APMC RAHATA supervision shall be such as may be approved by the

Engineer-in-charge. They shall not be varied without the prior approval of the Engineer. Night work

which requires supervision shall not be permitted except when specifically allowed by Engineer each

time, if requested by the contractor. The contractor shall provide necessary lighting arrangements etc. for

night as directed by Engineer without any extra cost to APMC RAHATA.

Further, the Contractor shall submit the progress report of work in prescribed form and charts etc. at

periodical intervals, as may be specified by the Engineer-in-charge. Schedule shall be in the form of

progress charts, forms, progress statement and/or reports as may be approved by the Engineer.

The Contractor shall maintain proforma, charts, details regarding machinery, equipment, labour,

materials, personnel etc. as may be specified by the Engineer and submit periodical returns thereof as

may be specified by the Engineer –in-charge.

8. AGENT AND WORK-ORDER BOOK :-

The Contractor shall himself manage the work or engage an authorised all-time agent on the

work capable of managing and guiding the work and understanding the specifications and contract

conditions. A qualified and experienced, Engineer shall be provided by the contractor as his agent for

technical matters in case the Engineer-in-charge considers this is essential for the work and so directs

Contractors. He will take orders as will be given by the Engineer-in-charge or his representative and

shall be responsible for carrying them out.

This agent shall not be changed without prior intimation to the Engineer-in-charge and his

representative on the work site. The Contractor shall supply to the Engineer the details of al supervisory

and other staff employed by the Contractor and notify changes when made, and satisfy the Engineer

regarding the quantity and sufficiency of the staff, thus employed. The Engineer will have the

unquestionable right to ask for changes in the quality and number of Contractors supervisory staff and to

order removal from work of any of such staff. The Contractor shall comply with such orders and effect

replacements to the satisfaction of the Engineer-in-charge.

A work order book shall be maintained on site and it shall be the property of Government and

the Contractor shall promptly sign orders given therein by the executive Engineer or his representative

and his superior officers and comply with them. The compliance shall be reported by the Contractor to

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 73

the Engineer in good time so that it can be checked. The blank work order book with machine numbered

pages will be provided by the Department free of charge for this purpose. The Contractor will be

allowed to copy out instructions therein from time to time.

9) SETTING OUT FOR (BUILDING WORKS) :-

The Engineer-in-charge shall furnish the Contactor with only the four corner of the works site and

a level bench mark and the Contractor shall set out the works and shall provide an efficient staff for the

purpose and shall solely responsible for the accuracy of such setting out.

The Contractor shall provide, fix and be responsible for the maintenance of all stacks, templates,

level marks, profile and other similar things and shall take all necessary precautions to prevent their

removal or disturbance and shall be responsible for the consequence of such removal or disturbance

should be same take place and for their efficient and timely reinstatement. The

Contractor shall also responsible for the maintenance of all existing survey marks, distance marks

and centre line marks, either existing or supplied and fixed by the Contractor. The work shall be set out

to the satisfaction of the Engineer-in-charge. The approval thereof or joining with the Contractor by the

Engineer-in-charge in setting out the work, shall not relieve the contractor of any of his responsibilities.

Before beginning the work, the Contractor shall at his own cost provide all necessary references

and level posts, pegs, bamboos, flags, ranging rods, strings and other material for proper layout of the

work in accordance with the scheme for bearing marks acceptable to the Engineer-in-charge. The centre,

longitudinal or face lines and cross lines shall be marked by means of small masonry pillars. Each pillar

shall have distinct mark at the centre to enable the theodolite to be set over it. No work shall be started

until all these points are checked and approved by the Engineer-in-charge in waiting but such approval

shall not relieve the Contractor of any of his responsibilities. The Contractor shall also provide all labour,

material and other facilities, as necessary for the proper checking of layout and inspection of the points

during construction.

Pillars bearing geodetic marks located at the sites of units of works under construction should be

protected and fenced by the Contractor. On completion of works, the Contractor must submit the

geodetic documents according to which the work was carried out.

10) RESPONSIBILITIES FOR LEVEL AND ALIGNMENT :-

The Contractor shall be exclusively and entirely responsible for the horizontal and vertical alignment, the

levels and correctness for every part of the work and shall rectify effectually any errors or in perfections

therein, such rectifications shall be carried out by the Contractor, at his own cost, when instructions are

issued to that effect by the Engineer-in-charge.

11) LEVEL INSTRUMENTS :-

If measurements of items of the work are based on volumetric measurements calculates from levels taken

before and after construction of the item, a sufficient number of leveling instruments, staves, tapes etc.

will have to be kept available by the Contractor at the site of work for this purpose.

Lack of such leveling instruments, staves, tapes etc. in required numbers may cause delay in

measurements and the work. The contractor will have therefore to keep sufficient number of these readily

available at site.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 74

12) AUTHORITIES OF THE ENGINEER-IN-CHARGE’S REPRESENTATIVE :-

The duties of the representative of the Engineer-in-charge are to watch and supervise the work and to

test and examine any material to be used or workmanship employed in connection with works.

The Engineer-in-charge may from time to time, in writing delegate to his representative any powers and

authorities vested in the Engineer-in-charge and shall furnish to the Contractor a copy of all such

delegations of powers and authorities. Any written instructions of approval given by the representative

of the Engineer-in-charge to the Contractor within the items of such delegations (but not otherwise) shall

bind the Contractor and the departments as though if had been given by the Engineer –in-charge,

provided always as follows.

Failure of the representative of the Engineer-in-charge to disapprove any work or materials shall not

prejudice the power of the Engineer-in-charge thereafter to disapprove such work or material and so

order the putting down, removal or breaking up thereof.

13) CO-ORDINATION :-

When several agencies for different sub-works of the projects are to work simultaneously on the project

site, there must be full co-ordination and co-operation between different Contractors to ensure timely

completion of the whole project smoothly. The scheduled dates for completion specified in each

Contractor shall therefore, be strictly adhered to. Each Contractor may make his independent

arrangement for water, power, housing etc. if they so desire. On the other hand the Contractors are at

liberty to mutual agreement in this behalf and make joint agreement with the approval of the Engineer.

No single Contractor shall take or cause to be taken any steps or action that may cause, disruption,

discontent, or disturbance of work, labour or arrangement etc. of the other Contractor in the projection

localities. Any action by any Contractor which the Engineer in his unquestioned discretion may consider as

infringement of the above code, would be considered as a breach of contract conditions and shall be

dealt with accordingly.

In case of any dispute, disagreement between the Contractors, the Engineer’s decision regarding the co-

ordination, co-operation and facilities to be provided by any of the Contractors shall be final and

binding on the Contractors concerned and such a decision or decisions shall not vitiate any Contract nor

absolve the Contractor(s) of his/their obligations under the contract nor form the grounds for claim or

compensation.

14) ASSISTANCE IN PRODUCING PRIORITIES, PERMITS ETC. :-

The Engineer, on a written request by the Contractor, will if in his opinion, the request is reasonable and

in the interest of work and its progress, assist the Contractor in securing, the priorities for deliveries

transport permits for controlled materials, permit for quarries and other similar permits etc., where such

are needed. The APMC RAHATA will not, however, be responsible for the non-availability of such

facilities or delay in this behalf and no claims on account of such failures or delays shall be allowed by

the APMC RAHATA. The Contractor shall have to make his own arrangement for machinery required for

the work.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 75

15) QUARRIES :-

15.1 No quarries are available with APMC RAHATA. The Contractor(s) shall have to arrange

himself/themselves. However necessary assistance without any extra cost to APMC RAHATA will be

rendered for procuring he quarries if required by the Contractor.

15.2 The quarrying operations shall be carried out by the Contractor with proper equipment such as

compressors, jack-hammers, drill bits, etc. and sufficient number of workmen shall be employed so as to

get required out turn.

15.3 The Contractor shall carry out the works in quarries in conformity with all the rules and regulations

already laid down or that may be laid down from time to time by APMC RAHATA. Any cost incurred by

APMC RAHATA due to non-compliance of any rules or regulations or due to any damages by the

Contractor shall be the responsibility of the Contractor.

The Engineer-in-charge or his representative shall be given full facilities by the Contractor for inspection

at all times of the working of the quarry, records, maintained, the stocks of materials so as to enable him

to check that the working records and storage are all in accordance with the relevant rules. The

Engineer-in-charge or his representative shall at any times be allowed to inspect the works, buildings,

and equipment at the quarters.

15.4 The Contractor shall maintain at his own cost the books, registers etc. required to be maintained

under the relevant rules and regulations and as directed by the Engineer-in-charge. These books shall be

open for inspection at all times by the Engineer-in-charge or his representative and the contractor shall

furnish the copies or extract of book or registers as and when required.

15.5 All quarrying operations shall be carried out by the Contractor in organized and expeditious

manner, systematically and with proper planning.

16. COLLECTION OF MATERIALS :-

i) The materials shall not be stacked in place where it is liable to be damaged or lost due to traffic

passing over it, to be washed away by rain or floods, to be buried under the land slides etc. or slip

down an embankment or hill side etc. No claim for any loss due to these and similar causes will be

entertained.

ii) Before stacking the materials shall be free from earth, rubbish vegetable matter and other extraneous

substance and in the case of metal, screened to gauge, if so directed when ready. It shall be stacked

entirely clear of the roadway, on ground which has been cleaned of vegetation and leveled.

Frequency Chart for Testing of Materials

ANNEXURE A Sr. No. Material Test Frequency of

Testing Remarks

1. Sand i. Fineness Modulus

ii. Silt Content

At the beginning and if there is Change in source for silt content

Every batch of sand

2. Metal i) Crushing value

ii) Impact value

iii) Abrasion value

One test per 200 Cu.M. or part thereof.

PWD Hand

Book I.S.2386

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 76

iv) Water Absorption

v) Flakiness Index

vi) Stripping value

vii) Gradation

One test per 100

Cu.m. or part thereof.

Part-II

3. Cement

Concrete

I) Compressive Strength Upto 5 Cum 1-Set, 6 to15 Cum – 2 Set, 16 to 30 – 3 Set, 31 to 50 – 4 Set, 51 & above – 4 Set + One additional set for each 50Cum or part thereof

MORT&H

Specification 1716

4. Cement i) Compo Strength

ii) Initial setting time

iii) Final setting time

iv) Specific Gravity

v) Soundness

vi) Fineness

One test for each consignment of 50 M.T. (1000 bags) or part thereof.

I.S.269

12269

5. Steel i) Weight per Meter

ii) Ultimate Tensile stress

iii) Yield stress

iv) Elongation

One test for every 5.0

M.T. or part thereof

for each diameter.

I.S.432

6. Water Bound

Macadam

i) Aggregate Index Value

ii) Gradation

iii) Flakiness index

& Elongation Index

iv) Atterberg limits

of binding material

v) Atterberg limits

of portion of

aggregates passing

425 Micron.

1 test per 200 Cum.

1 test per 100 Cum.

1 test per 200 Cum.

One test per 25 M3

of binding material

One test per 100 Cum.

7. Granular Sub-

base

i) Gradation ii) CBR

As required

1 test per 500 Cum.

As required

1 test per Km.

17. TEMPORARY QUARTERS AND SITE OFFICE :-

i) The Contractor shall at his own expense maintain sufficient experienced supervisory staff etc. required

for the work and shall make his own arrangement, provide housing for them with all necessary

arrangements, including fire preventive measures etc. as directed by the Engineer-in-charge. General

layout for such structures shall be go approved from the Engineer-in-charge. It

will be the responsibility of the Contractor to get his layout plan of temporary structure approved from

the APMC RAHATA.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 77

ii) The Contractor shall provide, furnish, maintain and remove on completion of the work, a suitable office

on the work site for the use of Engineer and representative. He should provide a basket type or suitable

latrine, urinals and keep them clean daily. This will be supposed to be included in his rate.

18. TREASURE TROVE :-

In the event of discovery by the contractor his employers during the progress of the work of any

treasure, fossils, minerals or other articles or things of value or interest the contractor shall give

immediate notice thereof to the Engineer-in-charge and forthwith make over the Engineer-in-charge such

treasure or other things, which shall be the property of the APMC RAHATA.

19. PATENTED DEVICE, MATERIALS AND PROCESSES :-

Whenever the Contractor desires to use any designed devices, materials or process covered

by the letter of patent or copy right, the right for such use shall be secured by suitable legal

arrangement and agreement with patent owner and the copy of their agreement shall be filed with the

Engineer-in-charge if so desired by the later.

20. DAMAGE BY FLOOD OR ACCIDENTS :-

The Contractor shall take all precautions against damage by floods or like or from accident etc. No compensation will be allowed to the Contractor on this account or for correcting and repairing any such damage to the work during construction. The Contractor shall be liable to make good at his cost any plant or materials belonging to the APMC RAHATA lost or damaged by floods or from

any other cause which is in his charge.

21. POLICE PROTECTION :-

For the Special Protection of camp of the Contractor’s works, the APMC RAHATA will help the Contractor

as far as possible to arrange for such protection with the concerned authorities, if so required by the

Contractor in writing. The full cost of such protection shall be borne by the Contractor.

22. SUPERVISION AND INSPECTION OF WORKS AND QUALITY CONTROL :-

22.1 SUPERVISION :-

The Contractor shall either himself supervise the execution of work or shall appoint the competent agent

aproned by the Engineer –in-charge, to act on his behalf. If in the opinion of the Engineer-in-charge, the

Contractor has himself no sufficient knowledge and experience of receiving instructions or cannot give his

full attention to the works, the Contractor shall at his own expenses employ as his accredited agent a

qualified Engineer approved by the Engineer-in-charge.

Orders given to the Contractor’s agent shall be considered to have the force as if these had been given

to the Contractor himself. If the contractor fails to appoint a suitable agent as directed by the Engineer-

in-charge, the Engineer-in-charge shall have full power to suspend the execution of the work until such

date a suitable agent is appointed and the Contractor shall be responsible for

the delay so caused to the work and the Contractor shall not be entitled for any compensation on this

behalf.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 78

22.2 INSPECTION :-

Any way affect him even to reject the work which is alleged to be completed and to suspend the issue of

his certificate of completion until such alteration and modifications or reconstruction have been effected

at the cost of the Contractor as shall enable him to certify that the work has been completed to his

satisfaction.

The Contractor shall provide at his cost necessary ladders and such arrangements as to provide

necessary facilities and assistance for proper inspection of all parts of the work at his own cost.

23. INITIAL MEASUREMENTS FOR RECORD:-

Where, for proper measurement of the work, it is necessary to have an initial set of levels or other

measurements taken, the same as recorded in the authorized field book or measurement book by the

Engineer or his authorized representative will be signed by the Contractor who will be entitled to have a

true copy of the same made at his cost. Any failure on the part of the Contractor to get such levels etc.,

recorded before starting the work will render him liable to accept the decision of the Engineer as to the

basis of taking measurements. Likewise the Contractor will not cover any work which will render its

subsequent measurements difficult or impossible without first getting the same jointly measured by himself

and the authorized representative of the APMC RAHATA. The record of such measurements on the APMC

RAHATA side will be signed by the Contractor and he will be entitled to have a true copy of the same

made at his cost.

24. SAMPLES AND TESTING OF MATERIALS:-

i) All materials to be used on work shall be got approved in advance from the Engineer-in-charge. ii) The Contractor shall at his risk and cost make all arrangements and / or shall provide for all such facilities as the Engineer-in-charge may require for collecting, preparing required number of samples for tests or for analysis at such time and to such place or places as may be directed by the Engineer-in-charge. iii) The Contractor shall if and when required, submit at his cost the samples of materials to be tested or analysed and if, so directed, shall not make use of or incorporate in the work any materials represented by the samples until the required tests or analysis have been made and the materials, finally accepted by the Engineer-in-charge. iv) The Contractor shall not be eligible for any claim or compensation either arising out of any delay in the work or due to any corrective measures required to be taken on account of and as a result of testing of the materials. v) The Contractor or his authorised representative will be allowed to remain present in the departmental laboratory while testing samples furnished by him. However, the results of all the tests carried out in the departmental laboratory in the presence or absence of the Contractor or his authorised representative will be binding on the Contractor. (a) 70% tests shall have to be carried out in his field laboratory and 30% in Quality Control Laboratory. In respect of other construction material which is not mentioned in the following table, 50% tests shall be carried out in the Contractors field laboratory and 50% tests in the nearest quality control laboratory of the Department. In case where there is no field laboratory, 100% tests shall be carried out in the nearest Quality Control Laboratory of the Department. (b) The tests which can not be carried out both in field laboratory and Vigilance & Quality Control Circle’s laboratories, shall becarried out100 % in the laboratories of Government Engineering College / Government Polytechnic at the entire cost of Contractor.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 79

vii) in case of materials supplied by the Government, if the Contractor demands certain testing, the charges thereof shall be paid by the Contractor if the testing results are satisfactory and by the Department if the same are not satisfactory. b) The testing of materials shall be carried out as per the frequency specified by the Superintending Engineer, Vigilance & Quality Control Circle, Rahata and shall be the responsibility of Contractor. c)The material required for testing shall be sent by the contractor to the specified laboratory at his own risk and cost. d) In case the desired results are not obtained during testing or the materials rejected due to unsatisfactory results, the testing charges shall not be paid to the contractor. e) It shall be obligatory on contractor to produce the test results along with receipt of payment made to the Laboratory, for releasing payment towards Testing Charges. f) In case additional testing of material is found necessary due to change in source, no separate payment shall be made and it shall be the entire responsibility of contractor. g) Material Testing shall be carried out as directed by the Engineer-In-Charge.

