Page 1: Florida Gas Transmission Mainline Hydrostatic Test

Florida Gas TransmissionMainline Hydrostatic Test

From the Palmetto Expressway Interchange with Okeechobee Road to the Intersection of Milam Dairy Road with NW 64th Street

Miami-Dade County

Page 2: Florida Gas Transmission Mainline Hydrostatic Test

Who is Florida Gas Transmission (FGT)?

Why is FGT testing?What is the test exactly?When will the test occur?Where will the test take place?How will the test be conducted?How will the test affect me?

Today’s Outline

Page 3: Florida Gas Transmission Mainline Hydrostatic Test

Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf

Provide 65% of all the natural gas for power generation in Miami-Dade County

18” diameter Mainline serving South FloridaCustomers include:

Electric utility companies Local distributors Industrial clients

Florida Gas Transmission Company

Page 4: Florida Gas Transmission Mainline Hydrostatic Test

The U.S. Department of Transportation regulates all interstate pipelines

Testing is federally mandatedBest practice to confirm the safety

and reliability of the pipeline Safety is our #1 priority Ensure continued superb client service

Need for the Test

Page 5: Florida Gas Transmission Mainline Hydrostatic Test

Hydrostatic Test Remove the natural gas from the line• Controlled release vents harmlessly into

atmosphere• LDC-service is continued on parallel loop

system Test the integrity of the pipeline by

filling the line with water• Put the water under pressure for a fixed

period of time

Nature of the Test

Page 6: Florida Gas Transmission Mainline Hydrostatic Test

Hydrotesting the 18” Mainline systemStandard, common pipeline test

procedureRecent, successful 18” Mainline tests

were completed in: Saint Lucie Palm Beach

Began Miami-Dade testing February 2011

Background

Martin Broward

Page 7: Florida Gas Transmission Mainline Hydrostatic Test

Public Awareness Campaign

Project Process

Begin Project

Obtain Permits

"Pig" Existing System

Correct Any Anomalies

Conduct Hydrotest

End Project

Prepare System for Testing

Page 8: Florida Gas Transmission Mainline Hydrostatic Test

TASK DATECommunity Awareness January – April

Permit Applications January – MarchSystem Preparation January – February

Test Preparation February – MarchConduct Hydrotest March 29 – April 26, 2012

Test window has tentatively been set: March 29 – April 26, 2012 Coordinated with FP&L and regulators

Project Schedule

Page 9: Florida Gas Transmission Mainline Hydrostatic Test

Total Project Length = 2.2 miles Begin: W 39th Street (NW 91st Terrace) End: NW 64th Street

Generally follows 3 roadway alignments: Palmetto Expressway (SR 826) & W 20th Ave Hialeah Expressway (SR 934) & NW 74th St Milam Dairy Road (NW 72nd Ave / SR 969)

Hialeah, Medley, Miami-Dade County

Project Location

Page 10: Florida Gas Transmission Mainline Hydrostatic Test

Project Limit

Project Limit

N

Project Location (con’t)

Page 11: Florida Gas Transmission Mainline Hydrostatic Test

Remove natural gas from the 18” Mainline Completed the week before the hydrotest

Fill the line with waterPressurize the system

Normal operating pressure is 722 PSI Test pressure is up to 1,444 PSI• Relatively short duration (approx. 30 minutes)

Reduce pressure to 1,108 PSI•Maintain for 8 hours

How the Test is Performed

Page 12: Florida Gas Transmission Mainline Hydrostatic Test

De-pressurize the lineDrain the water from the systemIf any integrity issues are found:

They are corrected as soon as possible The hydrotest is performed again• Any re-testing will be performed as soon as

possible, during the same hoursResume normal natural gas service

How the Test is Performed (con’t)

Page 13: Florida Gas Transmission Mainline Hydrostatic Test

Safety is our #1 priorityPerformed extensive test

preparations, including an inspection of the entire system

Pipe anomalies will be repaired in advance of conducting the hydrotest

For the duration of the high pressure test, as a safety consideration, we plan to isolate the pipeline route from people and traffic

Safety During the Test

Page 14: Florida Gas Transmission Mainline Hydrostatic Test

Advance Preparations Make all key stakeholders aware• Adjacent property owners• Emergency service providers•General driving public

Announcements• Flyers, newspaper, FL511, website, etc.

Dynamic message signs• 2 weeks in advance

Conducting the Test

Page 15: Florida Gas Transmission Mainline Hydrostatic Test

Night of the Test Begin at midnight Close cross streets with barricades Law enforcement support Confirm all-clear for entire corridor Conduct hydrotest Reopen roadways at approximately 4:00

AM

Conducting the Test (Con’t)

Page 16: Florida Gas Transmission Mainline Hydrostatic Test

General Utility Permit from the Florida Department of Transportation is in process

Emergency responders will be able to cross as needed

Officers will be stationed atmajor cross street detours

Traffic Control During the Test

Page 17: Florida Gas Transmission Mainline Hydrostatic Test

Project Location – District 13

Page 18: Florida Gas Transmission Mainline Hydrostatic Test

Project Location – District 12

Page 19: Florida Gas Transmission Mainline Hydrostatic Test

Please visit our website:www.fgthydrotest.com

Or contact FGT:Mr. Terry Coleman

2405 Lucien Way, Suite 200Maitland, FL 32751

Toll Free – 800.381.1477Office – 407.838.7054Fax – 407.838.7052

Email – [email protected]

For More Information

Page 20: Florida Gas Transmission Mainline Hydrostatic Test

FGT 18” Mainline Hydrotest Summary

Federal mandate Testing with water Test window is

tentatively March 29 – April 26, 2012

Midnight – 4:00 AM Road closures with law

enforcement W 20th Ave Hialeah Expwy & NW 74th St Milam Dairy Rd (NW 72nd

Ave) Emergency vehicles can

always cross

Project Limit

Project Limit

N

Page 21: Florida Gas Transmission Mainline Hydrostatic Test