Final Presentation. The Team Competition Overview Design Constraints & Improvements System...

57
SECON 2013 Final Presentation

Transcript of Final Presentation. The Team Competition Overview Design Constraints & Improvements System...

Page 1: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SECON 2013

Final Presentation

Page 2: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 3: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

THE TEAM

Jackson KnottElectrical Engineer• Hardware Packaging• Navigation

Brian LampkinElectrical Engineer• PCB Design• Vision

Ian TurnipseedElectrical Engineer• Hardware

Packaging• Vision

Matt WilliamsElectrical Engineer• Hardware Packaging• Website

John MorrisonElectrical Engineer• Hardware

Packaging• Navigation

Matt WattsElectrical Engineer• PCB Design• Navigation

Dr. Robert ReeseAdvisor

Page 4: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 5: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

THE COURSE

1) Starting Zone2) Loading Zone3) Sea Delivery Zone4) Rail Delivery Zone5) Air Delivery Zone

Page 6: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

COMPETITION FORMAT

Qualifying RoundDrive One Foot Forward

Preliminary RoundsThree 5 Minute RunsScore will be Sum of the Three

RunsTop 8 Teams Advance

Final RoundsSingle-Elimination BracketSeeding based on Preliminary

Standings

Page 7: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

QUALIFYING ROUND

Four Available Practice Courses

Page 8: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SCORING

Rail Cargo (Six Blocks) 50 Points: Correct Size 100 Points: Correct Color

Sea Cargo (Six Blocks) 50 Points: Correct Size 100 Points: Correct Color

Air Cargo (Two Blocks) 350 Points: Correct Size 100 Points: Correct Color

Deductions 20 Points: Wrong

Zone

Page 9: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 10: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

Type Name

Manufacturability Modular Design

Sustainability Battery Life

DESIGN CONSTRAINTS - PRACTICAL

Page 11: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

Modular Design PCB

LayoutPopulation

ChassisLayout Optimization

Page 12: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

PCB Layout and Population PIC24 Breakout Board Headers/Locking Connectors

Page 13: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

Chassis Layout Optimization

Battery Compartment

Molex Battery Connection

Page 14: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

Chassis Layout Optimization Battery Terminal Strip

Page 15: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

Chassis Layout Optimization Cable Tray for Routing

Page 16: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MANUFACTURABILITY

Chassis Layout Optimization Wheels Grippers

Page 17: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SUSTAINABILITY

Maximum Battery Life Average Current draw for the

system is 2.3 A Battery Rating is 4400 mAh Therefore, Overall Battery

life is about 2 hours.

Page 18: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SUSTAINABILITY

Through testing, we found that the battery performance dropped after 20-30 minutes of use.

To obtain the highest possible performance throughout the SECON Hardware Competition, the battery packs were charged following each run.

Page 19: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

Name Description

Multiple Block Carrier

The robot must carry the maximum allowed number of blocks.

Navigation The robot must navigate the course autonomously.

Detection The robot must detect color and size of blocks and spaces.

Speed The robot must travel at a speed of 0.4 feet/second.

Size The robot must be no larger in size than 12”x12”x16”[1]

DESIGN CONSTRAINTS - TECHNICAL

Page 20: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MULTIPLE BLOCK CARRIER

Two Claws Two Servo Motors for Each

GripperArm Upright/Arm LoweredClaw Opened/Claw Closed

Same Side Alignment for Each Gripper

Page 21: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MULTIPLE BLOCK CARRIER

Arm UprightPeriod High = 1400

µs

Arm LoweredPeriod High = 2350

µs

Page 22: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

MULTIPLE BLOCK CARRIER

Gripper Opened

Period High = 1800 µs

Gripper Closed

Period High = 600 µs

Page 23: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

NAVIGATION

Autonomous Infrared Distance Sensing Encoders

Page 24: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

NAVIGATION

Infrared Distance Sensor Testing

0 0.5 1 1.5 2 2.50

2

4

6

8

10

12

14

f(x) = − 1.18497448028744 x³ + 6.93058969354016 x² − 14.7408192713436 x + 13.2485638848871

