4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
FM and BIM - BSRIA · • Data transfer: direct to FM CAFM systems ... FM and BIM: The EIR and WLC...
Transcript of FM and BIM - BSRIA · • Data transfer: direct to FM CAFM systems ... FM and BIM: The EIR and WLC...
FM and BIM
The Employer`s Information Requirements (EIR) and Whole Life Cycle (WLC) perspective
Institute of Facility Management Simon Ashworth
Information Management in FM
Simon Ashworth [email protected]
+41 79 138 6852
5th February 2016
FM and BIM: The EIR and WLC Perspective 2 Simon Ashworth
Simon Ashworth Experience: Practice management roles: Qualifications:
20+ years in FM FM, PM, Service support, transition MSc-FM, MEng, BEng-Civil
ZHAW Lecturing Design & construction PhD “FM and BIM”
Defence Academy of the United Kingdom
FM and BIM: The EIR and WLC Perspective 3 Simon Ashworth
Agenda 1. Digital Trends: impact on Real Estate and FM
2. Paradigm Change: in Industry thinking
3. Seeing the Big Picture: the possible savings
4. WLC Perspective: where should our focus be
5. FM and the EIR: defining Information needs
6. BIM Tools: standards and guidelines
7. Future: FM and BIM
8. Take Home Messages
FM and BIM: The EIR and WLC Perspective 4 Simon Ashworth
1. Digital Trends
FM and BIM: The EIR and WLC Perspective 5 Simon Ashworth
Trends: SMART …er buildings
Towler (2015)
FM and BIM: The EIR and WLC Perspective 6 Simon Ashworth
Top megatrend : greatest impact on work towards 2020: • Technological advances (80%).
Top workplace initiative: greatest development potential towards 2020:
• Intelligent buildings (61%). Impact on FM:
• “FM providers will have to conduct systemic design, including employing building information modelling (BIM) techniques”.
• “FM providers should use information from BIM to improve building designs and inputs to their models by analysing how people actually move through and use workspaces”.
Trends: FM - ISS 2020 Vision
Source: NWOW Survey, 2013
FM and BIM: The EIR and WLC Perspective 7 Simon Ashworth
“FM & Clients: Information needs over WLC for BIM process”
Construction: Digital Knowledge Gap: Clients and FM
Government Strategy: Level 3 BIM
i nformation
BIM adoption in the O&M phase is currently less than 10% (Eadie, et al., 2015).
FM and BIM: The EIR and WLC Perspective 8 Simon Ashworth
2. Paradigm Change
FM and BIM: The EIR and WLC Perspective 9 Simon Ashworth
Why a paradigm change in thinking?
Historical Government reports:
• Constructing the Team: (Latham, 1994) waste 25-30%
• Modernising Construction: (Bourn, 2001) 73% projects over price, 70% late
• Accelerating Change: (Egan, 2002) lowest cost not value for money
• Rethinking Construction: (Egan, 2008) failures: committed leadership, customer focus, integrated teams, quality, commitment to people
• Never Waste a Good Crisis: (Wolstenholme, 2009) value is created over WLC
• Exploring procurement in the Construction Industry (CIOB, 2010): still issues with projects budget overrun (94%) and late delivery (93%)
… Improved since 1994 ???
FM and BIM: The EIR and WLC Perspective 10 Simon Ashworth
Traditional FM problems
Acceptance & opening
death valley of knowhow
Co
nst
ruct
ion
Pro
ject
Info
rmat
ion
3D
Gra
ph
ical
N
on
-gra
ph
ical
D
ocu
men
ts
FM In
form
atio
n n
eed
s
Pro
du
cts
Pro
cess
es
Serv
ices
C
ost
s
Construction Use RIBA Stage 0-5 Construction Betriebsvorbereitung
RIBA Stage 7 In Use RIBA Stage 6: Handover and Close out
Asset Information Requirements (AIR)
Employers Information Requirements (EIR)
Organisational Information Requirements (OIR)
Information Needs AIM Optimise Assets
Asset Management Strategy & Policy
FM and BIM: The EIR and WLC Perspective 11 Simon Ashworth
3. Seeing the Big Picture
NBS (2015)
FM and BIM: The EIR and WLC Perspective 12 Simon Ashworth
Why BIM?
