First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project...

23
First Quarterly Project Tracking Report 2016 January 2016

Transcript of First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project...

Page 1: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

F i r s t Q u a r t e r l y P r o j e c t T r a c k i n g R e p o r t 2 0 1 6

January 2016

Page 2: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 1

Table of Contents

Executive Summary .....................................................................................................................................2

NTC Project Summary ................................................................................................................................4

NTC Issuance ...................................................................................................................................7

NTC Withdraw.................................................................................................................................7

Completed Projects ..........................................................................................................................9

Project Status Summary .................................................................................................................13

Balanced Portfolio ........................................................................................................................................15

Priority Projects ...........................................................................................................................................17

Out-of-Bandwidth Projects .........................................................................................................................19

Responsiveness Report ................................................................................................................................20

Appendix I ....................................................................................................................................................22

Page 3: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 2

Executive Summary

SPP actively monitors and supports the progress of transmission expansion projects, emphasizing the importance of maintaining accountability for areas such as grid regional reliability standards, firm transmission commitments and Tariff cost recovery. Each quarter SPP staff solicits feedback from the project owners to determine the progress of each approved transmission project. This quarterly report charts the progress of all SPP Transmission Expansion Plan (STEP) projects approved either directly by the SPP Board of Directors (Board) or through a FERC filed service agreement under the SPP Open Access Transmission Tariff (OATT). The reporting period for this report is August 1, 2015 through October 31, 2015. Table 1 provides a summary of all projects in the current Project Tracking Portfolio (PTP), which includes all Network Upgrades in which construction activities are ongoing, or construction has completed but not all the close-out requirements have been fulfilled in accordance to Section 13 of Business Practice 7060. The PTP includes all active Network Upgrades including transmission lines, transformers, substations, and devices. Table 1 below summarizes the PTP for this quarter. Figures 1 reflects the percentage cost of each upgrade type in the PTP. Figure 2 shows the percentage cost of each project status in the PTP.

Upgrade Type No. of Upgrades Estimated Cost Miles of

New Miles of Rebuild

Miles of Voltage

Conversion Balanced Portfolio 3 $62,949,252 30.9 0.0 0.0 Economic 4 $37,921,000 0.0 0.0 28.8 High Priority 94 $1,758,909,144 1351.2 11.5 0.0 Regional Reliability 296 $2,979,219,628 1534.2 475.4 593.4 Transmission Service 22 $100,458,294 12.7 15.3 0.0 Zonal Reliability 9 $109,022,970 34.7 28.5 0.0

NTC Projects Subtotal 428 $5,048,480,288 2963.8 530.6 622.2 Generation Interconnection 60 $251,427,355 20.0 0.0 0.0 Regional Reliability - Non OATT 1 $7,107,090 0.0 0.0 0.0 TO - Sponsored 7 $47,602,536 22.7 0.0 0.0

Non-NTC Projects Subtotal 68 $306,136,981 42.7 0.0 0.0 Total 496 $5,354,617,269 3006.5 530.6 622.2

Table 1: Q1 2016 Portfolio Summary

Page 4: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 3

1%0.7%

5%

33%

56%

2% 2%

Balanced Portfolio

Economic

Generation Interconnection

High Priority

Regional Reliability

Transmission Service

Zonal Reliability

Figure 2: Percentage of Project Status on Cost Basis

10%

16%

32%7%

30%

2%

1% 1% 0.3% 2%

Closed Out

Complete

On Schedule < 4

On Schedule > 4

Delay - Mitigation

Suspended

NTC - Commitment Window

NTC-C Project Estimate Wind

RFP Response Window

Re-evaluation

Figure 1: Percentage of Project Type on Cost Basis

Page 5: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 4

NTC Project Summary

In adherence to the OATT and Business Practice 7060, SPP issues Notifications to Construct (NTCs) to Designated Transmission Owners (DTOs) to commence the construction of Network Upgrades that have been approved or endorsed by the Board intended to meet the construction needs of the STEP, OATT, or Regional Transmission Organization (RTO). Figure 3 reflects project status within each source study, and Table 2 provides the supporting data. Figure 4 shows the amount of estimated cost by in-service year for all Network Upgrades that have been issued an NTC or NTC-C. Figure 5 shows the cost trend of all the Board-approved studies that have resulted in NTCs. Note: Figures 3, 4, and 5, and Table 2 provide data for all projects for which SPP has issued an NTC or NTC-C, regardless of completion date, and therefore include data from Network Upgrades no longer included in PTP.

