FEDERAL PROJECT MANAGEMENT UNIT (FPMU) - … PROJECT MANAGEMENT UNIT (FPMU) RURAL ACCESS AND...
-
Upload
truonghanh -
Category
Documents
-
view
217 -
download
3
Transcript of FEDERAL PROJECT MANAGEMENT UNIT (FPMU) - … PROJECT MANAGEMENT UNIT (FPMU) RURAL ACCESS AND...
FEDERAL REPUBLIC OF NIGERIA FEDERAL PROJECT MANAGEMENT UNIT (FPMU)
RURAL ACCESS AND MOBILITY PROJECT (RAMP)
Consulting Services for Detailed Engineering, Safeguard Studies & Preparation of Bidding Documents for Prioritised Roads in ENUGU STATE under RAMP 2
Abbreviated Resettlement Action Plan (ARAP) Report -(Revised)
June, 2012
RP713 v3 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
2
CONTACT INFORMATION
Firm: PHEMAN PENIEL CONSULTANTS Ltd
Address: 76B, Adeniyi Jones Avenue (2nd Floor),
PO Box 14006, Ikeja,
Lagos, Nigeria
Tel:. 0803 403 1493
0805 507 3665
0807 884 5071
Text: 0807 884 5071
Email: [email protected],
Website: www.phemanpeniel.com
Contact
Person: Engr. Dr. Emmanuel A. ADEYEMO, Ph.D., C.Eng., FASCE, FNSE,FNICE
CEO/Managing Principal
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
3
TABLE OF CONTENTS Page
Title Page 1
Contact Information 2
Table of Contents 3
Submission Letter 5
Abbreviations and Acronyms 6
List of Tables 7
List of Figures 8
List of Pictures 8
Executive Summary 9
1.0 Introduction 15
1.1 Background of the Project 15
1.2 Objective of RAMP 15
1.3 General Objectives of the Consultancy Services 15
1.4 Objectives of the ARAP Study 17
1.5 Land Acquisition and Resettlement Plan Objective 17
1.6 Description of Project Road 18
1.7 Description of Proposed Works 18
1.8 Site Visits and Surveys 19
1.9 Public Consultations 19
1.10 Potential Economic and Social Impacts 20
1.11 Approach and Methodology 24
1.12 Communication Principles 27
2.0 Legislative and Regulatory Framework 30
2.1 Introduction 30
2.2 Identification and Categorisation of Loss and Impact 30
2.3 Eligibility of PAPs 31
2.4 Method of Valuation and Compensation 32
2.5 Grievance Redress Mechanisms and Procedures 34
2.6 Important Principles in Project Implementation 35
2.7 Mechanisms for Consultation and Participation of Displaced Persons 35
2.8 Income Restoration Strategy 36
2.9 Arrangement for Monitoring by Implementation Agency 37
3.0 Socio-Economic Survey and Properties of Affected Population 39
3.1 Socio-economic Survey of the affected population 39
32. Survey Methodology 39
3.3 Project Area Population 40
3.4 Demographic Characteristics of Enugu State 40
3.5 Result of Socio-economic Survey 41
3.6 Project Affected Persons and Properties 43
4.0 Valuation and Compensation Procedures 45
4.1 Introduction 45
4.2 Eligibility Criteria for Project-affected Persons 45
4.3 Consultations 46
4.4 The Valuation Process 46
4.5 Basis of Valuation 46
4.6 Method of Valuation 46
4.7 Disturbance and Other Incidental Contingencies 47
4.8 Modes of Restitution 47
4.9 Value of Land 47
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
4
4.10 Value of Affected Structures and Crops 48
4.11 Compensation and other Assistance 49
4.12 Entitlement Matrix 50
5.0 Public Consultations 51
5.1 Project Affected Persons 51
5.2 Future Consultations 51
6.0 Grievance Procedure 52
6.1 Grievance Redress Mechanism 52
6.2 Grievance and Redress Procedure 53
7.0 Institutional Responsibilities 55
7.1 Introduction 55
7.2 Implementation Roles and Responsibilities 55
7.3 Measures for Strengthening Organizational Capability 58
8.0 Monitoring and Evaluation 60
8.1 Objectives 60
8.2 ARAP Monitoring Framework 60
8.3 Internal Performance Monitoring 63
8.4 Impact Monitoring 65
9.0 Resettlement Budget and Planning 67
10.0 Implementation Schedules 68
10.1 Introduction 68
10.2 Plan Preparation 68
10.3 Consultation and Disclosure 69
10.4 RoW Acquisition and Construction 69
10.5 Monitoring And Evaluation 70
10.6 Update of the Baseline Data 70
11.0 Disclosure 71
ANNEXES
Annex 1A: List of PAPs Consulted in Umuaniagu (Ozalla)
Community (on Road #13) 72
Annex 1B: List of PAPs Consulted in Umuaniagu (Ozalla)
Community (on Road #13) 74
Annex 1C: List of PAPs, their Affected Structures and
Compensation: UMUANIAGU VILLAGE 75
Annex 1D: List of PAPs, their Affected Structures and
Compensation: OJOR VILLAGE 77
Annex 2A: Minutes of the Consultation and Notification
Meeting on the Proposed UNTH-ENUGUAGU NDIAGU
-UMUANIAGU-OBE AMURI ROAD (11.88km)
HELD IN UMUANIAGU ON THE 29TH MAY, 2012 78
Annex 2B: Minutes of the Consultation and Notification
Meeting on the Proposed ADANI-AJABA-IGGA-OJOR
ROAD (9.94km) Held in OJOR on the 30TH MAY, 2012
at 11.00am 81
Annex 3A: Relocation of a Major Shrine: Procedure and Costs 87
Annex 3B: Relocation of a Minor Shrine: Procedure and Costs 89
Annex 4: Grassroot Organisations in Affected Communities 90
Annex 5: Terms of Reference (TOR) 91
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
5
June 26, 2012
The National Coordinator, (Federal Project Management Unit),
RURAL ACCESS and MOBILITY PROJECT (RAMP),
NAIC House,
Plot 590, Zone AO,
Along Airport Road, Central Area, Abuja, Nigeria
Dear Sir,
Re: Consulting Services for Detailed Engineering, Safeguard Studies & Preparation of Bidding
Documents for Prioritised Roads in ENUGU STATE under RAMP 2
Abbreviated Resettlement Action Plan (ARAP)-Revised
We hereby submit the revised Abbreviated Resettlement Action Plan (ARAP) on the above
project.
In accordance with the Terms of Reference (TOR) and the signed Contract Agreement, this
report has been prepared and submitted in 5 hard copies and 1 electronic copy.
Thank you very much.
Yours sincerely,
Pheman Peniel Consultants Ltd.
Engr. Dr. Emmanuel A. ADEYEMO
CEO/Managing Principal
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
6
ABBREVIATIONS and ACRONYMS
AADT Average Annual Daily Traffic
ADT Average Daily Traffic
ARAP Abbreviated Resettlement Action Plan
AFD Agence Francaise de Developpment
CBN Central Bank of Nigeria
DFID Department for International Development, UK
DP Displaced Persons
ESG Enugu State Government
ESIA Environmental and Social Impact Assessment
ESMF Environmental and Social Management Framework
ESMP Environmental and Social Management Plan
FGD Focus Group Discussion
FGN Federal Government of Nigeria
FMoH Federal Ministry of Health
FMW Federal Ministry of Works
FPMU Federal Project Management Unit
GDP Gross Domestic Product
HIV/AIDS Human Immunodeficiency Virus/Acquired Immune Deficiency Syndrome
IDA International Development Association
LEEDS Local Economic Empowerment and Development Strategy
LGA Local Government Authority
NBS National Bureau of Statistics
NEEDS National Economic Empowerment and Development Strategy
PAD Project Appraisal Document
PAP Project Affected Person
PIM Project Implementation Manual
PRA Participatory Rural Appraisal
PRS Poverty Reduction Strategy
RAMP Rural Access and Mobility Project
RAP Resettlement Action Plan
RoW Right of Way
RPF Resettlement Policy Framework
SEEDS State Economic Empowerment and Development Strategy
SPIU State Project Implementation Unit
SSI Semi Structured Interview
WHO World Health Organisation
WB World Bank
UN United Nations
UNICEF United Nations International Children Education Fund
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
7
LIST OF TABLES Page
Table 1.1: Prioritized Cluster of Roads in Enugu State 18
Table 1.2: Potential Economic and Social Impacts at UMUANIAGU 21
Table 1.3: Potential Economic and Social Impacts at OJOR 22
Table 2.1: Time Table for Eligibility, Compensation and Site Take-over 32
Table 3.1: Population Characteristics of Affected Communities 40
Table 3.2: Projected Population Distribution for the LGAs within RAMP Intervention Areas 41
Table 3.3: Number of PAPs Enumerated 42
Table 3.4 Gender Distribution of PAPs 42
Table 3.5: Number of Dependants of PAPs 42
Table 3.6: Occupation of PAPs 42
Table 3.7: Net Daily Income of PAPs 42
Table 3.8: Categories of PAPs 43
Table 4.1: Entitlement Matrix 50
Table 6.1: Membership of Grievance Redress Committee at Umuaniagu 53
Table 6.2: Membership of Grievance Redress Committee at Ojor 53
Table 8.1: ARAP Monitoring Framework 61
Table 8.2: Information Milestone 64
Table 9.1: Resettlement Budget and Finances 67
Table 10.1: Schedule for the Implementation of the Major Activities 69
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
8
LIST OF FIGURES Page
Figure 1.1: Administrative Map of Enugu State showing the Senatorial District 16
Figure 1.2: RAMP Intervention Area Map of Enugu State 16
Figure 1.3: Location Map of Road #13 23
Figure 1.4: Location Map of Road #12 23
LIST OF PICTURES Page
Pix 2A – 1: PAPs and Project Team @ UMUANIAGU 80
Pix 2A – 2: Women Group (PAPs) @ UMUANIAGU 81
Pix 2A – 3: Men Group (PAPs) @ UMUANIAGU 81
Pix 2B – 1: PAPs and Project Team @ OJOR 85
Pix 2B – 2: Transformer @ OJOR 85
Pix 2B – 3: A minor shrine @ OJOR 86
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
9
EXECUTIVE SUMMARY
ES.1 BACKGROUND ON THE PROJECT
The Federal Government of Nigeria has commenced with the implementation of the Rural Access and
Mobility Project (RAMP) in Enugu State with support financing from the World Bank and the Agence Francaise
De Developpment (AFD) and guided by the Government’s Rural Travel and Transport Policy (RTTP). The
objective of the consultancy services is to carry out detailed engineering design including cost estimates as
well as environmental and social studies, resettlement action plan and to prepare the bidding documents for
prioritized rural road rehabilitation works in the state of Enugu. This component involves the rehabilitation works
for an indicative 203.45kM of rural and state roads which are divided into four prioritized clusters of roads with
lengths of 59.26km, 57.16km, 42.22km and 44.81km of roads. This is an Abbreviated Resettlement Action Plan
(ARAP) for the proposed Enugu State RAMP rural road projects.
Nigeria’s rural transport infrastructure has been identified as a crucial component for the economic
development of the country and this can be achieved by designing and implementing a rural roads network
and linking the rural communities to the urban areas. Most of the rural roads are in poor condition, and impose
significant cost to the national and state economies especially to the agricultural activities due to increased
vehicle operating costs and travel times. As a result of this, the Federal Government of Nigeria (FGN) has given
priority to the provision of adequate transport facilities to meet the needs of the rural population.
ES.2 Objectives of the ARAP Study
The objective of the ARAP is to clarify the principles and procedures that will govern the mitigation of adverse
social impacts induced by project operations. Specifically, the ARAP is designed to ensure:
All types of losses are identified, clearly defined and properly categorized to reflect the nature of the
loss.
A standard or measure for defining eligibility and entitlement in order to have a fair basis for assessing
compensation for the loss or impact suffered.
Compliance with provisions of the Laws of the Federal Republic of Nigeria and World Bank
Operational Policies (OP 4.12, paragraph 2(b)): that resettlement activity would be conceived and
executed as development programs, providing sufficient investment resources to enable the PAPs to
share in project benefits.
Displaced persons will be compensated for their losses at full replacement cost and provided
assistance for disturbance prior to the beginning of civil works.
A comprehensive database, based on which values will be assessed, validated in the event of
disputes and more importantly serve as the database for monitoring and evaluation of the
resettlement instrument.
The project affected persons would be consulted and given the chance of participating in the
design, implementation and monitoring of the resettlement.
ES.3 Methodology
The following approach and methodology was adopted for the study
i. Research Reports and Surveys
ii. Compliance with the National, State and International Land-use and Resettlement Standards
iii. Public Consultations
iv. Identification, Selection and Survey of Project-affected Persons (PAPs)
v. Inventory of Potential Losses
vi. Methodology for the Valuation of Assets
vii. Assessment of Project Alternatives
viii. Calculation of ARAP Costs
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
10
ix. Implementation Schedule
x. List of PAPs, their Affected Structures and Compensation
ES.4 Public Consultations and Justification for ARAP
Two project roads, Road #13: UNTH-Enuguagu Ndiagu-Umuaniagu-Obe Amuri Road (11.88kM) and Road #12:
Adani-Asaba-Igga-Ojor Road (9.94kM) have been identified to have potential environmental and social
impacts that will involve compensation to and relocation of project affected persons (PAPs) at Umuaniagu
and Ojor respectively. Public Consultation is a requirement for RAP study by the Federal Ministry of the
Environment and the World Bank. The Consultant through the support of SPIU and community leaders held
consultations with the two identified project affected communities and persons living adjacent to the road
alignments during the site visits. During these meetings, the affected communities were informed on the
extent of encroachment of the proposed roads on their farmlands, shrines and communal facility. The
Consultant’s public consultation was done in two stages.
Meetings/Consultations were held with the communities where 148 community members were present
at Umuaniagu (Ozalla) and 58 community members were in attendance at Ojor. The two communities
were notified of the meetings on 23rd May, 2012 through the SPIU and were reminded by text messages
and phone calls. While the Umuaniagu consultation was held on 29th May, 2012, that of Ojor was held
on 30th May, 2012. One major decision at these meetings was the acceptance by the people of the
communities for the roads to pass through their communities. Men and women from both communities
attended these public consultations.
After the community consultation, specific meetings were held with identified project-affected persons
and the extents of encroachment, resettlement and compensation were determined. One hundred
(100) PAPs (49 Males and 51Females) were surveyed in Umuaniagu (Ozalla) Community; forty (40) PAPs
(20 Males and 20 Females) in Ojor Community.
The economic and social screenings/surveys as indicated by Tables ES.1 and ES.2 below have shown that the
projects will not involve significant land acquisition because the projects will be carried out for most part on
the existing right of way (RoW) and footpaths with minor land acquisition. Only two communities i.e.