Voltage

Dist

ance

to W

all

Page 25: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

NAVIGATION

Encountered Issue

Page 26: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

NAVIGATION

Design Improvement Extra IR Sensors Added for Precise

Navigation

Page 27: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

DETECTION

Mini-ITX and Camera Camera Ignores White and Black Detect Size and Color of

Blocks/Zones Serial Communication with

PIC24

Page 28: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

DETECTION

Size: 2 RGB: 231,123,99

Page 29: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

DETECTION

Brown and Green Filters

Page 30: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

DETECTION

Sliders to control detection zones

Page 31: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

DETECTION

Design Improvement Camera Mount

Locking 5 Degrees of

Freedom Light Source

Illuminates Blocks/Zones

Servo-Deployed Hood

Blocks Ambient Light

Page 32: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SPEED

Minimum Speed of 0.4 feet/sec. At 12 Volts, motors perform at 150 RPMWheel Diameter (d) = 90 mm.Circumference (c) = πd = 282.6Distance per Minute = c*RPM = 42,390

mm/min.Distance per Second = 706.5 mm/sec. =

2.32 ft/sec.

Page 33: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SPEED

Drive Motor TestingFor a Speed of 0.4 ft/sec, motors must run at

17.2%

Required for Task Completion Fast Speed (40% Duty Cycle)

Page 34: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SIZE

Robot must fit within a 12”x12”x16” Volume

12”

16”

Page 35: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 36: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Integration of all Subsystems Ensure that the Robot can do the

following: Avoid Walls Detect a Block Pick Up/Set Down a Block Match a Block with Correct Loading

Zone

Page 37: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Calibration for Competition Courses

Page 38: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Preparing for Preliminary Run

Page 39: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Vision System Preparation

Page 40: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Round Beginning

Page 41: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Approaching the Drop Zone with Blocks

Page 42: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

Preparing for Delivery

Page 43: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

SYSTEM TESTING

The Delivery

Page 44: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

PRELIMINARY RESULTS

1) Western Carolina University – 4950 Points2) University of Alabama – 1700 Points3) University of Evansville (IN) – 1440 Points

4) Mississippi State University – 1150 Points

5) FAMU/FSU – 840 Points6) UNC-Asheville – 800 Points7) North Carolina A&T – 710 Points8) Tennessee Tech University – 650 Points

Page 45: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

FINAL RESULTS

T5) Mississippi State

Page 46: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 47: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

January February March April

PCB Population

System Testing

Packaging

Debugging & Optimization

Competition

TIMELINE

Page 48: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

OUTLINE

The Team Competition Overview Design Constraints &

Improvements System Testing Timeline Bill of Materials

Page 49: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

BILL OF MATERIALS

Page 50: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

BILL OF MATERIALS

Page 51: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

BILL OF MATERIALS

Item Cost

Computer ~$270

14.8V/4400mAh Battery ~$80

(2) 67:1 Metal Gearmotors w/ Encoders & Wheels

~$75

(6) Servo-Motors (Arm, Claw, Hood) ~$180

(5) Infrared Distance Sensors ~$75

(4) Robotic Claws ~$40

(2) Front Wheel Casters ~$10

Camera w/ Telescoping Rod ~$70

Lights ~$5

Fan Cables ~$30

Printed Circuit Board w/ Fabrication ~$200

Course Construction ~$150

Miscellaneous Hardware Materials ~$50

Page 52: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

BILL OF MATERIALS

Unit Subtotal: ~$1235 Spares & Other Necessities: ~$365 Final Project Cost: ~$1600

Page 53: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

[1] IEEE SoutheastCon 2013 Hardware Competition. Final Version. 11 Sep. 2012. http://ewh.ieee.org/reg/3/southeastcon2013/documents/Final_SECON_2013_Hardware_Rules.pdf

REFERENCES

Page 54: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

Questions

Page 55: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

IAN TURNIPSEED

YEE-HAW

RIDE ‘EM Cowboy

Page 56: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

PREPPING FOR THE FINALS

Crack is

Whack

Watch out for

that seagull

Page 57: Final Presentation.  The Team  Competition Overview  Design Constraints & Improvements  System Testing  Timeline  Bill of Materials.

AT THE BANQUET

Shhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhh

hhhhh

We’re all

adults now