25.CHANGE OF CEMENT CONTENTS ETC. :-

The tendered rates for any item, involving the use of cement, shall apply to the quantity of cement for

the mix for that item in the specifications, if for any reasons except those required for compensating the

deficiencies, in the components, the cement content and properties are altered by the Engineer (Engineer-

in-charge) at any time or from time to time only to account for the additional cost shall be paid

separately, if such altered and extra cement content from that laid down in the specification/mix design

done as per prevailing I. S. code with prior approval from the competent authority for such changes and

at the rate approved by APMC RAHATA. Likewise for reduction in the cement content, rates for that shall

be reduced rate approved by APMC RAHATA. If any additives in concrete/compounds for

waterproofing material besides the specifications etc. are ordered by the Engineer-in-charge in writing

to be added to the mortar or concrete, no extra rate shall be payable for this and which shall be

carried out as pet directions of the Engineer-in-charge, provided cost of such additives/compounds etc.

shall be borne by APMC RAHATA.

26. CEMENT CONCRETE ;-

GENERAL a) All concrete shall be controlled concrete and machine mixed, unless otherwise directed by Engineer-in-charge. For controlled or high grade concrete, the grading of aggregates shall be got approved from the Engineer. b) The correct proportions and the total amount of water for the mix will be determined by means of preliminary tests and shall be got approved by the Engineer. However, such approval does not relieve the Contract from his responsibility regarding the minimum works strength requirements. Work test shall be taken in accordance with relevant codes and specifications. All proportioning of aggregates shall be done by weight if so ordered by the Engineer. c) i) All mixing shall be done by mechanical means in approved mixers. The Engineer may at his discretion, allow in writing hand mixing of concrete for minor items where small quantities are involved but in that case the Contractor shall increase the cement content of the mixture by 10% without any extra cost to the APMC RAHATA. ii) Conventional type mechanical mixer if found necessary for particular item, may be used with permission of Engineer-in-charge d) The form work used shall be made preferably of steel or with lining of steel. Wooden shutters may be allowed at the discretion of the Engineer e.g. lintels, small slabs and beams coping, etc.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 80

e) The concrete shall be mechanically vibrated for proper compaction by the method approved by the Engineer. f) The concrete shall be cured only by sweet potable water for full 21 days after the time or the period specified in the detailed specification or as may be directed by Engineer-in-charge. g) Minimum Cement content of concrete shall be as per prevailing I.S. Code. REINFORCED CONCRETE WORK The work included in this contract shall be carried out in addition to this specification detailed herein, in accordance with specifications and regulations as laid down in the following standard specifications IS 8112 - 1989 - Specification for 43 grade ordinary Portland cement. IS 12269 - 1989 - Specification for 53 grade ordinary Portland cement. IS 1786 - 1985 - Specification for cold twisted bars IS 383 - 1976 - Specification for coarse and fine aggregate from

natural Courses for concrete. IS 432 - 1982 - Specification for mild steel and medium steel bars. IS 456 - 2000 - Code of practice for plain and reinforced concrete. IS 1489-1991 - Portland puzzolona cement * For T.M.T. (Fe 500) reinforcement bars, prevailing I.S. code shall be followed. 27. MISCELLANEOUS :- 27.1 Rate shall be inclusive of all taxes, royalties and cesses etc. 27.2 For providing electric wiring or water lines etc. recesses shall be provided if necessary

through walls, slabs, beams, etc. and later on refilled up with bricks or stone chipping, cement mortar without any extra cost.

27.3 In case it becomes necessary for the due fulfillment and performance of the contract for the Contractor to occupy land outside the APMC RAHATA limits, the Contractor will have to make his own arrangements with the land owners and to pay such rents if they are payable as mutually agreed between them. The Department will afford the Contractor all the reasonable assistance to enable him to obtain Government land for such purpose on usual terms and conditions as per rules of Government, if such land is available.

27.4 The special provision in detailed specifications or wording if any item shall gain precedence over

corresponding contradictory provision (if any) in the standard specifications where reference to

such specifications is given without reproducing the details in contract.

27.5 Suitable separating Barricades and enclosures shall be provided to separate material brought

by Contractor & same applied for the material obtained from different sources of supply.

27.6 The stacking and storage of construction material at site shall be in such a manner as to prevent

deterioration or infusion of foreign matter and to ensure the preservation of their quality,

properties and fitness for the work. Suitable precautions shall be taken by the Contractor to

protect the material against atmospheric actions, fire and other hazards. The material likely to

be carried away by wind shall be stored in suitable stores or with suitable barricades and

where there is likelihood of substance of soil, such heavy materials shall be stored on approved

platforms.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 81

27.7 The Contractor shall be responsible for making good the damages done to the existing property

during construction by his men.

27.8 It is found necessary from safety point of view to test any part of the structure, the test shall

be carried out by the contractor with the help of the APMC RAHATA at his own cost.

27.9 Defective work is liable to be rejected at any stage. The Contractor, on no account can refuse

to rectify the defects merely on reasons that further work has been carried out. No extra

payment shall be made for rectification.

27.10 In the schedule ‘B’ the work has been divided into sections but notwithstanding this, every part

of it shall be deemed supplementary to and complementary of every other part.

27.11 General directions or detailed description of work, materials and items coverage of rates given

in the specifications are not necessarily repeated in the bill of quantities, Reference is,

however, drawn to the appropriate section clause(s) of the General Specifications in

accordance with which the work is to be carried out.

27.12 In absence of specific directions to the contrary, the rates and prices inserted in the items are

to be considered as the full inclusive rates and prices for the finished work described

thereunder and are to cover all labour, materials, wastage, temporary work, plant overhead

charges and profits, as well as the general liabilities, obligations and risks arising out of the

general conditions of Contract.

27.13 The quantities set down against the item in the schedule ‘B’ are only estimated quantities of

each kind of work included in the contract and are not to be taken as a guarantee that the

quantities scheduled will be carried out or required or that they will not be exceeded.

27.14 All measurements will be made in accordance with the General Conditions of Contract.

27.15 The details shown on drawings and all other information pertaining to the work shall be treated

as indicative and provisional only and are liable to variation as found necessary while

preparing working drawing which will be supplied by the APMC RAHATA during execution.

The Contractor shall not, on account of such variation be entitled to any increase over the ones

quoted in the tender which are on quantity basis.

27.16 Extraneous materials and steps to minimize dust nuisance during construction shall be as per

clause 111 of M.O.S.T. specification New Delhi, August 2001edition.

28.PROTECTION OF UNDERGROUND TELEPHONE CABLE AND AREAL TELEPHONE WIRES AND

POLES, TRANSMISSION TOWERS, ELECTRICITY CABLES AND WATER SUPPLY/DRAINAGE LINES;-

During the execution of work it is likely that the Contractor may meet with telephone cable, electrical

cables, water supply & drainage lines etc. it will, therefore, be the responsibility of the Contractor to

protect them carefully. All such cases should be brought to the notice of the Engineer-in-charge by the

Contractor and also to the concerned Department. Any damage whatsoever done to those cables and

pipelines by the Contractor shall be made good by him at his cost.

29. MEDICAL AND SANITARY ARRANGEMENTS TO BE PROVIDED FOR LABOUR EMPLOYED IN THE CONSTRUCTION BY THE CONTRACTOR

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 82

a) The Contractor shall provide an adequate supply of potable water for the use of labourers on work

and in Camps.

b) The Contractor shall construct trench or semi permanent latrines for the use of the Labourers.

Separate latrines shall be provided for men and women.

c) The Contractor shall build sufficient number of huts on a suitable plot of land for use of the Labourers

according to the following specifications:-

1. Huts of Bamboos and Grass may be constructed.

2. A good site not liable to submergence shall be selected on high ground remote from jungle but well

provided with trees, shall be chosen wherever it is available. The neighborhood of tank, jungle grass

or wood should be particularly avoided. Campus should not be established close to large cutting of

earth work.

3. The lines of huts shall have open spaces of at least ten yards between rows. When a good natural

site cannot be procured, particular attention should be given to the drainage.

4. There should be no overcrowding. Floor space at the rate of 3Sq. meter. Per heads shall be

provided. Care should be taken to see that the huts are kept clean and in good order.

5. The Contractor must find his own land and if he wants Government land, he should apply for it.

Assessment for it if demanded will be payable by Contractor. However the Department does not

bind itself for making available the required land.

6. The Contractor shall construct a sufficient number of bathing places. Washing places should also be

provided for the purpose of washing clothes.

7. The Contractor shall make sufficient arrangements for draining away the surface and sullage water

as well as water from the bathing and washing places and shall dispose of this waste water in such

way as not to cause any nuisance. He shall also keep the premises clean by employing sufficient

number of sweepers.

d) The Contractor shall engage a medical officer with a travelling dispensary for a Camp containing

500 or more person if there is no Government or other private dispensary situated within 8

kilometers from the camp. In case of emergency the Contractor shall arrange at his cost for transport

for quick medical help to his stick worker.

e) The Contractor shall provide the necessary staff for effecting a satisfactory drainage system and

cleanliness of the camp to the satisfaction of the Engineer. At least one sweeper per 200 persons

should be engaged.

f) The assistant Director of Public Health shall be consulted before opening a labour camp and his

instruction on matters such as water supply, sanitary conveniences, the camp site accommodation and

food supply shall be followed by the Contractor.

g) The Contractor shall make arrangements for all antimalaria-measures to be provided for the labours

employed on the work. The antimalaria measures shall be provided as directed by the Assistant

Director of Public Health.

h) In addition to above all provisions of the relevant labour act pertaining to basic amenities to be

provided to the labourer shall be applicable which will be arranged by the contractor.

30. SAFETY CODE :- Suitable scaffolds shall be provided for workman for all work that cannot safely be done from the ground or from solid construction except such short period works as can be done safely from ladders. When ladder is used an extra mazdoor shall be engaged for holding the ladder and if the ladder is used for carrying materials as well, suitable footholds and handholds shall be

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 83

provides on the ladder and the ladder shall be given an inclination no steeper than 1 to 4 (1 horizontal and 4 vertical). Scaffolding or staging more than 3.25 m above the ground or floors, swing or suspended from an overhead support or erected with stationary supports, shall have a guard rail properly attached, bolted, braced and otherwise assured atleast 1 m high above the floor or platform of such scaffolding or staging and extending along the entire length of the outside and ends thereof with only such openings as may be necessary for the delivery of material. Such scaffolding or staging shall be so fastened as to prevent it from swaying from the building or structure. Working platform, gangways, and stairways shall be so constructed that they do not sag unduly or is more than 3.25 m above ground level or floor level, it shall be closely boarded, have adequate width and be suitably fenced as described in 2 above Every opening in floor of the building or in a working platform shall be provided with suitable protection to prevent fall of person or materials by providing suitable fencing or railing with minimum height of 1 meter. Safe means of access shall be provided to all working platform and other working places. Every ladder shall be securely fixed. No portable single ladder shall be over 9 m in length, width between side rails in a rung ladder shall in no case be less than 30 cms for ladders upto and including 3 m in length. For longer ladders this width shall be increased atleast 6 mm for each additional 30 cms of length. Uniform step spacing shall not exceed 30 cm. Adequate precaution shall be taken to prevent danger from electrical equipments. No materials on any of the site shall be stacked or placed as to cause danger or inconvenience to any person or the public. The Contractor shall provide all necessary fencing and lights to protect public from accidents and shall be bound to bear expenses of defense of every suit, action or other proceedings at law that may be brought by any person for injury sustained owing to neglect of the above precaution and to pay any damages and costs which may be awarded in any such suit, action or proceeding to any such person or which may with the consent of the Contractor, to be paid to compromise any claim by such person. 31. EXCAVATION AND TRENCHING :- All trenches, 1.5 meters or more in depth, shall at all times be supplied with atleast 1 ladder for each 30 meter in length or fraction thereof. Ladder shall be extended from bottom of trench to atleast 1 meter above surface of the ground, sides of trench which is 1.5 meters or more in depth shall be stepped back to give suitable slope or security held by timber bracing, so as to avoid the danger of sides collapsing. Excavated materials shall not be placed within 1.3 meters of edge of trench or half of depth of trench whichever is more. Cutting shall be done from top to bottom under no circumstances shall undermining or undercutting be done. 32. DEMOLITION :- Before any demolition work is commenced and also during the process of the work :- a) All roads and open areas adjacent to the work site shall either be closed or suitably protected.

No electric cable or apparatus which is liable to be source of danger or a cable or apparatus used by

operator shall remain electrically charged.

b)All practical steps, shall be taken to prevent danger to person employed, from risk or fire or explosion

or hooding. No floor, roof or other part of a building shall be so overloaded with debris of materials as

to render it unsafe.

All necessary personal safety equipments as considered adequate by the Engineer-in-charge shall be available for use of person employed on the site and maintained in a condition suitable for immediate use and the Contractor shall take adequate step to ensure proper use of equipment by those concerned.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 84

a) Workers employed on mixing asphaltic material cement and lime mortars concrete shall be provided

with protective footwear and protecting goggles.

b) Those engaged in handling any materials, which is injurious to eyes shall be provided with protective

goggles.

c) Those engaged in welding work shall be provided with welder’s protective eye shields.

d) Stone breakers shall be provided with protection goggles and protective clothing and seated at

sufficiently safe intervals.

e) When workers are employed in sewers and manholes which are in use, the Contractor shall ensure that

manhole covers are opened and manholes are ventilated at least for an hour before workers are

allowed to get into them. Manholes opened shall be cordoned off with suitable railing and provided with

warning signals or boards to prevent accident to public.

f) The Contractor shall not employ, men below the age of 18 and women on the work painting with

products containing lead in any form wherever men above the age of 18 are employed on the work of

lead painting the following. Precaution shall be taken.

i) No paint containing lead or lead product shall be used except in the form of paste or readymade

paint.

ii) Suitable face masks shall be supplied for use workers when paint is applied in the form of spray or a surface having lead paint dry rubbed and scrapped. g) When work is done near any place where there is risk of drowning all necessary equipment shall be

provided and kept ready for use and all necessary steps taken for prompt rescue of any person in

danger and adequate provision made for prompt first and treatment of all injuries likely to be sustained

during the course of the work.

Use of hoisting machines and shackles including the attachments, anchorage supports shall confirm to the following :- a) i) These shall be of good mechanical construction, round materials and adequate strength and free

from potent defects and shall be kept in good repair and in good working order.

ii) Every rope used in hoisting or lowering materials or as means of suspension shall be of durable

quality and of adequate strength and free from potent defects.

b) Every crane driver or hoisting appliance operator shall be properly qualified and no person under

the age of 21 years shall be in charge of any hoisting machine including any scaffolding.

c) In case of every hoisting machine and of every chain ring hook, shackle ownel and pulley block used

in hoisting or lowering or as means of suspension safe working load shall be ascertained by adequate

means. Every hoisting machines and all gear referred to above shall be painly marked with safe working

loads.

In case of a hoisting machine having a variable safe working load, each safe working load and the

condition under which is applicable shall be clearly indicated. No part of any machine or of any gear

referred to above in this paragraph shall be loaded beyond safe working load except for the purpose

of testing.

d) In case of departmental machines safe working load shall be notified by the engineer-in-charge. As

regards Contractor’s machines the Contractors shall notify safe working load of each machine to the

Engineer-in-charge whenever, he brings it to site of work and get it verified by the Engineer-in-charge.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 85

Motors, gearing, transmission, electric wiring and other dangerous parts of hoisting appliances shall be provided with such means as well reduce to the minimum risk of accidental descent of load. Adequate precaution shall be taken to reduce to the minimum risk of any part of a suspended load becoming accidentally displaced, when workers are employed. On electrical installations which are already energised insulating material wearing approved such as gloves, sleeves and coats as may be necessary shall be provided. Workers shall not wear any rings, watches and carry keys or other materials which are good conductors of electricity. All scaffolds, ladders and other safely devices mentioned or described herein shall be maintained in a safe condition and no scaffold ladder or equipment shall be altered or removed while it is in use. Adequate washing facilities shall be provided at or near places of work. These safety provisions shall be brought to the notice of all concerned by display on a notice board at a prominent place at the work spot. Persons responsible ensuring compliance with the safety code shall be named therein by the Contractor. i) To ensure effective enforcement of the rules and regulations relating to safety precautions,

arrangements made by the Contractor shall be open to inspection by the Engineer-in-charge or his

representatives and the inspecting officers.

ii) Failure to comply with the provisions hereunder shall make the Contractor liable to pay to the

Department as penalty an amount not exceeding Rs.50/- for each default and decision of the Engineer-

in-charge shall be final and binding.