Ozalla/Umuniagu on Road #13 and Ojoo on Road #12 will be affected. Temporal farm lands and cultural
sites and communal facilities along the RoW of the roads corridors will be displaced affecting access to
means of livelihood. The total area of land to be acquired is 9,300 square metres, affecting 129 households
and 140 people. The World Bank’s Operational Policy 4.12 (Involuntary Resettlement) is therefore triggered.
This abbreviated RAP has been prepared in line with the Resettlement Policy Framework.
One hundred (100) PAPs (49 Males and 51Females) were affected by the project in Umuaniagu (Ozalla)
Community and forty (40) PAPs (20 Males and 20 Females) were affected by the project in Ojor Community.
Two project roads, Road #13: UNTH-Enuguagu Ndiagu-Umuaniagu-Obe Amuri Road (11.88kM) and Road #12:
Adani-Asaba-Igga-Ojor Road (9.94kM) have been identified to have potential economic and social impacts
that will involve compensation to and relocation of project affected persons (PAPs) at Umuaniagu and Ojor
respectively. There are altogether one hundred and forty (140) PAPs affected by the projects in the two (2)
communities. Therefore, an Abbreviated Resettlement Action Plan (ARAP) has been prepared for the project.
ES 4.1 Assessment of Project Alternatives
The following four project alternatives were examined in the course of this study;
No Project Alternative: This would mean that the rural areas will not be linked and the anticipated rural
access and associated socio-economic development will remain elusive.
Delayed Project Alternative: This alternative would lead to increase in estimated project cost and would
hinder the full implementation.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
11
Alternative Route: The alternative routes identified during the prioritization study would not achieve the
required rural road network and are more expensive.
Planned Project Alternative: This alternative will link the rural areas, and the anticipated rural access and
associated socio-economic development will be achieved. They are economically and socially viable.
ES.5 Identified Potential Economic and Social Impacts for ARAP
Tables ES.1 and ES.2 provide details of identified social and economic impacts requiring abbreviated
resettlement action plans.
Table ES.1: Potential Economic and Social Impacts for ARAP: Umuaniagu on Road #13
#.
Location
Chainage
Existing Economic and
Social Conditions
Potential
Impacts
ARAP Proposals
and Compensation Plan
Number
of PAPs
Land Area
Per Person
(m2)
1.
Umuaniagu
Village on
Road #13
2+050
Three (3) major traditional
religion shrines located
within the RoW of the
proposed road and belong
to the community. They are
a communal cultural
heritage sites.
Shrines will be
encroached
upon and
eliminated
The shrines will be
relocated to locations
religiously acceptable to
the community but will be
outside the RoW of the
proposed road. The
community through the
custodian of the shrines
will be compensated for
the cost of relocation
The community
is affected by the
project but one
person, the high
priest, who is the
custodian of the
major shrines will
collect the
compensation
1
NA
2.
Umuaniagu
Village on
Road #13
2+050
to
2+550
63 Oil Palm Trees and 54
Fruit Trees on Cassava
Farmland on the RoW of
the proposed road.
Trees on
Cassava
Farmland will
be encroached
upon and
eliminated.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
19
NA
3.
Umuaniagu
Village on
Road #13
2+050
to
2+550
4,500 square metres of
Cassava and Farmland on
the RoW of the proposed
road.
Cassava crops
will be
destroyed and
Farmland
encroached
upon.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
100
45.0
Table ES.2: Potential Economic and Social Impacts for ARAP: Ojor on Road #12
Land Area
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
12
#.
Location
Chainage
Existing Economic and
Social Conditions
Potential
Impacts
ARAP Proposals
and Compensation Plan
Number
of PAPs
Per Person
(m2)
1.
Ojor
Community
on Road
#12
8+825
Three (3) major shrines
(3m x 3m) and forty(40)
minor shrines (worship
spots under trees), all
traditional religion shrines
of the community are
located within the RoW of
the proposed road. They
are a communal cultural
heritage site.
Shrine
locations will
be encroached
upon and
destroyed
The shrines will be
relocated to locations
religiously acceptable to
the community but will be
outside the RoW of the
proposed road. The
community through the
custodians of the shrines
will be compensated for
the cost of relocation
The community
is affected by the
project but one
person, the high
priest, who is
the custodian of
the shrine will
collect the
compensation
for 3 major
shrines and five
persons
representing five
families will
collect
compensation
for 40 minor
shrines
6
NA
2.
Ojor
Community
on Road
#12
8+825
to
9+075
1,200 square metres of
Cassava and Farmland on
the RoW of the proposed
road.
Cassava will be
destroyed and
Farmland
encroached
upon.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
34
35.294
3.
Ojor
Community
on Road
#12
8+890
A community transformer
with protective blockwall
(5m x 5m) is on the RoW
of the proposed road.
Community
transformer
will be
damaged.
Community
may be
disconnected
from national
grid.
The transformer will be
relocated about 10metres
away from its current
location. The cost of
relocation will be paid to
the community through
the traditional ruler, who
will coordinate the
relocation assignment.
1
NA
4.
Ojor
Community
on Road
#12
9+200
to
9+800
Land area (600m x 6m) i.e.
3m on either sides beyond
the cassava farm to be
acquired for the road.
Road works
will encroach
on the land
This is a case of land
acquisition for the road
project and compensation
will be paid to the owners.
The land
belongs to the
traditional ruler
1
3,600
ES.6 Categories of PAPs: Table ES.3 below give the categories of PAPs on the project routes. The categories
do overlap in Table ES.3: Categories of Project Affected Persons
Location
Project Affected People
Sub-
total
Fully Affected
Removal of
Plantation
Land
Acquisition
Relocated or
Shifted backwards
Umuaniagu (Ozalla) on Road #13) 19 100 3 100
Ojor Village (on Road #12) 0 40 6 40
Total 140
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
13
ES.7 Results of Socio-economic Survey of Project Affected Peoples (PAPs): Tables ES.4 to ES.10 provide the
outcomes of the census and socio-economic survey of PAPs in the two project affected villages.
Table ES.4: Number of PAPs Enumerated
Table ES.5: Gender Distribution of PAPs
Project Affected Area
Male
%
Female
%
Total
Umuaniagu (on Road #13) 49 49.0 51 51.0 100
Ojoo (on Road #12) 20 50.0 20 50.0 40
Table ES.6: Number of Dependants of PAPs
Project Affected Area
Range of Dependants (%)
1-2 3-5 6-8 9 & above
Umuaniagu (on Road #13) 42 50 7 1
Ojoo (on Road #12) 15 55 20 10
Table ES.7: Occupation of PAPs
Project Affected Area
Occupation of PAPs (%)
Farming
Transport
Operator
Petty
Trading
Umuaniagu (on Road #13) 60 40
Ojoo (on Road #12) 55 10 35
Table ES.8: Net Daily Income of PAPs
Project Affected Area
Net Daily Income of PAPs (NGN)
Less than 500 500-1000 1001-1500 1501-2000 Above 2000
Umuaniagu (on Road #13) 52 40 7 1 0
Ojoo (on Road #12) 22 15 3 0 0
ES.8 RESETTLEMENT BUDGET AND FINANCING
Budgetary provisions have been made in the proposed rural road project to ensure that the mitigation
commitments, including compensation and the monitoring programs are fully implemented. FPMU/SPIU shall
make direct payments to all project affected persons and this will be done after an audit of eligible PAPs
would have been carried out. This audit is a physical verification exercise to further confirm the actual
number of PAPs by requesting them to appear physically for identification, to confirm the number of PAPs
that are still alive as of the time of compensating them, to check against multiple registrations and to issue
them identification cards. In a case, where a PAP is demised as of the time the compensation would be
paid, their children will be identified and paid the deceased’s compensation. The overall budget for the
resettlement action plan is presented in Table ES.5.
Project Affected Area
#. of PAPs Enumerated
%
Umuaniagu (on Road #13) 100 71.4
Ojoo (on Road #12) 40 28.6
Total 140 100
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
14
Table ES.5: ARAP Budget for Enugu State RAMP Roads
#.
Location/Description
Unit
Quantity
Rates
(NGN)
Total Amount
(NGN)
1.0
UMUANIAGU (OZALLA) Community on Road #13
1.1
4,500 Square Metre of Cassava Farmland @ Umuaniagu
SQ.M
4,500
925.926
4,166,667.00
1.2
Major Traditional Religious Shrine @ Umuaniagu
Nos.
3
250,000
750.000.00
1.3
Baskets of Cassava Lost to Road Encroachment
Nos.
281
1,500
421,500.00
1.4
Palm Trees Lost to Road Encroachment
Nos.
63
18,000
1,134,000.00
1.5
Other Valuable Trees Lost to Road Encroachment
Nos.
54
15,000
810,000.00
Sub-Total for Umuaniagu Community on Road #13 N7,282,167.00
#.
Location/Description
Unit
Quantity
Rates
(NGN)
Total Amount
(NGN)
2.0
OJOR Community on Road #12
2.1
Virgin Land @ Ojor
SQ.M
3,600
925.926
3,333,333.60
2.2
Major Traditional Religious Shrine @ Umuaniagu
Nos.
3
250,000
750,000.00
2.3
Minor Traditional Religious Shrine @ Umuaniagu
Nos.
40
2,000
80,000.00
2.4
Cassava Farmland @ Ojor
SQ.M
1,200
925.926
1,111,111.20
2.6
Baskets of Cassava Lost to Road Encroachment
Nos.
75
1,500
112,500.00
2.7
Relocation of Community Transformer
LS
750,000.000
3.0 Sub-Total for Ojor Community on Road #12 N6,136,944.53
4.0 Total for Umuaniagu and Ojoo Communities N13,419,111.53
5.0 Cost for Impact Monitoring (5% of 4.0) N670,955.58
6.0 Sub-Total N14,090,067.11
7.0 Contingency (5% of 6.0) N704,503.36
Total ARAP Cost Estimate for Enugu RAMP ROAD PROJECTS
N14,794,570.47
1.0 INTRODUCTION
1.1 BACKGROUND ON THE PROJECT
The Federal Government of Nigeria has commenced with the implementation of the Rural
Access and Mobility Project (RAMP) in Enugu State with support financing from the World Bank
and the Agence Francaise De Developpment (AFD) and guided by the Government’s Rural
Travel and Transport Policy (RTTP). The lead agency for the Federal Government is the Federal
Department of Agriculture (FDA) of the Federal Ministry of Agriculture and Rural Development
(FMARD). The Federal Project Management Unit (FPMU) is overseeing the project on behalf of
FDA, while the Enugu State Government is expected to implement it. The administrative map of
Enugu State is shown in Figure 1.1.
The overall objectives of RAMP is to support participating state and local governments in
providing improved all-weather access roads in selected and prioritized rural intervention
areas, rehabilitate prioritized river crossings and support the institutional reforms in the transport
sector leading to optimization and improvement of the sector management in Enugu State.
This component involves the rehabilitation works for an indicative 203.45kM of rural and state
roads in Enugu State as well as the related design studies and external supervision activities.
1.2 Objective of RAMP 2
The objective of RAMP 2 is to provide rural communities with improved access to social services
and economic opportunities, and to enhance the capacity of relevant government institutions
to better manage rural transport infrastructure. The indicative objective is to rehabilitate
203.45km of rural roads in Enugu State. Road standards will be determined as part of the road
design studies, with proper economic justification. Considering traffic levels observed on rural
roads in Enugu state (current average daily vehicle traffic (AADT) of less than 50 vehicles per
day (vpd) and typical current motorcycle traffic of 50 to 100 cycles per day), it is expected
that the RAMP-2 project will rehabilitate existing roads, without any paving/asphalt treatment
involved. The list of the high priority roads in six (6) intervention areas in Enugu State is detailed
in Table 1.1 and the sub-division of the state into intervention areas is shown in Figure 1.2.
1.3 General Objective of the Consultancy Services
The objective of the various consultancy services is to carry out detailed engineering design
including cost estimates as well as environmental and social studies and to prepare the
bidding documents for prioritized rural road rehabilitation works in the state of Enugu. The
different assignments therefore involve survey of the roads, soil and materials testing, detailed
Engineering design, drainage structure design, preparation of detailed working drawings and
bidding documents as well as Bill of Engineering Measurement and Evaluation (BEME) and
confidential cost estimate. Also conducted was an Environmental and Social Impact
Assessment (ESIA) for the selected road rehabilitation works- together with the associated
Environmental Management Plan, and, where appropriate, a Resettlement Action Plan (RAP).
One set of studies and bidding documents will have to be prepared for each of the four
prioritized clusters of roads in Enugu State, for respectively 59.26km, 57.16km, 42.22km and
44.81km of roads. (See Table 1.1).
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
16
Figure 1.1: Administrative Map of Enugu State showing the Senatorial Districts
Figure 1.2: RAMP Intervention Area Map of Enugu State
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
17
1.4 Objectives of the ARAP Study
The objective of the ARAP is to clarify the principles and procedures that will govern the
mitigation of adverse social impacts induced by project operations. Specifically, the ARAP is
designed to ensure:
All types of losses are identified, clearly defined and properly categorized to reflect the
nature of the loss.
A standard or measure for defining eligibility and entitlement in order to have a fair basis
for assessing compensation for the loss or impact suffered.
Compliance with provisions of the Laws of the Federal Republic of Nigeria and World Bank
Operational Policies (OP 4.12, paragraph 2(b)): that resettlement activity would be
conceived and executed as development programs, providing sufficient investment
resources to enable the PAPs to share in project benefits.
Displaced persons will be compensated for their losses at full replacement cost and
provided assistance for disturbance prior to the beginning of civil works.
A comprehensive database, based on which values will be assessed, validated in the
event of disputes and more importantly serve as the database for monitoring and
evaluation of the resettlement instrument.
The project affected persons would be consulted and given the chance of participating
in the design, implementation and monitoring of the resettlement.
1.5 Land Acquisition and Resettlement Plan Objective
The resettlement action plan for the road project is driven by the objectives of the World Bank
OP 4.12 to avoid involuntary resettlement where feasible, or minimise, explore all viable
alternative project designs. Land acquisition along the route will be minimal and restricted to
the existing right of way. The project will require the acquisition of new lands due to
encroachment of the roads’ rights of way on farmlands and virgin lands in two villages but the
acquisition will not extend beyond the required space in the right of way and set- backs.
Eligible people for resettlement and assistance are the Project Affected Person (PAP) identified
in locations where there is encroachment into the RoW. Permanently displaced persons and
properties shall be relocated to other vacant spaces within the project area, while temporarily
displaced persons will be required to shift backwards, away from the RoW.