Figure 3: Project Status by NTC Source Study

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400OnSchedule

Suspended

Delayed

Complete

$ M

illio

n

Page 6: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 5

Source Study Complete Delayed Suspended On Schedule Total

2006 STEP $190,913,935 $0 $0 $0 $190,913,935 2007 STEP $498,162,103 $17,964,000 $0 $0 $516,126,103 2008 STEP $421,172,520 $3,300,000 $0 $0 $424,472,520 Balanced Portfolio $831,489,690 $0 $0 $0 $831,489,690 2009 STEP $525,286,046 $7,900,000 $0 $0 $533,186,046 Priority Projects $854,531,082 $127,995,000 $0 $336,433,874 $1,318,959,956 2010 STEP $104,489,964 $33,303,460 $0 $2,332,800 $140,126,224 2012 ITPNT $143,150,500 $45,412,744 $0 $0 $188,563,244 2012 ITP10 $0 $313,376,623 $0 $459,979,086 $773,355,709 2013 ITPNT $174,383,367 $259,849,094 $0 $74,354,343 $508,586,804 2014 ITPNT $13,211,898 $391,423,776 $0 $235,276,941 $639,912,615 HPILS $140,350,190 $146,340,377 $0 $538,997,418 $825,687,985 2015 ITPNT $0 $226,969,366 $66,047,297 $24,673,361 $317,690,023 2015 ITP10 $0 $411,000 $18,553,018 $76,052,596 $95,016,613 IS Integration Study $205,500,000 $38,000,000 $0 $111,000,000 $354,500,000 Ag Studies $682,992,858 $84,772,718 $0 $44,310,189 $812,075,765 DPA Studies $119,635,923 $70,628,077 $0 $7,652,131 $197,916,131 GI Studies $420,370,577 $10,521,809 $0 $158,200,172 $589,092,557

Total $5,325,640,651 $1,778,168,045 $84,600,315 $2,069,262,909 $9,257,671,920 Table 2: Project Status by NTC Source Study

Figure 4: Estimated Cost for NTC Projects per In-Service Year

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

$1,800

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021

$58 $59

$184

$338$392

$340

$983

$562

$1,770

$785

$1,286

$259$320

$125

New Q4 2015 NTC

Modified Q4 2015 NTC

Previous NTC

$ M

illio

n

$1,283

$520

Page 7: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 6

Figure 5: Cost Trend per Board-Approved Study

$0

$200

$400

$600

$800

$1,000

$1,200

$1,400

$1,600

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

2006 STEP2007 STEP2008 STEPBalanced Portfolio2009 STEPPriority Projects2010 STEP2012 ITP102012 ITPNT2013 ITPNT2014 ITPNTHPILS2015 ITP102015 ITPNT

$ M

illio

n

Page 8: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 7

NTC Issuance Three new NTCs were issued since the last quarterly report as a result of the completion of Aggregate Study, SPP-2014-AG1-AFS-6, with a total estimated cost of $19.9 million. NTC No. 200360 was issued to Southwestern Public Service Company (SPS) after they submitted an updated cost estimate to SPP in response to a Notification to Construct with Conditions (NTC-C). The NTC-C was issued as a result of the 2015 ITP Near-Term Assessment approved by the Board in January. For these Network Upgrades, all cost estimates were found to meet the conditional requirements of the NTC-C, and therefore SPS was issued an NTC for the Network Upgrades without the NTC-C conditions. The total estimated cost of the Network Upgrades described in this NTC is $30.0 million. Three NTCs were issued as a result of requested scope modifications by DTOs. The modifications were evaluated by Staff and determined to cause no adverse impact to the SPP Transmission System. Table 3 summarizes the NTC activity from October 1, 2015 through December 31, 2015. NTC ID values in bold font indicate NTC-Cs.

