Fimcon Warehouse Project VAL. NO.9

download Fimcon Warehouse Project VAL. NO.9

of 14

Transcript of Fimcon Warehouse Project VAL. NO.9

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    1/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Contractor :- Sojimi Services Limited

    Architect :- Uudex Associates

    Commencement Date :- 31st August, 2010 Completion Date :- 4th December,2010

    Valuation No :- Nine Date :- 9th February 2012

    Contract Sum :- =N= 108,950,357.96

    =N= : K

    Preliminaries 3,120,000.00

    Builders' Work 58,286,286.60

    Nominated Sub-contractors(advance payment & work done) 36,755,155.91

    Builder's materials on site -

    Attendance to Main Contractor on Specialist Works 918,878.90

    GROSS VALUATION =N= 99,080,321.41

    Less:Rentention:10% (main contractor only) 6,232,516.55

    92,847,804.86

    AddRelease of Retention -

    92,847,804.86

    Advance Payment - =N= 16,863,768.28

    Less : Repayment (main contractor see page 12 for details) 15,110,867.62=N= 77,736,937.24

    Add

    Fluctuation (main contractor only see detail on page 9) 398,700.00

    Value Added tax VAT -5% (main contractor only) 3,116,258.27

    Total net amount payable to Contractors =N= 81,251,895.51

    Less : Amount previously paid (see datails on page 13) 96,306,352.99

    Amount recommended for payment =N= (15,054,457.48)

    COSTFIELD ASSOCIATES

    Quantity Surveyors

    1.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    2/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Bill no. 1: Preliminaries

    BreakdownInitial Cost (installation) 50%

    Running/Continous Cost 35%

    Terminal Cost 15%

    4,000,000.00 = 100%

    FOR VALUATION NO. 2

    Initial Cost (installation) 50% 2,000,000.00

    Running Cost- base on time interval - on Account80% of 35% of =N=4,000,000.00 1,120,000.00

    3,120,000.00

    Bill no. 4: Warehouse

    Element no. 1 Substructure

    (Remeasurement) as at Valuation no. 2A =N= 21,077,774.00

    Page WH/2/ F - G:100% completed =N= 85,760.00

    Page WH/3/ D - E:100% completed =N= 26,754.00Element no.1 Substructure =N= =N= 21,190,288.00

    Element no. 2 Frame

    (Remeasurement) as at Valuation no. 8 =N= 3,132,802.00

    Element no.2 Frame =N= 3,132,802.00

    Element no. 3 Upper Floors

    (Remeasurement) as at Valuation no. 8 =N= 4,383,067.00

    Element no.3 Upper Floors =N= 4,383,067.00

    Element no. 4 Staircase

    Page WH/6/ A - N:100% completed =N= 315,585.00

    Page WH/6/ P:100% completed =N= 5,360.00

    Remeasurement-item WH/7/A

    Screeded bed on tread:14m2 @=N=1072.00 =N= 15,008.00

    Remeasurement-item WH/7/B

    Screeded backing on risers:57m @=N=163.00 =N= 9,291.00

    Page WH/7/ C - E:100% completed =N= 25,934.00

    Remeasurement-item WH/7/F- J

    Thickness of terrazzo slab changed from 18mm

    to 36mm

    Item WH/7/ F:5m2 @ =N=3860.00:100% completed =N= 19,300.00

    Item WH/7/ G -H:14m2 @ =N=3860.00:100% ditto =N= 54,040.00

    Item WH/7/ J:57m @ =N=584.00:100% completed =N= 33,288.00

    Page WH/7/ K - M:0% completed =N= -

    Element no.4 Staircase =N= 477,806.00

    Carried forward: =N= 29,183,963.002.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    3/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Brought forward: =N= 29,183,963.00