FM and BIM: The EIR and WLC Perspective 13 Simon Ashworth
Economic value
What is the value of the EU FM market?
Teichmann (2009)
655 Billion EUR
FM and BIM: The EIR and WLC Perspective 14 Simon Ashworth
FM and BIM: The EIR and WLC Perspective 15 Simon Ashworth
Value to UK economy
204 Billion UK FM Market (Teichmann, 2009) 107 Billion UK Construction Market (HM Gov, 2010) 307 Billion: what if we could make 1-5% efficiency savings?
3-15 billion Euros!!!
FM and BIM: The EIR and WLC Perspective 16 Simon Ashworth
4. WLC perspective
Lao Tzu: “Value lies not in the artefact … but in the use of the space within
FM and BIM: The EIR and WLC Perspective 17 Simon Ashworth
Focus? ….Value for money
Design Process
Economics: A buildings relative costs over 30 years
Ratio of costs
Construction
Maintenance
Operation
1 5 200
FM and BIM: The EIR and WLC Perspective 18 Simon Ashworth
Buildings vs. People
CABE, 2005
People 85%
Buildings 15%
Cost of asset over 30 years
FM and BIM: The EIR and WLC Perspective 19 Simon Ashworth
Early FM Involvement?
ISO 15686-5 (2008)
80% Long term WLC costs - fixed in first 20% early design
FM and BIM: The EIR and WLC Perspective 20 Simon Ashworth
How BIM will help?
MacLeamy Effort Curve HOK (2010)
Design Effort
FM and BIM: The EIR and WLC Perspective 21 Simon Ashworth Neukom W. (2003)
Alignment of Strategy
BIM STRATEGY
FM and BIM: The EIR and WLC Perspective 22 Simon Ashworth
5. BIM Tools (Standards and Guidelines)
FM and BIM: The EIR and WLC Perspective 23 Simon Ashworth
BIM Support framework
BIM Level 2: Components: 1. PAS1192-2 BIM – Construction Phase (EIR) 2. PAS1192-3 BIM – Operational Phase (OIR, AIR) 3. BS1192-4 COBie (AIM, CAFM Tools) 4. PAS1192-5 BIM - Security 5. CIC Protocol BIM - Contracts 6. GSL Government Soft Landings 7. dPoW Digital Plan of Work (RIBA 2013) 8. Uniclass 2015 BIM Classification system
FM and BIM: The EIR and WLC Perspective 24 Simon Ashworth
(PAS 1192-2, 2013)
(AIM)
Asset Information Model
To ensure FM / AM
Operational Efficiency
Start with the end in mind …
WHAT Information is
Needed?
ASSET MANAGEMENT
STRATEGY
ISO 55000? Start
End
CLIENT
BIM STRATEGY
FM and BIM: The EIR and WLC Perspective 25 Simon Ashworth
PAS1192:3 Operation OIR Information needed to run the business AIR Information needed about the assets AIM Information data set for all assets
Operational phase
FM/Client Strategy
FM and BIM: The EIR and WLC Perspective 26 Simon Ashworth
BIM Library & dPoW
BIM Objects: • Standardised for better usability • Defined rule sets and criteria • FM (Valuable data for O&M)
FM and BIM: The EIR and WLC Perspective 27 Simon Ashworth
COBie: Information exchange 3 types of Information: 1. Graphical BIM models 2. PDF Documents 3. Non-graphical (COBie)
BS1192-4 Information exchange Note: non-graphical into CAFM
FM and BIM: The EIR and WLC Perspective 28 Simon Ashworth
Soft landings
• Handover period of care (up to 3 years) • Prove the design meets the users requirements
FM and BIM: The EIR and WLC Perspective 29 Simon Ashworth
BIM Road maps
Data driven: in line with RIBA 2013 stages 0 - 7
FM and BIM: The EIR and WLC Perspective 30 Simon Ashworth
6. FM and the EIR
FM and BIM: The EIR and WLC Perspective 31 Simon Ashworth
How BIM can help?
