Transcript of Flow Chart
Executive
Quality Control
Estimating AdminSales
Accounting
(knows to close out job
and do any final billing)
Project Management
Sales
Mix Design/Cost
from Quality
Control
Foreman
Handles Contracts,
review, filing,
distribution, create
subcontracts, etc.
Approve
Reject
Create/WriteJob Review
(with Sales, Executive, Safety,
Quality Control, Foreman,
Project Manager, Admin)
(go over how the job went
(both well and bad), why,
and what to do for
future jobs)
Start
End
Research
Review
Customer Phone Call BrainstormSales
Files documents
in OnBase
Submit job setup
package, distributes
forms as needed
Estimating
Makes sure estimate matches
contract (amt, format, etc.)
Project Management
Review Contract
for errors, fine print,
anything odd, etc.
Creates Documents
for job setup
Admin
(posts schedules on S drive,
also schedules handoff meeting)
Plant (Customer)
Safety
Audit
Safety
Accounting
Sales
Now
everything
depends on
the schedule
Plant (Customer)
Crew
Safety Gear/ISTC training
Staff
Item Sheet
(indicates job scope)
Job Setup package
Job Setup package
Proposal, HCSS Estimate,
Sales Tax Approach form,
mix design costs, notes,
drawings, sales tax
mentioned in proposal,
estimated start/end dates
Accounting
(sales tax approach form,
customer in good status) Tax Forms,
review, filing,
distribution, etc.
Proposal, sales tax
mentioned in proposal,
job setup sheet started
Signed Proposal or contract
referring to our proposal #,
job setup sheet portion
complete, tax forms,
available time frame
Account setup in InField,
ViewPoint, etc.
Documents
(pre-arrival notifications,
background checks, etc.,
schedule any training, etc.)
Handoff Meeting
Project Mgmt
(determine equip. staging area, know
where scope includes, etc.)
Safety
(look for safety risks, know
where site is, etc.)
Foreman
(ensure site ready, know where site is,
assign worker to receive equip
(coordinates with PM) etc.)
Quality Control
(look for potential quality issues,
Agreement on
Future Solutions
Scheduling
Looks at jobsite
Scheduling
(creates temporary
and hard schedules)
Scheduling
(if been a while, revisit site as
necessary)
Project Mgmt
Safety
Foreman
Quality ControlScheduling
Job Books
Site Inspection
(Expected to be familiar
with jobsite by this point)
Safety
(gathers PPE, badges,
etc. for everyone as
needed and passes
them out)
Equipment Placed in
staging area onsiteCrew Member
(assigned by
Foreman if
needed to
receive
equipment)
SALES ESTIMATING PROPOSAL JOB SETUP PRE-START PREP PRODUCTION JOB END REVIEW
Admin
(schedules review meeting
with Foreman, Project Manager,
Executive, Sales, Quality Control,
Safety, and invite Accounting)
Plant (Customer)
WORK STARTS
(the following
happens
simultaneously)
Foreman
(helps the crew do the work, records
time and material usage and
equipment hours, works with QC to
keep job quality up, works with PM to
keep job on schedule and on budget,
works with Safety to keep everyone
safe, gets customer to sign T&M
documents as needed
Crew
(follows the instruction of the
Foreman to do the work
laid out in the job)
Project Management
(coordinates equipment deliver/
removal, material delivery,
collects time and material usage
from Foreman, summarizes and
reports to accounting time and
material usage, works with
Foreman to keep job on schedule
and on budget, does job
forecasts for accounting
Safety
(regularly visits jobsite, does
safety inspections, works
with crew and foremen to
keep everyone working
safely and according to
regulations/ rules)
Quality Control
(regularly inspects the jobsite and
work being performed, looks for
any quality problems, works with
foreman to keep job quality high)
Accounting
(uses data from PM to create invoices
and collect payments, tracks customer
payments, works with Executive on
how to handle past due invoices if
necessary)
Plant (Customer)
Staff
(help do inspections, keep job
quality high, etc.)