NTC ID DTO NTC Issue Date Upgrade Type Source

Study

No. of

Upgrades

Estimated Cost of New

Upgrades

Estimated Cost of Previously

Approved Upgrades

200349 AEP 11/3/2015 Regional Reliability SPP-2014-AG1-AFS-6 1 $7,430,909

200358 GRDA 12/2/2015 Regional Reliability SPP-2014-AG1-AFS-6 4 $7,719,238

200359 SPS 12/2/2015 Regional Reliability SPP-2014-AG1-AFS-6 2 $4,763,242

200360 SPS 12/7/2015 Regional Reliability 2015 ITPNT 8 $30,027,505 200361 AEP 12/11/2015 Regional Reliability 2016 ITPNT 1 $1,600,349 200362 MKEC 12/21/2015 High Priority HPILS 5 $43,265,193

200363 WR 12/21/2015 High Priority HPILS 1 Included in NTC 200263

Total 22 $19,913,389 $74,893,047 Table 3: Q4 2015 NTC Issuance Summary

NTC Withdraw NTCs were withdrawn for 17 Network Upgrades since the last quarterly report, totaling an estimated $62.9 million. Sixteen of the withdrawn Network Upgrades were determined to no longer be needed as a part of the ongoing 2016 ITP Near-Term Assessment. The Board approved the withdrawals at its meeting in October.

Page 9: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 8

One Network Upgrade designated to American Electric Power (AEP) was withdrawn as a result of analysis done in association with Aggregate Study, SPP-2014-AG1-AFS-6. Table 4 lists the NTC Withdraw activity from July 1, 2015 through September 30, 2015. NTC ID values in bold font indicate NTC-Cs.

NTC ID DTO NTC

Withdraw Date

Upgrade Type Original Source Study No. of

Upgrades

Estimated Cost of

Withdrawn Upgrades

200351 AEP 11/3/2015 Regional Reliability 2010 STEP 1 $14,500,000

200352 WFEC 11/3/2015 Regional Reliability 2008 STEP/2014 ITPNT/DPA-

2012-MARCH-143-147 3 $4,155,000 200353 GRDA 11/3/2015 Regional Reliability 2015 ITPNT 3 $1,359,521 200354 OGE 11/3/2015 Regional Reliability 2015 ITPNT 1 $647,712 200355 SPS 11/3/2015 Regional Reliability 2015 ITP10 3 $19,534,266 200356 WR 11/3/2015 Regional Reliability 2015 ITPNT 1 $6,088,561 200357 GMO 11/13/2015 Regional Reliability 2015 ITPNT 1 $4,329,248 200360 SPS 12/7/2015 Regional Reliability 2015 ITPNT 3 $4,857,840 200364 AEP 12/21/2015 Regional Reliability SPP-2014-AG1-AFS-6 1 $7,430,909

Total 17 $62,903,057 Table 4: Q4 2015 NTC Withdraw Summary

Page 10: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 9

Completed Projects Twelve Network Upgrades with NTCs and one Generation Interconnection Network Upgrade were verified as completed during the reporting period, totaling an estimated $101 million. Table 5 lists the Network Upgrades reported and confirmed as completed during the reporting period. Table 6 summarizes the completed projects over the previous year, including Network Upgrades not yet confirmed as completed. Figure 6 reflects the completed projects by upgrade type on a cost basis for the current year and the following year based on current projected in-service dates. Tables 7 and 8 summarize all Network Upgrades that include construction of transmission lines, both for the current year and the following year. Note: Previous quarter’s updated results are listed as the Transmission Owners may make adjustments to final costs and status of projects completed during the year.