This Abbreviated Resettlement Action Plan (ARAP) aims at developing resettlement and
compensation criteria as well as institutional arrangements to meet the requirements of the
people who may be affected by the proposed project. The anticipated impacts on people
include land acquisition, loss of physical structures, loss of access to livelihood and loss of
access to economic resources. The ARAP is prepared to the standards and specifications of
relevant legislations of the Federal Republic of Nigeria, the Enugu State Government, and the
operational policy of the World Bank, OP 4.12. This ARAP will assess (quantify and qualify) the
presumed adverse impacts of its road rehabilitation operations and suggest mitigation
measures including budget to address the issues.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
18
1.6 Description of the Road Projects
Table 1.1 provides the names, lengths, locations, intervention areas of the high priority roads
and rural roads requiring ARAP under the second stage of the Rural Access and Mobility
Project (RAMP2) in Enugu State. Table 1.1: Prioritised Clusters of Roads in Enugu State
Cluster
Description: Intervention Areas and Road Links
Length
(KM)
ARAP?
1.
UDI Intervention Area
Rd 32 Umuabi-Ehuhe Achi Road 9.48km
Rd 36 Abor Road 4.46km
Rd 37 Egede – Awhum Road 6.50km
Rd 39 St. Mary Ngwo – Nsude Road: 6.25km
EZEAGU/OJI RIVER Intervention Area
Rd 41 Ugwuoba – Nkwere Inyi- Inyi Road 19.88km
Rd 42 Isu Abaraji – Akpugo Eze – Inyi Market Road 12.69km
Total for Cluster #1 59.26kM
2.
NKANU EAST/NKANU WEST/ENUGU SOUTH Intervention Area
Rd 13 UNTH – Enuguagu Ndiagu-Umuaniagu–Obe – Amuri Road 11.88km Yes
Rd 18 Mbogodo – Obinagu Uwani Akpugo – Ihuokpara Road 15.0km
ANINRI/AWGU Intervention Area
Rd 23 Mamaku-Awangbidi-Nkwe-Ezere-Isuochi Road 9.28km
Rd 24 Uhueze Nenwe – Nomeh – Mburubu – Nara Road 21.00km
Total for Cluster #2 57.16kM
3.
IZI UZO Intervention Area
Rd 3 Neke – Umualor Road 16.84km
Rd 5 Neke – Mbu – Ogbodo Aba – Obollo Etiti Road 25.38km
Total for Cluster #3 42.22kM
4.
UZO UWANI Intervention Area
Rd 9a Ukpabi – Nimbo – Ugbene Ajima – Eziani Road 28.62km
Rd 9b Ikwuoka –Amagu – Ajuona – Akabusiyi – Obimo Road 6.25km
Rd 12 Adani – Asaba – Igga - Ojor 9.94km Yes
Total for Cluster #4 44.81kM
Grand Total
203.45kM
1.7 Description of the Proposed Works
1.7.1 Description of the Proposed Works
The project will involve works at the pre-construction phase, construction phase and
operational phase. Pre-construction phase activities involved investigation of:
Location of borrow pits, PAPs and the affected natural and human resources
Location of sources of water to be used in construction activities; and
Road alignment survey, traffic survey along the roads and engineering design.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
19
Construction phase activities will involve the following:
Construction of all roads listed on Table 1.1 of a total length of 203.45km;
Placement of road signs along the road.
Construction of the roads in communities will also require the provision of some basic road
infrastructures such as road signs etc other activities will include:
Haulage of materials;
Construction of temporary work camps;
Earthworks; and Construction supervision and monitoring.
After road reconstruction, the following measures will be undertaken:
Landscaping on specific sites where necessary;
Tree planting along the corridors, and
Road safety measures, such as bumps and signage.
1.8 Site Visits and Survey
To understand the biophysical nature of the roads alignment area the field team visited the
site. A survey along the roads alignment was done and observations made of human habitat,
vegetation and existing ecosystems and places of cultural significance among others. The site
was visited between 19th and 23rd March, 2012 for route alignment identification, confirmation
and conduct baseline studies. A detailed site investigation for social and environmental studies
was then carried out from 16th to 20th April, 2012 and a census of PAPs from 28th to 30th May,
2012. The outcome of the census of PAPs are detailed in Chapter 3.0: Socio-economic survey
of Project Affected Persons of this report. During the site visits, the team held consultations with
members of the community and project affected persons.
1.9 Public Consultations
Two project roads, Road #13: UNTH-Enuguagu Ndiagu-Umuaniagu-Obe Amuri Road (11.88kM)
and Road #12: Adani-Asaba-Igga-Ojor Road (9.94kM) have been identified to have potential
environmental and social impacts that will involve compensation to and relocation of project
affected persons (PAPs) at Umuaniagu and Ojor respectively. Public Consultation is a
requirement for RAP study by the Federal Ministry of the Environment and the World Bank. The
Consultant through the help of SPIU and community leaders held consultations with the two
identified project affected communities and persons living adjacent to the road alignments
during the site visits. During these meetings, the affected communities were informed on the
encroachment of the proposed roads on their farmlands, shrines and communal facility. The
Consultant’s public consultation was done in two stages.
Meetings/Consultations were held with the communities where 148 community members
were present at Umuaniagu (Ozalla) and 58 community members were in attendance at
Ojor. The two communities were notified of the meetings on 23rd May, 2012 through the
SPIU and were reminded by text messages and phone calls. The Umuaniagu consultation
was held on 29th May, 2012; the Ojor consultation was held on 30th May, 2012. The
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
20
consultation informed the communities of the proposed project; the feedback from these
meetings included the acceptance by the people of the communities for the roads to
pass through their communities. Men and women from both communities attended these
public consultations.
After the community consultation, specific meetings were held with identified project-
affected persons and the extents of encroachment, resettlement and compensation
were determined. The PAPs were constituted by both men and women. One hundred
(100) PAPs (49 Males and 51Females) were surveyed in Umuaniagu (Ozalla) Community
and forty (40) PAPs (20 Males and 20 Females) were consulted in Ojor Community.
1.10 Potential Economic and Social Impacts
Though during project preparation, the exact locations for project activities were known in
sufficient details, the real economic and social impacts, in terms of land acquisition, loss of
economic activities and who the Project Affected Persons (PAPs) are were not known.
Subsequently, Environmental and Social Management Framework (ESMF) and Resettlement
Policy Framework (RPF) outlining the principle and procedures that would be followed in
preparing site specific Environmental and Social Impact Assessment (ESIA) and Abbreviated
Resettlement Action Plans (ARAPs) were prepared by FPMU and disclosed by the project in
Nigeria and at World Bank InfoShop prior to appraisal in May, 2011. The ESMF and RPF have
screening mechanisms/checklists for screening subproject for their EA category, potential
environmental and social impacts as well as the needed mitigation measures. The two
safeguard instruments as noted in the RAMP PAD provided the mechanisms to identify impacts
for which standard mitigation measures are suggested and will be applied during the
implementation phase.
The economic and social screenings/surveys as indicated by Tables 1.2 and 1.3 below have
shown that the projects will not involve significant land acquisition because the projects will be
carried out for most part on the existing right of way (RoW) and footpaths with minor land
acquisition. Only two communities i.e. Ozalla/Umuniagu on Road #13 and Ojoo on Road #12
will be affected. Temporal farm lands and cultural sites and communal facilities along the RoW
of the roads corridors will be displaced affecting access to means of livelihood. The total area
of land to be acquired is 9,300 square metres, affecting 129 households and 140 people. The
World Bank’s Operational Policy 4.12 (Involuntary Resettlement) is therefore triggered. This
abbreviated RAP has been prepared in line with the Resettlement Policy Framework.
Hence, the need to prepare an abbreviated resettlement action plan (ARAP) in line with World
Bank OP 4.12 to ensure that the Project Affected Persons (PAPs) are adequately compensated
or provided assistance. The goal of this Abbreviated Resettlement Action Plan is to provide
actual resettlement plan for the projected affected people in Enugu State.
One hundred (100) PAPs (49 Males and 51Females) were affected by the project in Umuaniagu
(Ozalla) Community and forty (40) PAPs (20 Males and 20 Females) were affected by the
project in Ojor Community. Two project roads, Road #13: UNTH-Enuguagu Ndiagu-Umuaniagu-
Obe Amuri Road (11.88kM) and Road #12: Adani-Asaba-Igga-Ojor Road (9.94kM) have been
identified to have potential economic and social impacts that will involve compensation to
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
21
and relocation of project affected persons (PAPs) at Umuaniagu and Ojor respectively. There
are altogether one hundred and forty (140) PAPs are affected by the projects in the two (2)
communities.
Therefore, from the above, the project would qualify for Abbreviated Resettlement Action Plan
(ARAP).
Table 1.2: Potential Economic and Social Impacts for ARAP: Umuaniagu on Road #13
#.
Location
Chainage
Existing Economic and
Social Conditions
Potential
Impacts
ARAP Proposals
and Compensation Plan
Number
of PAPs
Land Area
Per Person
(m2)
1.
Umuaniagu
Village on
Road #13
2+050
Three (3) major traditional
religion shrines located
within the RoW of the
proposed road and belong
to the community. They are
a communal cultural
heritage sites.
Shrines will be
encroached
upon and
eliminated
The shrines will be
relocated to locations
religiously acceptable to
the community but will be
outside the RoW of the
proposed road. The
community through the
custodian of the shrines
will be compensated for
the cost of relocation
The community
is affected by the
project but one
person, the high
priest, who is the
custodian of the
major shrines will
collect the
compensation
1
NA
2.
Umuaniagu
Village on
Road #13
2+050
to
2+550
63 Oil Palm Trees and 54
Fruit Trees on Cassava
Farmland on the RoW of
the proposed road.
Trees on
Cassava
Farmland will
be encroached
upon and
eliminated.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
19
NA
3.
Umuaniagu
Village on
Road #13
2+050
to
2+550
4,500 square metres of
Cassava and Farmland on
the RoW of the proposed
road.
Cassava crops
will be
destroyed and
Farmland
encroached
upon.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
100
45.0
The location maps of Road #13 and Road #12 are shown on Figures 1.3 and 1.4 respectively.
Their locations in Nkanu West/Nkanu East/Enugu South intervention area and Uzo Uwani
intervention area are indicated on Figure 1.2 and Table 1.1.
The procedures for relocation and compensation for relocation of major and minor shrines are
detailed in Annex 3A and Annex 3B respectively.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
22
Table 1.3: Potential Economic and Social Impacts for ARAP: Ojor on Road #12
#.
Location
Chainage
Existing Economic and
Social Conditions
Potential
Impacts
ARAP Proposals
and Compensation Plan
Number
of PAPs
Land Area
Per Person
(m2)
1.
Ojor
Community
on Road
#12
8+825
Three (3) major shrines
(3m x 3m) and forty(40)
minor shrines (worship
spots under trees), all
traditional religion shrines
of the community are
located within the RoW of
the proposed road. They
are a communal cultural
heritage site.
Shrine
locations will
be encroached
upon and
destroyed
The shrines will be
relocated to locations
religiously acceptable to
the community but will be
outside the RoW of the
proposed road. The
community through the
custodians of the shrines
will be compensated for
the cost of relocation
The community
is affected by the
project but one
person, the high
priest, who is
the custodian of
the shrine will
collect the
compensation
for 3 major
shrines and five
persons
representing five
families will
collect
compensation
for 40 minor
shrines
6
NA
2.
Ojor
Community
on Road
#12
8+825
to
9+075
1,200 square metres of
Cassava and Farmland on
the RoW of the proposed
road.
Cassava will be
destroyed and
Farmland
encroached
upon.
This is a case of land
acquisition for the road
project.. The owners will
be compensated for both
economic loss and land.
34
35.294
3.
Ojor
Community
on Road
#12
8+890
A community transformer
with protective blockwall
(5m x 5m) is on the RoW
of the proposed road.
Community
transformer
will be
damaged.
Community
may be
disconnected
from national
grid.
The transformer will be
relocated about 10metres
away from its current
location. The cost of
relocation will be paid to
the community through
the traditional ruler, who
will coordinate the
relocation assignment.
1
NA
4.
Ojor
Community
on Road
#12
9+200
to
9+800
Land area (600m x 6m) i.e.
3m on either sides beyond
the cassava farm to be
acquired for the road.
Road works
will encroach
on the land
This is a case of land
acquisition for the road
project and compensation
will be paid to the owners.
The land
belongs to the
traditional ruler
1
3,600
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
23
Figure 1.3: Location Map of Road #13
Figure 1.4: Location Map of Road #12
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
24
1.11 Approach and Methodology
1.11.1 Research Reports and Surveys
This report is built upon the following works;
i. An Environmental and Social Management Framework (ESMF) including Environmental
and Social Management and Monitoring Plans of May 2008 produced by the Federal
Project Management Unit of RAMP for Enugu and Osun States.
ii. A Resettlement Policy Framework produced by the Federal Project Management Unit of
RAMP.
iii. Prioritisation Study Report for Enugu State prepared by Pheman Peniel Consultants for
FPMU in 2010.
iv. RAMP2 project appraisal document of 2011.
v. Terms of Reference for the preparation of ARAP report by FPMU.
vi. Reporting format prepared and made available by FPMU’s ARAP Consultant
These reports form an important backdrop to this report. They are available from the FPMU
Office.
1.11.2 Compliance with the National, State and International Land-use and Resettlement
Standards
The approach taken throughout this report is consistent with the policy guidelines of the
following bodies.
i. Federal Ministry of the Environment of Nigeria’s Environmental Guidelines(1999
Presidential Directives)
ii. Land-use Act Cap 202 LFN 1990
iii. Nigerian Urban and Regional Planning Law No. 88, 1992
iv. Other Government laws and regulations regarding environment and social issues;
v. World Bank Environmental and Social Safeguard Policies (OP4.01, BP4.01 and GP4.01)
vi. World Bank Operational Policy (OP 4.12) on Involuntary Resettlement;
vii. World Bank Rural Roads Checklist;
.
1.11.2 Public Consultations
1.11.2.1 Methodology for the Identification and Selection of Project-affected Persons (PAPs)
In each of the villages affected, as soon as the economic and social impacts of the proposed
road projects were determined and the affected land, farms, shrines and structure were
identified, the traditional ruler of the community was contacted and was briefed of the project,
its importance and the need for the project to acquire land, involuntarily displace people and
their livelihood, shrines and communal structures. Thereafter, the traditional leader
communicated this development to his council of chiefs at a meeting they held after our first
visit in April, 2012. The outcome of the combined meeting of the elders and the traditional
leader was that the proposed road project was welcomed with enthusiasm and they pledged
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
25
on their part to fully support and participate in the implementation of the project. They also
decided to convene a meeting of all project affected families and persons in order to properly
identify those actually affected by the project to the combined team of the Consultant and
SPIU. In each village, a meeting of all potentially affected persons and their village traditional
council was held on May 28th, 2012 prior to the project team meeting with them on May 29th
and May 30th, 2012. It was at this meeting, that the traditional council screened all the
potentially affected people and came out with a final list of those that are actually affected.
Individual PAPs and families confirmed these lists and ensured that all potential PAPs were on
the lists. Officials of the SPIU also verified the authenticity of the lists before final submission to
the project team. These lists were passed to the visiting project team in Umuaniagu on May
29th, 2012 and in Ojor on May 30th, 2012. The lists of PAPs for Umuaniagu and Ojor are given
under Annexes 1A and 1B of this report.
