Final Design -Assignment III

download Final Design -Assignment III

of 67

description

Ethylbenzene

Transcript of Final Design -Assignment III

  • 7/14/2019 Final Design -Assignment III

    1/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 1

    UNIVERSITY OF SOUTH AFRICA

    Department of Civil and Chemical Engineering

    Amilcar J Beukes (3358-346-3)

    Chemical Process Design IV Module B: Plant Design

    CPD4M2C (Year Module)

    FINAL DESIGN REPORT III:

    Conceptual Design

    Dr. Bilal Patel 17 September 2012

  • 7/14/2019 Final Design -Assignment III

    2/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 2

    17 September 2012

  • 7/14/2019 Final Design -Assignment III

    3/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 3

    EXECUTIVE SUMMARY:

    (i) Introduction and Background Information

    The conceptual design of an ethylbenzene production facility is performed. Theindustrial production of ethylbenzene is achieved by the direct alkylation reaction

    between benzene and ethylene.

    In the production of ethyl benzene from the two reactants, benzene and ethylene, a

    byproduct (di-ethyl benzene) may be produced. The optimization process regarding

    selectivity between the two products (ethyl benzene and di-ethyl benzene) should

    favour the production of ethyl benzene rather than di-ethyl benzene. The reaction is

    carried out in a 74.22 m3 Alkylation catalytic packed-bed reactor.

    The design includes an economic viability test, together with a HAZOP analysis anda preliminary environmental impact assessment. A concise P&ID drawing is also

    included in the design which would be supported by a comprehensive control

    philosophy and a start-up and shut-down procedure.

    (ii) Objective

    The facility is to produce 100 000 metric tons per annum of ethylbenzene with a

    purity of at least 99.5 wt%. The design includes a process simulation, a HAZOP

    study and a detailed design of the alkylation reactor and one of the distillation

    columns. A preliminary environmental impact assessment is also included in thisfinal design document. The economic viability of the intended project was performed

    and included in the design.

    (iii) Process Description

    Benzene and ethylene is fed to a single packed-bed reactor where most of the

    reactants are converted to ethylbenzene. The product stream from the reactor is sent

    downstream to different separation units, where benzene is recovered and recycled

    to be re-used and to increase the overall plant conversion. A flash drum together

    with two distillation columns is used to separate unwanted material from the desiredproduct (ethylbenzene).

    (iv) Conclusions and Recommendations

    The design confirmed the possibility and economic viability of producing the

    specified amount of ethyl benzene. The PEIA additionally indicated that a facility of

    this kind would not have a negative impact on the environment nor will it infringe

    upon the social fabric of the inhabitants living in close approximation of the proposed

    plant.

    It was also found that careful optimization of the reactor operations should be done

  • 7/14/2019 Final Design -Assignment III

    4/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 4

    to enhance the overall production of ethylbenzene and to avoid wastage of costs.

    Further observations showed that a single reactor could not effectively convert the

    high ratio of benzene in the feed to ethylbenzene. A series of smaller reactors are

    therefore recommended.

  • 7/14/2019 Final Design -Assignment III

    5/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 5

    Table of Contents

    EXECUTIVE SUMMARY: ................................................................................................................... 3

    1. INTRODUCTION: ............................................................................................................................ 8

    2. LITERATURE SURVEY:................................................................................................................. 9

    2.1 Chemical Reactions: ................................................................................................................. 9

    2.2 Process Component Properties and Description:................................................................. 9

    3. DESIGN BASIS:............................................................................................................................. 11

    3.1 General Design Considerations: ........................................................................................... 11

    3.2 Design Philosophy................................................................................................................... 11

    3.2.1 Key Assumptions:............................................................................................................. 12

    3.2.2 ChemCad Operations: ..................................................................................................... 12

    4. OVERALL PROCESS DESCRIPTION:...................................................................................... 12

    4.1 Process Simulation:................................................................................................................. 13

    5. ETHYL BENZENE PRODUCTION FACILITY, UNIT 100. ...................................................... 14

    5.1 Process Notes:......................................................................................................................... 14

    5.2 Process Description: ............................................................................................................... 15

    5.3 Process Units: .......................................................................................................................... 17

    5.3.1 The Benzene Feed Drum (V-101) ................................................................................. 17

    5.3.2 The Fired-Heater (H-101)................................................................................................ 175.3.3 The Alkylation Reactor (R-101):..................................................................................... 19

    5.3.4 Flash Drum (V-101): ........................................................................................................ 21

    5.3.5 Benzene Tower (T-101): ................................................................................................. 22

    5.3.6 Ethylbenzene Column (T-102): ...................................................................................... 23

    5.3.7 Liquid Pumps (P-10i, i = 1, 2, 3): ................................................................................... 23

    6. START-UP AND SHUT-DOWN PROCEDURES: .................................................................... 26

    6.1 Start-Up Procedure: ................................................................................................................ 27

    6.2 Shut-Down Procedure: ........................................................................................................... 27

    7. EQUIPMENT LIST:........................................................................................................................ 28

    8. UTILITY REQUIRMENT SCHEDULE: ....................................................................................... 28

    9. PRELIMINARY ENVIRONMENTAL IMPACT ASSESSMENT: .............................................. 29

    10. HAZOP STUDY: .......................................................................................................................... 30

    11. DETAILED DESIGN:................................................................................................................... 35

    11.1 Reactor Design .......................................................................................................................... 35

    11.2 Benzene Tower Design: ............................................................................................................. 40

  • 7/14/2019 Final Design -Assignment III

    6/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 6

    THE TOWER PLATE SPECIFICATIONS: ............................................................................................ 40

    12. PLANT COST ESTIMATIONS:.................................................................................................. 41

    12.1 Capacity Effect on Equipment Costs:................................................................................. 41

    12.2 Labour Requirements: .......................................................................................................... 43

    12.3 Plant Operation Time: ........................................................................................................... 44

    11.4 Economic Analysis: ............................................................................................................... 45

    11.4.1 Cost Estimation: ............................................................................................................. 45

    12.4.2 Manufacturing Costs:..................................................................................................... 47

    12.4.3 Profitibility ........................................................................................................................ 48

    13. CONCLUSIONS: ......................................................................................................................... 50

    REFERENCES ................................................................................................................................... 50

    APPENDIX: ......................................................................................................................................... 51

    PFD with Stream Table: ................................................................................................................ 51

    Centrifugal Pump (P-101 A/B) DATA SHEET: .......................................................................... 51

    BENZENE TOWER DESIGN: ...................................................................................................... 52

    Design Calculations of a Benzene Tower: ............................................................................. 52

    CAPCOST SPREADSHEET: ....................................................................................................... 61

    Reactor Design: (PolyMath Program Output Report) ............................................................... 66

    Table 1: Commercial Process used to Produce Ethyl Benzene ................................................... 9

    Table 2: Equipment List..................................................................................................................... 28

    Table 3: PEIA ...................................................................................................................................... 30

    Table 4: HAZOP Study on REACTOR............................................................................................ 33

    Table 5: HAZOP Study on FLASH DRUM ..................................................................................... 34

    Table 6: HAZOP Study on BENZENE TOWER ............................................................................ 34

    Table 7: PolyMath Program .............................................................................................................. 38

    Table 8 Spec Sheet Benzene Tower.............................................................................................. 40

    Table 9: CEPCI in 2012 (Turton et al.)............................................................................................ 42Table 10: Labour Costs ..................................................................................................................... 44

    Table 11: Equipment Cost ................................................................................................................ 46

    Table 12: Costs Structure ................................................................................................................. 47

    Table 13: Total Annual Costs ........................................................................................................... 48

    Figure 1: Block Flow Process Diagram for the Production of Ethyl Benzene ........................... 13

    Figure 2: PFD from ChemCad simulation ...................................................................................... 14

    Figure 3: Stream Table from ChemCad.......................................................................................... 14

    Figure 4: P&ID Diagram for the Production of Ethyl Benzene via the Alkylation of Benzene 16

  • 7/14/2019 Final Design -Assignment III

    7/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 7

    Figure 5: Benzene Feed Drum (V-101) .......................................................................................... 17

    Figure 6: Fired-Heater (H-101)......................................................................................................... 18

    Figure 7: Alkylation Reactor (R-101) ............................................................................................... 19

    Figure 8: Heat Exchanger (E-101) and Flash Drum (V-101) ....................................................... 21

    Figure 9: Benzene Tower (T-101) ................................................................................................... 22

    Figure 10: Ethylbenzene Column (T-102) ...................................................................................... 23

    Figure 11: Liquid Pumps (P-10i, i = 1, 2, 3) ................................................................................... 24

    Figure 12: Flow Rate Profile along length of Reactor................................................................... 37

    Figure 13: Flow Rate Profiles ........................................................................................................... 38

    Figure 14: Drawing of Alkylation Reactor with Dimensions ......................................................... 39

    Figure 15: Benzene Tower Dimensions.......................................................................................... 41

    Figure 16: Extrapolation of Index..................................................................................................... 43

    Figure 17: CEPCI (courtesy of www.EngineeringToolBox.com ) ............................................... 43

    Figure 18:Utility Schedule and Costs .............................................................................................. 63

  • 7/14/2019 Final Design -Assignment III

    8/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 8

    1. INTRODUCTION:

    A conceptual design of an ethylbenzene production facility is to be performed. The

    industrial production of ethyl benzene is achieved by the direct alkylation reaction

    between benzene and ethylene. The ethyl benzene is then used as the primary raw

    material in the production of styrene. Styrene is converted into polystyrene bypolymerization. Polystyrene in turn is an important polymer in the chemical industry.