    Element no. 5 External and Internal wall

    (Remeasurement) as at Valuation no. 8 =N= 5,178,208.00

    At entrance to staircase

    225mm block wall:2m2 @=N=3259.00 =N= 6,518.00

    Element no.5 External and Internal Wall =N= 5,184,726.00

    Element no. 8 Doors

    (Remeasurement)

    Page WH/11/ A -6no @=N=17,281.00 =N= 103,686.00

    Page WH/11/ B -14no @=N=15,437.00 =N= 216,110.00

    Page WH/11/ C :0% completed =N= -

    Page WH/11/ D -125m @=N=557.00 =N= 69,625.00

    Page WH/11/ E -20no @=N=1,029.00 =N= 20,580.00

    Page WH/11/ F -20no @=N=6,432.00 =N= 128,640.00

    Page WH/11/ G -H :0% completed =N= -

    Element no.8 Doors =N= 538,641.00

    Element no. 9 Fittings and Fixtures

    Page WH/12/ A - B :0% completed =N= -

    Element no. 9 Fittings and Fixtures =N= -

    Element no. 11 Floor,Wall & Ceiling Finishings

    Page WH/15/ A- B:100% completed =N= 1,588,747.00

    Page WH/15/ C - E:118m2 @ =N=643.00 =N= 75,874.00

    Page WH/15/ F - H:118m2 @ =N=1544.00 =N= 182,192.00

    Page WH/15/J: 100% completed =N= 48,020.00

    Additional works

    12no transluscent ceiling sheets@ =N=2,500.00 =N= 30,000.00

    Remeasurement-page WH/15/K

    Rendering to soffit of slab:468m2 @=N=1072.00 =N= 501,696.00

    Page WH/15/ L:100% completed =N= 1,902,800.00

    Page WH/15/M:29m2 @ =N=1029.00 =N= 29,841.00

    Carried forward: =N= 4,359,170.00 34,907,330.003.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    4/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Brought forward: =N= 4,359,170.00 34,907,330.00