Notwithstanding the above conditions 1 to 14 the Contractor is not exempted from the operation of any other Act or rules inforce.

33. SCOPE OF RATES FOR DIFFERENT ITEMS OF WORK :-

For item rate contract, the contract unit rates for different items of work shall be payment in full for

completing the work to the requirements of the specifications including full compensation for all the

operations detailed in the relevant sections of these specifications under ‘Rates’ in the absence of any

directions to the contrary, the rates are to be considered as the full inclusive rate for finished work

covering all labour materials, wastage, temporary work, plant, equipment, overhead charges and profit

as well as the general liabilities, obligations and risks arising out of the General Condition of Contract.

The item rates quoted by the Contractor shall unless otherwise specified, also include compliance

with/supply of the following :-

j) General works such as setting out, clearance of site before setting out and clearance of works after

completion.

ii) A detailed programme for the construction and completion of the works (using CPM/PERT techniques)

giving, in addition to construction activities, detailed network activities for the submission and approval of

materials, procurement of critical materials and equipment, fabrication of special products/equipments

and their installations and testing and for all activities of the employer that are likely to effect the

progress of work, etc. including updating of all such activities on the basis of the decisions taken at the

periodic site review meeting or as directed by the Engineer.

iii) Samples of various materials proposed to be used on the work for conducting tests thereon as

required as per the provisions of the contract.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 86

iv) Design of the mixes as per the relevant clauses of the specifications giving proportions of ingredients,

sources of aggregates and binder along with accompanying trial mixes as per the relevant clauses of

these specifications to be submitted to the Engineer for his approval before use of the works.

v) Detailed design calculations and drawings for all temporary works (such as formwork, staging,

centering, specialized constructional handling and launching equipment and the like).

vi) Detailed drawings for templates support and end anchorage, details for prestressing cable profiles,

bar bending and cutting schedules for reinforcement, material lists for fabrication of structural steel, etc.

vii) Mill test reports for all mild and high tensile steel and cast steel as per the relevant provisions of the

specifications.

viii) Testing of various finished items and materials including bitumen, cement, concrete, bearings as

required under these specifications and furnishing test reports/certificates.

ix) Inspection report in respect of formwork, staging, reinforcement and other items of work as per the

relevant specifications.

x) Any other data which may be required as per these specifications or the conditions of contract or any

other annexure/schedules forming part of the contract.

xi) Any item of work which is not specifically provided in the bill of Quantities but which necessary for

complying with the provisions of the contract; and

xii) All temporary works, formwork and false works

34. COMPETENCY OF TENDERERS

No contract will be awarded except to responsible bidders capable of performing the class of work

contemplated. Before the award of the contract, any bidder may by required to show that he has the

necessary facilities, experience ability and financial resources to perform the work in a satisfactory

manner and within the time stipulated, the contractor may be required to furnish the department with

formal sworn statement as to their experience and the financial status.

The tenderer will be deemed to have inspected the site and to have satisfied himself as to the nature of

all works, all existing roads, water ways and from the site and Works (Whether by water or by land) on

or near the site and the building that may be required for temporary purposes in connection with the

construction, completion and maintenance of the works, and must make his own enquires as to work yard

sites and depots and dumps and as to the acquisition of such additional sites and areas as may be

necessary for temporary purposes for constructing, completing and maintaining the works.

35. PAYMENT

The tenderer must understand clearly that the rates quoted are the completed work and include all costs

due to labour, scaffolding, plant, supervision, service, works power. transport etc. and include all extras

to cover the cost of right work if and when- required and no claim for additional payment beyond the

prices or rates quotes will be entertained and the tenderer will not be entitled subsequently to make any

claim on the ground of misrepresentation. or on the ground that he was supplied with information or

given any promise or guarantee by the APMC RAHATA or by any person (whether a member in the

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 87

employee of the APMC RAHATA or not) nor shall any failure on his part to obtain all necessary therein

relieve him from any risks or liabilities arising out of, consequent upon, the submission of a tender.

a) RUNNING BILLS :-

One payments in a month will be granted by the Engineer-in-charge if the progress is satisfactory.

Minimum R.A. Bill amount should be Rs.25.00 Lakhs (Rs. Twenty Lakhs.) Contractor should submit bills to

the Engineer-in-charge in appropriate forms.

b) FINAL BILL :-

The contractor should submit final bill within five months after completion of the work and the same will

be paid if it is in order. Disputed item and claims if any shall be exclude from the final bill and settled

separately later on.

36. HANDING OVER OF WORK:-

All the works and materials before finally taken over by Government will be the entire liability of the

Contractor for guarding, maintaining and making good any damages of any magnitude. Interim

payments made for such work will not alter this position. The handing over by the Contractor and taking

over by the responsible authority of APMC RAHATA or his authorized representative will be always in

writing of which copies will go to the authorized representative of his authorized representative and the

Contractor. It is, however, understood that before taking over such work APMC RAHATA will not put it

into regular use as distinct from casual or incidental one, except as specifically mentioned elsewhere in

this contract, or as mutually agreed to.

37. CLAIMS

Bills for extra work or for any claim shall be paid separately apart from the interim bills for the main

work. The payment of bills for the main work shall not be with held for want of decision on the extras or

claims not covered in the appendices.

Claims for extra work shall be registered within 30 days of occurrence of the event. However bills for

these claims including supporting data/details may be submitted subsequently.

38. MAINTENANCE :-

BUILDINGS :-

a) The Contractor shall maintain the finished and completed item of civil work as per Schedule ‘B’ and

specification for a period 10 (ten) years for water proofing and 7 (seven) years for polyurethane and 1

(One) years for remaining items after the completion of work without any extra cost to APMC RAHATA

irrespective of designs, standards and specifications etc. The Contractor shall get done the civil work as

per specifications etc. The contractor shall get6 done the civil work as per specifications and drawing

and keep the building in good condition throughout the 10 years for water proofing and polyurethane

and 2 years for remaining items. 10% (Ten percent) amount of waterproofing work and 10% (Ten

percent) amount of Antitermite Treatment work only shall be withheld from running account bill for 10

years towards waterproofing from the date of actual completion of work as maintenance charges of the

maintaining and keeping the building in good condition.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 88

b) On completion of the work in all respects, necessary certificates will be issued by the APMC RAHATA

and the defects liability period will be counted from the date of issue of such certificates.

c) Defective work is liable to be rejected at any stage. The Contractor no account can refuse to rectify

the defects merely on reasons that further work has been carried out. No extra payment shall be made

for such rectification.

39. SUBMISSION OF MEASUREMENTS & WORKING DRAWING :- In super session to whatever has been defined in clause 10 and 11 of B-1 agreement form or else where in the N.I.T. documents, the contractor shall submit detailed measurements of work done along with each monthly bill and Final bill. The Engineer-in-charge shall effect necessary checking of the measurements and then effect payment within 10 days of submission of measurements, if possible. If it is proved that the measurements are mindfully and swollen incorrect / irrelevant the Engineer-in-charge shall deduct 25% of the actual payment due, towards correction of payment. Working drawing The contractor shall submit two sets of working drawings on the base of which the measurements as aforesaid, shall be based. 40. TECHNICAL COMPLETION REPORT. The contractor shall submit Technical completion report along with his final bill, which shall include i) Detailed measurements ii) Working drawings. iii) Details of material brought on site and consumed in the work, which shall also indicate standard consumption and deviation, if any, with reasons. iv) Test results of all materials used in work with an abstract of total tests carried out and required as per frequency of tests as laid down in the relevant M.O.S.T. specifications. v) Rougho-metre survey data as laid down in Acceptance criteria. vi) Design calculations / Job-Mix formula etc.

vii) Maintenance-manual.

41. QUALITY ASSURANCE AND MAINTENANCE (FOR WORK COSTING MORE THAN 100 LAKHS) :-

Ensure the specified quality which will also include necessary surveys, temporary works, etc. the

Contractor shall prepare a quality assurance plan and get the same approved from the Engineer-in-

charge within one month from the date of work order. For this the Contractor shall submit an organization

chart of his technical personnel to be deployed on the work along with their qualification, job

descriptions defining the functions of reporting, supervising, inspecting and approving. The Contractor

shall also submit a list of tools, equipment and the machinery and instrumentation which he proposes to

use for the construction and for testing in the field and/or in the laboratory and monitoring. The

Contractor shall modify/supplement the organization chart and the list of machinery, equipment, etc. as

per the directions of the APMC RAHATA and shall deploy the personnel and equipment on the field as

per the approved chart and list respectively. The Contractor shall submit written method statements

detailing his exact proposals of execution of the work in accordance with the specification. He will have

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 89

to get these approved from the Engineer-in-charge. The quality of the work shall be properly

documented through certificate, records, checklists and logbooks of results etc. Such records shall be

complied from the beginning of the work and be continuously updated and supplemented and this will

be the responsibility of the Contractor. The forms should be got approved from the Engineer-in-charge.

41.1.1 Contractor shall prepare a Quality Assurance Plan (QAP) for this work. The QAP shall include the following :- i) Bar chart and CPM/ PERT ii) Personnel deployment with their responsibilities. iii) Schedule of weekly / Monthly Meeting at site office involving all functions iv) Use of Computer for Project Management. v) Training to Technical /Non-Technical Personnel Programme and implemention. vi) Monthly Progress Reports. vii) Quality Procedures. viii) Calibration of instruments used on site ix) Material sources and testing frequency and reports. x) Safety measures. xi) Reference to appropriate approved drawings. xii) Defect Liability : how the contractor going to deal with this. xiii) Reference to specification, codes etc. The contractor shall give the above plan to Engineer-in-charge within 15 days from the date of work order. The Engineer–in-charge will approve the plan within about a week’s time. The contractor shall adhere to the procedure stipulated in the tender document and quality assurance plan prepared by him. 41.1.2 The contractor shall prepare detailed completion drawing after completion of the work. He shall also prepare and submit a maintenance manual giving procedure for maintenance, including inspection, tools and equipment to be used, means of accessibility for all parts of the structure. He shall also include in the manual, the specification for maintenance work that would be appropriate for his design and technique of construction. This manual shall be submitted within the contract period. 41.1.3 The contractor shall make comprehensive inspection of the structure every six months after completion of the work till the end of defect liability period. The defects noticed if any shall be rectified at his own cost under the supervision of Engineer-in- charge. 41.2 Where the work is to be done on lump sum basis on Contractor's design, the Contractor shall also prepare and submit a maintenance manual giving procedure for maintenance, with the periodicity of maintenance works including inspections, tools and equipment to be used, means of accessibility for all parts of the structure. He shall also include in the manual the specifications for maintenance work that would be appropriate for his design and technique of construction. This manual shall be submitted within the contract period 42. PHOTOGRAPHS :- So as to observe the progress of work at different stages of execution of work the contractor shall take

out colored photograph at 3 stages i. e. 1) Before execution 2) during execution 3) After completion of

work. Contractor shall take out at least 15 photographs of different location of each sub works at each

stage. The photographs will be of post card size same shall be submitted along with the R.A. Bill in

duplicate. No extra cost shall be paid to the contractor on this account.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 90

43. ADDITIONAL SPECIAL CONDITIONS :- 1.0 Details of works carried out by the contractor of similar type and magnitude, similar work

environment within the limit of municipal corporation which may be of Government /Non Government but

must be in India. The contractor shall be aware of the municipal corporation Bye-laws of Building

Permission & shall follow it scrupulously.

2.0 Shuttering requirement.

Contractor must have shuttering and formwork of Marine Ply / Steel plates, Acrospan.

The Maximum eight repetition will be allowed for all types of wooden shuttering material. Contractor

shall used adjustable metal props for supporting all R.C.C. elements.

3.0 For all the Items of Concrete work, Crushed sand (Maximum 30 %) may be used. The percentage of

Cursh sand must be as per mix design taken from PWD Quality Control lab. The crushed sand must

follow all the provisions of the relevant codes and specifically of Vertical Shaft Impact crusher (VSI) sand.

4.0 The cement to be used in the various Items must be of P. P. C. grade and for the concrete work the

P.P.C. cement shall have minimum 26% of fly ash content.

5.0 The natural sand to be used in various items shall be as per IS 383- 1970 .

6.0 All the cementitious work should be properly cured as per the requirement of the item. If the

different methodology is adopted for curing other than water, then the contractor shall get it approved

in advance from the Engineer-In-Charge. and shall give the particulars about the consumption, way of

monitoring etc. In case of curing with water the contractor has to do the separate pipe line, sprinkler etc.

7.0 The placement of the concrete and the shuttering shall be as per relevant I.S Codes.

8.0 Staff safety.

While executing the work, necessary precautions regarding safety of labour, supervisory staff, public

and traffic users shall be taken by the agency according to rules and regulations specified by the

Government of India / Government of Maharashtra and as directed by District Court.

Suitable scaffolds shall be provided for workmen for all works that cannot safely be done from the

ground, or from solid construction except such short period works as can be done safely from ladders.

When ladder is used an extra mazdoor shall be engaged to hold the ladder and if the ladder is used

for carrying materials as well, suitable footholds and handholds shall be provided on the ladder and the

ladder shall be given an inclination not steeper than 1 to 4 ( 1 horizontal and 4 vertical).

Scaffolding or staging more than 3.25 m. above the ground or floors, swing or suspended from an

overhead support or erected with stationary support, shall have a guard rail properly attached, bolted,

braced and otherwise assured at least 1 m. high above the floor or platform of such scaffolding or

staging and extending along the entire length of the outside and ends thereof with only such openings as

may be necessary for the delivery of materials.

Such scaffolding or staging shall be so fastened as to prevent it from swaying from the

building or structure.

All the Staff ,labour at site sould be protected with the appropriate safety measures.

9.0. Contractor should use New centering material for all the concreting work with the maximum

repetition shall not exceed 8 Numbers. At the same time the Centering material shall be got approved

from the Engineer -In-Charge.in advance.

10.0 Steel to be used shall be invariably from the integrated plant steel more specifically

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 91

TATA,SAIL,JINDAL etc. and the cement to be used shall be of ACC,ULTRATEK or equivalent. Any imported

material regarding steel, cement will not be allowed.

11.0 For steel cutting, bending, shuttering and allied works specific location shall be earmarked at site.

All the transportation vehicle shall be equipped with vehicle tracker. Proper care to be taken to avoid

the corrosion of the steel at store / yard by applying cement slurry without claiming for any extra cost.

44. ERASURES

Persons tendering are informed that no erasure or alteration by them in the text of the documents sent

herewith will be allowed. Any such erasure or alteration will be disregarded.

45. ACCEPTANCE

Intimation of acceptance of tender will be given by a letter sent by registered post to the address given

below the signatures of the tenderer in the tender.

46. CONTRACTOR'S RESPONSIBILITY

The contractor's tender in accordance with the specification and contract drawings shall be deemed to be

an admission on his part that he has fully acquainted himself with the details thereof and no claim on his

part which may be arise on account of his insufficient examination of the said specification on drawing

shall be in any circumstances be considered.

The contractor shall undertake to do all things and supply all plant materials, supervision and labour

which Engineer may consider necessary for the execution of the work under the contractor or which the

APMC RAHATA would have had to undertake, do or supply had they themselves carried out the

construction of the work.

47. INFORMATION REGARDING LABOUR

The contractor shall submit daily report to the Engineer-in-charge regarding the strength of labour

employed by him on work both skilled and unskilled in the prescribed statement as supplied by the

Engineer-in-charge from time to time. The Contractor if directed by the Engineer-in-charge shall increase

the strength of the labour both skilled unskilled.

48. PROGRAMME

The Engineer-in-charge may at any time give direction as to the order and manner in which the several

parts of the works shall be carried out and the contractor shall at all times subject to an appeal to the

APMC RAHATA strictly observe such direction,

49. METHOD FOR CARRYING OUT THE WORK

The contractor shall furnish for the approval of the Engineer-in-charge a schedule giving the programme

of the work giving details of the methods of execution proposed to be adopted. No work shall be

carried out by any other method except that approval by the Engineer-in-charge. The Engineer-in-

charge may suggest suitable modification in the programme and methods prepared by the contractor.

Adoption of any such changes will not entitle the contractor for claiming any extra rate.

50. REPORTS

The contractor shall furnish to the Engineer-in-charge every week during the progress of the works a

classified weekly report of the number of people employed on the work during the week presiding

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 92

report. The contractor shall also furnish to the Engineer-in-charge (a) A weekly medical report showing

the health of the contractors’ camp and number of persons ill or incapacitated and the nature of their

illness, (b) A report of any accidents which may have occurred within 24 hrs. of its concurrence.