    This design, however, focuses on the production of ethyl benzene only.

    In the production of ethyl benzene from the two reactants, benzene and ethylene, a

    byproduct (diethyl benzene) may be produced. The optimization process regarding

    selectivity between the two products (ethyl benzene and di-ethyl benzene) should

    favour the production of ethyl benzene rather than di-ethyl benzene. The reaction is

    normally performed in the presence of an acidic catalyst.

    The design further includes an economic viability test, together with a HAZOPanalysis and a preliminary environmental impact assessment. A concise P&ID

    drawing is included in the design which would be supported by a comprehensive

    control philosophy and a start-up and shut-down procedure.

  • 7/14/2019 Final Design -Assignment III

    9/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 9

    2. LITERATURE SURVEY:

    Commercially, ethyl benzene is produced by vapour or liquid phase alkylation of

    benzene with ethylene (P. K. Sahoo et al.,2011). The reaction type can be classified

    according to the catalyst used. Two type of catalysts are commonly used, namely a

    zeolite-based or a Lewis acid catalyst. The catalyst type will also dictate the bi-products produced.

    Table 1 shows the different processes available to produce ethyl benzene on

    industrial scale.

    Table 1: Commercial Processes used to Produce Ethyl Benzene (SRI Consulting, 1999)

    2.1 Chemical Reactions:The direct alkylation reaction between benzene and ethylene produces the

    ethylbenzene in the presence of an acidic catalyst. The reaction is shown below:

    C6H6 + C2H4 C6H5C2H5 (reaction 1)

    Benzene ethylene ethyl benzene

    The reaction between benzene and ethylene may also produce a further reaction

    between ethylene and ethyl benzene to produce the undesired product, di-ethyl

    benzene, according to the following reaction:

    C6H5C2H5 + C2H4 C6H4 (C2H5)2 (reaction 2)

    Ethyl benzene ethylene di-ethyl benzene

    Other side reactions are not included in this design.

    2.2 Process Component Properties and Description:

    2.2.1 Benzene:

    Benzene chemically defined by the formula C6H6 and classed in the hydrocarbon

    family because it contains only carbon and hydrogen atoms. It can be naturally found

    Liquid-phase, aluminum chloride catalyst

    Liquid-phase, aluminum chloride catalyst

    Liquid-phase, aluminum chloride catalyst

    Liquid-phase, boron trifluoride catalyst

    Separation from C8 aromatics:

    Distillation (superfractionation) Badger

    Eurotecnica

    UOP

    Developer

    Alkylation of benzene with ethylene

    Vapour-phase, zeolite-catalyst (Appl to this Design)

    Liquid-phase, zeolite catalyst

    Extraction and purification

    Liquid-phase adsorption

    Monsato

    Union Carbide/Badger

    Petroflex

    UOP

    Mobil/Badger

    Lummus Crest/Unocal/UOP

    Process Type/Technology

  • 7/14/2019 Final Design -Assignment III

    10/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 10

    in volcanoes and Forest fires. Industrially it is used as a solvent in the manufacture

    of paints and products such as dyes, detergents, nylon, plastics, drugs and

    pesticides. Benzene is also a byproduct of the coking process during steel

    production. Being a natural ingredient of crude oil, it is known as the most basic

    petrochemical.

    It is characterized as aromatic because of its sweet smell. It is a colourless highly

    flammable gas which evaporates into the air very quickly and dissolves slightly in

    water. Benzene boils at 80.1C (176.2F) and freezes at 5.45.5C (41.7 41.9F).

    2.2.2 Eth ylen e:

    Ethylene is chemically defined by the formula C2H4 is one of the simplest

    unsaturated hydrocarbons. Being a natural plant hormone it is widely used in the

    agricultural industry to force fruit to ripen. The other use of ethylene is in the

    manufacture of plastics, such as packing films, wire coatings, and squeeze bottles.

    Ethylene melts at -169 degrees Celsius and boils at -104 degrees Celsius. It is

    characterized as a colourless , flammable , sweet and musky smelling gas. Ethylene

    is also known as Ethene and can be produced in two ways:

    1. Through fractional distillation it can be extracted from natural gas.

    2. Through fractional distillation it can be extracted from crude oil.

    Ethylene is the raw material used in the manufacture of polymers such as

    polyethylene (PE), polyethylene terephthalate (PET), polyvinyl chloride (PVC) and

    polystyrene (PS) as well as fibers and other organic chemicals.

    2.2.3 Ethy l b enzene:

    Ethyl benzene is an organic compound with the formula C6H5C2H5 => C8H10. This

    aromatic hydrocarbon is important in the petrochemical industry as an intermediate

    in the production of styrene, which in turn is used for making polystyrene, a common

    plastic material.

    It melts at -95 C and boils at 136 C. Ethyl benzene is a clear colourless aromatic

    liquid which evaporates easily and is highly flammable. Ethyl benzene is used as asolvent in the coatings industry for paints, lacquers, and varnishes. It can be

    detected in air, water and soil.

  • 7/14/2019 Final Design -Assignment III

    11/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 11

    3. DESIGN BASIS:

    The objective of this design document is to demonstrate a design of an ethyl

    benzene production facility that will produce 100 000 metric tons of ethyl benzene

    per annum. The ethyl benzene product should have a purity of at least 99.5 weight

    %. Being the first unit erected at the plant, the plant would therefore be located atunit 100 of the facility.

    The raw materials used in the production process will be limited to a pure benzene

    stream available at 1 bar and 25 C as well as an ethylene stream available at 1 bar

    and 25 C containing 5 mol % ethane. Periodic shut-downs and maintenance would

    mean that annual plant operations would be reduced to 330 days per year.

    3.1 General Design Considerations:

    The ethyl benzene production plant will have to meet the following design

    requirements:

    Location UNIT 100

    Available Utilities

    LP Steam @ 618 kPa saturated

    MP Steam @ 1135 kPa saturated

    HP Steam @ 4237 kPa saturated

    Fuel Gas external supply and internal production

    Electricity external supply and internal production

    Boiler Feed Water

    Cooling Water @ 516 kPa and 30 C

    Plant Control Designed to use Closed and Open-loop

    control

    Unattended control operations to dominate

    Plant Design Life Expectancy 30 years

    Process/Plant Safety NOSA and periodic Hazop Analysis

    Considerations

    Process Water Municipal Potable Water Supply

    3.2 Design Philosophy

    The design is limited to a preliminary study and analysis of the production of ethylbenzene used in the chemical industry. The design approach was to use thecomputer package ChemCad, PolyMath and Microsoft Excel to perform the energyand material balances over the unit processes and to determine most of the keyparameters that influences the processes. The operating parameters included thefollowing:

    the operating temperatures the feed composition, amounts and conditions to the plant

    available utilities

  • 7/14/2019 Final Design -Assignment III

    12/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 12

    Most of the data was obtained from literature as well as the prescribeddocumentations made available on MyUnisa. The assumptions made are clearlystated and justified where needed. A preliminary process flow diagram (PFD) isincluded to give a visual indication of the process.

    The production capacity of the production facility is provided in the user specificationdata supplied.

    3.2.1 Key Assumptions:

    The following key assumptions were made with regards to the ChemCad simulation:

    It was assumed that the reactor achieved a 98 % conversion of benzene,according to the reaction 1 above

    The alkylation reactor was assumed to be adiabatic Flow rates were assumed to be constant with negligible fluctuations in stream

    compositions

    Impurity levels in all streams were assumed to be negligible or non-existent,except were stated otherwise

    3.2.2 ChemCad Operations:

    ChemCad was used to perform the material balances over the entire process.

    4. OVERALL PROCESS DESCRIPTION:

    Benzene and ethylene feed streams are fed to a reactor to produce ethyl benzene. A

    conversion of 98 % for benzene is achieved in the reactor. The reactions take place

    in an adiabatic reactor. Non-condensable gases in the reactor effluent are separated

    from the mixed liquids in a phase separator. The ethyl benzene product and theunreacted benzene are then separated by distillation in the distillation column

    downstream from the separator. The overhead from the distillation column contains

    mostly benzene which is recycled back as reactor feed. Figure 1 shows a block flow

    diagram of the process.

  • 7/14/2019 Final Design -Assignment III

    13/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 13

    Figure 1: Block Flow Process Diagram for the Production of Ethyl Benzene

    4.1 Process Simulation:

    A ChemCad simulation was performed on this design problem. The design basis

    was used to perform typical optimization simulations of the design parameters.

    In the simulation, a stoichiometric reactor was used with a 98% conversion of

    benzene. Only the main benzene-ethylene reaction was included, since it was

    assumed that there were no other reactions taking place and that the process

    conditions was favourable to assume same.

