Floatover Installation Methods

download Floatover Installation Methods

of 28

description

floatover

Transcript of Floatover Installation Methods

  • By - Uday Kulkarni and Pradeep Jain

    03 Sep 2013

    Float Over Installation of Topsides 1

    Float-Over Installation of Topsides

    Copyright & Disclaimer : Some of the material used in this presentation are Technip proprietary items and shall not be

    used or reproduced for any purpose without prior written permission from Technip. Some of the material used in this

    presentation is taken from public domain (ex. Internet) and is used purely for educational purpose

  • Content

    1. What is Floatover?

    2. Types of Floatover Installations

    3. Vessels/Barges used

    4. Floatover Stages

    5. Floatover Engineering & Design

    6. Systems and components used in Floatover

    7. Recent Floatover Installations

    8. Video

    9. Floatover Installation Today & Tomorrow

    2 Float Over Installation of Topsides - Content

  • Conventional Installation method

    Float Over Installation of Topsides 3

    Heavier topsides (typ.> 4000MT) are installed by dividing it into

    number of modules.

    Multiple lifts using Derrick Barge are required to install the

    complete Topside

    What is Floatover?

  • Floatover Method

    In a floatover, the completed topside module from the yard is transported on a barge

    Float Over Installation of Topsides - Introduction 4

    The vessel is positioned within or around the legs of a pre-installed substructure

    The module is settled onto the jacket legs by vessel ballasting only or by combination of vessel ballasting and Jacking system

    A complete single integrated deck is installed using float-over

  • Float Over Installation of Topsides 5

    Types of Floatover Installations

    1. Active Floatover This is done using Jacks in addition to Ballasting of Barge 2. Passive Floatover This is done only by Ballasting / de-ballasting of barge

    Floatover using Loose Slot method This is done using mooring and anchor lines only. Generally no contact with sub-structure is involved

    Floatover using Tight Slot method This is done using fenders in addition to mooring and anchor lines

  • Floatover Vessels

    I. Cargo Barge

    II. Self propelled Vessels

    III. Multiple vessels in Catamaran configuration

    Float Over Installation of Topsides - Vessels 6

  • Floatover by Cargo Barge

    Float Over Installation of Topsides By Cargo Barge 7

    P52 Project by Technip for Petrobras Brazil

    25000 MT Deck

    Semisubmersible Hull

    Cargo Barge

  • Floatover using Self propelled Barge

    Float Over Installation of Topsides By Self Propelled Barge

    8

    East Area Project by Technip in Nigeria

    18000 MT Deck Preinstalled Jacket

  • Floatover by Catamaran Barge

    Float Over Installation of Topsides By Catamaran Barge 9

    Kikeh Spar Project by Technip

    4000 MT Topside

    Spar Hull

  • Floatover Stages

    Floatover is done broadly in following 5 stages-

    Stage-1 : Stand-Off

    Stage-2 : Docking

    Stage-3 : Pre-Mating

    Stage-4 : Mating & Vertical Load Transfer

    Stage-5 : Un-docking and Exit

    Float Over Installation of Topsides - Phases 10

  • Stage-1: Stand-Off (Conceptual)

    Float Over Installation of Topsides - Phases 11

    The vessel is at a safe distance from the substructure but connected to

    the mooring system, and final preparations such as preparing the vessels rapid ballast system or the hydraulic jacks are under way.

  • Stand-Off (Actual Operation)

    Float Over Installation of Topsides -Phases 12

  • Stage-2 : Docking (Conceptual)

    Float Over Installation of Topsides - Phases 13

    The vessel enters the substructure

  • Docking (Actual Operation)

    Float Over Installation of Topsides - Phases 14

  • Stage-3 : Pre-Mating

    Float Over Installation of Topsides - Phases 15

    Ballasting the vessel to match the leg mating units (LMU) with receptors on top of

    the substructure legs and removing the remaining tie downs. No weight transfer

    yet occurs.

  • Stage-4 : Mating & Load Transfer

    Float Over Installation of Topsides -Phases 16

    The topsides is lowered onto the substructure by either rapid ballasting of

    the vessel or by contracting the hydraulic jacks. The topsides weight is

    transferred to the jacket completely

  • Schematic Floatover Installation using Jacks

    Float Over Installation of Topsides 17

    Barge

    Integrated deck

    Jacket Legs

  • Stage-5 : Un-docking and Exit

    Float Over Installation of Topsides - Phases 18

    Continue ballasting, so that a gap is created between the underside of deck

    and the vessels Deck Support Frame (DSF), to ensure vessel motions will not cause contact between the two. The vessel is withdrawn from the jacket slot.