51. TRESPASS

The contractor shall at all times be responsible for any damage or trespass committed by his agents and

work people in carrying out the work, unless such damage or trespass is authorised by the Engineer-in-

charge in writing.

52. CONTROLED MATERIAL: (NOT APPLICABLE)

The APMC RAHATA supply controlled material such as steel, cement, etc. required only for the

construction of the work in question of the contractors. The rates at which this material will be charged to

the contractor and the place where they will be delivered to the contractor have been mentioned in

Schedule "A" of the tender form attached in documents.

As regards other control materials, the APMC RAHATA issue only permits to the contractor for the same

and cooperates with the contractor in securing the same. All incidentals charges met within procuring

these materials shall be borne by the contractor himself.

The contractor shall submit monthly returns in the prescribed form as to the receipt and actual quantities

of the controlled materials supplied and used during the month, to the Engineer-in-charge on the close of

every calendar month.

The contractor shall permit the Engineer-in-charge or his representative to inspect the stock of the

controlled material stored by him at any time, whenever, the Engineer in-charge of his representative

desires.

53. PERMIT AND LICENCES

The contractor shall procure at his own expenses or permit and licenses pay all the charges and fees and

give all notices necessary in connection with the lawful prosecution of the work.

54. PATENTED DEVICES, MATERIALS AND PROCESSES

Whenever the contractor desires to use any design, device, material, or process converted by LETTER

PATENT or copy-right for such use shall be scurried by suitable legal agreement with the patents or

owner, and copy of their agreement shall be filed with the Engineer-in-charge.

55. PLANT

The contractor must at his own expenses supply sound plant for the whole of the work sufficient to

perform the work within the time agreed in contract at his own expenses extend or improve it or keep it

is through repair. All unused material and all plants implements not removed by the contractor within two

months to the completion date of works, shall become the property of the Corporation and the contractor

shall not been titled to any payment or compensation whatsoever in respect thereof.

56. EMPLOYMENT OF RESIDENT ENGINEER

The contractor must employ a skilled and full qualified and authorised Engineer. This Resident Engineer

will be considered at any time to be acting for the contractor with full responsibility in every respect.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 93

57. FOREMEN, WATCHMEN AND WORKMEN

Competent foremen and watchmen shall be employed by the contractor. The APMC RAHATA will at all

time have right to remove from the work any foremen or watchmen or men who give sufficient reason by

their unfitness or by their conduct for complaint.

58. EXAMINATION OF PLANTS AND LOCATION

Statement as to the condition under which the work is to be performed including plants, survey

measurement dimensions, calculations, estimates is made solely to furnish a base for comparison, of

tenders and the Corporation does not guarantee of its correctness.

The contractor must satisfy himself by his own investigation and reason regarding all conditions affecting

the work to be done and labour and material needed and make his bid in sole reliance thereon.

59. INSPECTION OF WORK AND MATERIALS

The inspection of the work shall not relive the contractor of any of his obligations to fulfill the terms of the

contract as herein prescribed by the plans and the specifications and drawings. The contractor shall

furnish the Engineer-in-charge or his authorised representative with every reasonable facility and

assistance whether or not the work as performed is in accordance with the requirements and intent of the

plans and specifications. If so directed the contractor shall, at any time, before the acceptance of work

reopen the portions of the finished work necessary for inspection. After the inspection the contractor shall

restore said portions of the work to the condition required by the specification. The contractor shall

furnish written information to the APMC RAHATA stating the original sources of supply and dates of

manufacture of all materials that are manufactured away from the actual site of the work. In order to

insure a proper time for required inspection and approval, this information shall be furnished at least two

week (or otherwise directed by the Engineer-in-charge) in advance of the incorporation in the work of

any such materials.

An order book shall be maintained on the work and the contractor or his supervisor shall sign the order

and instructions given to him by the officer-in-charge and shall carry them out promptly.

60. SUPPLY OF MATERIALS

The tenderer must also satisfy himself as to the sources of supply and sufficiently of the different

materials referred in the specifications or indicated on the drawings and as to the provision of water for

work and must examine and consider all other matters and all possible and probable contingencies and

generally must obtain his own information on all matters affecting the construction, completion and

maintenance of the work and all matters which may influence him in making his tender and fixing several

rates and price therein. He must also obtain from the Corporation statement of the places where it is

permitted for him to deposit the material excavated. The contractor must accept the entire site as he

finds it. Any work that may be necessary to carry out the contract must be provided for in his contract

price.

61. APPROVAL OF FOUNDATION

The foundation concrete shall be laid only after approval of foundation by the Site Engineer of APMC

RAHATA

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 94

62. STORAGE OF MATERIAL:

It will be the sole responsibility of the contractor at his own risk & cost to store & secure all the material

required for the work.

63. ADDITIONAL CONDITIONS BINDING ON THE CONTRACTOR

1. The contractor will have to appoint full time qualified Engineer who will be responsible for

day to day supervision and execution of the work strictly accordingly to the requirements

of APMC RAHATA. The contractor will furnish name of such Engineer with qualification and

data of his experience in past.

2. As regards the interpretation of the specification and details regarding construction,

decision of APMC RAHATA, shall be final and will be binding on contractor.

3. Since the work is of urgent nature, the contractor will see that it is completed in all respects

within time limit specified and no extension in time limit will be granted normally.

4. The contractor will have to make definite arrangements for curing of all items i.e. masonry,

plaster, R.C.C. etc. for which he will construct sump well of adequate storage and will

provide pump of adequate for lifting water directly on the work.

5. For all grades of concrete including R.C.C. work normally mechanical mixers should be

used. The contractor should also use mechanical vibrator for all R.C.C. items. APMC

RAHATA may however allow hand mixing in suitable cases after taking due precautions in

this behalf.

6. The work should be carried out as per detailed specifications and in workmen like manner.

Quality control test will be carried out at the cost of contractor. In order to get rough idea

Schedule of quality control test is enclosed. However, APMC RAHATA will have discretion

to either increase or decrease the number of such tests on reasonable grounds. The

necessary improvements will have to be immediately implemented by the contractor to suit

the result of such quality tests.

7. Cement will not be supplied by the APMC RAHATA. However, it is responsibility of the

contractor to get cement tested well in time and failure on account of cement quality will

be the sole responsibility of the contractor.

The contractor will also take care that, tested steel is procured and use. The failure on

account of quality of steel is a sole responsibility of the contractor.

8. At the start of work, contractor will have to construct one independent site office of

adequate size for Site Engineer of APMC RAHATA At site office, contractor has to provide

one steel table, minimum two chairs along with one small steel cupboard to keep office

record/ drawings. The said site office shall remain in custody of APMC RAHATA till final

completion of work.

9. The agency will have to arrange for one dumpy level with staff and tripod for survey

purpose and the same is to be kept at the site till completion of work.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 95

ANNEXURE – I SCADA

CONDITIONS

CONDITIONS UNDER USE OF SPECIALISED MACHINERY 34.1.6 Use of Specialized Machinery as per Statement 2A

(1) Scanned copy of proof of ownership of

(a) Reversible Drum Type Concrete Mixer with SCADA with collecting cum weighing belt conveyor (b) Transit mixers and / or concrete pumps of desired number and capacity with SCADA (c) Static Roller of 8 to 10 Tonne / Smooth wheeled Power Roller - 1 No. (d) Vibratory Roller - 2 Nos. with inbuilt Compaction analyser as per IRC SP : 2013. Out of two, and another one with compaction analyser for Soil / GSB/WBM. It shall be owned / confirmed purchase order of 8 to 10 tonne static weight with amplitude and frequency of vibration desired for Bituminous work and separately one for another non B.T. works with SCADA. (h) Batch mix RMC plant concrete mixer with SCADA

(2) Contractor shall own a Drum Type Hot Mix Plant as required under this contract then he should

give details of its current location and under taking whether the Batch Type Plants needs to be shifted or otherwise for this work.

Note : Please see the Additional General Conditions and Specifications Para No. 35.1 & 35.2

Supervising control and data acquisition for Bituminous and Concrete works (SCADA).

(3) Scanned copy of Valid Certificate issued by the Assistant Chief Engineer (Mech.) of Public

Works Department / Region, to the effect that specialised Machinery enlisted in Statement No. 2 ‘A’ attached herewith are in “Efficient” – “Working condition” and in conformity with MORT&H Specifications, must be enclosed in Envelope No.1. in absence of this this Certificate, Envelope No.2 will not be opened. along with this statement as well as their proof of ownership of machinery ( i.e. attested copies of invoices) as well as the valid certificate issued by the Assistant Chief Engineer (Mech) of Public Works Department to the effect that these machineries are in " Efficient Wording Condition" and in conformity with MORT&H Specifications.

Note : Please see the Additional General Conditions and Specifications Para No. 35.1 & 35.2

Supervising control and data acquisition for Bituminous and concrete works (SCADA)

35.6 THE OFFER OF THE CONTRACTOR SHALL INCLUDE: (1) The cost of procuring, establishing, running, operating & maintaining SCADA including all Censors,

Vehicle Tracking System (VTS) and any other instrumentation, automation required to acquire the desired data, mentioned at 35.1 to 35.4 above.

2) Web connectivity to all locations where data is being acquired, transmitted, processed, stored and retrieved with minimum speed of 1 MPBS and 100 % availability. The contactor shall provide the web application in such a manner that it shall first update the above data in real time on PWD’s works monitoring e-governance web application automatically.

(3) Web-based application including Computer Software, Hardware etc. to transmit, process, store and retrieve the data in the forms and formats as prescribed by the Engineer In charge.

(4) Arrangement for security of data, Disaster recovery arrangements shall be as per I.T. Industry practice, during the construction period and upto defect liability period.(DLP). Handing over the data on the Web Server after DLP in Electronic form as instructed by Engineer In charge.

(5) Calibration of all SCADA related attachments /accessories as per the specification:- Web based application to monitor the schedule of Calibration of all SCADA related attachment/accessories. The

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 96

invalidity of calibration shall lead to non-acceptance of work or measurement and the Contractor shall not be paid for such non-accepted work or measurements

(6) Submission of printed and authenticated reports to the Engineer Incharge as and when required.

(7) Point (1) to (6) above shall be arranged and maintained during contract period and defect liability period.

(8) Cost includes rectification, fine tuning, corrections, additions & alterations to the system to the satisfaction of Engineer Incharge.

(9) All data generated as per this special condition of contract shall be the property of PWD.

35.6 The Contractor shall make all necessary arrangement required under Clause 35.1 to 35.4 above

(Supervising control and data acquisition for Bituminous / WBM / Testing Equipments items) well in advance before starting of the related items of work. All necessary arrangements so made shall be offered for inspection to Engineer In charge one month prior to the start of the related items of work. Changes if any, after his inspection suggested by the Engineer In charge shall be carried out at no extra cost and within the period of Three days. A fresh request for inspection, of Engineer In charge after such rectifications shall be requested by the Contractor and final approval to the SCADA arrangements as specified in Clause-19 shall be obtained.

35.7 Additional general Condition and Specifications

a) Intelligent Compacting System - (Page No. 155 Clause No.506.6)

The contractor shall also provide intelligent compacting system on the compactor used for compaction work of PWD. The intelligent compacting system shall have GPS, temperature sensors and screen fitted on the compactor. This system shall be IP-65 compliant. This compaction system shall also record the number of passes made by the compactor. The system shall have the monitor that shall show that compaction in graphical form to the operator on the compactor. The contractor shall provide real time data transfer to the web application to monitor the compaction remotely. The Contractor shall provide the web application in such a manner that it also updates the compaction data in real time on PWD's works management e-governance application dashboard. The intelligent compacting system shall be connected with dashboard system. The contractor shall provide software facility for PWD officials to update QAP (Quality Assurance Plan) related data for compaction through its web application that will get transferred to the intelligent compacting system to bench mark the acceptance norms for colour coding, no of passes and acceptable temperature and density levels. The contractor shall provide compaction register that shall contain information related to the compaction for further analysis. The compaction register shall maintain following record RUN ID, DATE and TIME of compaction, latitude, longitude, location, temperatures (in case of asphalt), density (for soil it can be derived as a compaction measurement value). no of passes, colour for temperature, colour for number of passes. The contractor shall provide web application to replicate the actual view as shown on the monitor of the compactor through live streaming of the compaction operations. The system shall be inbuilt provided by the original manufacturer of compactor. In no case the retrofitted system shall be accepted.

Web Connectivity- The contractor shall provide web connectivity through satellite communication supporting mobile devices to the above monitoring system(mobile VSAT). The web connectivity shall have minimum two MBPS internet speed and 99% availability. Software should be intelligent; in case of connectivity failure it should maintain the pending files and send them as soon as it is connected. The contractor shall make sure that the entire software and hardware solution is virus free.

The offer of contractor shall be inclusive of all. He shall not be paid separately.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 97

Extract from specifications for Road and Bridge works by MORT&H

902 Control of alignment , level and surface regularity.

902.1 General All works performed shall conform to the lines, grades, cross section and dimensions shown on the drawings or as directed by the Engineer, subject, to the permitted tolerances described hereinafter.

902.2 Horizontal alignment

Horizontal alignments shall be reckoned with respect to the center line of the carriageway as shown on the drawings. The edges of the carriageway as constructed shall be correct within a tolerance of + 10 mm. therefrom. The corresponding tolerance for edges of the roadway and lower layers of pavements shall be 3.25 mm.

902.3 Sub-grade Levels

The levels of the Sub-grade and different pavement courses as constructed, shall not vary from those calculated with reference to the longitudinal and cross profile of the road shown on the drawings or as directed by the engineer beyond the tolerance + 6 mm or 0.6 mm. providing . However, that the negative tolerance for wearing course, if the thickness of the former is thereby reduces by more than 6 mm. for fixable pavements and 5 mm. for concrete pavements. For checking compliance with the above requirement for sub-grade, sub-base and base course, measurements of the surface levels shall be taken on a grid of points places at 6.25 m. longitudinally and 3.5 m. transversely. For any 10 consecutive measurements taken longitudinally or transversely , not more than one measurement shall be permitted to exceed the tolerance as above, this one measurement being not in excess of 5 mm. above the permitted tolerance. For checking compliance with the above requirement for bituminous wearing course and concrete pavements , measurements of the surface level shall be taken on a grid of points spaced at 6.25 m. along the length and at 0.5 m. from the edges and at the center of the pavement. In any length of pavement, compliance shall be deemed to be met for final road surface only if the tolerance given above is satisfied for any point on the surface.

902.4 Surface Regularity of pavement courses

The Longitudinal profile shall be checked within a 3 meter long straight edge /moving straight edge as desired by the Engineer at the middle of each traffic lane a line parallel to the center line of the road. The maximum permitted number of surface irregularities shall be as per Table 900-2.

Irregularity Surface of carriageway and paved shoulders

Surface of Lay bays, services Areas and all bituminous base Course.

4mm 7mm 4mm 7mm Length (m)

300 75 300 75 300 75 300 75

National Highway Expressways

20 9 2 1 40 18 4 2

Roads of Lower Category

40 18 4 2 60 27 6 3

The maximum allowable difference between the road surface and underside of a 3 m. straight edge when placed parallel with, or at right angles to the center line of the road at points decided by the Engineer shall be.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 98

For Pavement surface ( Bituminous and cement concrete) 3 mm. For Bituminous base courses 6 mm. For Granular Sub-base courses 8 mm. For Sub-base under concrete Pavements 10 mm.

902.5 Rectification

Where the surface regularity of sub-grade and the various pavement courses fall outside the specified tolerances, the contractor shall be liable to rectify these in the manner described below and to the satisfaction of the Engineer.

Bituminous Construction:- For bituminous other than wearing course, where the surface is low , the deficiency shall be corrected by adding fresh material over a suitable tack coat if needed and recompacting to specifications. Where the surface is high , the full depth of the layer shall be removed and replaced with the fresh material and compacted to specifications.

Abstract from Standard Specifications for Roads and Bridges of Government of Maharashtra. Rd.33

Picking the road surface including sectioning complete

Rd.33.1 General: The item provides and sectioning of the road surface for receiving the new metal surface.

Rd.33.2 Road Diversion: If the traffic cannot be allowed to pass over the roadside shoulders during picking, spreading and compacting operations, diversions should be taken out and maintained as specified under Item No. BR.1.

Rd.33.3 Picking: All the caked mud, slush, animal droppings, vegetation and all other rubbish accumulated on the road surface shall be removed. Where the section of the road surface is good, the road surface shall be picked lightly only, to loosen the surface stones. Where section is uneven, picking shall be done a little deeper to enable the sectioning to be done to the required shape with the picked up material. The picking shall always be ahead of the spreading of metal and compaction by about 100 metres. The edges of the picking shall be truly in a line or curve as the case may be. This can be achieved by trying to nails driven on the road edge and ranging for a sufficiently long length. The picked up surface shall be sectioned to the required grade and camber, super elevation or transition section. Template shall be sued to obtain correct and uniform camber , super elevation or transition section as the case may be. The road surface may be watered by the contractor for easier picking without claiming extra for the same. The junctions of the picked and non-picked surfaces shall be diagonal.