The project team had meeting with the identified PAPs in Umuaniagu and Ojor on May 29th,
2012 and May 30th, 2012 respectively and had a joint visit to the areas of economic and social
impacts. (See Annexes 2A and 2B for minutes of meetings).
A survey of PAPs and associated project-affected properties was carried out between 29th and
30th May, 2012 after identifying PAPs. Observations made of human habitat, vegetation and
existing ecosystems and places of cultural significance among others. A preliminary visit was
made to the site between 19th and 23rd March, 2012 for route alignment identification,
confirmation and conduct baseline studies. Further site investigation for social and economic
studies was carried out from 16th to 20th April, 2012. During the site visits, the team was also able
to meet other relevant stakeholders such as the traditional rulers, local government officials,
women organizations and youth organisations. The list of stakeholder groups consulted are
provided in Annex 4 of this report.
1.11.3 Project Alternatives
For the proposed roads rehabilitation project, a number of alternatives were considered and
these include: a no-project alternative; delayed project alternative; an alternative site and the
planned project alternative. A summary of these alternatives is presented below:
1.11.3.1 No-Project Alternative
This alternative assumes that the entire project concept will be cancelled and scrapped. This is
an inferior alternative when compared to the option of going ahead with the project.
Although if this option is taken, it would mean that the negative economic and social impacts
of the project would be completely avoided, not implementing the project will also lead to:
(i) Continued lack of rural access and mobility
(ii) Continued lack of economic empowerment, development and transformation in the
rural areas.
(iii) Failure to generate employment opportunities as anticipated;
1.11.3.2 Delayed Project Alternative
This option means that the project will not be implemented at this time; rather, a delay will be in
effect until such a time when certain conditions are met or requirements fulfilled. This kind of
option is usually adopted when there are regulatory requirements that need to be met, when
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
26
the political and economic climate is inclement for project implementation or in a period of
war. Presently, the country is not at war. Similarly, the government of Nigeria is encouraging
and courting foreign direct investment (FDI) and socio-economic development. The planned
project can attract foreign investment, in addition to all the added values indicated earlier.
Therefore, delaying the project will in turn delay the realization of the positive benefits
expected from the project. In addition, given the very high level of inflation in Nigeria’s
economy, a delay of 1 year could potentially cause up to a 25% increase in project costs.
Therefore the option of delaying the project is not an optimal one.
1.11.3.3 Alternative Project Location
A prior study identified the current routes as being one of the priority roads under RAMP. While
there are other route options from the initial prioritization study, the costs, especially in terms of
resettlement and compensation are quite high and would render the entire project unfeasible.
Therefore, the current project routes appears to be the most expedient, based on the various
considerations and as such, an alternative location will not be optimal.
1.11.3.4 The Planned Project Alternative
This alternative assumes that the planned project will proceed as conceptualized. This means
that the rural roads will be reconstructed and will cover a total distance of 203.45km. This
alternative will also include the construction of drainage along the route.
This alternative involves a lot of construction work, along with the associated positive and
negative impacts. The essence of a project of this nature is to ensure that activities are
undertaken in a way that minimizes the negative impacts while enhancing the positive
impacts. To this end, there is a need for detailed description of the project, so that any activity
that can result in negative impacts on the environment (biophysical and socio-economic) can
be easily identified and remedial measures planned for them.
1.11.4 Inventory of Potential Losses
The combined team of the Consultant and SPIU have visited each section of the roads to
identify any assets and people who may be negatively affected by the proposed road-works.
An inventory of potential losses has been developed for each section and had formed the
basis of the ARAP. Discussions with affected persons and communities regarding compensation
options and grievance redress procedures have been completed for the affected roads.
1.11.5 Methodology for the Valuation of Assets
This valuation was carried out by the Consultant’s Contract/Procurement Specialist. Part of his
duty is to prepare cost estimates for all items of work under the current contract. In appraising
the properties affected by the road project, a combination of the Replacement Cost and the
Direct Capital Comparative Methods were used in arriving at the open market capital value of
the structures, plantation and land. Market research of current prices of similar assets was
carried out in the vicinity of the project and the agreed final prices were adopted in
consultation with the PAPs. The PAPs were adequately involved in the negotiations that
produced and in agreement with the rates and figures that were applied in computing the
final compensation costs. (See Annexes 2A and 2B for minutes of meetings with PAPs and Table
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
27
4.12-Entitlement Matrix). More detailed information on the two methods of valuation are
available in Chapter Four of this report.
1.11.6 Calculation of ARAP Costs
The ARAP budget for Enugu RAMP Roads is provided under Table 9.1 in Chapter 9 of this report.
1.11.7 Implementation Schedule
The schedule of implement the ARAP is given under Table 10.1 in Chapter 10 of this report.
1.11.8 List of PAPs, their Affected Structures and Compensation
The list of PAPs, their affected structures and computed compensations are available in
Annexes 2A and 2B for Umuaniagu and Ojor respectively
1.12 Communication Principle
The main objectives of the communication plan are to provide sufficient and accessible
information to the PAPs, communities along the routes of the project roads, women
organisations, youth organisations and other stakeholders in an objective manner in order
to allow them to know and be sensitised about the project and consequently to be
actively involved in project implementation. The communication plan is also supposed to
promote awareness of the project-associated ARAP to the PAPs and affected
communities.
1.12.1 Project Phases
The various phases of the project identified for communication purposes include:
i. Preparation and design;
ii. Implementation (i.e. preconstruction and construction); and
iii. Post construction and evaluation.
1.12.2 Communication Stages and Tools
The communication strategy to be used during three phases of the project involves a three-
step approach:
i. Stakeholder sensitization;
ii. Public education; and
iii. Evaluation.
This three-step approach is directly linked to the phases identified above i.e. (1)Preparation
and design; (2) Implementation (i.e. preconstruction and construction); and (3) Post
construction and evaluation.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
28
(i) Stakeholder Sensitization
The stakeholders will be informed about Enugu State rural road projects under RAMP2, the type
of roads to be provided and create a mechanism for interaction with stakeholders in general,
including those based in the project affected communities, communities along project routes
and intervention areas, NGOs, youth organisations, transport unions, farmers association, local
government administrators, state institutions, students, women organizations, traditional rulers
and custodians of community cultural heritage. Stakeholder sensitization will continue
throughout the three stages of project implementation, but will be very significant during
Preparation and Design phase.
A number of communication tools that has been identified and will be used to disseminate
information include but not limited to: Workshops Consultation and Educational materials
(ii) Public Education
Sensitizations at this level will be targeted at the general public who are the ultimate
beneficiaries of the project. The Abbreviated Resettlement Action Plan will be disclosed and
publicly displaced as. Disseminate information on the criteria for selecting the PAPs, economic
and social impacts of the projects were determined and continue to spread information
regarding the type of projects to be funded under RAMP2. FPMU/SPIU will place the ARAP in
designated places and at least through the construction phase. These will consist of Local
Government Area headquarters in the two intervention areas, Enugu State Government
secretariat, palaces of traditional rulers, Federal Ministry of Environment, FPMU office, SPIU office
and any other public place as directed by the World Bank. FPMU/SPIU will run public
advertisement in the electronic media on the availability of the ARAP report in designated
places. FPMU will advise its public relations and legal units to maintain contact with the
relevant Ministries, other public agencies, local representatives and communities. A channel of
interaction with stakeholders will be consolidated. Public education will be more pronounced
during Implementation (i.e. preconstruction and construction) phase. .
The focus will be on communication through the media. The strategy to be employed will
include: Radio and television interviews, Newspaper advertisements, Radio and television
advertisements and documentaries, Billboards, Handbills and other published materials.
Additionally, there will be a series of seminars and public consultations to educate the general
public. However, it must be noted that the Enugu RAMP State project office have already
conducted some sensitization on the project.
(iii) Evaluation
The assessment process during this phase includes but not limited to: Evaluation of participation
in and feedback from workshops/conferences/discussions/ presentations, Evidence of strategy
implementation, Evidence of translation of strategy into work operations, Tracking media
coverage including volume and nature of coverage, Tracking Parliament/Government and
social discussions on the project and Monitoring website usage (eg. search hits).
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
29
This stage of communication will be necessary the third phase of project implementation i.e.
Post-construction and Evaluation.
The communication tools will be print and electronic media. The strategy to be employed will
include: Newspaper advertisements, Radio and television advertisements and documentaries,
and Handbills and other published materials.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
30
2.0 LEGISLATIVE AND REGULATORY FRAMEWORK
2.1 Introduction
The Federal Government of Nigeria and the World Bank are committed to ensure that the
involuntary resettlement of people and their economic activities and disruptions of economic
activities of PAPs in the project zone does not result in socio-economic hardship for the
affected persons. Nigeria recognizes that improving safety in the road corridor by modifying
existing land use within the safety corridor in the road reservation (i.e. partial or complete
demolition of sheds, building and farmlands) requires the application of both national policies
and laws and the relevant policies of the World Bank- the financing institution of the RAMP
project.
Resettlement of PAPs will be carried out in accordance with an abbreviated RAP prepared in
accordance with the RAMP2-specific Resettlement Policy Framework (RPF).
2.2 Identification and Categorisation of Loss and Impact
The implementation of RAMP II project will lead to some degrees of land acquisition which in
turn, could lead to physical displacement from land (e.g. denial of access to usual means of
livelihood). It must be noted that project affected persons will be identified by the types of
losses they suffer or the impact of the project on them.
Project implementation personnel will:
i. Ensure that identification and categorization of the likely loss or impact is undertaken
during the planning and design stages of each sub-project;
ii. Establish the magnitude and coverage of impacts early in the project planning in order
to justify the resettlement instrument to adopt. General categorization of losses will be
done to reflect extent of loss in terms of the following: Permanent or Temporary Loss; Full
or Partial Loss; Minimal or Significant Loss
iii. Determine specific losses or impacts to reflect the exact nature of loss whether visible
and tangible or intangible and categorize into the following losses: Physical loss of assets
which will be determined by assessing the interest or right to ownership, occupation and
possession; Loss of income, loss of livelihood and opportunities to employment; Impacts
arising from disturbance/disruptions.
2.2.1 Project Affected Persons (PAPs)
Project Affected Persons (PAPs) are those who stand to lose as a consequence of the project,
all or part of their physical and non-physical assets, landed properties, farmlands or productive
lands, economic crops, important cultural sites such as shrines and community facilities. Such
impacts may be permanent or temporary. In this ARAP, the PAPs consist of; individuals who
have their land acquired as part of establishment of RoW, individuals who carry out livelihood
activities in the RoW, individuals who are custodians of historical cultural sites and individuals
(traditional) rulers who are custodians of communal facilities.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
31
Essentially, the PAPs may be classified into two groups: Those who have formal legal rights to
the land they occupy; Those who do not have formal legal rights to land, but have a claim to
land that is recognized or recognizable under the national, local, or traditional laws including
those measures put in place by the land policy.
2.2.2 The Screening Process
Each project proposed for inclusion in the RAMP II projects was screened and classified
according to its economic and social impact. A reconnaissance survey was carried out by
inspecting and detailing each road’s existing conditions, facilities, structures and features. The
roads were screened for the following; environmentally sensitive areas, displacement and
resettlement of livelihood activities, historical cultural sites, economic assets, general positive
impacts, general negative impacts and communal facilities. The outcome of the screening
exercise are given under Tables 1.2 and 1.3.
Therefore, the steps undertaken for the ARAP study included a screening process as described
above; a socioeconomic census and land asset inventory of the area; and identification of
Project Affected Persons (PAPs). This was followed by the development of a Abbreviated
Resettlement Action Plan. Thereafter the ARAP will be approved by the Bank, implemented
and monitored. The goal of screening is to identify and consider resettlement issues as early as
possible.
2.3 Eligibility of PAPs
2.3.1 Eligibility
Irrespective of their status or whether they have formal titles, legal rights or not, all PAPs are
eligible for some kind of assistance if they occupied the project area before the cut-off date.
Persons who occupied the area after the socio-economic study (census and valuation) are not
eligible for compensation or any form of resettlement assistance. All persons residing,
conducting activities or earning income within the project affected areas at the cut-off-date
i.e. May 31, 2012, which is the last day of inventory of loss will be entitled to compensation and
resettlement assistance. To determine their eligibility, PAPs are classified as follows:
i. Person who have formal right to land (including customary and traditional rights
recognised under Nigerian law);
ii. Persons who do not have formal legal right to lands or other assets at the time of the
census, but who have claim to such legal rights by virtue of occupation or use of those
assets.
2.3.2 Cut-Off Date
In order to avoid an influx of outsiders to project areas and misuse of the compensation policy,
the date of the census will serve as the cut-off date for eligibility and no new PAPs will be
eligible for compensation after this date. The Cut-Off Date for eligibility for compensation or
resettlement under this project is 31st May, 2012. This cut-off date has been agreed upon with
the PAPs and announced to them by SPIU and SPIU is also expected to make it public through
appropriate means of reach-out such as radio and television announcements during the
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
32
regular community awareness campaigns. The detailed census of PAPs has been be
appended to this ARAP. (See Annexes 1A and 1B). Table 2.1 below provides information on the
agreed time table for eligibility, compensation and site take-over.
Table 2.1: Time Table for Eligibility, Compensation and Site Take-over
#.
Activity
Date
1. Census/Survey/Screening of PAPs: Umuaniagu May 28, 2012
2. Census/Survey/Screening of PAPs: Ojor May 29, 2012
3. Cut-Off Date for Eligibility: Umuaniagu May, 31, 2012
4. Cut-Off Date for Eligibility: Ojor May, 31, 2012
5. Public Disclosure of ARAP July 31, 2012
6. Final Date for Compensation: Umuaniagu August 31, 2012
7. Final Date for Compensation: Ojor August 31, 2012
8 Date of Site Take-Over by SPIU: Umuaniagu September 30, 2012
9. Date of Site Take-Over by SPIU: Ojor September 30, 2012
10. Security Patrol Put-In-Place: Umuaniagu September 30, 2012
11. Security Patrol Put-In-Place: Ojor September 30, 2012
2.3.3 Proof of Eligibility
The FPMU/SPIU will consider various forms of evidence as proof of eligibility to cover:
i. Affected persons with legal/formal legal rights, documented in the form of certificates of
occupancy, tenancy agreements, rent receipts, among others.
Unprocessed/unregistered formal legal documents will not bar eligibility and procedures
for confirming authenticity of such documents will be established in the ARAP.
ii. Affected persons with no formal or recognized legal rights .
iii. Criteria for establishing non-formal, undocumented or unrecognised claims to eligibility
shall be established paying particular attention to each situation and its peculiarities.