    Page WH/16/A:48m2 @ =N=1029.00 =N= 49,392.00

    Page WH/16/B:32m @ =N=103.00 =N= 3,296.00

    Page WH/16/C:43 m @ =N=103.00 =N= 4,429.00

    Page WH/16/D:48m2 @ =N=3087.00 =N= 148,176.00

    Page WH/16/E:29m2 @ =N=1544.00 =N= 44,776.00

    Page WH/16/F:32m @ =N=154.00 =N= 4,928.00

    Page WH/16/G:43m @ =N=154.00 =N= 6,622.00

    Remeasurement-page WH/16/H

    Rendering on ext.wall:1036m2 @=N=1072.00(100%) =N= 1,110,592.00

    Page WH/16/ J:100% completed =N= 44,571.00

    Element no. 11 Floor,Wall & Ceiling Finishings =N= 5,775,952.00

    Element no. 12 Painting & Decoration

    Page WH/17/ A- B:60% completed =N= 645,267.00Remeasurement-page WH/17/C

    Painting to soffit of slab:468m2 @=N=729-70%complete =N= 238,820.40

    Page WH/17/ D - E:0% completed =N= -

    Page WH/17/ F - G:0% completed =N= -

    Element no. 12 Painting & Decoration =N= 884,087.40

    Bill no. 5: External Works

    Site clearance

    Page EX/1/A - E: 100% completed =N= 628,006.00

    Oversite Excavation

    Page EX/1/F: 100% completed =N= 373,433.00

    Fence wall -front elevation

    Substructure

    Excavation for column pit:5m3@=N=1,072.00 =N= 5,360.00

    Ditto trench for foundation:13m3 @ =N=1072.00 =N= 13,936.00

    Reinforced conc.column bases:2m3@=N=21,440 =N= 42,880.00

    Ditto column in foundation:1m3@=N=21,440 =N= 21,440.00

    Reinforcement to column bases: 200kg @=N=206 =N= 41,200.00

    Ditto for column in foundation:100kg @=N=206.00 =N= 20,600.00

    Formwork to sides of col.in fdn:10m2 @=N=1029 =N= 10,290.00

    Plain insitu conc.foundation bed:3m3@=N=18,010 =N= 54,030.00

    225mm block wall filled solid:20m2 @=N=4717.00 =N= 94,340.00

    Superstructure225mm hollow block wall :20m2 @=N=3259.00 =N= 65,180.00

    Reinforced conc.column:2m3@=N=21,440 =N= 42,880.00

    Reinforcement to column: 200kg @=N=206 =N= 41,200.00

    Formwork to sides of column:18m2 @=N=1029 =N= 18,522.00

    Carried forward: =N= 1,473,297.00 41,567,369.404.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    5/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Brought forward: =N= 1,473,297.00 41,567,369.40

    Fence wall -front elevation continuesSuperstructure continues

    Rendering on front fence wall :40m2 @=N=1029.00 =N= 41,160.00

    Rendering on front fence columns:36m2 @=N=1029 =N= 37,044.00

    Fence wall -existing fence & generator house

    Substructure

    Excavate trench for foundation:3m3 @ =N=1072.00 =N= 3,216.00

    Plain insitu conc.foundation bed:1m3@=N=18,010 =N= 18,010.00

    225mm block wall filled solid:4m2 @=N=4717.00 =N= 18,868.00

    Superstructure

    225mm hollow block wall :10m2 @=N=3259.00 =N= 32,590.00

    Cement & sand rendering on ditto:10m2@=N=1072 =N= 10,720.00

    Fence wall -rear & left hand side elevations

    Cement & sand rendering ditto:163m2@=N=1072 =N= 174,736.00

    Gate House

    Page EX/4/A - L: 100% completed =N= 130,231.00

    Page EX/5/A - L: 100% completed =N= 349,026.00

    Page EX/6/A - C: 100% completed =N= 100,932.00

    Page EX/6/F - L: 100% completed =N= 72,368.00

    Page EX/7/G: 100% completed =N= 26,800.00

    Page EX/7/H: 0% completed =N= -

    Page EX/7/J- K: 0% completed =N= -

    Page EX/8/A - B: 0% completed =N= -

    Page EX/8/C: 100% completed =N= 38,073.00

    Page EX/8/D: 0% completed =N= -

    Generator House

    Page EX/9/A - M: 100% completed =N= 277,461.00

    Page EX/10/A - J: 100% completed =N= 406,169.00

    Remeasurement-item EX/10/K

    230mm block wall:25m2 @=N=4717.00 =N= 117,925.00

    Remeasurement-item EX/10/L

    230mm block wall:66m2 @=N=3259.00 =N= 215,094.00

    Page EX/10/M: 100% completed =N= 6,690.00

    Page EX/10/N - P: 100% completed =N= 64,320.00

    Page EX/11/A - C: 100% completed =N= 104,001.00

    Page EX/11/F - L: 100% completed =N= 119,086.00

    Page EX/11/M - N: 0% completed =N= -

    Carried forward: =N= 3,837,817.00 41,567,369.40

    5.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    6/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Brought forward: =N= 3,837,817.00 41,567,369.40