Rd 33.4 Item to include: Picking, watering if required, sectioning and grinding, Divisions including barricading warning signals, lights , etc. unless separately provided in the tender, the work satisfactorily.

Rd 33.5 Mode and Measurement of Payment: The contract rate shall be one Sq.Metre of surface picked & sectioned. The area picked shall be worked out in Sq. Metres correct upto a Sq. Mt. The width shall be limited to the width specified or as ordered by the Engineer. The length shall be measured along the center line of the road. The dimensions shall be recorded correct upto one decimal of a meter increased width on curves shall be measured.

Rd 41 General: The item provides for the supply of stone aggregate of the specified type and size at the roadside including obtaining the stones of the specified quality from approved sources, crushing them in mechanical crushers, conveying to the road side with all leads and lifts stacking in regular heaps as specified hereinafter uniformly along the road side.

41.2 Quarries: Stones of approved type for crushing aggregate shall be obtained from quarries as specified in Section No. Rd 19.2

41.3 Stone aggregates :

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 99

For light or medium traffic For heavy traffic Los Angles abrasion test, percent fines maximum

25 17

Aggregate crushing test, percent, fines maximum

23 17

Water absorption by weight after 24 hours immersion , percent, not more than

1 1

41.3.1 Quality: The aggregates shall be obtained by crushing approved stones of specified type in a mechanical crusher and shall be clean, strong, tough, dense, durable, close grained and free from soft, decayed and weathered portions and from coating of dust, dirt or other objectionable matter. They shall preferably have good hydrophobic characteristics they shall generally satisfy the following requirements.

Test shall be carried out according to I.S. 383-1970. Test considered necessary shall be carried out in an approved laboratory when the Engineer considers quality to be doubtful or there is dispute about the quality. If the results are satisfactory, the cost of tests shall be borne by the Department and if unsatisfactory by the contractor.

Rd 41.3.2 Size: Size of the metal and chips shall be as under : Standard size Wholly passing through Square

mesh of internal dimension Wholly retained on square mesh of internal dimension. 40 mm. ( about 1.5") 50 mm. ( about 2" ) 25 mm. ( about 1" )

22 mm. ( about 1") 40 mm. ( about 1.5") 20 mm. (about 0.75") 20 mm. ( about 0.75") 25 mm. ( about 1") 12 mm. (about 0.50") 12 mm. ( about 0.05") 20 mm. ( about 0.75") 10 mm. (about 0.75") 10 mm. ( about 0.75") 12 mm. ( about 0.50") 6 mm. (about 0.25") 6 mm. ( about 0.25") 10 mm. ( about 0.75") 5 mm. (about 3/16")

Note : Not more than 20% of any sample shall exceed in its greatest dimension , standard size plus 25

mm, for 40 mm. standard size and standard size plus 12 mm. For 25 mm., 20 mm. and 12 mm. standard size and standard size plus 6 mm. for 10 mm. standard sizes.

The pieces shall be roughly cubical in shape and more or less of uniform size with sharp edges for interlocking, rounded flaky, thin elongated pieces shall not be accepted. Before collection , samples of metal and chips shall be got approved for quality, size and shape by the Engineer who will keep them in his office for reference. They shall be completely any at the time of use.

Rd 41.3.3 Conveyance: According to Specification No. Rd 19.3.3

Rd 41.3.4 Stocking: According to Specification No. Rd.22.3.4 wherever a mixture of aggregates of two or more standard sizes is specified for the work, each size of aggregates shall be stacked separately and entirely clear of the carriageway and where possible clear of the shoulders also. They shall be stacked in such a manner as to prevent mixture, deterioration or contamination.

Rd 41.4 Special points: According to Specification No. Rd. 19.4

Rd 42.5 Item to include: Crushing aggregates to the specified sizes from approved rubble and

other items included in Specification No. Rd 19.5

Rd 41.4 Special points: According to Specification No. Rd. 19.4

Rd 42.5 Item to include: Crushing aggregates to the specified sizes from approved rubble and other items included in Specification No. Rd 19.5

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 100

ANNEXURE – A QUALITY

CONTROL TESTS

Sr. No. Material Test 1 Cement i) Compressive strength

ii) Initial setting time iii) Final setting time iv) Specific gravity v) Soundness vi) Fineness vii) Std. Consistency

2 Steel i) Weight per meter ii) Ultimate Tensile Stress iii) Yield Stress iv) Elongation

3 Granular i) Density of Compacted layer ii) C.B.R.

4 Lime / Cement stabilized soil sub base

i) Quantity of lime / cement ii) Degree of pulverisation iii) Lime / Cement content iv) CBR or unconfined compressive strength test on a set of 3 specimens. v) Density of compacted layer

5 Water Bound Macadam i) Aggregate impact value ii) Flakiness index & Elongation index

6 Wet Mix Macadam i) Impact value ii) Flakiness index & Elongation index iii) Density of compacted layer

7 Murum i) Optimum Dry Density ii) C.B.R. iii) Liquid & Plastic Limit / Plasticity Index iv) Filed Density 100% P.D. v) Filed Moisture Content

8 Thermoplastic Paint i) Glass beed contents and grading analysis ii) Reflectance & yellowness index iii) Flow ability iv) Drying time

9 Inter locking concrete paving block i) Compressive strength ii) Flexural test iii) Resistance to wear

10 Cement Concrete i) Mix design 11 Reinforcement steel bars i) Tensile strength

ii) % Elongation 12 Sand i) Water Absorption & Specific Gravity

ii) Fineness Modulus iii) Silt Content iv) Bulkage

13 Water i) P.H. Value / For Water ii) Chloride & Sulphate Content

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 101

ANNEXURE – B

Construction Material Testing & Its Frequency

(Whichever is applicable)

Sr. Material Rate Frequency 1 CEMENT

1) Consistency 2) Initial & Final Setting time 3) Fitness 4) Specific Gravity 5) Soundness 6) Compressive Strength

Test per 50 M.t. above six tests shall be carried

2 a)

b) c) d) e) f) g)

METAL 1) Sieve Analysis (Gradation)(Concrete work) 2) Sieve Analysis Red Book Specification 3) Sieve Absorption Granular Sub Base

(N.H. Work) MOST Water Absorption Impact (Concrete WBM/BT) Crushing Abrasion Flakiness & Elongation Index Plasticity Index for blindage used for WBM

1 Test for Every day work 1 Test per 100 m3 1 Test per 200 m3

1 Test per 200 m3 1 Test per 200 m3 1 Test per for Each Source 1 Test per for Each Source 1 Test per 200 m3 1 Test per 25 m3

3 SAND 1) Water Absorption & Specific Gravity 2) Fitness Modulus 3) Slit Content 4) Bulkage

1 Test per for Each Source 1 Test per for Each day 1 Test per for Each day work 1 Test per for Each day work

4 Concrete Mix Design Compressive strength C.C. Cubes for Qty. Qty. upto 5 m3 6-15 m3 16-30 m3 31-50 m3 quantity above 51 m3

1 Concrete Mix Design for each grade of concrete per every per hour 1 Set (3 Nos.) 2 Set (3 Nos.) 3 Set (3 Nos.) 4 Set (3 Nos.) 4 + 1 additional set per 50 m3

5 MURUM / SOIL for earth work 1) Optimum Dry Density 2) C.B.R. 3) Liquid & Plastic Limit / Plasticity Index 4) Filed Density 100% P.D. 5) Filed Moisture Content

2 Test per 3000 m3 1 Test per 3000 m3 1 Test per 3000 m3 1 Test per 3000 m3 1 Test per 3000 m3

6 WATER 1) P.H. Value / For Water and Sand 2) Chloride & Sulphate content

1 test per Source 2 test per Source

7 Steel 1) Wt. per metre 2) Ultimate Tensile Stress 3) Yield stress 4) Elongation

One test for every 5.0 MT or partner of for each diametre

8 Pavement Quality Concrete 2 cubes and 2 beams per 150 cubic metre or part thereof 1 test 7 days other 28 days strength or Minimum 6 cubes & 6 beams per day work whichever is More

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 102

59. PHOTOGRAPHS :- So as to observe the progress of work at different stages of execution of work the contractor

shall take out colored photograph at 3 stages i. e. 1) Before execution 2) during execution 3)

After completion of work. Contractor shall take out at least 15 photographs of different location

of each sub works at each stage. The photographs will be of post card size same shall be

submitted along with the R.A. Bill in duplicate. No extra cost shall be paid to the contractor on

this account.

60. ADDITIONAL SPECIAL CONDITIONS :- 1.0 Details of works carried out by the contractor of similar type and magnitude, similar work

environment within the limit of municipal corporation which may be of Government /Non

Government but must be in India. The contractor shall be aware of the municipal corporation

Bye-laws of Building Permission & shall follow it scrupulously.

2.0 Shuttering requirement.

Contractor must have shuttering and formwork of Marine Ply / Steel plates, Acrospan.

The Maximum eight repetition will be allowed for all types of wooden shuttering material.

Contractor shall used adjustable metal props for supporting all R.C.C. elements.

3.0 For all the Items of Concrete work, Crushed sand (Maximum 30 %) may be used. The

percentage of Cursh sand must be as per mix design taken from PWD Quality Control lab. The

crushed sand must follow all the provisions of the relevant codes and specifically of Vertical

Shaft Impact crusher (VSI) sand.

4.0 The cement to be used in the various Items must be of P. P. C. grade and for the concrete

work the P.P.C. cement shall have minimum 26% of fly ash content.

5.0 The natural sand to be used in various items shall be as per IS 383- 1970 .

6.0 All the cementitious work should be properly cured as per the requirement of the item. If the

different methodology is adopted for curing other than water, then the contractor shall get it

approved in advance from the Engineer-In-Charge. and shall give the particulars about the

consumption, way of monitoring etc. In case of curing with water the contractor has to do the

separate pipe line, sprinkler etc.

7.0 The placement of the concrete and the shuttering shall be as per relevant I.S Codes.

8.0 Staff safety.

While executing the work, necessary precautions regarding safety of labour, supervisory staff,

public and traffic users shall be taken by the agency according to rules and regulations

specified by the Government of India / Government of Maharashtra and as directed by District

Court.

Suitable scaffolds shall be provided for workmen for all works that cannot safely be done from

the ground, or from solid construction except such short period works as can be done safely from

ladders. When ladder is used an extra mazdoor shall be engaged to hold the ladder and if the

ladder is used for carrying materials as well, suitable footholds and handholds shall be provided

on the ladder and the ladder shall be given an inclination not steeper than 1 to 4 ( 1 horizontal

and 4 vertical).

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 103

Scaffolding or staging more than 3.25 m. above the ground or floors, swing or suspended from

an overhead support or erected with stationary support, shall have a guard rail properly

attached, bolted, braced and otherwise assured at least 1 m. high above the floor or platform

of such scaffolding or staging and extending along the entire length of the outside and ends

thereof with only such openings as may be necessary for the delivery of materials.

Such scaffolding or staging shall be so fastened as to prevent it from swaying from the

building or structure.

All the Staff ,labour at site sould be protected with the appropriate safety measures.

9.0. Contractor should use New centering material for all the concreting work with the maximum

repetition shall not exceed 8 Numbers. At the same time the Centering material shall be got

approved from the Engineer -In-Charge.in advance.

10.0 Steel to be used shall be invariably from the integrated plant steel more specifically

TATA,SAIL,JINDAL etc. and the cement to be used shall be of ACC,ULTRATEK or equivalent. Any

imported material regarding steel, cement will not be allowed.

11.0 For steel cutting, bending, shuttering and allied works specific location shall be earmarked

at site. All the transportation vehicle shall be equipped with vehicle tracker. Proper care to be

taken to avoid the corrosion of the steel at store / yard by applying cement slurry without

claiming for any extra cost.

61. ERASURES

Persons tendering are informed that no erasure or alteration by them in the text of the

documents sent herewith will be allowed. Any such erasure or alteration will be disregarded.

62. ACCEPTANCE

Intimation of acceptance of tender will be given by a letter sent by registered post to the

address given below the signatures of the tenderer in the tender.

63. CONTRACTOR'S RESPONSIBILITY

The contractor's tender in accordance with the specification and contract drawings shall be

deemed to be an admission on his part that he has fully acquainted himself with the details

thereof and no claim on his part which may be arise on account of his insufficient examination of

the said specification on drawing shall be in any circumstances be considered.

The contractor shall undertake to do all things and supply all plant materials, supervision and

labour which Engineer may consider necessary for the execution of the work under the contractor

or which the APMC RAHATA would have had to undertake, do or supply had they themselves

carried out the construction of the work.

64. INFORMATION REGARDING LABOUR

The contractor shall submit daily report to the Engineer-in-charge regarding the strength of

labour employed by him on work both skilled and unskilled in the prescribed statement as

supplied by the Engineer-in-charge from time to time. The Contractor if directed by the Engineer-

in-charge shall increase the strength of the labour both skilled unskilled.

65. PROGRAMME

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 104

The Engineer-in-charge may at any time give direction as to the order and manner in which the

several parts of the works shall be carried out and the contractor shall at all times subject to an

appeal to the APMC RAHATA strictly observe such direction,

66. METHOD FOR CARRYING OUT THE WORK

The contractor shall furnish for the approval of the Engineer-in-charge a schedule giving the

programme of the work giving details of the methods of execution proposed to be adopted. No

work shall be carried out by any other method except that approval by the Engineer-in-charge.

The Engineer-in-charge may suggest suitable modification in the programme and methods

prepared by the contractor. Adoption of any such changes will not entitle the contractor for

claiming any extra rate.

67. REPORTS

The contractor shall furnish to the Engineer-in-charge every week during the progress of the

works a classified weekly report of the number of people employed on the work during the

week presiding report. The contractor shall also furnish to the Engineer-in-charge (a) A weekly

medical report showing the health of the contractors’ camp and number of persons ill or

incapacitated and the nature of their illness, (b) A report of any accidents which may have

occurred within 24 hrs. of its concurrence.

68. TRESPASS

The contractor shall at all times be responsible for any damage or trespass committed by his

agents and work people in carrying out the work, unless such damage or trespass is authorised

by the Engineer-in-charge in writing.

69. CONTROLED MATERIAL: (NOT APPLICABLE)

The APMC RAHATA supply controlled material such as steel, cement, etc. required only for the

construction of the work in question of the contractors. The rates at which this material will be

charged to the contractor and the place where they will be delivered to the contractor have

been mentioned in Schedule "A" of the tender form attached in documents.

As regards other control materials, the APMC RAHATA issue only permits to the contractor for the

same and cooperates with the contractor in securing the same. All incidentals charges met within

procuring these materials shall be borne by the contractor himself.

The contractor shall submit monthly returns in the prescribed form as to the receipt and actual

quantities of the controlled materials supplied and used during the month, to the Engineer-in-

charge on the close of every calendar month.

The contractor shall permit the Engineer-in-charge or his representative to inspect the stock of the

controlled material stored by him at any time, whenever, the Engineer in-charge of his

representative desires.

70. PERMIT AND LICENCES

The contractor shall procure at his own expenses or permit and licenses pay all the charges and

fees and give all notices necessary in connection with the lawful prosecution of the work.

71. PATENTED DEVICES, MATERIALS AND PROCESSES

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 105

Whenever the contractor desires to use any design, device, material, or process converted by

LETTER PATENT or copy-right for such use shall be scurried by suitable legal agreement with the

patents or owner, and copy of their agreement shall be filed with the Engineer-in-charge.

72. PLANT

The contractor must at his own expenses supply sound plant for the whole of the work sufficient

to perform the work within the time agreed in contract at his own expenses extend or improve it

or keep it is through repair. All unused material and all plants implements not removed by the

contractor within two months to the completion date of works, shall become the property of the

Corporation and the contractor shall not been titled to any payment or compensation whatsoever

in respect thereof.

73 EMPLOYMENT OF RESIDENT ENGINEER

The contractor must employ a skilled and full qualified and authorised Engineer. This Resident

Engineer will be considered at any time to be acting for the contractor with full responsibility in

every respect.

74. FOREMEN, WATCHMEN AND WORKMEN

Competent foremen and watchmen shall be employed by the contractor. The APMC RAHATA will

at all time have right to remove from the work any foremen or watchmen or men who give

sufficient reason by their unfitness or by their conduct for complaint.

75. EXAMINATION OF PLANTS AND LOCATION

Statement as to the condition under which the work is to be performed including plants, survey

measurement dimensions, calculations, estimates is made solely to furnish a base for comparison,

of tenders and the Corporation does not guarantee of its correctness.

The contractor must satisfy himself by his own investigation and reason regarding all conditions

affecting the work to be done and labour and material needed and make his bid in sole

reliance thereon.