UID Network Upgrade Name Owner NTC Source

Study Cost Estimate 10471 FLETCHER - MARLOW JCT 69KV CKT 1 WFEC 2007 STEP $2,000,000 10522 GRANDFIELD - INDIAHOMA 138KV CKT 1 WFEC 2007 STEP $1,125,000 11356 Crosby County Interchange 115/69 kV Transformer Ckt 2 SPS 2013 ITPNT $1,861,774 50085 CARTER JCT 69KV WFEC 2007 STEP $324,000 50366 CANTON - TALOGA 69KV CKT 1 WFEC Ag Studies $4,800,000 50406 Diamondback Interchange 115/69 kV Transformer Ckt 1 SPS 2012 ITPNT $5,400,001 50407 Sulphur Interchange - Diamondback Interchange 115 kV Ckt 1 SPS 2012 ITPNT $8,000,000 50560 Potash Junction 115/69 kV Transformer Ckt 1 SPS 2013 ITPNT $2,500,000 50579 Criner - Payne Switching Station 138 kV WFEC 2013 ITPNT $3,000,000 50580 Payne Switching Station 138 kV WFEC 2013 ITPNT $250,000 50708 Potash Junction - Road Runner 230 kV Ckt 1 SPS HPILS $49,157,007 50709 Road Runner 230/115 kV Substation SPS HPILS $9,350,766 50752 Eddy County - Tolk 345kV Ckt 1 SPS GI Studies $13,224,349

Total $100,992,897 Table 5: Q4 2015 Completed Network Upgrades

Page 11: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 10

Upgrade Type Q1 2015 Q2 2015 Q3 2015 Q4 2015 Total

Regional Reliability 23 16 17 9 65

$171,441,736 $57,396,463 $108,784,227 $24,460,775 $362,083,201

Transmission Service

2 0 4 1 7

$328,302 $0 $15,753,551 $4,800,000 $20,881,853

Balanced Portfolio 0 3 0 0 3

$0 $62,949,252 $0 $0 $62,949,252

High Priority 16 1 5 2 24

$519,103,747 $327,861 $21,867,439 $58,507,773 $599,806,820

Economic 0 0 0 0 0

$0 $0 $0 $0 $0

Zonal Reliability 0 0 1 0 1

$0 $0 $355,000 $0 $355,000

Generation Interconnection

7 2 7 9 25

$22,983,169 $13,322,627 $60,083,256 $26,656,091 $123,045,144

Table 6: Completed Project Summary through 4th Quarter 2015

Page 12: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 11

Voltage Class

Number of Upgrades

Miles of New

Miles of Rebuild/ Reconductor

Miles of Voltage

Conversion Estimated Cost

69 15 29.6 37.3 0.0 $78,289,610 115 10 122.3 0.0 0.0 $108,112,647 138 14 42.4 32.9 21.6 $87,651,670 161 1 0.0 0.0 0.0 $4,410,087 230 4 101.4 0.0 0.0 $95,411,328 345 11 490.7 0.0 0.0 $559,953,044

Total 55 786.4 70.2 21.6 $933,828,387 Table 7: Line Upgrade Summary for Previous 12 Months

Figure 6: Completed Projects by Upgrade Type

$0

$100

$200

$300

$400

$500

$600

$700

$800

Q1 2015 Q2 2015 Q3 2015 Q4 2015 Q1 2016Projected

Q2 2016Projected

Q3 2016Projected

Q4 2016Projected

Generation Interconnection

Zonal Reliability

Economic

High Priority

Balanced Portfolio

Transmission Service

Regional Reliability$ M

illio

n

Page 13: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 12

Voltage Class

Number of Upgrades

Miles of New

Miles of Rebuild/ Reconductor

Miles of Voltage

Conversion Estimated Cost

69 11 44.0 63.2 0.0 $79,591,852 115 10 130.2 10.3 4.5 $131,963,360 138 8 32.0 31.9 16.5 $73,319,715 161 0 0.0 0.0 0.0 $0 230 2 0.0 0.0 122.0 $10,946,820 345 5 278.3 0.0 0.0 $393,705,678

Total 36 484.45 105.42 143.01 $689,527,424 Table 8: Line Upgrade Projections for Next 12 Months