    A Flash Drum was chosen for the phase separation and a distillation column was

    chosen for the benzene tower. All of the above is subject to changes in the

    consequent phases of this design problem. Optimization of the above will also be

    done.

    ReactorPhase

    Separator

    Benzene Tower

    Conversion

    98% Benzene

    Benzene

    Ethylene

    Mixed liquids

    Mixed gases

    Ethylbenzene

    Recycled Benzene

    Primary Reaction: C6H6C + C2H4 C6H5C2H5 Di-Ethylbenzene

    EthylBenzeneColumn

    Secondary Reaction: C6H5C2H5 + C2H4 C6H4(C2H5)2

  • 7/14/2019 Final Design -Assignment III

    14/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 14

    Figure 2: PFD from ChemCad simulation

    Figure 3: Stream Table from ChemCad

    5. ETHYL BENZENE PRODUCTION FACILITY, UNIT 100.

    5.1 Process Notes:

    Ethyl benzene is commonly used in the production of styrene, a precursor in the

    production to polystyrene and many other copolymers of industrial importance.

    Industrially, ethyl benzene is produced by the direct alkylation reaction of benzene

    with ethylene in the presence of an aluminum chloride catalyst or a zeolite catalyst.

    The vast majority of ethyl benzene alkylation units are performed in an adiabatic

    reactor. Most commonly two-or-more reactors are used in series with inter-stage

    cooling accompanied by the relevant heat exchangers. Additionally, to avoid

    undesired side reaction or undesired products, a benzene-ethylene feed ratio of at

    FLOW SUMMARIES:

    Stream No. 1 2 3 4 5 6 7 8 9 10

    Stream Name benzene recycle

    Temp C 25 25 15.874 400 696.7777 70 70 70 134.3185 44.439

    Pres bar 1.1 1.1 1.1 0.9 2 1.1 1.1 1.1 1.1 1.1

    Enth MJ/h 3.14E+05 2.91E+05 6.60E+05 1.47E+06 1.47E+06 3.35E+04 -2.07E+04 5.43E+04 7.93E+04 5.52E+04

    Vapor mass frac. 0 1 0 1 1 0 1 0 0 0

    Total kmol/h 6400.9 6393.2 14248.6 14248.3 8174.7 8174.7 400.4 7774.3 6319.9 1454.4

    Total kg/h 500000.0 180000.0 802943.1 802921.0 802915.0 802915.0 16864.8 786050.0 663107.0 122943.1

    Total std L m3/h 565.356 513.793 1218.744 1218.719 935.086 935.086 35.229 899.857 760.261 139.595

    Total std V m3/h 143467.54 143295.5 319362.38 319355.7 183224.95 183224.96 8974.48 174250.49 141651.15 32599.33

    Flowrates in kg/h

    Benzene 500000.029 0 587611 587585 113154.499 113154.513 3674.039 109480.507 21870.008 87610.438

    Ethylene 0 170387.792 170387.792 170387.792 0 0 0 0 0 0

    Ethylbenzene 0 0 35329.806 35332.812 680145 680145 3578.555 676566.302 641237 35329.799

    Ethane 0 9612.215 9615.033 9615.032 9615.032 9615.032 9612.214 2.818 0 2.818

  • 7/14/2019 Final Design -Assignment III

    15/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 15

    least 8:1 should be considered. The most prominent undesired product is di-ethyl

    benzene.

    5.2 Process Description:

    The P&ID Diagram of the ethyl benzene process is shown in Figure 4. A pure stream

    of benzene is mixed with an ethylene and benzene-rich recycled stream. The mixedstream is sent through a fired heater (H-101) where it is brought to the reaction

    temperature of 400 C. The mixed stream then enters as the feed to an adiabatic

    packed-bed reactor (R-101). The elevated temperatures mean that the reaction

    inside the reactor takes place in the gas phase. The reaction is exothermic.

    The effluent from the reactor is passed through the heat exchanger (E-101), where it

    is cooled to 80 C prior to a flash drum (V-101). The inert ethane, unreacted benzene

    and ethylene, together with the ethyl benzene product are separated in the flash

    drum. The overhead from the flash drum is received as fuel gas while the condensed

    liquid is sent to a distillation column, the benzene tower (T-101). This means that all

    the bottoms from the flash drum are sent to the benzene tower where the unreacted

    benzene is sent back to the feed stream as recycled feed to the reactor.

    The ethyl benzene is captured in the bottoms of the tower.

  • 7/14/2019 Final Design -Assignment III

    16/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 16

    Figure 4: P&ID Diagram for the Production of Ethyl Benzene via the Alkylation of Benzene

    H-101FiredHeater

    R-101Reactor

    E-101ReactorEffluentCooler

    V-102FlashDrum

    T-101BenzeneTower

    E-104Condenser

    E-103TowerKettleReboiler

    UNISA

    D

    C

    B

    A

    D

    C

    B

    A

    6 5 4 3 2 1

    TITLE: PFD of EthylbenzeneManufacturing Process

    Department: CHEMICAL ENGINEERING

    SCALE: A4

    UNIT: 100

    DATE: September 2012CPD4M2CAmilcar J BeukesPlant Design

    87

    1

    2

    9

    Benzene

    Ethylene

    Fuel Gas

    Di-ethylbenzene

    R-101

    V-102

    T-101

    3

    6

    4

    Air

    Natural Gas

    E-101

    E-104

    E-103

    H-101LIC V-101

    5

    V-101BenzeneFeedDrum

    TC

    LC

    PC

    FC

    LCLC

    AC

    FC

    AC

    TC

    AC

    PC

    P-102 A/B

    P-101 A/B

    ACO2

    1

    2

    3

    1

    T-102

    E-106

    E-105

    Ethylbenzene

    TC

    LC

    PC

    FC

    LC

    AC

    FC

    3

    1P-103 A/B

    E-102

    V-103V-104

    2

    1

    4

    5

    1 13

    C-101Compressor

    E-102TowerFeedHeater

    V-103RefluxDrum

    P-101 A/BTowerBottomsPump

    T-101EthylBenzeneColumn

    E-106Condenser

    E-105ColumnKettleReboiler

    E-102ColumnFeedHeater

    V-104RefluxDrum

    v1

    v2

    v3

    v4

    v5

    v6

    v7

    v8

    v9v10

    v11 v12

    v13

    v14v15

    v16 v17

    v18

    1 1

    1

    12

    1113

    14

    15

    10

    CODE DESCRIPTION

    1

    2

    3

    4

    5

    Chemical sewer drainage

    Sampling Port

    Vent to Flare

    Cooling Water

    Heating Water

    5

    PC

    3

    FFC

    AC

    FC

  • 7/14/2019 Final Design -Assignment III

    17/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 17

    5.3 Process Units:

    5.3.1 The Benzene Feed Drum (V-101)

    The inclusion of inventories in chemical plants is very important. In cases where

    major temporary disruption of flows occur, operations may resume unperturbed.

    These periodic cases may include late delivery of feed material to a plant, individualunit shut-downs for mandatory maintenance. The disadvantage is that large

    inventories may become costly, especially if the expected fluctuations in feed

    material are for a long period.

    The main purpose for the Benzene Feed Drum is to allow adequate mixing of the

    pure benzene feed and the recycled benzene that is routed back from the Benzene

    Tower.

    Figure 5: Benzene Feed Drum (V-101)

    CONTROL PHILOSOPHY:

    The level in the Benzene Feed Drum is to be controlled by adjusting the benzene

    feed flow into the vessel. An averaging level control strategy is applied so that the

    level remains within specified limits. This control strategy dictates that the

    manipulated flow should however not experience rapid variations that have a

    significant magnitude, which may cause irreparable damage to the equipment. The

    reason for this control strategy is the fact that slight variations in the level are notgoing to cause downstream problems. Tight level control is therefore not necessary

    for the feed drum, to satisfy the control objectives.

    5.3.2 The Fired-Heater (H-101)

    The primary purpose of the fired heater is topre-heat the feedstream to the reactor.

    Combustion reactions are taking place inside the heater. Air and fuel gasses are

    used to supply the heat to the burner. The air-to-gas ratio is important for the

    effective combustion of the gases. Air is normally supplied in excess, to allow for all

    the fuel gasses to be used, and hence the term complete combustion. Typical

  • 7/14/2019 Final Design -Assignment III

    18/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 18

    combustion gasses include the following, amongst others:

    CO2

    H2O

    CO

    SO2

    These gases may cause environmental problems and should be closely monitored.

    The reason for using natural gases to burn in air is the corresponding vast amount of

    heat energy that it produces.

    Figure 6: Fired-Heater (H-101)

    CONTROL PHILOSOPHY:

    The inlet temperature to the downstream reactor is of critical importance for the

    effective conversion of the specified reactants to produce high quality ethylbenzene.The control strategy for the fired heater would be to tightly control the outlet

    temperature (this temperature would also be the inlet temperature to the reactor).

    This control strategy is coupled in a cascade control loop downstream and would

    therefore be discussed further below under the reactor section.