76. INSPECTION OF WORK AND MATERIALS

The inspection of the work shall not relive the contractor of any of his obligations to fulfill the

terms of the contract as herein prescribed by the plans and the specifications and drawings.

The contractor shall furnish the Engineer-in-charge or his authorised representative with every

reasonable facility and assistance whether or not the work as performed is in accordance with

the requirements and intent of the plans and specifications. If so directed the contractor shall, at

any time, before the acceptance of work reopen the portions of the finished work necessary for

inspection. After the inspection the contractor shall restore said portions of the work to the

condition required by the specification.

The contractor shall furnish written information to the APMC RAHATA stating the original sources

of supply and dates of manufacture of all materials that are manufactured away from the

actual site of the work. In order to insure a proper time for required inspection and approval,

this information shall be furnished at least two week (or otherwise directed by the Engineer-in-

charge) in advance of the incorporation in the work of any such materials.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 106

An order book shall be maintained on the work and the contractor or his supervisor shall sign the

order and instructions given to him by the officer-in-charge and shall carry them out promptly.

77. SUPPLY OF MATERIALS

The tenderer must also satisfy himself as to the sources of supply and sufficiently of the different

materials referred in the specifications or indicated on the drawings and as to the provision of

water for work and must examine and consider all other matters and all possible and probable

contingencies and generally must obtain his own information on all matters affecting the

construction, completion and maintenance of the work and all matters which may influence him in

making his tender and fixing several rates and price therein. He must also obtain from the

Corporation statement of the places where it is permitted for him to deposit the material

excavated.

The contractor must accept the entire site as he finds it. Any work that may be necessary to carry

out the contract must be provided for in his contract price.

78. STORAGE OF MATERIAL:

It will be the sole responsibility of the contractor at his own risk & cost to store & secure all the

material required for the work.

79. ADDITIONAL CONDITIONS BINDING ON THE CONTRACTOR

1. The contractor will have to appoint full time qualified Engineer who will be responsible

for day to day supervision and execution of the work strictly accordingly to the

requirements of APMC RAHATA.

The contractor will furnish name of such Engineer with qualification and data of his

experience in past.

2. As regards the interpretation of the specification and details regarding construction,

decision of APMC RAHATA, shall be final and will be binding on contractor.

3. Since the work is of urgent nature, the contractor will see that it is completed in all

respects within time limit specified and no extension in time limit will be granted normally.

4. The contractor will have to make definite arrangements for curing of all items i.e.

masonry, plaster, R.C.C. etc. for which he will construct sump well of adequate storage

and will provide pump of adequate for lifting water directly on the work.

5. For all grades of concrete including R.C.C. work normally mechanical mixers should be

used. The contractor should also use mechanical vibrator for all R.C.C. items. APMC

RAHATA may however allow hand mixing in suitable cases after taking due precautions

in this behalf.

6. The work should be carried out as per detailed specifications and in workmen like

manner. Quality control test will be carried out at the cost of contractor. In order to get

rough idea Schedule of quality control test is enclosed. However, APMC RAHATA will

have discretion to either increase or decrease the number of such tests on reasonable

grounds. The necessary improvements will have to be immediately implemented by the

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 107

contractor to suit the result of such quality tests.

7. Cement will not be supplied by the APMC RAHATA. However, it is responsibility of the

contractor to get cement tested well in time and failure on account of cement quality will

be the sole responsibility of the contractor.

The contractor will also take care that, tested steel is procured and use. The failure on

account of quality of steel is a sole responsibility of the contractor.

8. At the start of work, contractor will have to construct one independent site office of

adequate size for Site Engineer of APMC RAHATA At site office, contractor has to

provide one steel table, minimum two chairs along with one small steel cupboard to keep

office record/ drawings. The said site office shall remain in custody of APMC RAHATA

till final completion of work.

9. The agency will have to arrange for one dumpy level with staff and tripod for survey

purpose and the same is to be kept at the site till completion of work.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 108

Name of Work: Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar,, Tal. Rahata, Dist. Ahmednagar Undertaking (I) I have gone through the procedure of submitting tender in Two Envelope System and I /we

am/are fully conversant with the details of procedure to be fallowed in the systems.

I /we will submit tender properly after reading all relevant details.

Date:

Signature of Contractor

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 109

PROFORMA OF BANK GUARANTEE FOR PERFORMANCE GUARANTEE

To,

The Secretary,

Agriculture Produce Market Committee,

At. Sakuri, Tal Rahata, Dist. Ahmednagar – 423107

Dear Sir,

In consideration of APMC RAHATA, Rahata (hereinafter referred to as the ‘Owner” which

expression shall unless repugnant to the context or meaning thereof include its successors,

administrators and assigns) having awarded to M/s. ___________________________

(hereinafter referred to as the ‘Contractor’ which expression shall unless repugnant to the context

of meaning thereof, include its successors, administrators executors and dated ___________ and

the same having been unequivocally accepted by the contractor resulting in a Contract bearing

No. __________ dated _________ valued at ____________ for agreed to provide contract

performance guarantee for the faithful performance of entire contract equivalent to the said

value of the contract to the owner.

We ______________________________________ (name and address) having its head office

at __________ (hereinafter referred to as the ‘Bank’ which expression shall unless repugnant to

the context or meaning thereof, include the successors administrators, executors and assigns) do

hereby guarantee and undertake to pay the owner, on demand any and all money payable by

the contractor to the extent of as aforesaid ___________ at ___________ any ___________

time ___________ up to ____________.

Without any demur, reservation, contest, recourse or protest and /or without any reference to

the contractor. Any such demand made by the owner on the bank shall be conclusive and binding

notwithstanding any difference between the owner and contractor or any dispute pending

before any court tribunal or any authority. The bank undertakes not to revoke this guarantee

during its currency without previous consent of the owner and further agrees that the guarantee

here in contained shall continue to be enforceable till the owner discharges this guarantee. The

owner shall have the fullest liberty, without affecting this guarantee, to postpone from time to

time the exercise of any powers vested in them or of any right which they might have against the

contractor, and to exercise the same at any covenants, contained or implied, in the contractor

between the owner and contractor or any other course of or remedy or security available to the

owner.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 110

The Bank shall not be released of its obligations under these presents y any exercise by the

owner of its liberty with reference to the matters aforesaid or any of them or by reason of any

other acts of omission or commission on the owner or by any other matters or thing whatsoever

which under law would, but for this provision, have the affect of relieving the bank. The bank

also agrees that the owner at its option shall be entitled to enforce this guarantee against the

bank as principal debtor, in the first instance without proceeding against the contract and

notwithstanding and security or other guarantee that the owner may have in relation to the

contractors liabilities.

The bank further agree with the owner that the owner shall have the fullest liberty without our

consent any without affecting in any manner our obligations hereunder to vary any of the terms

and conditions of the said agreement or to extend time of performance of the said contractor

from time to time or to postpone for any time or from time to time any of the powers exercised

by the company against the said contractor and to forbear or enforce any of the terms and

conditions relating the said agreement and we shall not be relieved from our liability by reason

of any such variation or extension being granted by the said corporation to the said contractor

or y any such matter or thing whatsoever which under the law relating to sureties would, but for

this provision, have effect of so relieving us.

This guarantee will not be discharged due to the change in the constitution of the bank or the

contractor.

The bank lastly undertakes not to revoke this guarantee during its currency except with the

previous consent of the owner in writing.

Notwithstanding anything contained herein above, our liability under this guarantee is restricted

to a sum of Rs. ___________ and the guarantee shall remain valid till ________ unless a claim

or action to invoke the guarantee is received in writing by us on or before _______ all your

rights under the guarantee shall be forfeited and the bank will be relieved and discharged of its

liabilities there under.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 111

DRAWINGS

CONTRACT DRAWINGS:- Contractor should visualize the nature of type of work contemplated and to ensure that the rates and prices quoted by him in the bill of quantities take due consideration of the complexities of work involved during actual execution/construction as experienced Contractors in the field. The tendered rates/prices for the work shall be deemed to include the cost of preparation, supply and delivery of all necessary drawings, prints, tracings and negatives which the Contractor is required to provide in accordance with the contract. DOCUMENTATION:- If so ordered by the Engineer in charge the Contractor will prepare drawings of the work at constructed and will supply original and three copies to the Engineer who will verify and certify these drawings. Final as constructed drawings shall then be prepared by the Contractor and supplied in triplicate along with a micro film or Soft copy in CD/DVD of the same to the Engineer for record and reference purposes at the Contractor’s cost.

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 112

SCHEDULE ‘B’ NOTES:- 1) All the quantities shown in the schedule ‘B’ are likely to vary at the time of actual

execution, as such claims on this account shall be entertained. 2) Rate of all items include all leads and lifts, labour, material involved for completed

item and site clearance 3) All rates are inclusive of all taxes, octroi chargers and royalty charges.

4) Work shall be carried out as per the instructions / orders and to the enter satisfaction of

Engineer-in-charge. 5) Government Circulars issued previously and will be issued hereafter are also binding

on the contractor. 6) The detailed specifications are as One Standard Specification Book Volume I Edition

2012 and Volume II Edition 2012 Published by the Govenement of Maharashtra in Public works Department and Specification for road and bridge work published

by Ministry of road Transport and Highway 5th revision 2013 7) Government Circulars issued previously and will be issued hereafter are biding on the

Contractor. Memorandum showing the items of work to be carried out by the contractor

Contractor APMC Rahata

Agriculture Produce Market Committee, Rahata 113

SCHEDULE B & SPECIFICATIONS

Page &

Item No. In

PWD DSR

Speci. Clause

No.

Addittional

Identity if any

1 153.32 Excavation for foundation in earth, soil of all types, sand, gravel and

soft murum, including removing the excavated material up to a

distance of 50 m. beyond the building area & stacking and spreading

as directed, dewatering, preparing the bed for the foundation and

necessary back filling, ramming, watering including shoring and

strutting etc. Complete. (Lift upto 1.5 m.) By Manual Means

145.95 Rupees One

Hundred Forty

Five and Ninety

Five Paise

Cubic Meter 22376.67 21.01 Bd.A.1 Page

No. 259

___

2 13.72 Excavation for foundation in earth, soils of all types, sand,gravel and

soft murum, including removing the excavated material upto a distance

of 50 meters beyond the building Area and stacking and spreading

as directed, dewatering, preparing the bed for the foundation and

necessary back filling, ramming, watering including shoring and

strutting etc. complete. (Lift from 1.5m to 3.0m) By Manual Means

194.25 Rupees One

Hundred Ninety

Four and Twenty

Five Paise

Cubic Meter 2664.73 21.03 Bd.A.1 Page

No. 259

___

3 16.26 Providing and laying in situ, cement concrete in M10 of trap/ granite/

quartzite/ gneiss metal for foundation and bedding including bailing

out water, formwork, compacting and curing complete, with fully

automatic micro processor based PLC with SCADA enabled reversible

Drum Type mixer, With natural sand.

4161.64 Rupees Four

Thousand One

Hundred Sixty

One and Sixty

Three Paise

Cubic Meter 67669.55 24.01 Bd. E. 1

Page No.

287

___

Estimate Rate

Rupees in

Words

Estimate Rate

Rupees in

figure

UNIT or Per

Total AMOUNT

according to estimated

Quantities

Referance to Std. Sp. Book Vol. I, IS

BHUTADA CONSULTANTS ARCHITECT, R.C.C. CONSULTANT, INTERIOR DESIGNER

Name of Work : Proposed Construction of Toilet Block, at Loni - Sheli Mendhi Bazaar, Tal. Rahata, Dist. Ahmednagar, For Agriculture Produce

Market Committee Rahata

OFFICE: Niwara Housing Society,Morge Wasti, Shrirampur 413709. PH. No. 210227

ABSTRACT SHEET : Toilet

Sr.

No.

Quantity

estimated

but may

be more or

less

ITEM DESCRIPTION

Contractor APMC Rahata 114

4 5.75 Providing and casting in situ cement concrete in M15 of trap/

granite/quartzite/gneiss metal for steps including steel centering,

plywood/steel formwork, compacting, roughening them if special finish

is to be provided, finishing uneven and honeycombed surface and

curing etc. complete. The Cement Mortar 1:3 plaster is considered for

rendering uneven and honeycombed surface, only. Newly laid

concrete shall be covered by gunny bag, plastic, tarpaulin etc.

(Wooden centering will not be allowed.),with fully automatic micro

processor based PLC with SCADA enabled reversible Drum Type

mixer ... With natural sand.

4737.04 Rupees Four

Thousand Seven

Hundred Thirty

Seven and Three

Paise

Cubic Meter 27220.83 24.04 Bd.E.2 Page

No. 288 and

B.7 Page No

38

___

5 22.09 Providing and laying in situ cement concrete M20 of trap / granite

/quartzite/ gneiss metal for R.C.C. work in foundations like raft, strip

foundations, grillage and footings of R.C.C. columns and steel

stanchions etc. including bailing out water, formwork, cover blocks

compaction and curing roughening the surface if special finish is to be

provided (Excluding reinforcement and structural steel) etc. etc.

complete, With fully automatic micro processor based PLC with SCADA

enabled reversible drum type concrete mixer . With natural sand.

5494.09 Rupees Five

Thousand Four

Hundred Ninety

Four and Eight

Paise

Cubic Meter 121358.94 25.01 Bd.F.3 Page

No. 298 and

B.7, Page

No.38

___

6 7.59 Providing and casting in situ cement concrete M20 of trap / granite

/quartzite/ gneiss metal for R.C.C. columns as per detailed designs

and drawing or as directed including centering, formwork, cover

blocks compaction finishing the formed surfaces with cement mortar

1:3 of sufficient minimum thickness to give a smooth and even surface

or roughening if special finish is to be provided and curing etc.

complete. (Excluding reinforcement and structural steel).With fully

automatic micro processor based PLC with SCADA enabled reversible

drum type concrete mixer With Natural sand.

8020.39 Rupees Eight

Thousand

Twenty and

Thirty Eight Paise

Cubic Meter 60846.68 25.21 Bd.F.5 Page

No. 300 and

B.7,

Page.No. 38

___

7 18.82 Providing & casting in situ cement concrete M20 of trap / granite

/quartzite/ gneiss metal for R.C.C. beams and lintels as per detailed

designs & drawings or as directed including centering, formwork,

cover blocks compaction & roughening the surface if special finish is to

be provided & curing etc. complete. (Excluding reinforcement and

structural steel). with fully automatic micro processor based PLC with

SCADA enabled concrete batch mix plant (pan mixer).... With natural

sand.

8776.39 Rupees Eight

Thousand Seven

Hundred

Seventy Six and

Thirty Eight Paise

Cubic Meter 165215.14 25.50 Bd.F.6 Page

No. 300 and

B.7, Page

No.38

___

Contractor APMC Rahata 115

8 11.51 Providing and casting in situ cement concrete M20 of trap/ granite /

quartzite/ gneiss metal for R.C.C. slabs and landings canopy as per

detailed designs and drawings including centering, formwork, cover

blocks compaction finishing the formed surfaces with cement mortar

1:3 of sufficient minimum thickness to give a smooth and even surface

or roughening if special finish is to be provided and curing etc.

complete, (Excluding reinforcement and structural steel).With fully

automatic micro processor based PLC with SCADA enabled reversible

drum type concrete mixer With natural sand.

8996.89 Rupees Eight

Thousand Nine

Hundred Ninety

Six and Eighty

Eight Paise

Cubic Meter 103513.11 25.60 Bd.F.8 Page

No. 302 and

B.7, Page

No.38

___

9 1.01 Providing & casting in situ cement concrete M20 of trap/ granite/

quartzite/ gneiss metal for R.C.C. chajja as per detailed design &

drawings including centering, formwork, cover blocks compacting ,

curing , finishing & rougheningthe surface if special finish is to be

provided & curing complete. (Excluding reinforcement and structural

steel).with fully automatic micro processor based PLC with SCADA

enabled concrete batch mix plant (pan mixer).... With Crushed sand.

10062.64 Rupees Ten

Thousand Sixty

Two and Sixty

Three Paise

Cubic Meter 10188.42 26.06 Bd.F.9 Page

No. 303 and

B.7, Page

No.38

___

10 0.11 Providing and casting in situ cement concrete in M20 of trap/ granite/

quartzite/ gneiss metal for R.C.C. pardi of required thickness including

centering, formwork, cover blocks compacting , curing , finishing &

roughening them if special finish is to be provided and curing

complete. (Excluding reinforcement and structural steel). With fully

automatic micro processor based PLC with SCADA enabled reversible

drum type concrete mixer. with reversible Drum Type mixer with

SCADA With natural sand.

9905.14 Rupees Nine

Thousand Nine

Hundred Five

and Thirteen

Paise

Cubic Meter 1069.76 26.13 Bd.F.11

Page No.