    Bill no. 5: External Works continuesGenerator House continues

    Additional works

    Asbestos ceiling tiles including hardwood noggins &

    covering strip:9m2 @=N=943.00 =N= 8,487.00

    Page EX/12/H: 100% completed =N= 47,334.00

    Page EX/12/J: 0% completed =N= -

    Remeasurement-item EX/12/K

    Cement & sand screeded bed:9m2 @=N=1029.00 =N= 9,261.00

    Page EX/12/L: 100% completed =N= 56,595.00

    Page EX/13/A: 0% completed =N= -

    Underground WaterTank

    Page EX/14/A - L: 100% completed =N= 632,793.00

    Page EX/14/ M: 0% completed(not done) =N= -

    Page EX/15/A - J: 100% completed =N= 932,161.00

    Remeasurement-page EX/15/K

    Page EX/15/K:36m2 @=N=3829-100% completed =N= 137,844.00

    Page EX/15/L: 100% completed =N= 20,368.00

    Remeasurement-page EX/15/M

    Page EX/15/M:36m2 @=N=1072-100% completed =N= 38,592.00

    Page EX/15/N: 100% completed =N= 15,485.00

    Remeasurement-page EX/15/P

    Page EX/15/P:36m2 @=N=815-100% completed =N= 29,340.00

    Page EX/15/Q: 100% completed =N= 13,851.00

    Remeasurement-page EX/15/R

    Page EX/15/R:36m2 @=N=617-100% completed =N= 22,212.00

    Remeasurement-page EX/16/A

    Page EX/16/A:55m2 @=N=1544-100% completed =N= 84,920.00

    Paved area

    Additional works

    Total paved areas within the site:958m2,

    Average excavation depth:470mm

    Excavation :450m3 @=N=1,072.00 =N= 482,400.00

    Total paved areas outside the site(ramp):127m2,

    Average excavation depth:400mm

    Excavation :51m3 @=N=1,072.00 =N= 54,672.00

    Remove excavated material from site

    :501m3 @=N=643.00 =N= 322,143.00

    Carried forward: =N= 6,746,275.00 41,567,369.40

    6.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    7/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works) Valuation No :- Nine Date :- 9th February, 2012

    Bill no. 5: External Works continues

    Brought forward: =N= 6,746,275.00 41,567,369.40

    Paved area continuesPage EX/17/A: 0% completed (not executed) =N= -

    Remeasurement

    Page EX/17/B: 683m2 @ =N=729.00 =N= 497,907.00

    Page EX/17/C: 530m2 @ =N=712.00 =N= 377,360.00

    Page EX/17/D: 573m2 @ =N=815.00 =N= 466,995.00

    Additional paving outside the site (ramp area)

    BRC mesh for concrete paving:112m2 @=N=815.00 =N= 91,280.00

    Concrete paving

    Page EX/17/E: 573m2 @ =N=5274.00 =N= 3,022,002.00

    Additional paving outside the site (ramp area)

    concrete paving:112m2 @=N=5726.00 =N= 641,312.00

    Page EX/17/F: 0% completed =N= -

    DrainagePage EX/17/G - L: 100% completed =N= 171,806.00

    Page EX/18/A - G: 100% completed =N= 2,541,577.00

    Page EX/18/H - J : 0% completed =N= -

    Page EX/18/K : 80% completed =N= 122,935.20

    Page EX/18/L - N : 0% completed =N= -

    Page EX/19/A - H : 0% completed =N= -

    Septic Tank

    Page EX/19/J - M: 100% completed =N= 100,899.00

    Page EX/20/A - M: 100% completed =N= 824,191.00

    Page EX/21/A - C: 100% completed =N= 89,016.00

    NOTE:Only 1no septic tank is included with warehouse

    Soak Away Pit:size 1200 x 1200mm x 1500mm deep

    Page EX/23/A - M: 50% completed =N= 187,532.00

    Page EX/24/A: 50% completed =N= 4,866.00

    NOTE:Only 1no is included with warehouse

    Soak Away Pit:size 2100 x 2100mm x 1800mm deep

    Page EX/24/B - N: 100% completed =N= 350,525.00

    Page EX/25/A - B: 100% completed =N= 57,422.00

    Additional works

    Transformer Base

    Excavation:1m3 @=N=1029.00 =N= 1,029.00

    150mm hardcore:1m2 @=N=772.00 =N= 772.00

    50mm concrete blinding:1m2 @=N=712.00 =N= 712.00

    Concrete base:1m3 @ =N= 21,440.00 =N= 21,440.00Reinforcement:48kg @ =N= 206.00 =N= 9,888.00