    The heat supplied or generated inside the heater will greatly depend on the air-to-

    gas ratio that is fed to the heater. It is for this reason that the heater outlet gas

    composition is controlled by a single feedback loop which would allow for the

    adjustment of the air inlet valve. This would ensure the most effective combustion to

  • 7/14/2019 Final Design -Assignment III

    19/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 19

    take place, while avoiding excess and unnecessary natural gas usage.

    5.3.3 The Alkylation Reactor (R-101):

    The alkylation reactor used in the design is a vapour-phase adiabatic reactor, with a

    reaction temperature of approximately 400 C. The following exothermic reaction

    takes place inside the reactor:

    C6H6 + C2H4 C6H5C2H5

    benzene ethylene ethyl benzene

    A major side reaction also takes place, but could be avoided by adjusting relevant

    process conditions. The undesired di-ethyl benzene is produced according to the

    following reaction:

    C6H5C2H5 + C2H4 C6H4 (C2H5)2

    Ethyl benzene ethylene di-ethyl benzene

    The reactor effluent is cooled in a heat exchanger that uses process cooling water. A

    conversion of 98% for benzene is assumed to take place inside the reactor.

    Figure 7: Alkylation Reactor (R-101)

    2

    Ethylene

    R-101

    6

    4

    Air

    Natural Gas

    H-101

    5

    AC

    TC

    AC

    O2

    2

    1

    v2

    v3v4

    v5

    PC

    3

    FFC

    AC

    11.5 Sch 45 SS

    PC

    PT

    PAHPAL

    101

    101101

    FC

  • 7/14/2019 Final Design -Assignment III

    20/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 20

    CONTROL PHILOSOPHY:

    The design criteria would be directed by a small range variation in the inlet

    temperature to the reactor. Tight control of the reactor inlet temperature would

    therefore be required. In addition to the inlet temperature requirements would be the

    percentage conversion inside the reactor. The reactor effluent composition shouldtherefore also be controlled.

    A cascade control strategy is used to control the reactor outlet composition, the

    reactor temperature and the fuel flow to the burner. A change in the fuel flow to the

    fired heater influences the feed temperature to the reactor which influences the

    reactor temperature (and the conversion inside the reactor) which further indirectly

    influences the reactor outlet composition. A three-level cascade control over the

    reactor would attenuate such a disturbance on the fuel flow to the fired heater. This

    would allow the outlet composition, the temperature inside the reactor and the fuel

    flow to the fired heater to be controlled.

    The reactor temperature and the fuel flow to the fired heater would act as the

    secondary controlled variables, while the effluent composition would act as the

    primary controlled variable. In cascade control, an additional secondary measuredprocess variable is used which has the characteristic of indicating the occurrence of

    the key disturbance (s). This means that should the outlet composition deviate from

    the set point, the fuel flow to the fired heater would be adjusted, which would mean

    that an adjustment to the reactor temperature would be initiated, which would bring

    the outlet composition back to its set point.

    The cascade controller would be effective in attenuating any variations in feed

    temperatures to the reactor as well as controlling the primary composition controller.

    The dynamics for the composition control will thus be greatly enhanced in

    comparison with a single feedback loop control strategy. A cascade control strategy

    is only employed if a feedback loop strategy would be too slow and if one or more

    secondary measured variables are available.

    A sudden increase in the pressure inside the reactor could pose a safety risk as well

    as potential damage to process equipment. It is therefore necessary to control the

    pressure in the reactor as well. The pressure is released through a pressure releasevalve that is vented to a flare that may incinerate the toxic gases released. The

    pressure release valve is controlled by a pressure controller, by means of a simple

    feedback loop.

    The reactor is also equipped with high and low pressure alarms. Should the pressure

    in the reactor drop below 1.2 bar, the low-pressure alarm would go off. Should the

    pressure inside the reactor increase above 3.5 bar the high-pressure alarm would be

    triggered. The alarms will give a digital indication as well as a manual (high pitched

    sound) indication. This will allow operators in the control room as well as operators at

  • 7/14/2019 Final Design -Assignment III

    21/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 21

    the plant itself to be aware of the situation.

    It is further important for the feed ratio to be adequate to produce enough of the

    desired product and to avoid excess production of unwanted by-products (such as

    di-ethylbenzene). For this reason, a cascade ratio control loop is included in the

    control strategy. A composition controller is used to control the feed ratio of benzeneversus ethylene to the reactor, while a ratio flow controller is used to control the

    amount of ethylene directed to the reactor feed stream.

    5.3.4 Flash Drum (V-101):

    The flash drum is used as a phase separator. The condensable gases from the

    reactor (benzene and ethyl benzene) are separated from the non-condensable

    gases. The bottom condensed liquids are then sent to the benzene tower. The

    overhead gases are captured as fuel gases that are used in other process units

    upstream and downstream.

    The flash process includes both the phase separator (V-102) and the heat

    exchanger (E-101).

    Figure 8: Heat Exchanger (E-101) and Flash Drum (V-101)

    CONTROL PHILOSOPHY:

    The control objectives of the Flash Drum, is to control the bottoms composition, the

    level and the pressure in the drum. Three single loop controllers are used to control

    the three parameters of concern. Due to the sensitive nature of the phase separation

    process and the high dependence on the feed temperature to the Flash Drum, the

    bottoms composition is controlled by adjusting the cooling water inlet flow valve to

    the Reactor Effluent Cooler (E-101).

    The level in the drum is controlled by a single level controller that adjusts the valve

    that allows the bottoms to flow to the Benzene Tower. The pressure inside the drum

  • 7/14/2019 Final Design -Assignment III

    22/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 22

    is controlled by a single loop pressure controller that adjusts the top outlet valve.

    5.3.5 Benzene Tower (T-101):

    All the benzene and lighter components are separated from the heavier ethyl

    benzene. The lighter gases are recycled to the feed of the reactor, while the ethyl

    benzene together with the other by-products is captured as bottoms liquid.

    Figure 9: Benzene Tower (T-101)

    CONTROL PHILOSOPHY:

    The dynamics of the Benzene Tower is such that long dead times and long analyser

    delays may be expected. A myriad of controllers may be required to adequately

    control the relevant parameters to satisfy the design objectives of such a tower. It is

    for this reason that two cascade control loops are employed and three single loop

    controls.

    The level inside the bottom part of the tower is controlled by adjusting the bottomsoutlet valve. The bottoms composition is controlled as the primary controlled variable

    in cascade control loop where the feed to the Tower Reboiler (E-103) act as the

    secondary controlled variable. This allows for a consistently high quality separation

    process inside the tower.

    The temperature inside the tower is controlled via a cascade control system that

    uses the reflux flow to the tower as secondary variable, while adjusting the reflux

    valve to the tower. A level controller is also used to control the level in the reflux

    drum, which is situated after the condenser. The pressure in the overhead is then

    controlled by adjusting the valve after the condenser.

  • 7/14/2019 Final Design -Assignment III

    23/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 23

    This control strategy allows for safe, effective and efficient operations of the Benzene

    Tower.

    5.3.6 Ethylbenzene Column (T-102):

    The bottoms product from benzene tower (T-101) is sent to ethylbenzene column (T-

    102). In the ethylbenzene column, the ethylbenzene is recovered as a top productand the di-ethylbenzene is collected in the bottoms liquid stream.

    Figure 10: Ethylbenzene Column (T-102)

    CONTROL PHILOSOPHY:

    The control strategy for the Ethylbenzene Column is similar to that of the Benzene

    Tower. Please see above.

    5.3.7 Liquid Pumps (P-10i, i = 1, 2, 3):

    The best choice of pump for transporting liquid, such as benzene, ethylene and

    ethylbenzene is the centrifugal pump. It is a simple concept of converting electrical

    energy into kinetic energy and thereby creating pressure used to transport a fluidwhere it is needed. The kinetic energy conversion is actualized through the rotational

    acceleration of the impeller. The rotating action creates a suction that moves the

    water in continuous pockets, creating a low pressure is at the inlet of the pump and

    an area of high pressure at the exit.

    The kinetic energy that is created and used to transport the fluid is proportional to the

    velocity with which the fluid exits the pump i.e. the greater the energy the fluid exit.

    This was formulated by the Dutch-Swiss mathematician, Daniel Bernoulliin his well-

    known formula, the Bernoulli Equation.

  • 7/14/2019 Final Design -Assignment III

    24/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 24

    Figure 11: Liquid Pumps (P-10i, i = 1, 2, 3)

    The start-up procedure can be given in point form:

    Make sure the immediate upstream process unit(s) has adequate feed fluid to

    avoid cavitations

    Ensure upstream valves are sufficiently open before pump start-up

    Before starting the pump, allow the fluid to wet the inside of the pump casings

    While wetting the pump, open the airing bolt to allow trapped air bubbles to

    escape

    Start-up the pump

    Monitor the pump for a few minutes after extended periods of shut-down

    Downstream valves should be opened slowly to avoid pressure bursts that may

    damage the pump and/or other process units, equipment and instrumentation

    Shut-dow n proc edure:

    The procedure starts with slowly closing the furthest discharge valve and

    consecutively moving backwards up to the closest valve to the pump. Switch the pump motor off

    Close the upstream suction valves

    Maintenance:

    Centrifugal pump operations may encounter three general problems:

    Inadequate design

    Negligent operations

    Poor maintenance

    The general pump maintenance procedure for operators can be summarized into

    four basic steps, namely:

    1. Switch pump of and remove pump from system, by disconnecting all piping and

    electrical connections

    2. Disassemble the pump. Clean all parts and components.

    3. Drain all fluid from the bearing housing and inspect each component. Make sure

    damaged components are replaced

    4. Reassemble all components

  • 7/14/2019 Final Design -Assignment III

    25/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 25

    Operat ion:

    Cavitation is the main concern when operating a centrifugal pump. Cavitation occurs

    when the pressure of a liquid is rapidly decreased below its vapour pressure as a

    result of a flow phenomenon. The operational procedure to prevent cavitation is as

    follows.