2.3.4 Eligibility for Community Compensation
Communities permanently losing land and/or access to assets and or resources under
statutory/customary rights will be eligible for compensation. Example of community
compensation includes the shrines at Umuaniagu and Ojor and the transformer at Ojor. The
rationale for this is to ensure that the pre-project socio-economic status of communities
adversely impacted is also restored. The local community leaders will play a crucial role in
identifying users of land
2.4 Method of Valuation and Compensation
This valuation was carried out by the Consultant’s Contract/Procurement Specialist, whose duty
it is to prepare cost estimates for all items of work under the current consultancy contract. In
appraising the properties affected by the road project, a combination of the Replacement
Cost and the Direct Capital Comparative Methods were used in arriving at the open market
capital value of the structures, plantation and land. Market research of current prices of similar
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
33
assets was carried out in the vicinity of the project and the agreed final prices were adopted in
consultation with the PAPs. Calculations of the budgeted figures are provided in the Section
4.9, Section 4.10 and Table 9.1 of this report .
The decisions about costs and rates of compensation were arrived at in conjunction with the
PAPs after having consultation with them.
2.4.1 Method of Valuation
In ensuring that during the project implementation, PAPs will be provided full replacement cost
of lost structures and other impacted assets and are able to rebuild or replace their
structures/assets without difficulties. The valuation involves asset compensation rates based on
full replacement cost without depreciation. The replacement cost approach is based on the
premise that the costs of replacing productive assets is based on damages caused by project
operations. These costs are taken as a minimum estimate of the value of measures that will
reduce the damage or improve on on-site management practices and thereby prevent
damage. The approach involves direct replacement of expropriated assets and covers an
amount that is sufficient for asset replacement, moving expenses and other transaction costs.
The basis of valuation complies with the stated legal provisions and this necessitate that the
basis of valuation must assess the "Open Market Capital Value” which is usually the
Replacement Cost. It must be emphasized that this valuation was be based on comparisons to
recent comparable transactions/costs and comparable assets or land and not simply on
general tables that may be out of date and may be based on non-comparable assets or
land.
2.4.2 Methods of Compensation
Individual and household compensation will be made in cash, in kind, and/or through
assistance in the knowledge and presence of both man and wife and adult children or other
relevant stakeholders where applicable. When land holdings necessary for the livelihood of
affected persons is taken away or reduced in size by project works, OP4.12 clearly states that
the preferred form of compensation is to offer an equivalent parcel of land elsewhere, i.e.
“land for land.” Such land is not always available, but cash compensation is not the preferred
form of compensation in such cases. Thus in such case it is suggested that the following options
be adopted, in order of :Land for land, Compensation of land and cash or When it becomes
inevitable cash compensation.
2.4.4 Procedures for Delivery of Compensation
The procedure for delivery of compensation has been provided in this ARAP under Chapter 4.
However, the FPMU/SPIU are expected follow approved procedures whilst ensuring that:
i. Full payment of compensation is carried out before possession of acquired sites
ii. FPMU/SPIU formally make offers to affected persons and allow persons to accept or
reject offer, offer a counter claim and seek redress under the grievance procedures
established
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
34
iii. Land/Asset valuation committee communicates the amount to be paid to the acquiring
agency and the Ministry of lands will ensure that the amounts are fair and adequate.
iv. Cash shall be the preferred and first mode of payment; however payment may be by
banker’s draft where the amounts involved are substantial. FPMU/SPIU shall make
arrangements with nearest bank to effect payments by banker’s draft;
v. Payments are made to the affected person personally by the State Agency in the
presence of Land/Asset Valuation Committee and an independent witness of the
affected person/opinion leader
vi. Proper receipts are issued and copies given to the affected person, the Finance
Department of the State Agency and the Land/Asset Valuation committee;
vii. Comprehensive reports on payment made are submitted for review by Management of
the FPMU/SPIU and the Land/Asset Valuation committee.
2.5 Grievance Redress Mechanisms and Procedure
A Grievance Redress Committee will be set-up for each of the two affected communities, to
address complaints from ARAP implementation. This committee will be directly under the
National Coordinator, RAMP and its members will include State Coordinator, Enugu RAMP,
Legal Department, Accounts Department, traditional rulers, women organizations and NGOs.
The legal expert from RAMP shall be the secretary of the committee and they shall meet twice
every week to address pertinent issues raised. The functions of the Grievance Redress
Committee are:
i. Report to the aggrieved parties about the developments regarding their grievances
and the decision of the Project authorities.
ii. Provide support to affected persons on problems arising from loss of business area
and/or eviction from the RoW; and
iii. Record the grievance of the affected persons, categorize and prioritize the grievances
that need to be resolved by the Committee; and
iv. publicize within the list of affected persons and the functioning of the grievance redress
procedure established;
v. evaluate grievances from affected persons concerning the application to them of the
Entitlement Policy;
vi. recommend to the Social Officer, PIU as the case may be, solutions to such grievances
from affected persons;
vii. communicate the decisions to the Claimants;
viii. hear appeals from persons, households or groups who, not being affected persons,
believe that they are qualified to be recognized as affected persons, to recommend to
the PIU whether such persons should be recognized as affected persons, and to
communicate the decision of the PIU in that regard to the Claimants;
ix. ensure that all notices, forms, and other documentation required by Claimants are
made available in Local language understood by people.
The main objective of the grievance redress procedure will be to provide a mechanism to
mediate conflict, allow aggrieved PAPs to go to Grievance Redress Committee before
approaching the judiciary and cut down on lengthy litigation, which often delay such
infrastructure projects. It will also provide people who might have objections or concerns about
their assistance, a public consultation to raise their objections and through conflict resolution,
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
35
address these issues adequately. The committee will undertake a highly consultative process
for rural road construction. The committee will provide ample opportunity to redress complaints
informally, in addition to the existing formal administrative and legal procedures. However, the
major grievances that might require mitigations include:
i. Dispute about ownership;
ii. Delay in disbursement of assistance; and
iii. Improper distribution of assistance.
iv. Affected persons not enlisted;
v. Losses not correctly identified;
vi. Inadequate assistance or not in line with entitlement matrix
2.6 Important Principles in Project Implementation
The project will adhere to the following important principles in its implementation:
i. No civil works contracts for proposed projects site will be initiated unless land free of any
encumbrance is made available; this could be done in phases.
ii. No construction should be undertaken unless PAPs are compensated for their losses, and
have received their resettlement entitlements. That is, before any project activity is
implemented, PAPs will need to be compensated in accordance with the ARAP.
iii. For activities involving land acquisition or loss, denial or restriction to access, these
measures will include provision of compensation and of other assistance required for
relocation prior to displacement.
iv. Taking of land and related assets may take place only after compensation has been
paid and where applicable, resettlement sites and moving allowances have been
provided to displaced persons.
v. Information sharing and consultation with PAPs will continue throughout the planning
and implementation phase of the program, including the relocation and the restoration
of livelihoods.
vi. A completion survey of the delivery of compensation and resettlement entitlements will
be undertaken as per the RPF requirement.
vii. The schedule for the implementation of activities will be agreed to between the
Resettlement Committee and the PAPs. These include the
target dates for start and completion of civil works,
timetables for transfers of completed civil works to PAPs, and
dates of possession of land that PAPs are using.
The dates will be after transfer date for completed civil works to PAPs and payments of all
compensation. How these activities are linked to the implementation of the overall subproject
will also be agreed between the parties.
2.7 Mechanism for Consultation and Participation of Displaced Persons
The consultation process has ensured that all those identified as stakeholders have been
consulted. Subject to FPMU’s approval, information about the project will be shared with the
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
36
public, to enable meaningful contribution, and enhance the success of RAMP II. Road
construction works are expected to commence in January 2013 and completed in June, 2014.
There are many vehicles that could be used for communication and consultation such as listed
below:
Meetings, filling in of questionnaires/ application forms, public readings and explanations of
project ideas and requirements making public documents available at the national, local and
community levels at suitable locations like the official residences/offices of local elders,
announcement In various media, newspapers announcements placement in more than one
paper, preferably all local papers , notice board near project site, posters located in strategic
locations and many public places frequented by community and radio and local television.
Any of these means to use will take into account the low literacy levels prevalent in the rural
communities by allowing enough time for responses and feedback and putting messages in
the language readily understood by such people. Further participatory process can start in
October, 2012 and end in December, 2012. Information about the project may be translated
into and broadcasted through radio and television in the local languages of the beneficiary
communities such as Igbo, Igallamela and Pidgin English. Consultation meeting should also be
held in these three local languages in addition to the English language. For effective
consultation, the SPIU should hold specific events (preferably community-level meetings) at
which affected people will feel comfortable expressing their views. Similar events on this
project have been carefully documented and the minutes of these meetings together with
attendance lists have been included in this ARAP to demonstrate that consultation has taken
place. Generally, the SPIU are not required to accept every suggestion or demand made, but
they should take each reasonable suggestion into account as a matter of good faith.
2.8 Income Restoration Strategy
A participatory approach will be utilized in the development of an income generation
programme in order to ensure that the ideas, wishes and needs of the stakeholders are
included. The programme will support income generating activities with commercial potential
in the agricultural and non-farm sectors.
2.8.1 Income from Construction Activities and Other Measures
The remunerative involvement of stakeholders and in particular of the affected persons, in the
construction project has three main objectives.
i. Firstly, the income thus generated would produce a direct positive impact by injecting a
financial stimulant into the local economy.
ii. Secondly, the direct involvement of the population will develop a sense of belonging
and strengthen their appreciation of the project, and
iii. Thirdly, it should prove that small to medium sized channels and drains can effectively
be cleaned, deepened and widened with simple labour intensive methods.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
37
2.8.2 Gender Issues in Resettlement Plans
Gender analysis has been part of the social assessment and the analyses have been based on
findings from gender specific queries during primary data collection process and available
secondary data. Quantitative and qualitative analyses have brought out sex disaggregated
data and issues related to gender disparity, needs, constraints, and priorities; as well as
understanding whether there is a potential for gender based inequitable risks, benefits and
opportunities. Women have been given adequate consideration in this ARAP as 51% and 50%
of the PAPs in Umuaniagu and Ojor respectively are women. They were also fully engaged in
the consultation process. During the period of construction, women should also be considered
for skilled and unskilled labour-based construction works and other livelihood opportunities such
as provision of food, supply of water and cleaning services to the Contractor and Contractor’s
staff.
2.9 Arrangements for Monitoring by Implementing Agency
The WB’s safeguard policy (OP 4.12) states that the project sponsor (FPMU/SPIU in this instance)
are responsible for adequate Monitoring and Evaluation (M&E) of the activities set forth in the
resettlement instrument. Monitoring will provide both a warning system for the project sponsor
and a channel for the affected persons to make known their needs and their reactions to
resettlement execution. The sponsor’s M&E activities and programmes should be adequately
funded and staffed. Details of M&E activities, frequency and staffing are provided in Chapter 8
of this report.
The safeguards officer of the FPMU is expected play a key role in reporting the progress of
implementation as well as its compliance to the requirements of SPIU, FPMU and the World
Bank.
The FPMUs will institute an administrative reporting system that:
i. Provides timely information about all resettlement arising as a result of RAMP II project
activities;
ii. Identifies any grievances that have not been resolved at a local level and require
resolution through the involvement of the PMU; and
iii. Documents the timely completion of project resettlement obligations (i.e. payment of
the agreed-upon sums, construction of new structures, etc.) for all permanent and
temporary losses;
iv. Evaluates whether all PAPs have been compensated in accordance with the
requirements of this ARAP, and that PAPs have living standards that are equal to the
living standards before physical or economic displacement. Section 8.4 of this report
provides for impact monitoring and the Safeguard Officer of the FPMU/SPIU will be
responsible for impact monitoring. This exercise will be conducted twice (one every nine
months) during construction activities and funding will be provided byFPMU/SPIU.
In-house monitoring may need to be supplemented by independent external monitors to
ensure complete and objective information. Thus the project has developed an extensive M&E
system that includes:
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
38
i. Internal monitoring, in particular reporting by government officials and field consultants,
community participatory monitoring;
ii. External monitoring, with NGOs and journalists providing independent monitoring; and
iii. Impact evaluation.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
39
3.0 SOCIO-ECONOMIC SURVEY AND PROPERTIES OF AFFECTED POPULATION
3.1 SOCIO-ECONOMIC SURVEY OF AFFECTED POPULATION
A survey was undertaken of the PAPs in Umuaniagu and Ojor on 29th May, 2012 and 30th May,
2012 respectively with the purpose of documenting existing land use activities within the RoW
and the status of PAPs along the road corridors. The socio-economic survey was conducted on
the PAPs with a view to determining their existing socio-economic conditions, and how the
project impact may affect them. The survey outcomes of the following thematic socio-
economic indicators which were examined are provided under Tables 3.3 to 3.7 in this
chapter: Gender, Marital Status, Level of Education, Nature of trade/Occupation of PAPs,
Number of Dependants and Income Levels.
This chapter therefore presents the outcome of the survey that was conducted for the project.
The socio-economic survey was carried out to identify the following:
i. Public infrastructure and social services that will be affected
ii. Social and cultural characteristics of displaced communities in terms of gender,
professions etc.
iii. Current occupants of the right-of-way;
iv. Standard characteristics of displaced persons (baseline information on livelihood,
economic and social information, etc);
v. The magnitude of the expected loss (total or partial);
vi. Information on vulnerable groups or persons (for whom special provision may have to be
made)
3.2 Survey Methodology
Socio-economic data were collected during the survey using the census method which
entailed interviewing all persons living or operating within the right of way of the two affected
proposed routes using the survey instrument .
Mobilization of Staff: 5 enumerators comprising of 4 males and 1 female were
mobilized for the enumeration exercise. The project enumerators were carefully
selected, taking into consideration educational qualification, gender and research
experience, as well as language proficiency for effective communication with the
vendors.
Training of Field Staff: A training programme was organized for one day for the field
staff prior to the fieldwork, using the survey instrument. The purpose of the training was
to ensure a common understanding of the objectives of the study and the content of
the survey instrument, as well as to enhance the capacity of the researchers to
conduct the fieldwork, with a view to ensuring uniform administration of the research
instruments. In addition to the training, a rapid assessment was conducted and test
questionnaires were administered to ensure that enumerators perfectly understand
the survey procedures and documentation of information. In-house role plays were
also organized as part of the training for the research team.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
40
Fieldwork Logistics and Sampling Design: For the purpose of quick coverage, the
survey team worked as one big team, moving in a coordinated manner from one
location to another along the study axes.
Language of Communication: The interviews were conducted mainly in Igbo
(language of Umuaniagu Village of Ozalla) and Igallamella (language of Ojor
Village), followed by English and Pidgin (broken English).
Quality Control: In order to ensure the integrity of the data, all project activities were
conducted under close supervision. Appointed field supervisors provided round-the-
clock supervision for the fieldwork and conducted spot-checks on the interviewers.
Completed interview schedules were first screened by the supervisors and subjected
to a second level of screening in the office, prior to data entry.