    Formwork to sides:6m2 @ =N= 1029.00 =N= 6,174.00

    Carried forward: =N= 16,333,915.20 41,567,369.40

    7.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    8/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works) Valuation No :- Nine Date :- 9th February, 2012

    Bill no. 5: External Works continues

    Brought forward: =N= 16,333,915.20 41,567,369.40

    Additional works

    Machine Base

    Excavation:1m3 @=N=1029.00 =N= 1,029.00

    150mm hardcore:3m2 @=N=772.00 =N= 2,316.00

    50mm concrete blinding:3m2 @=N=712.00 =N= 2,136.00

    Concrete base:2m3 @ =N= 21,440.00 =N= 42,880.00

    Reinforcement:96kg @ =N= 206.00 =N= 19,776.00

    Formwork to sides:4m2 @ =N= 1029.00 =N= 4,116.00

    Isolation base

    Excavation:1m3 @=N=1029.00 =N= 1,029.00

    150mm hardcore:1m2 @=N=772.00 =N= 772.00

    50mm concrete blinding:1m2 @=N=712.00 =N= 712.00

    Concrete base:1m3 @ =N= 21,440.00 =N= 21,440.00Reinforcement:48kg @ =N= 206.00 =N= 9,888.00

    Formwork to sides:1m2 @ =N= 1029.00 =N= 1,029.00

    225mm hollow block wall :5m2 @=N=3259.00 =N= 16,295.00

    Engr Instruction dated 20/09/11 & 26/10/11 on

    Columns @ main,inner & pedestrian gate

    Substructure

    Excavation:10m3 @=N=1029.00 =N= 10,290.00

    Return,fill &rammed: 7m3 @=N=450.00 =N= 3,150.00

    Cart away excavated material: 3m3 @=N=643.00 =N= 1,929.00

    Column base &stub:3m3 @ =N= 21,440.00 =N= 64,320.00

    Reinforcement:300kg @ =N= 206.00 =N= 61,800.00

    Formwork to column stub sides:9m2 @ =N= 1029 =N= 9,261.00

    Superstructure

    Column:2m3 @ =N= 21,440.00 =N= 42,880.00

    Reinforcement:200kg @ =N= 206.00 =N= 41,200.00

    Formwork to column sides:26m2 @ =N= 1029.00 =N= 26,754.00

    Bill no. 5: External Works =N= 16,718,917.20

    Grand Total:Builders' Works =N= 58,286,286.60

    8.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    9/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Material on site as at 9th February 2012Flush doors:5no @=N=14,500.00 =N= 72,500.00

    Cement:374bags @=N=1,650.00 =N= 617,100.00

    Sharp sand:40tons @=N=3,500.00 =N= 140,000.00

    Granite:60tons @=N=6,000.00 =N= 360,000.00

    Reinforcement:5tons @=N=155,000.00 =N= 775,000.00

    The Client paid for them =N= -

    Fluctuation ClaimTotal amount approved to date(see costfield letter

    dated 14th July 2011 =N= 398,700.00

    Nominated Sub contractors' works

    M/S BELDICO =N= K

    (Electrical Installation)

    Accepted Quotation - 11,778,175.76

    Cumulative amount paid on electrical work done

    (See Prime Associates Valuation no.2 dated 19th

    October,2011) 11,184,872.00

    Less: Retention -5% 559,243.60

    10,625,628.40Less previouslypaid(certificate no. 8) 10,625,628.40

    Amount due in this Valuation -

    Note

    Calculation of the amortization of advance payment

    Total contract sum: =N= 11,778,175.76

    Total amount of advanced payment to be amortized: =N=

    Gross valuation for electrical sub contractor =N=

    Adv.payment to be deducted from this valuation =N=

    9.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    10/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Nominated Sub contractors' works continues

    MAPROMAR NIGERIA LIMITED(Mechanical Installation)