    Increase the pressure at the at the suction head of the pump

    The temperature liquid that is being pump must be reduced

    The flow rate as well as the head losses in the pump suction piping can be

    reduced

    Reduce the speed of the impeller

    Cavitation may cause the following damages to a pumping system:

    Damage to the pump impeller as well as degraded performance of the pump

    Vibration of the pump that results in flow and pressure disturbances

    CONTROL PHILOSOPHY

    Control strategies are important in pumping systems e specially when operating

    centrifugal pumps. Although these types of pumps are reliable, they often stop

    working. For this reason engineers design plants with back-up pumps as a standard.

    These pumps must have some form of automated control that will allow pumping

    systems to switch from a used pump that stops working to a back-up pump. Usually

    in pumping applications with adjustable speed drives and variable flow rates efficient

    control strategies is of utmost importance to throttling or bypass methods.The centrifugal pumps are all supplied with programme drive controllers to avoid

    operating pumps at speeds that may cause equipment damage or system

    resonances.

  • 7/14/2019 Final Design -Assignment III

    26/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 26

    6. START-UP AND SHUT-DOWN PROCEDURES:

    When starting-up a catalytic reactor it is important to monitor the temperature and

    concentration profiles of the reactants and products as they approach steady-state.

    Rapid overshoots and/or undershoots in the temperature may cause reactant and/or

    product degradation. Over/Under-shoot may also be a safety hazard and cause theactivity of the catalyst to be affected. A practical stability limit may be exceeded

    when start-up overshoots are excessive. This stability limit may include upper and

    lower boundary temperatures, reactant concentrations, product concentrations

    and/or the pressure drop across the catalytic bed.

    Before any upstream process units are started, the cooling fluid must be allowed to

    flow through the condensers. In the case of brand new columns, flushing of the

    whole system should be initiated to remove any unwanted material and early

    identification of blockages. Process control devices and instrumentation should be

    installed and tested as per the dictates of the P&ID provided. An operations manualof all equipment and instrumentation should be supplied by the manufacturer or

    drawn up by the design team in consultation with the HAZOP team (referred to later

    in this document). Process control software should be supplied by a general dealer

    and all control devices should be compatible with the latest software systems in the

    market today.

    The column and tower condensers are in series with a lot of other process units. It is

    imperative that the column and tower should not be switched off before process units

    upstream is not totally turned off and no liquid-vapour is fed to the column. All valves

    and equipment should be switched off in the tested order prescribed in theoperations manual provided. The column and tower must never be open to air for

    long periods as it may cause rusting of the interior.

    Annual shutdowns of the Ethylbenzene Plant should include internal inspections of

    heat exchangers and other process units. During these periodic inspections the

    following items should be considered:

    Scaling and corrosion of equipment

    Internal lining conditions

    Tube and piping surfaces Metal thickness tests should regularly be performed

    Expansion of equipment joints

    Welding joint conditions

    General condition of the heat exchangers and the fired heater

    If tube and/or piping leakages are suspected, extensive tests must be performed to

    replace or repair such tubes and/or pipes. Record sheets should be kept to ensure

    tubes and pipes dont exceed their repair life.

  • 7/14/2019 Final Design -Assignment III

    27/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 27

    6.1 Start-Up Procedure:

    1. Close all drain and flare valves

    2. Switch the benzene feed valve (v1) to manual mode

    3. Open valve manually to allow liquid to partially fill the feed drum (V-101)

    4. Slightly open drum outlet valve (v2)5. Allow liquid to flow through the pump and fired heater (H-101)

    6. Keep air and natural gas valves closed (va and v3)

    7. Open reactor feed and outlet valves (v4 and v5) to allow fluid to wet the catalyst

    and the interior of the reactor

    8. Keep the heat exchanger (E-101) valve (v6) closed

    9. Fluid will now flow into the flash drum and through the bottoms pump (P-102 A/B)

    10. Open valve (v8) and allow fluid to flow through tower feed heater (E-102), while

    filling the benzene tower (T-101)

    11. The same procedure would follow for the ethylbenzene column

    12. Do not open the two product valves (v15 and v17)13. Switch the pumps on when the fluid reaches the two product valves (v15 and

    v17)

    14. Immediately open the two valves (v15 and v17) and

    15. Open the air and gas valves (va and v3) and start the fired heater up

    16. Make sure all other valves are open

    17. Monitor the system closely until steady-state is reached

    18. Open all heat exchanger valves to allow process cooling and heating

    19. Switch all automated control systems on

    6.2 Shut-Down Procedure:

    1. Switch all pumps off and close air and gas valves (va and v3) to fired heater (H-

    101)

    2. Open drain and flare valves to allow the process units to fully drain

    3. Switch automated control systems off

    4. Allow system to cool off by closing heat exchanger valves

    5. Close valves starting from the furthest part of the plant downstream moving back

    up until the benzene feed valve (v1) is closed

    6. Allow fluids to drain into the chemical sewer

  • 7/14/2019 Final Design -Assignment III

    28/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 28

    7. EQUIPMENT LIST:

    Table 2: Equipment List

    Identification MOC Orientation Type

    V-101 CS Horizontal

    P-101 A/B CS Centrifugal

    C-101 CS Horizontal Centrifugal

    H-101 316SS/CS Vertical Fired

    R-101 SS/Refractory Vertical Adiabatic

    E-101 316SS/CS Shell&Tube

    V-102 SS Vertical

    P-102 A/B CS

    E-102 CS/SS Shell&Tube

    T-101 SS Vertical DistillationE-103 316SS Kettle

    E-104 SS Shell&Tube

    V-103 CS Horizontal

    P-103 A/B CS Centrifugal

    E-105 CS Shell&Tube

    T-102 SS Vertical Distillation

    E-106 CS Kettle

    E-107 SS Shell&Tube

    V-104 SS Horizontal

    Tower Feed Heater

    Benzene Tower

    EQUIPMENT

    Benzene Feed Drum

    Heater Feed Pump

    Ethylene Compressor

    Fired Heater

    Column Reboiler

    Column Condenser

    Column Reflux Drum

    Tower Reboiler

    Tower Condenser

    Tower Reflux Drum

    Tower Bottoms Pump

    Ethylbenzene Column Feed Heater

    Ethylbenzene Column

    Alkylation Reactor

    Reactor Effluent Cooler

    Flash Drum

    Flash Bottoms Pump

    8. UTILITY REQUIRMENT SCHEDULE:Name Total Module Cost Grass Roots Cost Utility Used Efficiency Actual Usage Annual Utility Cost

    C-101 9,100,000$ 13,000,000$ NA

    E-101 42,094$ 55,000$ Cooling Water 18500 MJ/h 52,000$

    E-102 33,600$ 43,900$ Low-Pressure Steam 1500 MJ/h 157,800$

    E-103 197,500$ 257,000$ Low-Pressure Steam 1300 MJ/h 136,700$

    E-104 359,000$ 444,000$ Cooling Water 4300 MJ/h 12,100$

    E-105 42,000$ 55,000$ Low-Pressure Steam 1500 MJ/h 157,800$

    E-106 197,500$ 257,000$ Low-Pressure Steam 1300 MJ/h 136,700$

    E-107 143,000$ 204,000$ Cooling Water 5000 MJ/h 14,000$

    H-101 2,340,000$ 3,340,000$ Natural Gas 0.9 12000 MJ/h 1,054,900$

    R-101 24,400$ 31,300$ N/A

    T-101 103,000$ 132,000$ NA

    T-102 204,000$ 250,000$ NA

    V-101 534,000$ 710,000$ NA

    V-102 208,000$ 245,000$ NA

    V-103 38,100$ 45,900$ NA

    V-104 24,600$ 32,200$ NA

    Totals 13,600,000$ 19,100,000$ 1,722,000$

  • 7/14/2019 Final Design -Assignment III

    29/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 29

    9. PRELIMINARY ENVIRONMENTAL IMPACT ASSESSMENT:

    Due to the sensitivity of setting up a chemical manufacturing plant that may be

    harmful to the environment as a whole, has led proposals for designing such plants

    to actively include detailed Environmental Impact Assessment (EIA) procedures

    which shall involve public participants. In this design document, a PreliminaryEnvironmental Impact Assessment (PEIA) will be performed.