3.3 Project Area Population
There are four (4) communities namely Enuguagu Ndiagu, Umuaniagu, Obe and Amuri on
Road #13 but only Umuaniagu is affected. There are also four (4) communities namely Adani,
Asaba, Igga and Ojor on Road #12 but only Ojor is affected. Ojoo and Umuaniagu (Ozalla) are
communities with permanent and temporal structures that will be affected by the road
projects. The populations of Umuaniagu and Ojor are summarized in Table 3.1.
Table 3.1: Population Characteristics of Affected Communities
#.
Intervention Area
/Community
Population Characteristics
Actual 2006 Population
Projected 2011 Population
Total
Male
Female
Total
Male
Female
1.
NKANU EAST/NKANU
WEST/ENUGU SOUTH
Intervention Area
(Umuaniagu/Ozalla
Community)
Rd 13 1,152 634 518 1,336 735 601
2.
UZO UWANI
Intervention Area
(Ojor Village)
Rd 12 408 224 184 473 260 213
3.4 Demographic Characteristics of Enugu State
Population Structure and Distribution: Based on the 2006 National Population and Housing
Census Figures, Enugu State has a population of 3,267,837 (1,596,042 males and 1,671,795
females) within a total area of 7,737.6 sq. km. This gives a population density of about 429
persons per sq. km., which is high when compared with the average national density of about
154 persons per sq. km. See Table 3.2 for more details on population statistics. Expectedly,
population concentration is highest in the urban centres, with densities ranging between 300
and 600 per sq.km. In a state where the great majority of the people are rural, densities affect
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
41
the intensity of land use and productivity of the land. Four population density regions are
recognised. Areas with over 600 persons per sq. km and between 400 and 600 persons per sq.
km. make up the congested rural districts.
Farmland is scarce in these two high density areas. The medium density areas support between
200 and 400 persons per sq. km, while the sparsely settled areas have an average density of
less than 200 persons per sq. km. The reason for the limited land acquisition in an area with high
land pressure and density is because the project roads have existing alignments and the
proposed upgrading do not require re-alignments. Based on this fact and the observation that
for most part, the rights of way of the roads do not infringe on the rights of the communities,
then there is limited land acquisition.
Table 3.2: Projected Population Distribution for the LGAs within RAMP Intervention Areas
#.
Local
Government
Area
2006
Population
Figures (A)
Area Sq.
Km (B)
Popul
ation
Per
Squar
e km Projected Population (3% Annual Growth)
2007 2008 2009 2010 2011
1 Aninri 133723 368.615 363 137735 141867 146122 150506 155022
2 Awgu 198134 447.17 443 204078 210200 216506 223002 229692
3 Enugu South
198723
70.98
2,800 204685 210825 217150 223665 230374
4 Isi-Uzo 148415 870.39 171 152868 157454 162177 167042 172054
5 Nkanu East 148774 708.515 210 153237 157834 162569 167446 172470
6 Nkanu West 146695 262.735 558 151096 155629 160298 165107 170060
7 Oji-River 126587 394.945 321 130385 134296 138325 142475 146749
8 Udi 234002 908.64 258 241022 248253 255700 263371 271273
9 Uzo-Uwani 124480 918.275 136 128214 132061 136023 140103 144306
Total 1,459,533 4,950 5,260 1503319 1548419 1594871 1642717 1691999
The six intervention areas have a total population of 1,459,533 according to the 2006
population census. As shown in Table 3.2 population distribution varies within LGAs with Udi
having the highest of 234002 (2006) and Uzo-Uwani having the least of 124480 (2006). The
projected population shows that by 2011 Udi will have grown to 271273.
3.5 Results of Socio-economic Survey of Project Affected Peoples (PAPs)
3.5.1 Gender
Women groups exist in some of the Intervention areas; these groups promote women’s
economic empowerment through marketing of farm produce such as oil and foodstuffs. The
bulk of women in the areas either engages in petty trading or supports their male counterparts
and guardians in farming and marketing of farm produce. See Tables 3.4 and 3.7 for details on
the socio-economic statistics of the PAPs.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
42
Table 3.3: Number of PAPs Enumerated
Table 3.4: Gender Distribution of PAPs
Project Affected Area
Male
%
Female
%
Total
Umuaniagu (on Road #13) 49 49.0 51 51.0 100
Ojoo (on Road #12) 20 50.0 20 50.0 40
Table 3.5: Number of Dependants of PAPs
Project Affected Area
Range of Dependants (%)
1-2 3-5 6-8 9 & above
Umuaniagu (on Road #13) 42 50 7 1
Ojoo (on Road #12) 15 55 20 10
Table 3.6: Occupation of PAPs
Project Affected Area
Occupation of PAPs (%)
Farming
Transport
Operators
Petty Trading
Umuaniagu (on Road #13) 60 40
Ojoo (on Road #12) 55 10 35
Table 3.7: Net Daily Income of PAPs
Project Affected Area
Net Daily Income of PAPs (NGN)
Less than 500 500-1000 1001-1500 1501-2000 Above 2000
Umuaniagu (on Road #13) 52 40 7 1 0
Ojoo (on Road #12) 22 15 3 0 0
3.5.2 Land Ownership, Tenure and Use
The customary rights to the land within the project catchment are either the community
ownership or the family ownership. Individuals or families may acquire land usually for building
or agriculture.
3.5.3 Employment
Agriculture is the major occupation with over 55% of the labour force in the two intervention
areas involved in crop cultivation and livestock rearing. Crops cultivated include maize,
sorghum, groundnuts, cassava, yam, beans and vegetable. Apart from retail trade and
services, males dominate in the other occupations. This is because custom and tradition tend
to regard these occupations as the preserve of males.
Petty trading and farm produce marketing account for 35%-40% per cent of all economic
activity, making this combined sector the second largest source of employment in all two
Project Affected Area
#. of PAPs Enumerated
%
Umuaniagu (on Road #13) 100 71.4
Ojoo (on Road #12) 40 28.6
Total 140 100
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
43
affected areas. These petty traders either hawk their produce by moving by foot from street to
street or sell their produce in designated village markets that are sufficiently outside the rights of
way of the proposed roads. They do not have to shift before, during and after construction.
3.5.4 Historical, Aesthetic and Cultural Resources
Few cultural sites such as shrines were identified. The rights of way of the two roads (Road#13
and Road #12) encroach on the current positions of major and minor shrines at Umuaniagu
(Ozalla) and Ojor respectively.
3.6 Project Affected Persons and Properties
The project affected persons are those individuals that will be physically displaced from their
work or business locations as a result of the proposed road projects. This means that the
individuals directly located within the portions of land designated for road construction and
drainage shall be entitled to assistance or compensation. These categories of project affected
persons are presented in Table 3.8 with some categories overlapping.
Table 3.8: Categories of Project Affected Persons
Location
Project Affected People
Sub- total
Fully Affected Removal of
Plantation Land
Acquisition Relocated or
Shifted backwards
Umuaniagu (Ozalla) on Road #13)
19
100
3
100
Ojor Village (on Road #12)
0
40
6
40 Total 140
3.6.1 Fully Affected Persons
In ensuring that the project impacts are reduced to the barest minimum, demolition of
structures either residential or commercial within the proposed route has been avoided. To this
end, FPMU will not demolish any residential or commercial structure along the proposed route.
Only four (4) major shrines with permanent structures and forty (40) minor shrines with
temporary (make-shift) structures will be shifted backwards/relocated off the rights of way of
the roads. Therefore, the fully affected persons are owners of landed properties whose crops
and land will be acquired and compensated for the costs of both land and crops. The shrines
are the village’s historical property under the custodianship of either the community traditional
ruler or the high priest. Either of the two is the sole authority or decision maker on the shifting of
the shrine. These shrines were established by the ancestors or founders of the communities.
Depending on the religious order of each village, the compensation for the shifting of the
shrines will either the received by the traditional ruler of the high priest.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
44
3.6.2 Partially Affected Persons
There are no partially affected persons or groups on the projects corridor.
3.6.3 Non-Affected Persons
This group of persons are those that are outside the RoW of the proposed routes and are not
affected by the project activities. They are market traders who do not have to shift away from
the sides of the road during construction. Their livelihoods will not be affected before, during
and after construction.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
45
4.0 VALUATION AND COMPENSATION PROCEDURES
4.1 Introduction
This chapter presents valuation procedure of estimates of assets and other costs to the people
who will be affected and the mode of restitution that can be followed. The valuation was done
by our Safeguard Specialist with support from the FPMU and the World Bank.
4.2 Eligibility Criteria for Project Affected Persons
To be described as a project affected person (PAP), the property or activity of the potential
PAP must fall within the RoW of the road(s) as indicated on the planning scheme of the area or
project road design. All activities being carried out in the right-of-way which existed prior to
their being marked for displacement are to be compensated for. Those eligible for
compensations are occupants and owners of properties that will be displaced.
All properties to be affected by construction and rehabilitation have been valued and
assessed according to laid down procedure. Details of extent of displacement and
compensation due PAPs for affected properties are provided in Annex 1C. Owners of affected
properties have been notified in several ways.
Farmlands, plantations, shrines, transformer and parcel of land to be affected by
construction have been identified.
Public consultations have been held in each of the affected communities. See Annex 1D
for minutes of the consultative meetings held with the affected communities.
A compensation valuation of all affected properties has been carried out to assess
commensurable values.
However only PAPs registered during the baseline survey were considered to be eligible for
compensation and the SPIU has notified the PAPs on this. Compensation will be made on or
before August 31, 2012 after the approval of this ARAP by the Bank.
4.3 Consultations
Consultations were held with all PAPs with farmlands, plantations, shrines, transformer and
parcel of land within the RoW on issues of their compensation. All properties that fall within the
right of way have been captured by measurements s as provided in the engineering drawings.
Project Affected Persons have been notified in several ways. These include identification of
farmlands, plantations, shrines, transformer and parcel of land by the Consultant and the
project team and in consultation with PAPs. During the exercise . the SPIU explained to all
affected persons about its readiness to implement the project. In addition to these two actions,
a survey of affected persons was initiated to collect data and at the same time to inform them
about the project. An initial compensation valuation of all affected properties was carried out
in April 16-20, 2012 and confirmed on May 29-30, 2012 to assess commensurable values.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
46
4.4 The Valuation Process
As per the planning scheme of the road corridor, land survey was carried out by the
Consultant’s Senior Highway Surveyor under the consultancy contract. Part of the duties of the
Senior Highway Surveyor is to carry out a survey of the RoWs of the roads, identify properties
that are within the RoWs in conjunction with SPIU and ascertain the level of encroachment.
Marking and numbering of all structures within the RoW have been done by the Senior
Highway Surveyor and the highway survey support team. In addition, the affected property
owners have been requested to furnish the RAMP/SPIU office with any relevant document
relating to their interest in the properties.
4.5 Basis of Valuation
The appraisal exercise was based on the Open Market Value which is defined as the best price
at which the sale of an interest in a property might reasonably be expected to have been
completed unconditionally for cash consideration on the date of the final valuation, which was
31st May, 2012.
The valuation was premised on the following;
i. A willing seller and a willing purchaser capable of purchasing a particular property in a
predetermined location or condition at a particular point in time;
ii. That prior to the date of valuation there had been a reasonable period (having regard
to the nature of the property and the state of the market) for the agreement of price
and for completion of terms;
iii. That the values will remain static during that period; That the property will be freely
exposed to the open market; and
iv. That no account will be taken of any higher price that might be paid by a purchaser
with special interest.
v. The open market value of the property is arrived at by the under listed methods based
on the purpose of valuation, the availability and reliability of basic data for the
valuation.
4.6 Method of Valuation
This valuation was carried out by the Consultant’s Contract/Procurement Specialist, whose duty
it is to prepare cost estimates for all items of work under the current contract. In appraising the
properties affected by the road project. A combination of the Replacement Cost and the
Direct Capital Comparative Methods were used in arriving at the open market capital value of
the structures, plantation and land. Market research of current prices of similar assets was
carried out in the vicinity of the project and the agreed final prices were adopted in
consultation with the PAPs. The PAPs were adequately involved in the negotiations that
produced and in agreement with the rates and figures that were applied in computing the
final compensation costs. Details of the how the compensation rates were calculated are
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
47
provided under Sections 4.9 and 4.10 of this Chapter (See Annexes 2A and 2B for minutes of
meetings with PAPs and Table 4.12-Entitlement Matrix). The two methods have been briefly
described below.
4.6.1 Replacement Cost Method
The Replacement Cost Method, which is used in estimating the value of the building/structure,
is based on the assumption that the capital value of an existing development can be equated
to the cost of reinstating the development on the same plot at the current labour, material and
other incidental costs. The estimated value represents the cost of the property as if new.
4.6.2 Direct Capital Comparative Method
The value of bare land is determined by the comparison of market evidence of recent sale of
plots in the vicinity or similar neighbourhood. Comparable data are collected and analyzed to
determine the unit rate per acre taking into consideration, statutory use, alternative use, size of
plot, nature and terms of interest, proximity of the land to utility services, peculiar advantages
of location, the trends of redevelopment and construction.
The appropriate adjustments are made to reflect the differences between the comparable
data and the affected land and the appropriate rate adopted for the assessment of the
current open market value of the affected land.
4.7 Disturbance and Other Incidental Contingencies
The project has impacted on properties to make room for the road reservation. Depending on
the extent to which a property is affected, the occupants will have to resettle elsewhere after
being compensated. Based upon the level of inconvenience these are quantified and
expressed as percentage of the total reinstatement cost of the property. The summation of the
above estimated values of the structure, land and the disturbances, gives the adequate and
fair amount of compensation payable to the affected person.
4.8 Modes of Restitution
Owners of permanent structures whose properties are affected by the project are protected
by law and would receive adequate compensation for their properties. In situations where the
beneficiary is not satisfied with the amount of compensation payable to him, he is at liberty to
seek redress with the grievance redress committee. However, the property cannot be
relocated until the issue is resolved.
4.9 Value of Land
Land is scarce in the South East of Nigeria and therefore is a high competition for land among
the people. This scenario makes land to be expensive, even in the rural areas. The standard
plot size of 18m x 36m has been taken as the basis of valuation in this report. It was agreed with
the PAPs in the two communities that a sum of N500,000 (Five hundred thousand Naira) should
be the monetary value for a standard plot of 18m x 36m dimensions after taking into
consideration current market values of standard plots in the same area. This comes down to a
land value of N925.926 per Square Metre. The following land area will be acquired.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
48
i. 4,500 Square Metre of Cassava Farmland @ Umuaniagu
ii. 1,200 Square Metre of Cassava Farmland @ Ojor
iii. 3,600 Square Metre of Virgin Land @ Ojor
4.10 Value of Affected Structures and Crops
There will be no demolition of structures hence structures will not be valued since PAPs will be
allowed to dismantle their structures and shift them a bit off the right of way of the proposed
roads. Under this section, the following structures and crops will be affected.
i. Transformer @ Ojor
ii. 3 Major Shrines (3m x 3m) @ Umuaniagu
iii. 3 Major Shrines (3m x 3.5m) @ Ojor
iv. 40 Small Shrines @ Ojor
v. Cassava Crops (4,500 Square Metres @ Umuaniagu)
vi. Cassava Crops (1,200 Square Metres @ Ojor)
vii. 63 Palm Trees @ Umuaniagu
viii. 54 Other Trees/Trunks @ Umuaniagu
The following decisions about costs and rates of compensation were arrived at in conjunction
with the PAPs after having consultated with them.