304 and B.7,

Page No. 38

___

11 1.63 Providing and casting in situ cement concrete in M20 of trap/ granite/

quartzite/ gneiss metal for R.C.C.coping to plinth or parapet and sill

of doors and windows moulded as per detailed drawings or

chamfered as approved by the Engineer including centering,

formwork, cover blocks compacting , curing , finishing & roughening

them if special finish is to be provided and curing complete. (Excluding

reinforcement and structural steel).With fully automatic micro processor

based PLC with SCADA enabled reversible drum type concrete mixer

With natural sand.

6492.64 Rupees Six

Thousand Four

Hundred Ninety

Two and Sixty

Three Paise

Cubic Meter 10594.14 26.21 Bd. F. 12

Page No.

304 & B7,

Pg 38

___

12 5.20 Providing and fixing in position TMT / HYSD steel bars reinforcement

of various diameters for R.C.C. pile caps, footings, foundations, slabs,

beams and columns, canopies, staircases, newels, chajjas, lintels,

pardies, coping, fins, arches etc. as per detailed design and drawings

and schedules including cutting, bending, hooking the bars, binding

with wires or tack welding and supporting as required completed.

53193.00 Rupees Fifty

Three Thousand

One Hundred

Ninety Three

Only

Metric Tonne 276432.77 26.35 Bd.F.17,

Page No.

306

___

Contractor APMC Rahata 116

13 50.00 Filling in plinth and floors with approved excavated material in 15cm.

to 20cm. layers including watering and compacting etc. complete.

57.75 Rupees Fifty

Seven and

Seventy Five

Paise

Cubic Meter 2887.50 21.36 Bd.A.10

Page No.

262

___

14 40.90 Filling in plinth and floors with contractors material/brought from

outside and approved by Engineer incharge in layers of 15cm. to

20cm. including watering and compaction etc. complete.

278.25 Rupees Two

Hundred

Seventy Eight

and Twenty Five

Paise

Cubic Meter 11380.88 21.37 Bd.A.11

Page No.

263

___

15 13.22 Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15

cm to 20 cm thick including hand packing and compacting etc.

complete.

666.86 Rupees Six

Hundred Sixty

Six and Eighty

Five Paise

Cubic Meter 8813.61 21.38 Bd.A.12

Page No.

264

___

16 86.42 Providing preconstructional antitermite treatment as per I.S. 6313

(PartII) by treating the bottom surface and sides of excavation at the

rate of 5 litres of emulsion concentrate of 0.5 percent of clorophyrifos

per square meter of surface area covering 10 years guarantee on

bond paper.

52.50 Rupees Fifty Two

and Fifty Paise

Cubic Meter 4537.18 21.22 ___ As directed

by Engineer

in charge.

17 14.82 Providing uncoursed rubble masonry of trap / granite / quartzite /

gneiss stones in cement mortar 1:6 in foundation and plinth of inner

walls / in plinth of external walls including bailing out water manually

, striking joints on un exposed faces and watering etc.complete.

3281.39 Rupees Three

Thousand Two

Hundred Eighty

One and Thirty

Eight Paise

Cubic Meter 48640.04 28.01 Bd.H.1 Page

No. 329

___

18 31.16 Providing second class Burnt Brick masonry with conventional/ I.S. type

bricks in cement mortar 1:6 in foundations and plinth of inner walls/ in

plinth external walls including bailing out water manually , striking

joints on unexposed faces, raking out joints on exposed faces and

watering etc. Complete.

5323.40 Rupees Five

Thousand Three

Hundred Twenty

Three and Thirty

Nine Paise

Cubic Meter 165889.11 27.01 Bd.G. 1

Page No.

313

___

19 22.87 Providing second class Burnt Brick masonry with conventional/ I.S. type

bricks in cement mortar 1:6 in superstructure including striking joints,

raking out joints, watering and scaffolding etc. Complete

5344.40 Rupees Five

Thousand Three

Hundred Forty

Four and Thirty

Nine Paise

Cubic Meter 122247.42 27.05 Bd.G.5 Page

No. 315

___

20 51.01 Providing second class Burnt Brick masonry with conventional/ I.S. type

bricks in cement mortar 1:4 in half brick thick wall including mild steel

longitudinal reinforcement of 2 bars of 6 mm diameter / 2 hoop iron

strips 25 mm X 1.6 mm placed at every third course, properly bent

and bonded at ends scaffolding, racking out joints and watering etc.

complete.

708.59 Rupees Seven

Hundred Eight

and Fifty Eight

Paise

Square Meter 36146.39 27.06 Bd.G.7 Page

No. 316

___

Contractor APMC Rahata 117

21 4.62 Providing second class Burnt Brick masonry with conventional / I.S.

type bricks in cement mortar 1:4 including scaffolding, racking out

joints and watering etc. in pillar of rectangular shapes as shown in the

drawings or as directed complete.

5396.90 Rupees Five

Thousand Three

Hundred Ninety

Six and Eighty

Nine Paise

Cubic Meter 24934.96 27.10 Bd.G.10 (a)

Page No.

318

___

22 69.11 Providing internal cement plaster 6 mm thick in a single coat in cement

mortar 1:4 without neeru finish to concrete surface in all positions

including scaffolding and curing etc. complete.

79.97 Rupees Seventy

Nine and Ninety

Seven Paise

Square Meter 5527.13 32.01 Bd.L.1 Page

No. 367

___

23 334.60 Providing internal cement plaster 12mm thick in single coat in cement

mortar 1:5 without neeru finish to concrete or brick surfaces, in all

positions including scaffolding and curing etc. complete.

120.28 Rupees One

Hundred Twenty

and Twenty

Eight Paise

Square Meter 40245.30 32.03 Bd. L.2 Page

No. 368

___

24 69.11 Providing neeru finish to plastered surfaces in all positions including

scaffolding and curing etc. complete. Ceiling

26.25 Rupees Twenty

Six and Twenty

Five Paise

Square Meter 1814.26 32.15 Bd. L.10,

Page

No.370

___

25 182.29 Providing neeru finish to plastered surfaces in all positions including

scaffolding and curing etc. complete. Wall

26.25 Rupees Twenty

Six and Twenty

Five Paise

Square Meter 4785.20 32.15 Bd. L.10,

Page

No.370

___

26 459.17 Providing sand faced plaster externally in cement mortar using

approved screened sand, in all positions including base coat of 15 mm

thick in cement mortar 1:4 using waterproofing compound at 1 kg per

cement bag curing the same for not less than 2 days and keeping the

surface of the base coat rough to receive the sand faced treatment 6

to 8 mm thick in cement mortar 1:4 finishing the surface by taking out

grains and curing for fourteen days scaffolding etc.complete.

429.86 Rupees Four

Hundred Twenty

Nine and Eighty

Five Paise

Square Meter 197377.30 32.11 Bd.L.7 Page

No. 369

___

27 54.50 Providing fine cement finish 1.5 mm thick over green plaster surface

including scaffolding curing etc. complete.

57.75 Rupees Fifty

Seven and

Seventy Five

Paise

Square Meter 3147.38 32.21 ---- As directed

by Engineer

in charge.

28 10.35 Providing patti/ band 100mm wide on plastered surface 12 mm to 15

mm thick in C.M. 1:3 line and level including neat finishing scaffolding

curing etc. complete.

26.25 Rupees Twenty

Six and Twenty

Five Paise

Running Meter 271.69 32.24 ---- As directed

by Engineer

in charge.

29 18.70 Labour charges for providing groove in external plaster having width

and spaced as directed by engineer incharge etc. complete.

26.25 Rupees Twenty

Six and Twenty

Five Paise

Running Meter 490.88 32.22 ---- As directed

by Engineer

in charge.

Contractor APMC Rahata 118

30 26.25 Providing and fixing chicken mesh of 22 gauge, with about 30 cm.

width at the junction of R.C.C members and brick work, of approved

quality including fixing mesh in position by necessary drilling in

concrete /B.B.masonry and or tying by binding wire etc. complete.

94.50 Rupees Ninety

Four and Fifty

Paise

Square Meter 2480.63 32.26 ---- As directed

by Engineer

in charge.

31 251.41 Providing and applying priming coat on concrete/ masonary/

Asbestos Cement plastered surfaces including scaffolding if necessary,

preparing the surface by thoroughly cleaning oil, grease, dirt and

other foreign matter and sand papering as required etc. complete.

18.90 Rupees Eighteen

and Ninety

Paise

Square Meter 4751.61 35.21 ---- As directed

by Engineer

in charge.

32 251.41 Providing & applying washable oilbound distemper of approved

colour and shade to old & new surfaces in two coats including

scaffolding, preparing the surfaces. (excluding the primer coat.) etc.

complete.

36.75 Rupees Thirty

Six and Seventy

Five Paise

Square Meter 9239.24 36.11 Bd.P.5 Page

No. 413

___

33 459.17 Providing and applying two coats of water proof cement paint of

approved manufacture and of approved colour to old plastered

surfaces including scaffolding if necessary, cleaning and preparing the

surface, watering for two days etc. complete.

53.55 Rupees Fifty

Three and Fifty

Five Paise

Square Meter 24588.40 35.14 ---- As directed

by Engineer

in charge.

34 97.65 Providing and fixing M40 grade thick vibrated pull cast or similar

type concrete frame with chamfer conforming to I.S. 65241983 having

6 mm dia. bars 3 Nos. And stirrups @250 mm c/c and fixing in wall

with 6 Nos of hold fast of 12 mm dia bars 500 mm long including

primer and oil painting etc, complete) frame size 60 mm x 100 mm .

690.90 Rupees Six

Hundred Ninety

and Ninety

Paise

Running Meter 67466.39 39.56 ---- As directed

by Engineer

in charge.

35 6.30 Providing and fixing solid core flush door shutter in single leaf 32 mm

thick decorative type of exterior grade as per detailed drawings

approved face veneers 3 mm thick on both faces or as directed, all

necessary beads, mouldings and lipping, wrought iron hold fasts,

chromium plated fixtures and fastenings, with brass mortise lock,

chromium plated handles on both sides, and finishing with French Polish

etc. complete.

2449.65 Rupees Two

Thousand Four

Hundred Forty

Nine and Sixty

Five Paise

Square Meter 15432.80 39.09 Bd-T34,

Page No.

499

___

Contractor APMC Rahata 119

36 25.20 Providing and fixing 30mm thick RAJSHRI or equivalent BRAND

FACTORY MADE SOLID PANEL PVC INTERNAL DOOR SHUTTER

consisting of frame made out of M.S. tubes of 19 gauge thickness and

size of 40mm x 20mm for stiles ,top, lock & bottom rails. M.S. frame

shall have a coat of steel primers of approved make and

manufacture. M.S. frame shall be covered with 5mm thick heat molded

Rajshri PVC C channel of size 30 x 100mm forming stiles, and 5mm

thick, 125mm wide PVC sheets for top rail, lock rail & bottom rail on

either side, and 15mm (5mm x 3) thick, 20mm wide cross PVC sheet as

gap insert for top rail & bottom rail. Paneling of 10 mm thick prelam

PVC sheet to be fitted in the M.S. frame welded / sealed to the stiles

& rails with 30mm wide x 5mm thick PVC sheet beading on either side,

and joined together with solvent cement adhesive etc. An additional

5mm thick PVC strip of 20mm width is to be stuck on the interior side

of the C Channel using PVC solvent cement adhesive. including stainless

steel fixtures and fastening Complete as per direction of

Engineerincharge, manufacturer's specification & drawing.

5106.15 Rupees Five

Thousand One

Hundred Six and

Fifteen Paise

Square Meter 128674.98 39.81 ---- As directed

by Engineer

in charge.

37 2.88 Providing and fixing in position (as per 1868 / 1982) Aluminium

sliding window of three tracks with rectangular pipe 95 x 38.10 x

0.90 mm at weight 0.637 kg/Rmt. with window frame bottom track

section 92 x 31.75 x 1.30 mm at weight 1.070 kg/Rmt.. Top and side

track section 92 x 31.75 x 1.30 mm at weight 0.933 kg/Rmt. The

shutter should be of bearing bottom 40 x 18 x 1.25 mm at weight

0.417 kg/Rmt. Inter locking section 40 x 18 x 1.10 mm at weight

0.469 kg/Rmt. and handle and top section 40 x 18 x 1.25 mm at

weight o.417 kg/Rmt. As per detailed drawings and as directed by

Engineerincharge with all necessary Aluminium sections fixtures and

fastenings such as roller bearing in nylon casting and self locking catch

fitted in vertical section of shutter including 5 mm thick plain glass and

aluminium mosquito net shutter with stainless steel jail with all required

screws and nuts etc, complete. With powder coating without box

4016.25 Rupees Four

Thousand

Sixteen and

Twenty Five

Paise

Square Meter 11566.80 39.44 ---- As directed

by Engineer

in charge.

38 6.48 Providing and fixing steel frame door of angle 40 x 40 x 5 mm with

16 mm dia. mild steel bars horizontally at 10cm c/c for ventilator

portion including iron hold fast for the fixing shutters including welding,

painting, finishing etc. complete.

2894.85 Rupees Two

Thousand Eight

Hundred Ninety

Four and Eighty

Five Paise

Square Meter 18758.63 39.36 ---- As directed

by Engineer

in charge.

Contractor APMC Rahata 120

39 2.88 Providing and fixing mild steel grill work for windows, ventilators, etc.

15 kg/sqm as per drawing including fixtures necessary welding and

painting with one coat of anticorrosive paint and two coats of oil

painting complete.

1090.95 Rupees One

Thousand Ninety

and Ninety Five

Paise

Square Meter 3141.94 40.02 Bd.U.1 Page

No. 537

___

40 36.89 Providing and laying Polished Kota stone flooring With HandCut

Polished Kota Stones 25mm to 30mm thick and required width in

plain/diamond pattern on bed of 1:6 Cement mortar including cement

float, filling joints with neat cement slurry, curing, cleaning and Mirror

Polishing etc. complete NoteWater absorption for item No,19 should

not exceed 0.05%.( Item to be used with prior permission of

Superintending Engineer )

1031.52 Rupees One

Thousand Thirty

One and Fifty

One Paise

Square Meter 38051.41 33.75 Bd. M3

page No.

380

___

41 36.89 Providing Mirror polishing to Kota Stone including using all necessary

stones and equipments cleaning, washing etc. complete. For Flooring

236.25 Rupees Two

Hundred Thirty

Six and Twenty

Five Paise

Square Meter 8714.97 33.28 ---- As directed

by Engineer

in charge.

42 7.52 Providing and laying Polished Kota stone Skirting With HandCut

Polished Kota Stones 25mm to 30mm thick and required width in

plain/diamond pattern on bed of 1:6 Cement mortar including cement

float, filling joints with neat cement slurry, curing, cleaning and Mirror

Polishing etc. complete NoteWater absorption for item No,19 should

not exceed 0.05%.( Item to be used with prior permission of

Superintending Engineer )

1031.52 Rupees One

Thousand Thirty

One and Fifty

One Paise

Square Meter 7760.11 33.75 Bd. M3

page No.

380

___

43 5.64 Providing and laying machine cut machine polished machine cut Kota

stone slabs 20 to 25 mm thick for treads and risers of steps and

staircases, with rounded nosing for the treads on a bed of 1:4 cement

mortar including cement float, filling joints with neat cement slurry,

curing, polishing and cleaning etc. complete.

1005.27 Rupees One

Thousand Five

and Twenty Six

Paise

Square Meter 5669.71 33.18 Bd.M.22

Page No.

390

___

44 13.32 Providing sills of polished Kota stone 25 mm to 30mm thick, on a bed

of 1:4 cement mortar including cement float, filling joints with slurry,

curing polishing and cleaning etc. complete.

921.27 Rupees Nine

Hundred Twenty

One and Twenty

Six Paise

Square Meter 12271.29 33.19 Bd.M.29

Page No.

391

___

45 17.28 Providing and laying ceramic tiles of RAK/ Kajaria/ Nitco/ Asian or

equivalent make having size 30 cm x 30 cm confirming

I.S.15622/2006 (group D IIA) and 7 to 8 mm thick for flooring in

required position laid on a bed of 1:4 cement mortar including cement

float, filling joint with white/colour cement slurry cleaning curing etc.

complete.

927.24 Rupees Nine

Hundred Twenty

Seven and

Twenty Four

Paise

Square Meter 16022.76 33.24 Bd.M.12

Page No.

385.

___

Contractor APMC Rahata 121

46 152.30 Providing and laying ceramic tiles of RAK/ Kajaria / Nitco /Asian or

equivalent make having size 30 cm. x 45 cm. for dado and skirting in

required position with readymade adhesive mortar of approved

quality on plaster of 1:2 cement mortar including joint filling with

white/ colour cement slurry cleaning curing etc. complete.

1088.07 Rupees One

Thousand Eighty

Eight and Seven

Paise

Square Meter 165716.22 33.26 Bd.M.13

Page No.

386.

___

47 Providing and fixing on walls/ ceiling/ floor ____ mm dia.

CPVC pipe with necessary fittings, remaking good the

demolished portion etc. complete.