    The PEIA is compiled as a forerunner for the EIA for the proposed Ethylbenzene

    Production Unit. The Processing plants that involve industrial scale operations would

    opt to be as close as possible to the source for the raw materials used to reduce

    astronomical costs related to the transportation and infrastructure. Also, when a lot of

    energy is required in an industrial operation, the plant should be close to an energy

    source and infrastructure. Chemical Production Plants are normally situated far from

    densely populated areas and for that reason the impact that such processes have on

    the environment is often overlooked. An increasing environmental awareness ofglobal warming and the future/present dangers posed by pollution has shed

    increasing light on the role and impact chemical processes have in the global crisis.

  • 7/14/2019 Final Design -Assignment III

    30/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 30

    Table 3: PEIA

    ITEM DESCRIPTION Risk Grade EFFECT ACTION REQUIRED

    E xc es sive heat releas ed to the environment highThe highly exothermic nature of theprocesses involved generate a lot of

    thermal energy that may escape

    Continuous monitoring of equipment isnecessary to ensure no excess ive heat losses

    Risk of fugitive emissions of toxic noxiousgases, eg. the c ombustion gases from the FiredHeater (H-101)

    high

    air quality deterioration canadversely affect the ecosy stem, thesurrounding fauna and flora as well

    as humans

    Emergency alert devices will be installed forquick detection of toxic gas emmissions,scrubbing units will be installed if needed

    Other toxic c ontaining gas emmissions aboveregulatory standards

    high

    The sulphur containing gasemmissions pose the danger ofproducing acid rain and serious

    health threats to humans

    The plantt is designed to eliminate this theat tothe environment

    Changes in water quality high

    increases in the salinity, odour,temperature, nutrients, turbudity, pHor contaminants/pollutants(eg. oils,

    toxins etc.

    Introduction of an additional water and waste-water treatment plant on-site might be

    proposed

    Ground water consumption high Depletion of ground water aquifersConsultations with local hydrology

    departments to keep ground water usagesbelow regulatory limits

    Landscape and visual disturbances low

    The Ethylbenzene plant will be builtin the vicinity of the existing Styrene

    plant boundaries which will haveminimal visual and landscape

    impact

    Proposed plant should not be extended outsidethe existing S tyrene Plant boundaries

    Affecting the exist ing demographic s of thesurrounding communities

    moderate

    The increasing influx of people fromother regions displacing the existing

    community members foremployment competition

    Employing local community members at theconstruction and operations of the proposed

    plant

    Dis rupt ions to the li vel ihood of communit y lowThe deprevation of access to the

    environment, facilities, etc.

    Keeping a continuous favourable relationshipwith the local communities and involving them

    in decision making

    Health, safety, privacy and general welfare ofcommunity members

    moderate

    Factors such as odour problems,noise, radiation, vibrations etc mayhinder the health, safety, privacyand general welfare of community

    members

    Educate and inform the relevant stakeholdersof the risks posed to them personally and sendout alerts well in advance when the problems

    may arise

    Changes in community resource low

    Local businesses may bethreatened by employment

    competition created by additionalemployment opportunities at theproposed plant with substantial

    losses in labour power

    Involving the community in employmentstrategies.

    Tourism lowTourism may suffer due to

    uninformed scares of proposedplants health risks

    Informing and involving tourism bureas of thehealth and safety issues related to the plant aswell as the environmental impact the proposed

    plant may or may not have.

    General and Endangered species moderateThreats to the habitat and resources

    of endangered species due to theconstruction the proposed plant

    Relevant documentations regarding the floraand fauna in the vicinity should be well

    researched to assess any impact the proposedplant may have on the different species and

    how to avoid it.

    In the workplace high

    Health and Safety iss ues inunfavourable working conditions,

    such as extreme heat environmentand toxic gas environments

    Draw up well researched and structured healthand safety manuals for staff, as well as

    adequate training of all relevant staff members.

    Infrastructure changes and demand lowInfrastructural changes in nearby

    residential areas may affect propertydemand

    Make provisions for additional infrastructuralconstruction rather then buying existing

    property to avoid overflooding the propertymarket

    Traffic changes lowSudden increases in traffic may

    cause time delays and frustrationsin the existing communities.

    Address future traffic prblems with localmunicipal authorities to achieve alternative

    means of transport or alternative trafficarrangements to avoid traffic congestion.

    Housing demand highHousing market may be flooded due

    to additional employmentBuild new houses for new employees.

    6. Health and safety

    7. Infrastructure, housing and traffic

    PRELIMINARY ENVIRONMENTAL IMPACT ASSESSMENT

    1. Air Quality

    2. Water Quality

    3. Lanscaping issues

    4. Socio-economic environment

    5. Fauna and Flora

    10. HAZOP STUDY:

    HAZOP is the industrialized method of identifying and preventing problems

    associated with hazardous conditions at a commercial plant, normally a chemical

  • 7/14/2019 Final Design -Assignment III

    31/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 31

    plant. The hazard identification procedure forms an integral part of design and

    operation of a new plant. The procedure is constantly repeated and revised during

    the design process to ensure safety and operability. If the design is preceded by a

    pilot study, such a study would be used to identify potential hazards and the

    significance of those potential hazards can then be assessed by means of a well-structured experiments.

    The HAZOP study is specifically employed to identify potential hazards. The design

    may be altered to eliminate some of these hazards. The main objectives of a HAZOP

    are therefore to:

    i. Identify potential hazards and/or mal-operations

    ii. Assess the most likely consequences

    iii. Recommend the most appropriate corrective actions to be taken

    For each plant a distinct HAZOP Team will be assembled to deal with hazardousconditions and problems associated with safety at the plant. The HAZOP Team Afor

    the Ethylbenzene Production Facility comprise of the following individuals:

    Project Engineer or Project Manager:

    This is the person who will manage the overall design of the new plant. All

    deliverables and important decisions vest in this person. He/she will also be

    responsible for the budget and cost estimations. It is therefore important that he/she

    be part of the HAZOP team. The identified hazardous conditions at the plant can

    then be reassessed and mitigated or eliminated by decisions taken by the Project

    Engineer together with his/her design team.

    Process, Chemical or Metal lurg ical Engin eer:

    The Process Engineer is the main person responsible for the detailed design and

    draw up of the process flow diagram and equipment selection. The in-depth

    knowledge of this individual will be critical in identifying hazardous conditions at

    specific processing units as well as knowledge of possible mitigating alternatives to

    attenuate such conditions. He/she may also estimate the likelihood of hazardous

    conditions causing damage or safety concerns.

    Comm iss ion ing Engineer:

    The initial start-up of the new plant is done under the auspices of this engineer.

    He/she may be the same person as the person in bullet number 2, above. At each

    start-up and shut-down of a chemical processing plant, non-steady state conditions

    prevail which may be a major safety and hazardous concern for the people and the

    plant equipment. The Commissioning Engineer will predict the likelihood of such

    dangers and with his theoretical knowledge and relevant experiences he/she will

    make informed decisions regarding those dangers.

    Instrumentat ion Design Engineer:

    This person will be in control of the process control systems installation. He/she will

  • 7/14/2019 Final Design -Assignment III

    32/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 32

    advise on the most appropriate control instrumentation and devices to use for the

    specific control strategies.

    Chemist :

    Chemical sampling will be important in the HAZOP study and the Chemist will be in

    control of the sampling to ensure accurate judgment regarding Hazardous material.

    Electr ical Engineer:

    The electrical engineer will be in control of all electrical equipment.

    HAZOP Expert:

    This person is normally an Environmental Scientist or a Health and Safety Officer,

    with vast experience in the operations of HAZOP studies. He/she will guide and

    manage the team accordingly. Even though this person may be lower ranked (Salary

    and Status) at the plant, he will be leading the team. It is expected that he/she lead

    the team without want or favour and with an iron fist to ensure a successful HAZOPstudy, since lives depend on this study.

    A HAZOP study was performed on the following process units:

    The Adiabatic Alkylation Reactor (R-101)

    The Flash Drum (V-102)

    The Benzene Tower (T-101)

  • 7/14/2019 Final Design -Assignment III

    33/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 33

    Table 4: HAZOP Study on REACTOR

    Page: 1 of 1

    100 Rev no.: Date:

    Meeting date:

    Material: Activity:

    Source: Destination:

    1 More of

    Sudden

    increase in

    Temperature

    Sudden increase in flow

    of air and fuel gas to

    Fired Heater, control

    dynamics too slow

    Fire in reactor,

    explosions, piping

    corrosion, damage

    caused to catalyst

    Reactor inlet

    temperature

    controlled

    2 Less of

    Sudden

    decrease in

    Temperature

    Insufficient fuel and air

    flow to Fired Heater,

    Decrease in reactant

    inlet flow

    Low reactor conversion

    Reactor inlet

    temperature

    controlled

    3 More of

    Concentration

    of Benzene in

    Effluent

    To much

    benzene in

    reactor effluent

    stream

    Low conversion due to:

    (i) low feed temperature

    or (ii) too little ethylene

    in reactor feed or (iii)

    deactivation of c atalyst

    ethyl benzene product

    not sufficiently

    produced

    Reactor outlet

    composition

    controlled. Reactor

    temperature

    controller installed.