Page 14: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 13

Project Status Summary SPP assigns a project status to all Network Upgrades based on the projected in-service dates provided by the DTOs relative to the Need Date determined for the project. Project status definitions are provided below:

• Complete: Construction complete and in-service • Closed Out: Construction complete and in-service; all close-out requirements fulfilled • On Schedule < 4: On Schedule within 4-year horizon • On Schedule > 4: On Schedule beyond 4-year horizon • Delayed: Projected In-Service Date beyond Need Date; interim mitigation provided or

project may change but time permits the implementation of project • Within NTC Commitment Window: NTC/NTC-C issued, still within the 90-day written

commitment to construct window and no commitment received • Within NTC-C Project Estimate Window: Within the NTC-C Project Estimate (CPE)

window • Within RFP Response Window: RFP issued for the project • Re-evaluation: Project active; pending re-evaluation • Suspended: Project suspended; pending re-evaluation

Figure 7 reflects a summary of project status by upgrade type on a cost basis.

Page 15: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 14

Figure 7: Project Status Summary on a Cost Basis

$0

$500

$1,000

$1,500

$2,000

$2,500

$3,000

RegionalReliability

TransmissionService

BalancedPortfolio

High Priority Economic GenerationInterconnection

SuspendedRe-evaluationRFP Response WindowWithin NTC-C Project Estimate WindowWithin NTC Commitment WindowDelayedOn Schedule > 4On Schedule < 4CompleteClosed Out

$ M

illio

n

Page 16: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 15

Balanced Portfolio

Approved in April 2009, the Balanced Portfolio was an initiative to develop a group of economic transmission upgrades that benefit the entire SPP region, and to allocate those project costs regionally. The projects that were issued NTCs as a result of the study include a diverse group of projects, estimated to add approximately 702 miles of new 345 kV transmission line to the SPP system. The total cost estimate for the projects making up the Balanced Portfolio increased 0.6% from the previous quarter to $831.5 million. Changes in the project costs this quarter are due to incorporating the latest information provided by the DTOs in their respective Formula Rate updates for completed projects. All the projects making up the Balanced Portfolio have been completed and placed into service. A final reallocation of Revenue Requirements for deficient Zone(s) will be performed once all actual costs have been reported. Figure 8 below depicts a historical view of the total estimated cost of the Balanced Portfolio. Table 9 provides a project summary of the projects making up the Balanced Portfolio.

$ M

illio

n

Figure 8: Balanced Portfolio Cost Estimate Trend

$691.2

$832.3

$903.0

$810.5

$831.5

$650.0

$700.0

$750.0

$800.0

$850.0

$900.0

$950.0

FERC Filing $896.7

Page 17: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 16

Project ID(s)

Project Owner(s) Project Name

Est. Line

Length

BP Report Estimates (6/2009)

Q3 2015 Cost Estimates

Q4 2015 Cost Estimates

Variance %

705/709 WFEC/OGE Gracemont Substation 345 kV N/A $8,000,000 $14,486,622 $14,486,622 0.0%

707/708 ITCGP/NPPD Spearville - Post Rock - Axtell 345 kV 226.9 $236,557,015 $203,702,073 $207,495,845 1.9%

698/699 OGE/GRDA Sooner - Cleveland 345 kV 36.0 $33,530,000 $50,018,622 $50,262,358 0.5%

702 KCPL Swissvale - Stilwell Tap 345 kV N/A $2,000,000 $2,875,727 $2,875,727 0.0%

700 OGE Seminole - Muskogee 345 kV 118.0 $129,000,000 $163,184,524 $163,416,396 0.1%

701/704 SPS/OGE Tuco – Woodward 345 kV 290.1 $227,727,500 $327,249,015 $330,003,491 0.8%