  • Float Over Installation of Topsides - Engineering 19

    Floatover Engineering & Design

    1. Jacket & Deck Configuration

    2. Installation Analysis

  • Float Over Installation of Topsides - Engineering 20

    Jacket Configuration for Floatover Installation

  • Deck Configuration for Floatover Installation

    Float Over Installation of Topsides 21

  • Non-Linear Time domain mating analysis is done for various floatover scenarios such as docking, mating and undocking condition

    Mating analysis is used to predict following

    Lateral forces for design of Jacket

    Loads in fenders

    Vertical and horizontal motions of stabbing cones

    Loads in LMUs and DSUs

    Maximum vertical barge motion post mating

    Installation Analysis

    Float Over Installation of Topsides - Engineering 22

  • Systems & Components used in Floatover

    Float Over Installation of Topsides - Equipments 23

    Barge Equipment

    1. Control room

    2. DSF & DSU

    3. Jacking System

    4. Ballast System

    5. Winches, Mooring Lines and Anchoring Lines

    6. Anti Surge Control system

    Jacket Equipment

    1. LMU (Leg Mating Unit)

    2. Jacket Fendering System

    Navigation & Position Aids

    Environmental Parameter monitoring system

  • LMU Leg Mating Unit

    Float Over Installation of Topsides 28

    Topside Weight = 13,000 MT

    LMU Height = 3.7m

    LMU Diameter = 2.0m

    LMU Weight = 24 MT

    LMU Installed in Jacket

    LMU-Video

    LMU

    LMU

  • Recent Floatover Installations

    29

    More than 20 floatover Installations done by Technip between 1987 to 2013

    Installation

    Date

    Ballasating

    (B)

    Jacking (J)

    PROJECT CLIENT LOCATION DECK WEIGHT LEGS Barge / Vessel

    1987 B Bhylene Offshore Terminal EGPC Egypt 2,200 t 8 Giant 12

    1988 B Zakum Accomodation Platform ADMA. OPCO Abu Dhabi 6,500 t 8 CB4 + CB1

    1991 B Khuff Production Platform ADNOC Abu Dhabi 2, 500 t 8 CB4

    1995 B + J COBO - COB P1 ELF Angola 9,500 t 8 Giant 4

    1996 B + J Qatargas Compression Platform QATARGAS Qatar 7,500 t 8 LB1

    2000 B G.I.P. ADMA OPCO Abu Dhabi 4,200 t 6 LB1

    2002 B CAKERAWALA CTOC Malaysia 18,000 t 8 S45

    2003 B + J AMENAM - AMP1 ELF Nigeria 11,000 t 8 Mighty Servant 3

    2003 B SOROOSH-NOW ROOZ (3 decks) SHELL Iran 9,000 t 0 LB2 / LB1

    2003 B SOUTH PARS (2 decks) NIOC / Petropars Iran 6,000 t 0 Iranian Barge

    2003 B NIPPON HELANG NIPPON OIL Malaysia 8,000 t 8 S45

    2005 B + J EAST AREA EXXON MOBIL Nigeria 18,000 t 8 Black Marlin

    2006 B + J AMENAM - AMP2 TOTAL Nigeria 9,600 t 8 Fjell

    2006 B P52 (4 Column Semi) Petrobras Brazil 25,000 t 4 Purpose Built Barge

    2006 B KIKEH (Spar) Murphy Malaysia 4,000 t 4 Catamaran Barges

    2008 B P51 (4 Column Semi) Petrobras Brazil 27,000 t 4 Purpose Built Barge

    2009 B North Belut Conoco/Philips Indonesia 13,500 t 8 S45

    2010 B GPF Adma.Opco Abu Dhabi 8,000 t 8 LB1

    2010 B P56 (4 Column Semi) Petrobras Brazil 27,000 t 4 Purpose Built Barge

    2011 B Turkmenistan Block 1 (4 Column GBS) Petronas Capian 5,500 t 4 Purpose Built Barge

    2013 B + J OFON 2 TOTAL Nigeria 16,000 t 8 Transshelf

  • Videos

    Floatover video

    Float Over Installation of Topsides 30

  • Floatover Installation Today and Tomorrow

    Float Over Installation of Topsides - Advantages 31

    Advantages Challenges

    A pre-commissioned, integrated, single piece topside can be installed

    Yard facilities have to be adequate to handle heavier topside for fabrication and loadout

    Can be used in shallow waters where HLVs cannot be used

    Installation windows are small

    Reduction in Offshore hook-up and commissioning time

    Heavier Jacket is required due to barge access slot at the top

    The project cost saving is of the order of 2% - 5%

    The entire operation from load-out, transportation and installation has to be well controlled

    The project schedules can be saved to the tune of 6% - 10%

    Experience is the key to success

    FUTURE Of Floatover

    Potential to install very heavy topsides ( > 35,000 MT) in open sea

    Can be used for fixed as well as floating structures

    In India this concept has great potential due to scarcity of HLVs for lifts > 4000 MT

  • Questions ???

    Float Over Installation of Topsides 32