    Accepted Quotation - 3,129,364.16

    Additional works 1?????????? 291,715.00

    Additional works 2????????? 92,820.00

    Additional works 3????????? 92,000.00

    3,605,899.16

    Cumulative amount paid on mechanical work done

    (See payment details from client 3,157,697.27

    Less: Retention -10% 315,769.73 retention not deducted because of direct

    =N= 2,841,927.54 paymentLess previously paid (See payment detail fromclient 3,157,697.27

    Amount due in this Valuation (315,769.73)

    Total amount paid to date 3,157,697.27

    Note

    Calculation of the amortization of advance payment

    Total amount of NSC works including preliminaries: =N= -

    Total amount of advanced payment to be amortized: =N= -

    Gross valuation for mechanical sub contractor =N=

    Adv.payment to be deducted from this valuation =N=

    PRIMOTEK SYSTEM

    (Fire Alarm Syetem)

    Accepted Quotation - 552,365.63Advance payment paid -70% 386,655.94 previously paid without deducting retention

    CHIDEX METALCO. (NIG)

    (Metal Works)

    Accepted Quotation - 1,269,180.00

    Additional works 1????????? 727,608.00

    Total amount paid as at 5th Oct,2011 1,753,608.00 previously paid without deducting retention

    CRITTALL - HOPE NIG. LTD

    (Roller Shutter doors)

    Accepted Quotation - 1,479,848.00

    Advance payment paid -100% 1,479,848.00 previously paid without deducting retention

    10.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    11/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Nominated Sub contractors' works continues

    SAINT LLOYDS CONCEPTS LTD

    (Aluminium Windows)

    Accepted Quotation - 1,227,950.00

    Total amount paid as at 1st Sept,2011 1,104,590.00 previously paid without deducting

    retention.

    TOWER ALUMINIUM (NIG) PLC

    (Aluminium Roofing)

    Accepted Quotation - -

    See payment detail from client 6,396,528.30 previously paid without deducting

    retention.

    MICKODAM ENGINEERING NIG.LTD

    (Structural Steel Works)

    Accepted Quotation - 10,850,000.00

    Variations:(see CIV-STRUCT letter dated

    14th March, 2011

    Additional steel mesh panel(item A) - 300,000.00

    Monitor mesh panel(item B) - 300,000.00

    Total 11,450,000.00

    Cumulative amount paid on Structural steel work

    (See payment details from client 11,850,600.00

    Amount due in this Valuation

    Payment to Nominated Sub Contractors.

    (as advance payment & work done) 36,755,155.91

    Attendance to Main Contractor on specialist

    Works(2.5% of =N=36,755,155.91) =N= 918,878.90

    11.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    12/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Calculation of the amortization of advance payment for main contractor

    Total amount of Builder's works including preliminaries: =N= 70,000,000.00

    Total amount of advanced payment to be amortized: =N= 16,863,768.28

    (see costfield letter dated 20th October, 2010)

    Gross valuation of Builder's work,preliminaries,

    attendance and fluctuation claim =N= 62,723,865.50

    Advance Payment to be deducted from Main.

    Contractor Valuation no.9 =N= 15,110,867.62

    Value Added tax - VAT -5% (main contractor only)

    Preliminaries 3,120,000.00

    Builders' Work 58,286,286.60

    Attendance to Main Contractor on Specialist Works 918,878.90

    62,325,165.50

    Value Added Tax to be paid through M.Contractor =N= 3,116,258.27

    Amount previously paid:

    (a)Main Contractor

    Total amount paid to main contractor (excluding

    advance payment) as stated in the statement of

    payment made supplied by the Client(18/11/2010

    to 30/01/2012) 59,551,197.08

    (b)Nominated Sub Contractors.