0.00 No Rupees Only ---- ---- ----

a 60.00 Providing and fixing on walls/ ceiling/ floor 15 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

176.40 Rupees One

Hundred

Seventy Six and

Forty Paise

Running Meter 10584.00 42.55 BD.V 5 page

551 &

As directed

by Engineer

in charge.

b 10.00 Providing and fixing on walls/ ceiling/ floor 20 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

204.75 Rupees Two

Hundred Four

and Seventy

Five Paise

Running Meter 2047.50 42.56 BD.V 5 page

551 &

As directed

by Engineer

in charge.

c 120.00 Providing and fixing on walls/ ceiling/ floor 25 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

248.85 Rupees Two

Hundred Forty

Eight and Eighty

Five Paise

Running Meter 29862.00 42.57 BD.V 5 page

551 &

As directed

by Engineer

in charge.

d 10.00 Providing and fixing on walls/ ceiling/ floor 32 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

312.90 Rupees Three

Hundred Twelve

and Ninety

Paise

Running Meter 3129.00 42.58 BD.V 5 page

551 &

As directed

by Engineer

in charge.

e 6.00 Providing and fixing on walls/ ceiling/ floor 40 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

376.95 Rupees Three

Hundred

Seventy Six and

Ninety Five

Paise

Running Meter 2261.70 42.59 BD.V 5 page

551 &

As directed

by Engineer

in charge.

f 10.00 Providing and fixing on walls/ ceiling/ floor 50 mm dia. CPVC pipe

with necessary fittings, remaking good the demolished portion etc.

complete.

549.15 Rupees Five

Hundred Forty

Nine and Fifteen

Paise

Running Meter 5491.50 42.60 BD.V 5 page

551 &

As directed

by Engineer

in charge.

48 Providing and fixing screw down ___mm dia. wheeled stop tap

of brass including necessary sockets/union nut complete

No Rupees Only 0.00 ---- ___

a 1.00 Providing and fixing screw down 15 mm dia. wheeled stop tap of

brass including necessary sockets/union nut complete

231.00 Rupees Two

Hundred Thirty

One Only

Numbers 231.00 41.43 Bd.V.9 Page

No. 555

___

Contractor APMC Rahata 122

b 3.00 Providing and fixing screw down 25 mm dia. wheeled stop tap of

brass including necessary sockets/union nut complete

417.90 Rupees Four

Hundred

Seventeen and

Ninety Paise

Numbers 1253.70 41.45 Bd.V.9 Page

No. 555

___

c 1.00 Providing and fixing screw down 40 mm dia. wheeled stop tap of

brass including necessary sockets/union nut complete

644.70 Rupees Six

Hundred Forty

Four and

Seventy Paise

Numbers 644.70 41.47 Bd.V.9 Page

No. 555

___

d 1.00 Providing and fixing screw down 50 mm dia. wheeled stop tap of

brass including necessary sockets/union nut complete

704.55 Rupees Seven

Hundred Four

and Fifty Five

Paise

Numbers 704.55 41.48 Bd.V.9 Page

No. 555

___

49 18.00 Providing and fixing 15 mm dia. screw down bib/ stop tap of brass

including necessary socket union nut complete.

211.05 Rupees Two

Hundred Eleven

and Five Paise

Numbers 3798.90 41.40 Bd.V.8 Page

No. 554

___

50 2.00 Providing and fixing 450mm x 550mm size superior type Belgium

mirror with 16mm dia. nickel plated towel rod etc. complete.

420.00 Rupees Four

Hundred Twenty

Only

Numbers 840.00 42.20 ---- As directed

by Engineer

in charge.

51 2.00 Providing and fixing European type white glazed earthenware water

closet pan with UPVC seat and lid with chromium plated brass hinges

and rubber buffers including UPVC and vent pipe up to the outside

face of wall 10 litre enameled low level flushing cistern with fittings

pipe stop tap brackets for fixing cistern 32 mm dia. UPVC flush pipe

with fittings and clamps ,20 mm dia.UPVC overflow pipe ,mosquito

proof couplings G.I. chain and pulley,with water Jet and fitting

including cutting and making good to the walls and floors testing etc.

complete. (prior approval of sample and brand by Ex. Engineer is

necessary before use)

3323.82 Rupees Three

Thousand Three

Hundred Twenty

Three and Eighty

Two Paise

Numbers 6647.64 43.19 ---- As directed

by Engineer

in charge.

52 14.00 Providing and fixing Orissa type white glazed earthenware 575 mm

water closet pan including S trap with earthenware foot rests, cast iron

soil and vent pipe upto outside face of the wall 1:2:4 brick bat lime

concrete bedding without flushing tank and its accessories etc.

complete.

2728.47 Rupees Two

Thousand Seven

Hundred Twenty

Eight and Forty

Seven Paise

Numbers 38198.60 42.30 ---- As directed

by Engineer

in charge.

53 4.00 Providing and fixing white glazed earthenware lipped flat

back/corner type Urinal with PVC 5 liters flushing cistern with fittings,

inlet pipe with stop tap, brackets for fixing the cistern, 32 mm

diameter P.V.C. flush pipe with fitting including lead soil pipe, lead

trap & soil pipe connection up to the outside face of wall.

2310.00 Rupees Two

Thousand Three

Hundred Ten

Only

Numbers 9240.00 41.60 Bd.V.26

Page No.

564

----

Contractor APMC Rahata 123

54 2.00 Providing and fixing white glazed earthenware Wash Hand Basin of

55cm. x 40 cm. size including cold water pillar tap/cold and hot water

pillar tap brackets, rubber plugs and brass chain, stop tap and

necessary pipe connections including P.V.C. waste pipe and trap up to

the outside face of the wall.

2260.65 Rupees Two

Thousand Two

Hundred Sixty

and Sixty Five

Paise

Numbers 4521.30 41.63 Bd.V.30

Page No.

565

----

55 11.00 Providing and fixing 10 cm PVC nahani trap with grating etc.

complete.

331.80 Rupees Three

Hundred Thirty

One and Eighty

Paise

Numbers 3649.80 42.67 BD.V 32 A

page 551

As directed

by Engineer

in charge.

56 2.00 Providing and fixing 15cm x 10cm salt glazed stoneware gully trap in

cement concrete 1:4:8 outside the building including cast iron grating

in the sink, connecting glazed stoneware pipe, brick masonry chamber

with cast iron lid and cast iron grating for the gully trap.

813.75 Rupees Eight

Hundred

Thirteen and

Seventy Five

Paise

Numbers 1627.50 42.02 Bd.V.38,

Page No.

572

----

57 Providing and fixing _____mm diaMetre UPVC soil / vent / waste

SWR pipe of required diaMetre conforming to IS13592:1992, and IS-

4985:2000 to withstand continuous internal hydraulic pressure of 4 kg

/ cm2 including necessary fixtures and fittings, such as bends, tees,

single junctions, double junctions and joining with rubber rings and

lubricants, on wall by means of clips or in ground including necessary

Excavation, laying refilling, trench testing etc. complete. (Prior

approval of sample and

brand by Ex. Engineer is necessary before use)

0.00 No Rupees Only ---- ---- ----

20.00 Providing and fixing 75mm diaMetre UPVC soil / vent / waste SWR

pipe of required diaMetre conforming to IS13592:1992, and IS-

4985:2000 to withstand continuous internal hydraulic pressure of 4 kg

/ cm2 including necessary fixtures and fittings, such as bends, tees,

single junctions, double junctions and joining with rubber rings and

lubricants, on wall by means of clips or in ground including necessary

Excavation, laying refilling, trench testing etc. complete. (Prior

approval of sample and

brand by Ex. Engineer is necessary before use)

341.25 Rupees Three

Hundred Forty

One and Twenty

Five Paise

Running Meter 6825.00 134/82A ---- As directed

by Engineer

in charge.

51.00 Providing and fixing 110mm diaMetre UPVC soil / vent / waste SWR

pipe of required diaMetre conforming to IS13592:1992, and IS-

4985:2000 to withstand continuous internal hydraulic pressure of 4 kg

/ cm2 including necessary fixtures and fittings, such as bends, tees,

single junctions, double junctions and joining with rubber rings and

lubricants, on wall by means of clips or in ground including necessary

Excavation, laying refilling, trench testing etc. complete. (Prior

approval of sample and

brand by Ex. Engineer is necessary before use)

425.25 Rupees Four

Hundred Twenty

Five and Twenty

Five Paise

Running Meter 21687.75 134/82B ---- As directed

by Engineer

in charge.

Contractor APMC Rahata 124

6.00 Providing and fixing 160mm diaMetre UPVC soil / vent / waste SWR

pipe of required diaMetre conforming to IS13592:1992, and IS-

4985:2000 to withstand continuous internal hydraulic pressure of 4 kg

/ cm2 including necessary fixtures and fittings, such as bends, tees,

single junctions, double junctions and joining with rubber rings and

lubricants, on wall by means of clips or in ground including necessary

Excavation, laying refilling, trench testing etc. complete. (Prior

approval of sample and

brand by Ex. Engineer is necessary before use)

624.75 Rupees Six

Hundred Twenty

Four and

Seventy Five

Paise

Running Meter 3748.50 134/82C ---- As directed

by Engineer

in charge.

58 6000.00 Providing and fixing H.D.P container Syntex or alike one piece

moulded water tank made out of high density polythyler and built

corrugated inclusive of delivery up to estination hoisting and fixing of

accessories such as inlet,outlet overflow pipe inclusive of all tanks

capacity between 200 to 1000 liters

7.46 Rupees Seven

and Forty Five

Paise

Liters 44730.00 42.53 ---- As directed

by Engineer

in charge.

59 2.00 Providing soak pit of size 120cm x 120cm x 120cm including

excavating and filling with brickbats.

620.55 Rupees Six

Hundred Twenty

and Fifty Five

Paise

Numbers 1241.10 42.19 Bd.V.46,

Page No.

576

----

60 8.00 Providing & constructing Brick Masonry Inspection Chamber 60cm x

45cm x 90cm including 1:4:8 cement concrete foundation 1:2:4 cement

concrete channels half round G.S.W. pipes, Brick Masonry, plastering

from inside and with frame fixed in cement concrete etc. complete with

R.C.C. Cover.

3924.09 Rupees Three

Thousand Nine

Hundred Twenty

Four and Nine

Paise

Numbers 31392.72 42.12 Bd.V.43,

Page No.

574

----

61 1.00 Providing & constructing Brick Masonry Inspection Chamber 90cm x

45cm x 90cm including 1:4:8 cement concrete foundation 1:2:4 cement

concrete channels half round G.S.W.pipes, Brick Masonry, plastering

from inside and with frame fixed in cement concrete with R.C.C. Cover.

5124.85 Rupees Five

Thousand One

Hundred Twenty

Four and Eighty

Five Paise

Numbers 5124.85 42.13 Bd.V.43,

Page No.

574

----

62 4.50 Providing and fixing 45 cm wide mild steel ladder of 40mm x 6 mm

mild steel flat stringers and steps of 18 mm dia. mild steel bar for

water tank including fixing it in (1:2:4) M15 cement concrete block

60cm x 30cm x 30cm & painting the ladder complete.(Anti Corossive

Paint)

665.70 Rupees Six

Hundred Sixty

Five and

Seventy Paise

Running Meter 2995.65 41.56 Bd. V. 19

Page No.

559

----

63 25.00 Providing and laying concrete pipes of I.S.NP. class of 300mm

diaMetre in proper line, level and slope including necessary collars,

excavation, laying, fixing with collars in cement mortar 1:1 and

refilling the trench complete. Spec. No.: Bd.V.41, Page No. 573

856.80 Rupees Eight

Hundred Fifty

Six and Eighty

Paise

Running Meter 21420.00 134/83D ---- As directed

by Engineer

in charge.

Contractor APMC Rahata 125

64 86.42 Providing cement based water proofing treatment to terraces (Indian

water proofing or alike) with brick bats laid in required slope to drain

the water for any span after cleaning the base surface. Applying a

coat of cement slurry admixed with approved water proofing

compound and laying the brick bats on bottom layer in C.M.1:5

admixed with approved water proofing compound filling up to half

depth of brick bats, curing this layer for 3 days, applying cement

slurry over this layer joints of brick bats with C.M.1:3 admixed with

approved water proofing compound and finally top finishing with

average 20 mm. thick layers of same mortar added with jute fiber at

1 Kg per bag including finishing the surface smooth with cement slurry

admixed with approved water proofing compound. Marking finished

surface with false squares of 300mm x 300 mm. making the junctions

at the parapet rounded and tapered top for required height, with

drip mould at the junction of plaster and parapet and curing and

covering 10 years Guarantee

against leakproofness on Court fee stamp paper of Rs. 500/including

ponding test etc. complete.

613.91 Rupees Six

Hundred

Thirteen and

Ninety Paise

Running Meter 53055.47 31.04 ---- As directed

by Engineer

in charge.

65 3.38 Providing and fixing machine cut mirror polished 18 mm to 20 mm

thick telephone black granite / Amba White / Cat bary brown / RBI

red / Ocean Brown granite stone partition with rounding the edges

etc. complete . Both side polish

3512.25 Rupees Three

Thousand Five

Hundred Twelve

and Twenty Five

Paise

Square Meter 11853.84 33.36 Bd.M.35

B/Page

No.393

----

66 7.92 Providing and fixing mild steel grill gate with angle iron frame 65 mm

x 65 mm x 10 mm with iron bars at 150mm.C/C and diagonal flats as

per the detailed drawing including hinges, pivot blocks locking

arrangement, welding riveting and oil painting of three coats of

approved shade. Weight of gate 35 Kg/smt.

1878.45 Rupees One

Thousand Eight

Hundred

Seventy Eight

and Forty Five

Paise

Square Meter 14877.32 44.10 Bd.W.6

Page No.

585

----

67 14.80 Providing and fixing heavy duty inter locking concrete Coloured

paving blocks of 80 mm thickness of having a strength of 300

kg/Sq.cm. of approved quality and shape on a bed of crushed sand

of 25 to 30 mm thick including skirting joints and cleaning etc.

complete

711.90 Rupees Seven

Hundred Eleven

and Ninety

Paise

Square Meter 10534.55 33.52 ---- As directed

by Engineer

in charge.

68 181.38 Royalty Charges 141.34 Rupees One

Hundred Forty

One and Thirty

Four Paise

Cubic Meter 25636.04

TOTAL of Civil Work Rs. 2491716.00

Say 2491716.00

Rupees Twenty Four Lac Ninety One Thousand Seven Hundred Sixteen Only

Contractor APMC Rahata 126

IMPORTANT NOTE : THE ABOVE RATES INCLUDE ALL TYPES OF TAXES LIKE GST, SALES TAX, OCTROI, ROYALTY ETC.

Contractor APMC Rahata 127

GROUND FLOOR77.40 SQ.M.

DATE

SCALE

DRN - BY

--PROJECT TITLE :13/03/2017

N

PROPOSED CONSTRUCTION OF TOILET BLOCKAT LONI, FOR RAHATA AGRICULTURE PRODUCEMARKET COMITTEE,SUBMARKET LONI. DIST- AHMEDNAGAR .

BUILT UP AREA

JABEDUL

Architect

BHUTADACONSULTANTS

Architect RCC consultant Interior Designer

Office: Niwara Housing Society, Morage WastiShrirampur - 413 709, Ph.no. 210227

email: [email protected]

+ 4.65 MPARAPET LVL.

+ 4.05 MTERRACE F.F.L.

+ 0.90 M

+ 0.00 MGROUND LVL.

FRONT ELEVATION

PLINTH L.V.L

+ 3.30 MLINTEL LVL.

+ 0.00 M

+ 0.45 M

+ 0.45 M

+ 0.45 M

1.20

8.35

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

1.50

M W

IDE

PASS

AG

E

1.50

M W

IDE

PASS

AG

E

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

W.C1.20 x 0.90 M

UP

+ 0.90 M + 0.90 M

± 0.00 M

8.01

LADIESTOILET

GENTSTOILET

DUCT

LADIESTOILET

GENTSTOILET

UPUP

+ 0.90 M + 0.90 M

± 0.00 M

10.35

1.80

1.20

UP

1.204.5

04.5

0

19.35

10.75

GROUND FLOOR77.40 SQ.M.

DATE

SCALE

DRN - BY

--PROJECT TITLE :13/03/2017

N

PROPOSED CONSTRUCTION OF TOILET BLOCKAT LONI, FOR RAHATA AGRICULTURE PRODUCEMARKET COMITTEE,SUBMARKET LONI. DIST- AHMEDNAGAR .

BUILT UP AREA

JABEDUL

Architect

BHUTADACONSULTANTS

Architect RCC consultant Interior Designer

Office: Niwara Housing Society, Morage WastiShrirampur - 413 709, Ph.no. 210227

email: [email protected]

GROUND FLOOR PLAN