    Ethylene feed

    controller installed

    4 More of

    Substantial

    pressure

    increase over

    catalyst bed

    Catalyst fouling and/or

    deactivation

    Ineffective conversion of

    reactants

    Reactor Pressure

    controlled

    5 Less of

    Pressure drop

    over catalyst

    bed

    Leakages

    gas escapes,

    insufficient products,

    low conversion

    Reactor Pressure

    controlled

    6 No Feed FlowNo reactants in

    inlet pipe

    Valve malfunction,

    blockages and/or

    leakages

    Empty reactor, no

    reactions taking place,

    no products

    Reactor inlet flow

    controlled

    7 More of

    Cooling fluid

    flow increase

    above required

    value

    Control valve fails open

    or controller fails and

    opens valve

    Reactor cools, reactant

    concentration buildup,

    runaway of reactor

    Temperature Alarm

    to indicate

    unwanted drop in

    reactor temperature,

    install high-flow

    alarm

    8 Less of

    Cooling fluidflow decrease

    below required

    value

    Plugged cooling line(partially), water source

    failure, control valve fail

    to respond

    Low cooling and

    reactor temperature

    increases. Possiblereactor runaway,

    reaction rate increases

    releasing additional

    heat, pressure

    increase, reactor

    explodes

    Install low-flow

    alarm, low-flow

    controller

    9 No

    Cooling fluid

    does not flow

    into reactor

    Control valve fails

    closed, cooling water

    service failure, controller

    fails and closes valve

    No cooling and reactor

    temperature increase.

    Reactor runaway. High

    buil-up of pressure may

    cause explosion.

    Equipment damage

    Install low-flow

    alarm, low-flow

    controller and water

    source failure alarm.

    Include a standby

    water source

    10 Reverse

    Cooling fluid

    flows

    backwards

    Backflow of cooling

    water due to high back

    pressure,control valve

    fails closed, cooling

    water service failure.

    No cooling and reactor

    temperature increase.

    Reactor runaway. High

    buil-up of pressure may

    cause explosion.

    Equipment damage

    Install no-flow

    alarm, no-flow

    controller. Include a

    standby water

    source. Install a

    water source

    switch. Install a no-return valve

    Actions

    Adjust fuel and air inflow to Fired

    Heater

    Increase reactant feed ratio, and

    control feed temperature by

    adjusting fuel and air to Fired

    Heater

    Possible

    Consequence Safeguards Comments

    Regenerate or replace catalyst

    Adjust fuel and air inflow to Fired

    Heater

    Frequent leakage inspections

    No flow indicator

    Stop plant and check water

    source. Check and correct water

    source failure. Switch cooling

    system to standby water source.

    Part Considered:

    R-101

    1-Aug-12

    TITLE:

    UNIT

    HAZOP Team:

    Ethylbenzene Production Plant

    A

    Adiabatic Reactor

    1-Aug-12

    Design intent:Process

    Parameter

    Carbon Steel

    Feed Tanks

    React Benzene with Ethylene

    Flash Drum (V-102)

    No.Deviation

    (Guide Word) Devia tion Possible causeElement

    (Study Node)

    Reactor

    Temperature

    Reactor

    Pressure

    Stop plant or fix valve and/or

    controller, adjust manual valve

    Cooling Coil

    Flow

    Stop plant and flush cooling pipe

    line with appropriate reagent.

    Replace and/or fix control valve

    Stop plant and check water

    source. Check and correct water

    source failure. Switch cooling

    system to standby water source.

    Replace and/or fix control valve

  • 7/14/2019 Final Design -Assignment III

    34/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 34

    Table 5: HAZOP Study on FLASH DRUM

    100 Rev no.: Date:Meeting date:

    Material: Activity:Source: Destination:

    1 more of Pressure

    too muchvapour flow,

    suddentemperature

    rise

    malfunction of ReactorEffluent Cooler (E-101)

    Corossion, equipment

    damage, pipingruptures

    Level Controller,

    Vapour OutletPressure Controller

    2 Less of No feed to flash

    drum

    Piping ruptures,upstream process

    malfunction

    Corossion, equipmentdamage

    Level Controller

    3 More of Pressure

    increase andlevel increase

    Upstream malfunctions,Reactor Effluent Cooler

    ineffective

    Corossion, equipmentdamage, piping

    ruptures

    Analys er and LevelController

    HAZOP team: APart c onsidered:

    Design intent: Stainless SteelAdiabati c React or (R-101)

    UNIT V-102

    No. Guide Word Element Deviation Possible cause Safeguards CommentsConsequence

    Benzene Tower (T-101)

    Acti ons

    1-Aug-121-Aug-12

    Flash Drum

    Phase Separation

    Flow

    Adjust bottoms outlet valve to

    allow more liquid drainage

    Open Flash Drum Vapour valve(v7) to release pressure

    Close bot toms valve (v9)

    Table 6: HAZOP Study on BENZENE TOWER

    100 Rev no.: Date:

    Meeting date:

    Material: Activity:

    Source: Destination:

    Adjust Vapour valve (v13), Decrease

    Reflux Flow to the Tower

    Adjust Vapour valve (v13), Decrease

    Reflux Flow to the Tower

    Malfunction of Tower Feed Heater (E-102),

    Leakages in Column, Temperature decrease in

    Tower

    Ineffective Production Rate,

    Bottoms Product

    Contaminated, Equipment

    Damage

    Temperature increase in TowerTower Feed Heater Malfunction

    Malfunction of Tower Feed Heater,Adjust bottoms outlet valve (v9) to allow

    level in Tower to drop

    Part c onsidered: Benzene Tower

    Design intent:Stainless Steel Phase Seperation

    Flash Drum Ethylbenzene Column

    UNIT T-101 Aug-12

    HAZOP team: A Aug-12

    Safeguards Comments Actions

    1 Less of

    Overhead

    Pressure

    Sudden

    decrease in

    Vapour Flow

    Temperature

    Controller, Pressure

    Controller in Vapour

    Product Stream

    No.Guide

    WordElement Deviation Possible cause Consequence

    2 More of

    Sudden

    increase in

    Vapour FlowVapour Stream

    Pressure Controller

    3 More of Bottoms

    Flow

    High Tower

    Level

    Equipment Damage, Ineffective

    separation of feed componentsLevel Controller

  • 7/14/2019 Final Design -Assignment III

    35/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 35

    11. DETAILED DESIGN:

    11.1 Reactor Design

    The production of ethyl benzene (EB) by the alkylation reaction of benzene (B) and

    ethylene (E) involves the following reactions:

    C6H6 + C2H4 C6H5C2H5 reaction 1

    benzene ethylene ethyl benzene

    A major side reaction also takes place, but could be avoided by adjusting relevant

    process conditions. The undesired di-ethyl benzene (DEB) is produced according to

    the following reaction:

    C6H5C2H5 + C2H4 C6H4 (C2H5)2

    Ethyl benzene ethylene di-ethyl benzene reaction 2

    The two reactions can be written in the form below:

    Reaction 1: B + E EB

    Reaction 2: EB + E DEB

    1. Mole Balances:

    Ethylene:

    Benzene:

    Ethyl benzene:

    Di-ethylbenzene:

    2. Rate Laws:

    Reaction 1:

    Reaction 2: R = 1.987 kcal/kmol.K

    k0,1 = 1.00 x 106

  • 7/14/2019 Final Design -Assignment III

    36/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 36

    k0,2 = 6.00 x 105

    E = 22 500 kcal/kmol

    Net Rates:

    3. Stoichiometry:

    The volumetric flow rate is

    We assume there is no pressure drop for the purpose of simplification and

    that the reaction is carried out isothermally. Therefore, P = P0 and T = T0, we

    also assume there is no change in the total number of moles. This means

    that:

    4. Parameter Evaluation:

    The plant is assumed to be running at 330 days/annum, to allow for periodic

    shut-down as well as maintenance, with a production rate of 100 000 metric

    tons per annum. This is equivalent to a 12 626 kg/hr ethyl benzene production

    rate. The benzene (B) and ethylene (E) is fed to the reactor at a ratio of 8:1,

    to avoid production of the unwanted di-ethylbenzene byproduct. The feed tothe reactor is therefore:

    and

  • 7/14/2019 Final Design -Assignment III

    37/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 37

    These equations are solved simultaneously using the PolyMath program. The flow

    rate profiles along the length of the reactor are shown in Figure 10 below.

    Figure 12: Flow Rate Profile along length of Reactor

    This profile indicates that a very small amount of di-ethylbenzene is produced in

    comparison to the ethyl benzene. This is mainly due to the high benzene ethylene

    feed ratio, a condition that favours the production of ethyl benzene.

    If we alter the feed ratio in such a manner that there is more ethylene than benzene

    in the feed we will observe a significant production of di-ethylbenzene. At a certain

    point in the reactor, ethyl benzene reacts (or is consumed) to such an extent that it

    starts to decrease along the remainder of the reactor. The graph below

    demonstrates this.