Transformer: The community transformer at Ojor will be moved a little backwards on the side of
the road it is currently located from the right of way of Road #12 at a cost of N750,000. This cost
estimate include the costs of dismantling the existing 5m x 5m x 2m protective blockwall, the
cost of preparing a new foundation for the transformer at a very nearby location, the cost of
temporarily disconnecting the village from the national grid, the cost of physically moving the
transformer to its new location, the cost of re-connecting the village to the national grid and
the cost of building a new 5m x 5m x 2m protective blockwall.
Major Shrines: There are 3Nos. (3m x 3m) major shrines and 3Nos. (3m x 3.5m) major shrine at
Umuaniagu and Ojor respectively. These major shrines will be moved and relocated off the
rights of way of Roads 13 and 12 at a cost of N250,000 per major shrine. They are enclosed with
makeshift structures. This cost estimate includes the cost of dismantling and moving the shrine
to their new locations, the cost of traditional sacrifices and rites to be performed and the cost
of erecting new makeshift walls around them.
Minor Shrines: These 40 minor shrines at Ojor will be shifted at a rate of N2,000 per minor shrine.
This estimate includes the cost of basic sacrifices to be performed.
Cassava Crops: It has been estimated that one (1) basket of cassava will be harvested per 16
square metre of cassava farm. Therefore, for the 4,500 square metre and 1200 square metre of
cassava farmland at Umuaniagu and Ojor 75 and 281 baskets of cassava crops will be
harvested respectively. The economic cost of a basket of cassava is estimated at N1,500.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
49
63 Oil Palm Trees: There are 63 palm trees at Umuaniagu and the economic cost of a tree has
be estimated at N18,000.
54 Other Trees: There are 54 other valuable fruit trees at Umuaniagu and the economic cost of
a tree has be estimated at N15,000.
4.11 Compensation and Other Assistance
Land taking will entail compensation for land, crops, and other structures on that land, as well
as other assistance in order to mitigate the adverse consequences that affect people and
communities when they give up property for public good. The form of resettlement agreeable
to the PAPs for both the permanent properties and temporary structures affected by the road
project is rehabilitation with monetary compensation. The process of mitigating the project
impacts on PAPs will therefore involve only rehabilitation, where the PAPs will continue to live
and carry on their livelihood in the project communities. It will not involve physically relocating
the PAPs by the FPMU/SPIU. Therefore the option for resettlement site identification, selection
and preparation for relocation is not envisaged.
4.11.1 Payment of Compensation
In accordance with the World Bank operational policy on involuntary resettlement (OP 4.12),
FPMU/SPIU will ensure that the conditions of the PAPs are restored to the status that is at the
minimum commensurate to their pre-project status. List of all PAPs has been documented in
the PAP register and will be provided to FPMU/SPIU. In addition, every person affected by the
project will be issued an identity card for easy identification and possible compensation. The
identity cards will serve as the major identification for restitution.
The ARAP implementation will verify the correctness of each PAPs as stated in the register and
ascertain that every person to be issued an identity card holder is correctly documented in the
register. On completion of the PAP audit list, the National Coordinator, RAMP will setup a
committee that will carry out payment and compensation. This team will consist of FPMU’s
accountant, legal and a social safeguard expert, traditional ruler, NGO and representatives of
women organisations. Payments will be made according to locations and adequate
information will be made available to all affected persons before payment. Such information
will include.
1. dates and locations of payment
2. list of eligible people and amount
3. mode of payment
4. location of payment etc.
Payment will be made directly in cash to each PAP. The decision to pay cash is hinged on the
probability that most of the PAPs have no bank account and have no formal education to be
able to carry out bank transactions. In the event that an individual is absent during payment,
the compensation committee will immediately communicate a new date of payment to such
PAP(s).
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
50
4.12 ENTITLEMENT MATRIX
Table 4.1 presents an entitlement matrix showing categories of project affected persons, type
of loss and compensation to PAPs to enable them move from the RsoW and continue with their
business.
Table 4.1: Entitlement Matrix
Type of Loss
Eligibility Criteria
Entitlement
Loss of Land (Rural)
Various interest and rights –
allodial title holder, freeholder,
leaseholder, tenant, licensee
Compensation – Capital Market Value of Asset at
N925.926 per Square Metre
Loss of economic trees-
Palm Trees
Owners of farm
N18,000 per Palm Tree
Loss of economic trees-
Other Valuable Trees
Owners of farm
N15,000 per Tree
Loss of Crops
Owners of farm
N1,500 per Basket of
Cassava
Relocation of Structure- Minor Shrine – Expense for
moving structure
Owners of Shrine
N2,000 per minor shrine
Relocation of Structure- Major Shrine – Expense for
moving structure
Custodians of Community
Shrine
N250,000 per major shrine
Relocation of Structure-
Transformer – Expense for
moving structure
Community
N750,000
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
51
5.0 PUBLIC CONSULTATIONS
5.1 Project Affected Persons
During the baseline socio-economic data collection from project affected persons in the
project zones on the affected roads on May 28-30, 2012 consultations were held with individual
PAP. During these consultations, the impacts of the project and proposed mitigation measures
were explained to them and they individually gave the assurance that they will cooperate to
ensure smooth implementation of the projects on the two roads. Annex1A and Annex 1B show
that 100 PAPs (49 Males and 51Females) were consulted in Umuaniagu (Ozalla) Community
and 40 PAPs (20 Males and 20 Females) were consulted in Ojor Community.
Prior to the commencement of the ARAP study, detailed consultations and public disclosure
were undertaken to disseminate to the people the intentions of federal and state government
through FPMU/SPIU towards the implementation of the road project. Key stakeholders that
were consulted for this RAP are local government administrations, traditional rulers and
communities sharing boundaries with the roads, community women groups, farmers etc..
The consultations, which were conducted prior and during the ARAP study is a follow-up to the
continuous consultations that FPMU/SPIU has been doing since the conceptualization stage of
this project.
5.1.2 Issues Discussed
Proposed road alignment;
Effects of project on properties falling within the ROW;
Environmental concerns for flora and fauna;
Effects of project on existing utilities;
Pedestrian-vehicular conflicts during construction and operation;
Historical and cultural areas of concern;
Resettlement and compensation process;
Means of evaluation of compensation; and
Grievance redress mechanism
5.2 Future Consultations
These will be held prior to the payment of compensations to the individual PAPs. They will be
notified about compensations due them and where to collect the compensation. They will also
be notified of the start date of civil works.
Work will not start on any roads until every PAP has been adequately compensated in
accordance with World Bank policies.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
52
6.0 GRIEVANCE PROCEDURE
The potential for disputes over relocation of structures to allow for working space during road
construction have been reduced. All affected persons have been consulted and an
agreement has been arrived at between the PAPs and the FPMU/SPIU on the suitable
compensation to be paid to the PAPs.
Each individual PAP has the right to refuse the compensation proposed and take his/her case
to the court of justice if he or she finds the compensation to be inadequate and unfair under
the replacement cost. However in the event of disagreement, the affected party may first seek recourse Grievance Committee under the Project Management Unit (FPMU) for that purpose.
6.1 Grievance Redress Mechanisms
Considering the challenges associated with grievance redress, it is advisable for FPMU/SPIU to
hire and co-opt an NGO to be a part of grievance redress. Grievance redress committee will
be set-up to address complaints from ARAP implementation. This committee will be directly
under the National Coordinator, RAMP and its members will include State Coordinator, Enugu
RAMP, Legal Department, Accounts Department, traditional rulers, women organisastions and
NGOs. The legal expert from RAMP shall be the secretary of the committee and they shall meet
twice every week to address pertinent issues raised. The functions of the Grievance Redress
Committee are:
Report to the aggrieved parties about the developments regarding their grievances
and the decision of the Project authorities.
Provide support to affected persons on problems arising from loss of business area
and/or eviction from the RoW; and
Record the grievance of the affected persons, categorize and prioritize the grievances
that need to be resolved by the Committee.
The main objective of the grievance redress procedure will be to provide a mechanism to
mediate conflict, allow aggrieved PAPs to go to Grievance Redress Committee before
approaching the judiciary and cut down on lengthy litigation, which often delay such
infrastructure projects. It will also provide people who might have objections or concerns about
their assistance, a public consultation to raise their objections and through conflict resolution,
address these issues adequately. The committee will undertake a highly consultative process
for rural road construction. The committee will provide ample opportunity to redress complaints
informally, in addition to the existing formal administrative and legal procedures. However, the
major grievances that might require mitigations include:
vii. Dispute about ownership;
viii. Delay in disbursement of assistance; and
ix. Improper distribution of assistance.
x. Affected persons not enlisted;
xi. Losses not correctly identified;
xii. Inadequate assistance or not in line with entitlement matrix
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
53
It is the responsibility of the grievance redress committee to satisfactorily address all complaints
brought by the project affected persons. On the condition that an affected person is not
satisfied with the decisions of the committee, such person has an opportunity to seek the
intervention of the National Coordinator, RAMP to address his/her grievance. Where any of
these informal options is not satisfactory, the complainant may take recourse to the
administrative and legal systems for satisfaction. Two grievance redress committees are being
proposed under this ARAP. Tables 6.1 and 6.2 show the proposed membership structure of the
grievance redress committees. The compositions of the committees fully represents the
different stakeholder groups that are relevant to the project.
Table 6.1: Membership of the Grievance Redress Committee for Umuaniagu Community
Name
Designation
Office Address
Telephone
Contact
Traditional Ruler Igwe Umuaniagu Royal Palace 08060096141
Engr. A. Mohammed Procurement, FPMU RAMP-FPMU, Abuja 08073747530
Engr. F. Nweke SC, SPIU RAMP, Enugu 08063583673
Engr. Dr. E.A. Adeyemo
Consultant
Pheman Peniel Consultants
Ltd
08034031493
Legal Expert RAMP Legal Dept RAMP-FPMU, Abuja 08073747530
Mrs. Bola Badmus FPMU, Accounts Dept. RAMP-FPMU, Abuja 08055476542
Civil Society Organisations
Two (2) CSO Representatives from Nkanu East/Nkanu West/Enugu South
Intervention Area
Local Women Organisations
Two (2) LWO Representatives from Nkanu East/Nkanu West/Enugu South
Intervention Area
Table 6.2: Membership of the Grievance Redress Committee for Ojor Community
Name
Designation
Office Address
Telephone
Contact
Traditional Ruler Igwe Ojor Royal Palace 08087321717
Engr. A. Mohammed Procurement, FPMU RAMP-FPMU, Abuja 08073747530
Engr. F. Nweke SC, SPIU RAMP, Enugu 08063583673
Engr. Dr. E.A. Adeyemo
Consultant
Pheman Peniel Consultants
Ltd
08034031493
Legal Expert RAMP Legal Dept RAMP-FPMU, Abuja 08073747530
Mrs. Bola Badmus FPMU, Accounts Dept. RAMP-FPMU, Abuja 08055476542
Civil Society Organisations Two (2) CSO Representatives from Uzo Uwani Intervention Area
Local Women Organisations Two (2) LWO Representatives from Uzo Uwani Intervention Area
The Civil Society Organisations and the Local Women organisations will be selected from
among organizations that are already based in or around the communities of impact.
6.2 Grievances and Redress Procedure
Cash compensation will be paid to all PAPs whose property will be affected by the project.
Should a PAP refuse the compensation suggested, litigation is settled by the courts. Each
individual PAP has the right to refuse the compensation rate proposed and take his case to
court if he/she finds the compensation to be inadequate and unfair under replacement cost;
however in the event of disagreement, the affected party may first seek recourse through
Grievance Redress Committee under FPMU for that purpose. The PAP is allowed to engage
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
54
his/her own valuer (at his own cost) to determine the compensation due. The Valuer and the
Grievance Committee together with other stake holders will negotiate a settlement. If the PAP
is still not convinced with what has been proposed, as stated above, he/she can take the case
to the court for redress. Section 2.5 provides additional details about this.
The objective of the grievance procedure stated above is to address the following: Provide
PAPs with avenues for making complaint or resolve any dispute that may arise during the
course of land, structure and any assets acquisition, including the process of moving homes;
Ensure that appropriate and mutually acceptable corrective actions are identified and
implemented to address complaints; Verify that complainants are satisfied with outcomes of
corrective actions; and Avoid the need to resort to judicial proceedings.
If appropriate, the individual grievances and corrective actions will be received in the light of
the project policy and procedures to determine if any changes to the current system are
warranted. This review will aid in avoiding similar grievances in the future.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
55
7.0 INSTITUTIONAL RESPONSIBILITIES
7.1 Introduction
A number of institutions exist that are involved either in development or implementation of
transportation policies in Enugu State. Such institutions include the Ministry of Works and
Infrastructure, State Project Implementation Unit (SPIU) Enugu State RAMP, Local Government
Councils and the traditional institution. The aforementioned institutions including Ministry of
Lands, Ministry of Housing, Physical Planning and Urban Development and Ministry of the
Environment have been identified as some of the institutions for resettlement. Most of the
institutions are related in function and some other cases have overlapping functions but are
duly recognised by law or customary norms of Enugu State. While most of them do not have
direct links with resettlement, some of them, by operation or functions, have related
responsibilities with resettlement.
7.2 Implementation Roles and Responsibilities
The roles and responsibilities of FPMU/SPIU and other agencies with regard to ARAP
implementation are detailed below.
7.2.1 FPMU/SPIU
The FPMU has ultimate responsibility for clearing and certifying the RoW prior to the
commencement of civil works in the project zone. FPMU has an implementation unit known as
the Project Management Unit that has the ultimate responsibility for the implementation of this
ARAP. Though various government agencies have a role to play to ensure the successful
implementation of this ARAP, the institutions that are responsible for ensuring the
implementation of this ARAP under RAMP2 are the FPMU, SPIU and The World Bank. FPMU will
work through the SPIU, Consultant and the Contractor to implement the clearance
programme. The SPIU will inform the project affected persons of the date to begin clearance
of the RoW.
Responsibilities for commitments proposed in the ARAP exist within FPMU/SPIU and are
delegated internally to other units in the agency as well as other government agencies. SPIU is
responsible for implementation in the state while the FPMU oversees the activities of the SPIU.
Perfect understanding of the proposed project exists in the agency as all units and staff
assigned to specific roles associated with resettlement, including impact minimization,
inventory preparation and confirmation, consultation and feedback, compensations,
monitoring and reporting.