BIM: allows virtual prototyping
• Early involvement: identify issues with D&C team on design
• Understand: how the asset will work in operation
• Information: define what is needed at handover
Many FM problems due to poor design
FM and BIM: The EIR and WLC Perspective 32 Simon Ashworth
FM Perception of BIM
Only 2 people from approx. 200 confirmed they use EN standards!
BIM and FM Survey
Aim:
Establish a benchmark regarding current perception of BIM and FM in Switzerland
https://www.researchgate.net May 2015
FM and BIM: The EIR and WLC Perspective 33 Simon Ashworth
Time for BIM to have a significant impact on FM:
• 2 – 5 years
Main benefits to FM:
• Increasing operational efficiency: asset maintenance and response times
• Cost savings: Whole Life cycle and FM operations
• Data transfer: direct to FM CAFM systems
• Transition improvement: (operational and information) from build to operation
• Cost estimates: faster and more accurate for tenders and projects
• Visualization tool: for clients and investors
Main FM concerns:
• Data management and knowledge and training with respect to BIM
• Cost of implementation (time and resources)
Survey: Key Findings
FM and BIM: The EIR and WLC Perspective 34 Simon Ashworth
Where do FMs start?
BS8356-1 Briefing for FM Help to define: • FM requirements • Information for the EIR
FM and BIM: The EIR and WLC Perspective 35 Simon Ashworth
EIR: Early development
BIM Task Group
FM and BIM: The EIR and WLC Perspective 36 Simon Ashworth
EIR: BuildingSMART
FM and BIM: The EIR and WLC Perspective 37 Simon Ashworth
EIR: should be client/FM owned
FM and BIM: The EIR and WLC Perspective 38 Simon Ashworth
Defining information
FM and BIM: The EIR and WLC Perspective 39 Simon Ashworth
Helping Clients: BIM Strategy and EIR
UK knowledge transfer to Switzerland
FM and BIM: The EIR and WLC Perspective 40 Simon Ashworth
6. The future of BIM and FM
FM and BIM: The EIR and WLC Perspective 41 Simon Ashworth
Move from BIM level 3 to 4
FM and BIM: The EIR and WLC Perspective 42 Simon Ashworth
Social benefits of BIM and FM
Level 4 BIM
Level 3 BIM
Level 2 BIM
Design Build Operate
Organisational Performance
Multiplied through Portfolio
Social Performance
Multiplied
through Society
20% 3000% 300% 80%
Delivery of Asset
Level 1 BIM
FM and BIM: The EIR and WLC Perspective 43 Simon Ashworth
GLOBAL MARKET:
£400B by 2020 for services related to smart systems for transport, energy, health care, water and waste
REQUIRES:
• Built Environment: smart, networked world
• People: a skilled digitally enabled workforce
• Digital infrastructure: framework for cyber security, regulation, contracts and privacy
• Data: government asset base, supporting new service opportunities and markets
• Technology sharing: across sectors to increase investment, value and collaboration
• Education: programme to develop skills and new ways of working across schools/industry
BIM Level 3: Future Development
Digital Built Britain
FM and BIM: The EIR and WLC Perspective 44 Simon Ashworth
IFM Research
Research topics:
• FM and BIM: EIR
• Swiss National BIM Library
• Scan to BIM workflow
• FM, AR and VR
• Model checking sustainability
FM and BIM: The EIR and WLC Perspective 45 Simon Ashworth
6. Take home messages
FM and BIM: The EIR and WLC Perspective 46 Simon Ashworth
FM & BIM: Take home messages
• BIM is becoming the norm
• BIM strategy must align with Client Asset Management Strategy
• FM and clients need early engagement in BIM process
• FM need to define what they need from the BIM process
• FM should own the EIR in the BIM process
FM and BIM: The EIR and WLC Perspective 47 Simon Ashworth
Questions? & Questionnaire
Please can we have your support in completing our short questionnaire for further research