703 TSMO Iatan – Nashua 345 kV 30.9 $54,444,000 $65,342,060 $62,949,252 -3.7%

Total 701.9 $691,258,515 $826,858,642 $831,489,691 0.6%

Table 9: Balanced Portfolio Summary

Page 18: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 17

Priority Projects

In April 2010 the SPP Board of Directors and Members Committee approved for construction a group of "priority" high voltage electric transmission projects estimated to bring benefits of at least $3.7 billion to the SPP region over 40 years. The projects issued NTCs as a result of the study are estimated to add 291 miles of new single circuit 345 kV transmission line and 435 miles of double circuit 345 kV transmission to the SPP region. In October 2010 the SPP Board of Directors approved an overall cost increase for the Priority Projects due to line rerouting and addition costs for reactive compensation. The total cost estimate for the Priority Projects after the variances were approved was $1.42 billion. The current total cost estimate of $1.32 billion for the projects making up the Priority Projects indicates an increase of 0.7% from the previous quarter’s total amount. Figure 9 below depicts a historical view of the total estimated cost of the Priority Projects. Table 10 provides a project summary of the projects making up the Priority Projects. Table 11 lists construction status updates for the Priority Projects not yet completed.

Figure 9: Priority Projects Cost Estimate Trend

$1,144.9

$1,449.7

$1,381.0

$1,319.0

$1,100.0

$1,150.0

$1,200.0

$1,250.0

$1,300.0

$1,350.0

$1,400.0

$1,450.0

$1,500.0

Additional Costs Approved by Board

$1,416.3

$ M

illio

n

Page 19: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 18

Project

ID(s) Project

Owner(s) Project Est. Line

Length

Board Approved Estimates (10/2010)

Q3 2015 Cost Estimates

Q4 2015 Cost Estimates

Var. %

937 AEP Tulsa Power Station 138 kV Reactor N/A $842,847 $614,753 $614,753 0.0%

940/941 SPS/OGE Hitchland – Woodward District 345 kV Dbl Ckt

128.8 $221,572,283 $229,382,512 $229,563,977 0.1%

942/943 PW/OGE Thistle – Woodward District 345 kV Dbl Ckt 106.6 $201,940,759 $185,264,405 $185,687,533 0.2%

945 ITCGP Spearville – Ironwood – Clark Co. – Thistle 345 kV Dbl Ckt

122.5 $293,235,000 $309,000,001 $318,138,968 3.0%

946 PW/WR Thistle – Wichita 345 kV Dbl Ckt 77.5 $163,488,000 $120,525,851 $120,525,851 0.0%

936 AEP Valliant – NW Texarkana 345 kV 76.3 $131,451,250 $127,995,000 $127,995,000 0.0%

938/939 OPPD/TSMO Nebraska City – Mullin Creek – Sibley 345 kV 215.0 $403,740,000 $336,433,874 $336,433,874 0.0%

Total 726.7 $1,416,270,139 $1,309,216,396 $1,318,959,956 0.7%

Table 11: Priority Projects Summary

Proj

ect I

D

Proj

ect N

ame

Proj

ecte

d In

-Ser

vice

D

ate

Engi

neer

ing

Siti

ng a

nd R

outi

ng

Envi

ronm

enta

l Stu

dies

Perm

its

Mat

eria

l Pro

cure

men

t

Cons

truc

tion

C Complete

936 Valliant – NW Texarkana 345 kV 10/1/2016 C C C IP IP IP

IP In Progress

938 Nebraska City – Mullin Creek – Sibley 345 kV (TSMO) 12/31/2016 C C C C IP IP

NS Not Started

939 Nebraska City – Mullin Creek – Sibley 345 kV (OPPD) 12/31/2016 IP C C IP IP IP

N/A Not Applicable

Table 10: Priority Projects Construction Status

Page 20: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 19

Out-of-Bandwidth Projects

In adherence to the Business Practice 7060, SPP reports projects that have updated cost values that exceed their established baseline values based upon a ±20% bandwidth. Variances are determined by total project cost. Six projects with a cost estimate greater than $5 million were identified as having exceeded the ±20% bandwidth requirement during the reporting period. Table 12 provides summary information and Table 13 lists the cost detail for the out-of-bandwidth projects for Q4 2015.