Site Access
Docs, Safe Work
WORK
COMPLETE
Quality Control
(does final inspection of job,
reports when done to PM)
Safety
(gets badges and
PPE back from
everyone, reports
when done to PM) Purchasing
(ensures not open PO’s,
reports when done to PM)
Job Close Out Form
(summarizes
contract and
change order amts,
checklist of all steps
complete, signifies
job is complete)
Sales
(lets customer know
done with job,
gets any feedback
from customer)
Plant (Customer)
Sales
Safety
Subcontractors/Vendors
Subcontractors/VendorsPO’s/Subcontracts
Subcontractors/Vendors
Plant (Customer)
Subcontractors/Vendors
(PM coordinates when they do
work, how long they are there,
billing information, etc.)
Subcontractors/Vendors
(off jobsite, final billing
turned in)
Plant (Customer)
Wants to add/change
something about the
scope of the job
CHANGE ORDERS
Is the change adding/
subtracting from existing
quantities of work?Yes
No
Sales
Project Management
Is the change small/minor? Yes
No
Sales
Is the job lump sum/has a
unit price? Yes
No
Executive Approve
Reject
Project Management
Sales
(gives customer PM
as a second contact
person in case they
need anything such
as change orders,
when bringing in
equipment, etc.)
Project Manager
(acts like a second point of
contact for the customer)
Plant (Customer)
Co
mm
unic
atio
n
Admin
Files documents
in OnBase
Revises item sheet,
etc. and reissues
documents as
needed
Admin
(posts revised schedule on S drive)Plant (Customer)
Safety
Accounting
Safety Gear/ISTC training
as needed Revised Item Sheet
(indicates job scope change)
Revised Job Setup
documents as needed
Revised Job Setup
documents as needed
Signed Proposal or contract
referring to our proposal #
Accounts adjusted
as needed
Scheduling
(adjusts schedule
as needed)
Subcontractors/VendorsRevised PO’s/Subcontracts
if needed
Project Management
Makes sure estimate matches
contract (amt, format, etc.)
Contract/Change Orders
Policy
Email from Customer
agreeing to proposal
Project Management
(follows policy on how to
proceed without contract but
with customer approval)
Quality Control
Foreman
Project Management
Safety
Plant (Customer)
Crew
Staff
Documents
(and changes or revisions,
background checks, etc.,
schedule any training, etc.)
Subcontractors/Vendors
Plant (Customer)
WORK STARTS
(the following
happens
simultaneously)
Marks down on calendar
to make sure receive
contract at a later date
Project Management
The job is a Time
& Material
contract type
Executive Approve
Reject
Project Management Plant (Customer)
LUMP SUM/UNIT PRICE CHANGE ORDERS
T&M Change Order Form
filled out and any email
correspondence attached
if any
Revised proposal based on
the original unit pricing
Signed copy of the T&M
Change Order Form (or a
new/revised purchase order)
Admin
Files documents
in OnBase
Revises item sheet,
etc. and reissues
documents as
needed
Project ManagementAdmin
(posts revised schedule
on S drive if needed)
Safety
Accounting
Safety Gear/ISTC
training
as needed
Revised Item Sheet
(indicates job scope change)
Revised Job Setup
documents as needed
Revised Job Setup
documents as needed
Accounts adjusted
as needed
Scheduling
(adjusts schedule
as needed)
Subcontractors/VendorsRevised PO’s/Subcontracts
if needed
Quality Control
Foreman
Project Management
Safety
Plant (Customer)
Crew
Staff
Documents
(any revisions or additions
for new crewmembers on
job, background checks, etc.,
schedule any training, etc.)
Subcontractors/Vendors
Plant (Customer)
WORK STARTS
(the following
happens
simultaneously)
T&M CHANGE ORDERS
Rebid (if needed)