    0

    0.002

    0.004

    0.006

    0.008

    0.01

    0.012

    0.014

    0 2 4 6 8 10 12

    Flow

    rate(kmol/s)

    reactor length (m)

    FE

    FEB

    FDEB

  • 7/14/2019 Final Design -Assignment III

    38/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 38

    Figure 13: Flow Rate Profiles

    The graph shows the significance of keeping the ratio of benzene and ethylene in the

    feed as high as possible to ensure a high production of ethyl benzene and a low

    production of the undesired di-ethylbenzene by-product. The conversion of benzene

    will however not be sufficiently high. To remedy this, a few reactors in series would

    increase the overall conversion of the plant together with a recycled stream of

    benzene that would ensure the maximum utilization of the reactants. Table 6 shows

    the PolyMath program used to perform the calculations for the reactor.

    Table 7: PolyMath Program

    __________________________________________________________________

    ODE Report (STIFF)

    Differential equations as entered by the user[1] d(FE)/d(L) = (-rate1-rate2)*A[2] d(FB)/d(L) = (-rate1)*A[3] d(FEB)/d(L) = (rate1-rate2)*A[4] d(FDEB)/d(L) = rate2*A

    Explicit equations as entered by the user

    [1] v0 = 0.261[2] CB = FB/v0[3] T = 673[4] k1 = 1.00*10^6*exp(-22500/(1.987*T))[5] CEB = FEB/v0[6] FT0 = (2000/(8.314*673))*v0[7] k2 = 6.00*10^5*exp(-22500/(1.987*T))[8] CE = FE/v0[9] rate1 = k1*CE*CB[10] rate2 = k2*CE*CEB[11] A = 7.07[12] X = (0.0810-FB)/0.0810

    ___________________________________________________________________

    0

    0.01

    0.02

    0.03

    0.04

    0.05

    0.06

    0.07

    0.08

    0 2 4 6 8 10 12

    flow

    rate(km

    ol/s)

    reactor length (m)

    FE

    FB

    FEB

    FDEB

  • 7/14/2019 Final Design -Assignment III

    39/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 39

    Figure 14: Drawing of Alkylation Reactor with Dimensions

    The packed bed reactor has the following specifications obtained from the

    calculations done in PolyMath:

    Volume = 74.22 m3

    Diameter = 3 m

    Length = 10.5 m

    Material of Construction = Carbon Steel

    Catalyst = Zeolite (ZSM -6)

    Maximum Pressure = 3.2 bar

    Maximum allowable temperature = 480 C Maximum allowable temperature for catalyst = 550 C

    Vertical orientation

    Catalyst Packed Tubes

    3 m

    10.5 m

    Inlet

    Outlet

  • 7/14/2019 Final Design -Assignment III

    40/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 40

    11.2 Benzene Tower Design:Table 8 Spec Sheet Benzene Tower

    THE TOWER PLATE SPECIFICATIONS:

    Layout Sketches:

    SPECIFICATION SHEET OF DISTILLATION COLUMN:

    PLATE THICKNESS:

    IDENTIFICATION:NO. REQUIRED:

    TRAY TYPE:

    FUNCTION:

    PLATE I.D:

    190 mm liquid

    ACTIVE HOLES:

    PLATE PRESSURE DROP:

    Benzene Tower (T-101)1

    Sieve Tray

    Benzene separation

    0.340 m

    Continuous

    70 % maximum rate

    OPERATIONS:

    TURNDOWN RATIO:

    PLATE MATERIAL:

    HOLE SIZE:

    PLATE SPACING:

    Stainless Steel

    5 mm

    0.5 m

    5 mm1100

  • 7/14/2019 Final Design -Assignment III

    41/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 41

    Figure 15: Benzene Tower Dimensions

    12. PLANT COST ESTIMATIONS:

    CAPCOST was used to obtain cost estimates for all standard/generic equipment

    such as the reactor, heat exchangers, pumps, fired heater, distillation columns and

    process vessels. Specialized equipment costs, such as the catalyst used in the

    reactor was obtained from industrial manufacturers advertisements online.

    The design and performances of the different processing units were determinedusing vendor supply information and from previous study material. Costing

    estimations were performed using commercially available software such as

    CAPCOST and vendor supply information. All the cost estimates use a 2nd quarter

    2012 basis. The operating costs were determined from the process material and

    energy balances together with manufacturers standard costs.

    12.1 Capacity Effect on Equipment Costs:

    The current equipment purchase costs can be obtained from the relation between an

    attribute of the equipment that is related to the capacity of the unit and is given in the

    equation below (Turton et al, 2009):

    ()

    With A = the equipment cost attribute

    C = the purchased cost

    n = cost exponent

    The subscripts a and b are related to the required attribute and the base attribute,

  • 7/14/2019 Final Design -Assignment III

    42/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 42

    respectively. In short, these types of correlations are used to determine cost

    estimates for equipment through the use of past purchasing costs data, by updating

    the present equipment unit with respect to its capacity attribute. The correlation

    below is also taken from the Turton textbook and include the decreasing effect that

    inflation has on equipment purchasing costs. This correlation is heavily dependenton time, since inflation is the erosion in the purchasing or buying power of money.

    The cost estimate is therefore calculated taking into consideration the changing

    conditions in the economy.

    ()With C = the purchased costs

    I = the cost index

    The subscripts 1 and 2 are related to the base time when the costs are known and

    the time when costs are desired, respectively. There are numerous cost indexes

    available in industry that includes the economic effect of inflation. For this design the

    Chemical Engineering Plant Cost Index (CEPCI) will be used since it was used in the

    CAPCOST excel spreadsheet as well.

    Table 9: CEPCI in 2012 (Turton et al.)

    Determination Year CEPCI

    2004 4442005 468

    2006 500

    2007 527

    2008 555

    2009 583

    2010 611

    2011 639

    2012 667

    Historic

    al

    Extrapolated

  • 7/14/2019 Final Design -Assignment III

    43/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 43

    Figure 16: Extrapolation of Index

    An estimation can be made to obtain the CEPCI cost indexin August 2012 as can

    be seen above in the Table and Figure above. The extrapolation is done by using the

    most recent data (2004-2006 in Turton et al, 2007) that showed a linear yearly

    increase in the index. This is only a rough estimate.

    The latest values for the CEPCI is given by

    (www.nt.ntnu.no/users//magnehi/cepci_2011_py.pdf)

    Figure 17: CEPCI (courtesy ofwww.EngineeringToolBox.com)

    12.2 Labour Requirements:

    Operating labour costs was determined from the number of major processing unit

    operations. The number of operators and supervisory staff was taken from the

    Suncors LO-CAT unit as an example. Standard industry salary was used tocalculate the labour costs. The total operating labour costs was therefore calculated

    by multiplying each worker with the estimated standard salary as per the dictates of

    444

    468

    500

    527555

    583

    611

    639

    667

    y = 28x - 55669

    R = 0.9932

    400

    450

    500

    550

    600

    650

    700

    2002 2004 2006 2008 2010 2012

    index

    year

    historical

    extrapolated to

    2012 for EB Plant

    Linear (historical)

    http://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdfhttp://www.engineeringtoolbox.com/http://www.engineeringtoolbox.com/http://www.engineeringtoolbox.com/http://www.engineeringtoolbox.com/http://www.engineeringtoolbox.com/http://www.nt.ntnu.no/users/magnehi/cepci_2011_py.pdf
  • 7/14/2019 Final Design -Assignment III

    44/67

    PLANT DESIGN: CPD4M2C

    PRODUCTION OF ETHYL BENZENE SEPTEMBER 2012 44

    South African petrochemical employees salaries as an example and standard.

    The number of operators that will be operating the plant was determined from the

    standard three shift/day rate of labour and with the four operators/shift required to

    operate the plant. The salaries were taken at a standard monthly salary that included

    bonus incentives and miscellaneous income after income tax deductions, to avoidtedious calculations. The same principles were performed on the supervisory units of

    the plant, which included the management, foremen, clerks, professionals, and the

    peremptory security personnel. The operating labour cost calculations are displayed

    in the table below.

    Table 10: Labour Costs

    12.3 Plant Operation Time:

    Industrial facilities use procedures to sustain the plant while the plant is still in

    operation. These procedures may include inspection, repairs, alterations,

    replacements as well as minor maintenance to existing process units. However, all

    industrial plants require a scheduled period to perform major maintenance that will

    be costly to the process but necessary. This is commonly called plant shutdowns.

    Delaying or ignoring scheduled plant shutdowns may be disastrous and may cause

    the entire facility to stop operations indefinitely. In performing economic analysis the

    total annual operating hours is important to determine since it is used in most cost

    estimate calculations. It is also used in the CAPCOST Excel Spreadsheet. The plant

    capacity factor refers to the amount of annual operating hours, presented as a

    percentage of the total possible operating hours per year available. There are 365days in a year that is available for a plant to operate, but sulphur recovery units

    normally only operate at a plant capacity factor of 90.4%. The equation follows:

    () This puts the annual operating hours of this design at 7920 operating hours per

    year. This amounts to 35 days of shutdown, which is almost 1.3 months. Due tothe high cost normally incurred by shutdowns in industrial plants, the possibility is

    Number Salary Salary Cost

    EMPLOYEE No. per month per month

    Managers 2 19,200.00R 38,400