PID Project Name Owner NTC

Source Study

Upgrade Type In-Service Date

502 Northwest Henderson - Poynter 69 kV Ckt 1 Rebuild AEP 2013 ITPNT Regional Reliability 6/6/2014

615 Crescent - Cottonwood 138 kV Voltage Conversion OGE 2008 STEP Regional Reliability 10/30/2014

795 Multi - Pleasant Hill 230/115 kV SPS 2009 STEP Regional Reliability 12/31/2014 882 Carthage - Rock Hill 69 kV Ckt 1 Rebuild AEP 2012 ITPNT Regional Reliability 6/1/2014

1012 Diana - Perdue 138 kV Rebuild AEP 2013 ITPNT Regional Reliability 12/31/2014 1029 Lynn County 115 kV Load Conversion SPS 2010 STEP Regional Reliability 4/22/2015

Table 12: Out-of-Bandwidth Project Summary

PID Baseline Cost Estimate

Baseline Cost Estimate Year

Baseline Cost Estimate with

Escalation

Latest Estimate or Final Cost

Variance Variance %

502 $7,815,833 2013 $8,211,510 $5,289,194 ($2,922,316) -35.59% 615 $9,552,704 2014 $9,791,522 $7,449,056 ($2,342,466) -23.92% 795 $53,875,562 2014 $55,222,451 $42,489,942 ($12,732,509) -23.06% 882 $11,830,128 2012 $12,739,754 $9,637,037 ($3,102,717) -24.35%

1012 $18,805,489 2013 $19,757,517 $14,986,466 ($4,771,051) -24.15% 1029 $5,342,685 2014 $5,476,252 $8,027,718 $2,551,466 46.59%

Table 13: Out-of-Bandwidth Project Cost Detail

Page 21: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 20

Responsiveness Report

Table 14 and Figures 10 and 11 provide insight into the responsiveness of DTOs constructing Network Upgrades within SPP in the Quarterly Project Tracking Report for Q4 2015. Note: Network Upgrades with statuses of “NTC Suspension”, “Re-evaluation”, “Within NTC Commitment Window”, “Within NTC-C Project Estimate Window”, and “Within RFP Response Window” were excluded from this analysis.

Project Owner

Number of Upgrades

Number of Upgrades Reviewed

Reviewed %

Number of ISD

Changes

ISD Change %

Number of Cost

Changes

Cost Change

%

AEP 53 4 8% 3 5.7% 1 1.9% BEPC 14 14 100% 10 71.4% 6 42.9% GMO 4 2 50% 0 0.0% 1 25.0%

GRDA 8 8 100% 0 0.0% 0 0.0% ITCGP 16 5 31% 0 0.0% 5 31.3% KCPL 6 3 50% 1 16.7% 0 0.0% LES 2 0 0% 0 0.0% 0 0.0%

MIDW 11 0 0% 1 9.1% 0 0.0% MKEC 13 1 8% 1 7.7% 2 15.4% NPPD 25 3 12% 0 0.0% 0 0.0% OGE 42 6 14% 2 4.8% 5 11.9%

OPPD 13 13 100% 0 0.0% 0 0.0% PW 4 0 0% 0 0.0% 0 0.0% SPS 139 139 100% 21 15.1% 28 20.1%

TSMO 5 0 0% 0 0.0% 0 0.0% WFEC 38 2 5% 9 23.7% 0 0.0%

WR 41 36 88% 0 0.0% 8 19.5% Total 441 239 54% 48 10.9% 58 13.2%

Table 14: Responsiveness Summary by Project Owner

Page 22: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 21

Figure 10: In-Service Date Changes by Project Owner

Figure 11: Cost Changes by Project Owner

0

20

40

60

80

100

120

140

160

In-Service Date Changes

0

20

40

60

80

100

120

140

160

Cost Changes

Page 23: First Quarterly Project Tracking Report 2016 2016 quarterly project tracking... · Q1 2016 Project Tracking Report 4 NTC Project Summary In adherence to the OATT and Business Practice

Southwest Power Pool, Inc.

Q1 2016 Project Tracking Report 22

Appendix I

See accompanying list of Network Upgrades