    M/S BELDICO

    Electrical Installation - adv payment& work done 10,625,628.40

    MAPROMAR NIGERIA LIMITED

    (Mechanical Installation -advance payment 3,157,697.27

    PRIMOTEK SYSTEM

    (Fire Alarm Syetem) 386,655.94

    CHIDEX METALCO. (NIG)

    (Metal Works) 1,753,608.00

    CRITTALL - HOPE NIG. LTD

    (Roller Shutter doors) 1,479,848.00

    SAINT LLOYDS CONCEPTS LTD

    (Aluminium Windows) 1,104,590.00

    TOWER ALUMINIUM (NIG) PLC

    (Aluminium Roofing) 6,396,528.30

    MICKODAM ENGINEERING NIG.LTD

    (Structural Steel Works) 11,850,600.00

    (Work done and advance payments) =N= 36,755,155.91

    12.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    13/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    Summary of amount previously paid:(a)Main Contractor 59,551,197.08

    (b)Nominated Sub Contractors. 36,755,155.91

    Total amount paid to M.Contractor & NSC =N= 96,306,352.99

    NOTE ON VALUATION

    Bill no. 1

    Preliminaries: 78% has been paid to date.The balance is for outstanding running cost and terminal cost.

    Bill no. 2

    Element no. 1: Substructure

    The outstanding works i.e concrete step has been done, therefore this element is 100% completed

    Element no. 2: FrameThis element is 100% completed

    Element no.3:Upper Floor

    This element is 100% completed

    Element no. 4: Staircase

    The outstanding is painting works.

    Element no. 5: External & Internal Walls

    This element is 100% completed

    Element no. 6: Roof

    Nominated sub contractor's works

    Element no. 7: Windows

    Nominated sub contractor's works

    Element no. 8: Doors

    3no.doors are yet be fixed and their ironmongery.

    Element no. 9: Fittings and Fixtures

    The items (hardwood lockers) under this element are not executed

    Element no. 11: Floor, Wall &Ceiling Finishings

    This element is 100% completed

    Bill no. 5: External Works:Underground water tank,generator house,gatehouse(1no), septic tanks(2no),

    soakaway pit(2no) manholes are at advance stage of completion.

    13.00

  • 8/3/2019 Fimcon Warehouse Project VAL. NO.9

    14/14

    COSTFIELD ASSOCIATES VALUATION

    Contract :- OFFICE/WAREHOUSE COMPLEX - Phase1 (Warehouse & External Works)

    Valuation No :- Nine Date :- 9th February, 2012

    NOTE ON VALUATION continues

    Main Contractor advance payment repayment

    The sum of =N=15,110,867.62 has been amortized out of =N=16,510,268.10 in this valuation.

    The balance is of =N=1,399,400.48 is yet to be amortised.

    Fluctuation

    As stated in Valuation no. 8

    Materials on site

    The approximate quantities of materials found on site are as stated in the valuation.

    Nominated Sub contractors' works

    M/S BELDICO

    (Electrical Installation)The amount stated as paid in the valuation is based on the details of the payment supplied by the Client.

    Retentions are not deducted.

    MAPROMAR NIGERIA LIMITED

    (Mechanical Installation)

    The amount stated as paid in the valuation is based on the details of the payment supplied by the Client.

    Retentions are not deducted.

    MICKODAM ENGINEERING NIG.LTD

    (Structural Steel Works)

    As stated in Valuation no. 8

    PRIMOTEK SYSTEM

    (Fire Alarm System)

    The Contractor is yet to start work on site.

    TOWER ALUMINUIM NIG (PLC)

    (Aluminium roofing)

    The amount stated as paid in the valuation is based on the details of the payment supplied by the Client.

    Retentions are not deducted.

    SAINT LLOYDS CONCEPTS LTD

    (Aluminium Windows)

    The amount stated as paid in the valuation is based on the details of the payment supplied by the Client.

    Retentions are not deducted.

    CHIDEX METAL CO. (NIG)

    (Metal Works)

    The amount stated as paid in the valuation is based on the details of the payment supplied by the Client.

    Retentions are not deducted.14.00