Environmental and Safeguard Unit is responsible for facilitating liaison with communities as
well as government agencies and local government department to facilitate stakeholder
consultations. This unit reports directly to the National Coordinator of RAMP on the process
of resettlement of affected people. This unit also liaises with the trade and market women
unions in ensuring that members of the union are appropriately informed on the
resettlement plan. It is the responsibility of the unit to adequately implement the
resettlement and provide all information to the World Bank as and when required. The unit is
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
56
also responsible for the identification of environmentally sensitive areas that are likely to be
affected by the project.
• Transport/Infrastructure Unit is responsible for supervising the contractors engaged in
construction of facilities and ensure strict adherence to project design specifications and
land acquisition. They also identify alternative project sites that will have minimal impacts on
socio-economic variables in affected project areas.
• Legal unit oversee all legal functions including resolution of grievances. It also provides
advice to the Resettlement implementation manager, including verification of
compensation and drafting of legal agreements with affected parties, local government
authorities etc.
• Accounts processes payments to the affected people and ensure proper accountability
throughout the project circle.
7.2.2 Ministry of Physical Planning and Urban Development
The Enugu State Ministry of Physical Planning and Urban Development Law, 2005 provides for
the administration of Physical Planning, Urban and Regional Development Agencies and for
connected purposes. The Ministry of physical Planning is given the ministerial responsibility for
initiation, formulation and implementation of policies and coordination of programmes on all
aspects of physical planning and urban development in Enugu State.
The Ministry has the power to acquire any land in connection with development activities, and
any right of occupancy on such land can be revoked in accordance with the provisions of the
Land Use Act. Payment of compensation generally under this law shall be in accordance with
the provisions of the Land Use Act. (sections 80-81).
Provision of alternative accommodation for a person likely to be displaced is available in
section 90 of the Law. The assistance includes Planning, or building alternative
accommodation or even financial assistance. There is also an appeal against any decision
and the procedure as established in section 105 of the law.
The roles of this ministry in the resettlement plan will include:
Verification of selected sites for resettlement and ensuring that such sites are ideally
suitable for affected people.
Invoke the physical planning and urban development law at the road.
Ensuring that FPMU/SPIU meets with the requirements of resettlement as specified in the
report
Make appropriate recommendation and input in the resettlement process.
Ensuring that affected people are adequately compensated as stated in this report
and
Carry out functions as may be directed by the Honourable Commissioner for physical
planning.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
57
7.2.3 Ministry of Works and Infrastructure
The Ministry formulates policies and oversees other agencies. It also sees to the implementation
of policy decisions and coordinates various transport laws and policies. Statutorily, the ministry is
mandated to: provide road infrastructures, enforce traffic regulations, carry out public
education and enlightenment and issuing guidelines for allocation of routes and prohibition of
use of bus stops and lay-bys as terminals and trading locations.
7.2.4 Ministry of the Environment
The Ministry is responsible for the overall environmental policy of the State. It imposes
responsibility on all facets of environmental media, and prohibition of certain acts and
conducts such as preventing;
People or person from constructing or putting any structure on roads, rail track,
People or persons from using any road, street or other setback as a mechanic workshop
People or person from display, selling or buying goods on roads, rail tracks, bridges and
road setbacks.
The Ministry is also empowered to create environmental sanitation corps, which has, as part of
its functions, the mandate to enforce state sanitation laws and street trading. It is also to assist
the State Ministry of Physical Planning, Local Governments and Law Enforcement Agencies in
monitoring matters affecting environmental sanitation.
The roles and responsibilities of the ministry is to direct the Health, Safety and Environment (HSE)
Department to work with the FPMU/SPIU to implement HSE plan for contractors engaged in
construction. In the same vein, the environmental sanitation corps shall assist FPMU/SPIU in the
resettlement of affected persons to allocated areas and enforce sanitations policy of the
government in those locations. During the implementation phase, it is the responsibility of the
ministry to ensure that people whom have been relocated do not return to their previous
locations. The HSE and the ministry report directly to the FPMU/SPIU.
7.2.5 Lands Bureau
The bureau has the responsibility for the formulation of policies and implementation pursuant to
the provisions of the Land Use Act, 1978 as amended under the 1990 Laws of the Federation of
Federal Republic of Nigeria. It also has the primary responsibility for land management in the
state. Part of its agencies includes the Land Use Advisory and Allocation Committee. Its
functions and power includes payment of compensation for the revocation of a right of
occupancy.
Since FPMU/SPIU is acquiring a small portion of new land for the purpose of this project, the
advisory and allocation committee shall work with the FPMU/SPIU to ensure that affected
people are compensated as stated in this report. They will also ensure FPMU/SPIU’s
compensation and assistance programme are in conformity with the provisions of the Land Use
Act where necessary.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
58
7.2.6 Local Government Authorities
The constitution of the Federal Republic of Nigeria approves the creation of Local Government
Councils in each of the 36 States of the federation. The local governments councils in the
intervention areas were created by the federal government to carry out their functions as
stated in the constitution. Since the local governments are directly involved in the allocation of
markets, it is imperative that they are part of the resettlement plan. Therefore, the roles and
responsibilities of the local authorities (physical planning or works department) in this
resettlement plan shall not be limited to the following.
Liaising with the FPMU/SPIU to verify adequacy of resettlement location and provide
approval for such sites.
Implement policies developed by FPMU/SPIU for project sustainability.
Liaise with FPMU/SPIU and participate in consultations with the communities.
7.2.7 Traditional Institutions
Traditional rulers in the community of impacts will be involved in the institutional arrangements
for project planning, implementation and operation. The will assist to;
ensure that activities of their subjects do not contravene the policy of FPMU/SPIU on the
project.
provide resettlement assistance in areas where necessary
participate in consultations and enlightenment of members and other affected people
participate in dispute resolution arising from resettlement activities
7.3 Measures for Strengthening Organizational Capability
There is supposed to be Safeguard Unit in FPMU/SPIU with well trained personnel in ARAP. It is
the responsibility of this unit to ensure that all identified members of the implementation team
are trained prior to implementation of resettlement and compensation. The training includes
the following.
The OP 4.12 of the World Bank and other World Bank operational policies on
environment,
Relevant Nigerian laws and policies relating to land acquisitions and resettlement,
Brief on the socio-economic survey report on the roads and junctions,
Compensation and supplementary assistance in the report,
Discuss implementation plan and adopt the implementation plan in the RAP report,
Designate specific roles and responsibilities for all members.
The safeguard unit will ensure that over zealousness of implementation team is curtailed
through adequate monitoring and any officer found wanting in his responsibility is replaced. It is
the responsibility of the National Coordinator therefore to:
Provide adequate logistics for the ARAP implementation team.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
59
Keep accurate records of resettlement and compensation data and ensure consistent
update of the information.
Strengthen report system and internal monitoring and solve the problems promptly.
Strengthen the independent monitoring and evaluation. The independent monitoring
and evaluation institution should report promptly to project director about the problems
and provide suggestions to solve them.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
60
8.0 MONITORING AND EVALUATION
8.1 Objectives
The World Bank operational policy (OP 4.12) states that the project sponsor, FPMU is responsible
for adequate M&E of the activities set forth in the resettlement instrument. Monitoring will
provide both a warning system for the project sponsor and a channel for the affected persons
to make known their needs and their reactions to resettlement execution. FPMU’s monitoring
and evaluation activities and programs shall be adequately funded and staffed. In-house
monitoring may need to be supplemented by independent monitors to ensure complete and
objective information. Accordingly, the primary responsibility for monitoring rests with FPMU.
Interestingly, FPMU is expected to have an Environmental and Social safeguard team, and an
implementation-monitoring unit. These different groups, in cooperation with each other and
with guidance from the External Relations Unit of FPMU will internally monitor the project.
Monitoring and Evaluation (M&E) procedures establish the effectiveness of all land and asset
acquisition and resettlement activities, in addition to the measures designed to mitigate
adverse social impacts. The procedures include internal track keeping efforts as well as
independent external monitoring.
The purpose of resettlement monitoring for the proposed road project will be to verify that:
Actions and commitments described in the ARAP are implemented;
Eligible project affected people receive their full compensation prior to the start of the
rehabilitation activities on the corridor;
ARAP actions and compensation measures have helped the people who sought cash
compensation in restoring their lost incomes and in sustaining/improving pre-project
living standards;
Complaints and grievances lodged by project affected people are followed up and,
where necessary, appropriate corrective actions are taken;
If necessary, changes in ARAP procedure are made to improve delivery of entitlements
to project affected people.
8.2 ARAP Monitoring Framework
There are three components of the monitoring framework for the proposed road construction
projects:
• Internal monitoring by FPMU/SPIU;
• Impact monitoring commissioned to specialized firms; and
• RAP Completion Audit.
The scope of each type of monitoring is briefly described in the following sections and in Table
8.1. The roles and responsibilities for internal and external monitoring are discussed along with
the reporting, staffing and resources needed for the monitoring program.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
61
Table 8.1: ARAP Monitoring Framework
Component
Activity
Type of
Information/Data
Collected
Source of
Information/Data
Collections
Methods
Responsibility
for Data
Collection,
Analyses and
Reporting
Frequency/Audience
of Reporting Internal
Performance
Monitoring
Measurement of
input, process,
output and
outcome
indicators
against
proposed
timeline and
budget,
including
compensation
disbursement
Quarterly
narrative status
and
compensation
disbursement
reports
FPMU/SPIU
ARAP team,
including
public relations
representatives
Semi annual or as
required by
FPMU/SPIU ARAP
management team
and World Bank. Impact
Monitoring Tracking
effectiveness of
inputs against
baseline
indicators
Assessment of
affected
people’s
satisfaction with
inputs, processes
and outputs.
Annual
quantitative and
qualitative
surveys. Regular
public meetings
and other
consultation with
project affected
people; review
of grievance
mechanism
outputs.
FPMU/SPIU
ARAP team,
including
public affairs
representatives
Panel of
Experts
Annual
In order to effectively report on the effectiveness of ARAP implementation, FPMU/SPIU, as the
project sponsor, will monitor the following key indicators, in keeping with World Bank
requirements on involuntary resettlement:
• The timely disbursement of compensation;
• Compensation disbursement to the correct parties;
• Public consultation and grievance procedures in place and functioning; and
• The physical progress of resettlement and rehabilitation, where applicable.
FPMU/SPIU’s monitoring will provide the ARAP management team with feedback on ARAP
implementation and help ensure that adverse impacts on affected people are mitigated in a
timely manner. M&E will be the main mechanism to alert management of any delays and
problems and will help FPMU/SPIU measure the extent to which the main objectives of the
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
62
resettlement plan have been achieved. ARAP monitoring and evaluation activities will be
adequately funded, implemented by qualified specialists and integrated into the overall
project management system.
FPMU/SPIU’s ARAP monitoring and evaluation activities will be supplemented and verified by
monitoring efforts of an independent Panel of Experts specialized in resettlement issues.
The establishment of appropriate indicators in the A is essential since what is measured is what
will be considered important. Indicators will be created for affected people as a whole, for key
stakeholder groups, and for special categories of affected groups such as women. Key
performance indicators for monitoring are commonly divided into five categories for World
Bank financed activities:
• Input indicators include the resources in terms of people, equipment and materials that
go into the ARAP. Examples of input indicators in the ARAP are the sources and
amounts of funding for various ARAP activities.
• Output indicators concern the activities and services, which are produced with the
inputs. Examples of output indicators in the ARAP include (i) a database for tracking
individual compensation; and (ii) the payment of compensation for loss of assets.
• Process indicators represent the change in the quality and quantity of access and
coverage of the activities and services. Examples of process indicators in the RAP
include:
i. The creation of grievance mechanisms;
ii. The establishment of stakeholder channels so that they can participate in
ARAP implementation; and
iii. Information dissemination activities.
• Outcome indicators include the delivery of compensation and other mitigation to
avoid economic and physical displacement caused by the Project. They measure
whether compensation is paid and received, whether the affected populations who
preferred cash compensation to in-kind resettlement assistance offered to them was
able to use compensation payment for sustained income.
The most important indicators for the ARAP in the near term concern outputs, processes and
outcomes since they define whether the planned level of effort is being made and whether
early implementation experience is being used to modify/redesign ARAP features. Over the
medium to long term, outcome and impact indicators are critical since they are the ultimate
measure of the ARAP’s effectiveness in restoring people’s livelihoods.
Monitoring indicators may have to be defined or re-defined during the course of project in
response to changes to project-related conditions. Consequently, implementation and
mitigation measures may have to be adopted to incorporate these changes into the M&E
plan.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
63
8.2.1 Reporting
ARAP monitoring reports will be prepared in accordance with World Bank guidelines. Progress
will be reported for the following tasks:
• Internal monitoring;
• Expert monitoring;
• Completion audit and;
• Compensation;
FPMU/SPIU will use a device such as a bar chart/Gantt chart or MS Project table to assess and
present information on progress of time bound actions.
8.2.2 Staff and Monitoring
The FPMU/SPIU ARAP management team will oversee all aspects of monitoring and evaluation,
and will provide high-level review of internal performance and impact monitoring and
associated reports. The management team will be supplemented by staff with appropriate skills
to carry out:
ARAP project resettlement requirements as defined by this ARAP;
Gathering and presentation of monitoring indicators to be used;
Design and implementation of basic techniques to be used for collecting information
and feedback from project affected people; and
Reporting requirements and formats.
8.3 Internal Performance Monitoring
Performance monitoring is an internal management function that will allow FPMU/SPIU to
measure physical progress against milestone input, process, output and outcome indicators
established in the ARAP. To ensure independence of internal monitoring arrangements within
the ARAP Management Team are made so that the roles of the monitoring staff are separated
from the other roles.
8.3.1 Types of Information/Data Collected
The information used in internal performance monitoring will include assessment of the
milestones outlined in Table 8.2 below.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
64
Table 8.2: Information Milestone
DDictator
Milestone
Input
Updated Census of affected people so that shop owners
and absentee owners are noted.
An updated asset inventory if more than a year elapses
between the cut-off date and the declaration of the
Final Investment Decision (FID).
An updated asset inventory if a decision is made to
enlarge any of the existing roads to cover the newly
affected areas.
Socioeconomic survey of a representative sample of
affected people to serve as baseline for subsequent
monitoring. Output
Valuation and determination of compensation for
affected assets conducted in accordance with relevant
legislative frameworks, (to be updated before FID).
Public meetings held: consultations with project affected
people (PAP) at the area level for areas to be included in
the project if a decision to add or to enlarge an access
road is made. Outcome and
Impact
Compensation payments disbursed: FPMU/SPIU will
conduct a field check to verify that compensation
payments have been received by land owners, farm
owners and other PAPs, and will confirm levels and timing
of payments.
Grievance redress procedures in place and functioning:
FPMU/SPIU will check the type of grievance issues and
the functioning/effectiveness of grievance redress
mechanisms by reviewing the processing of appeals at
all levels, the outcomes of grievances and PAP
satisfaction with grievance procedures. As part of this,
FPMU/SPIU will interview aggrieved affected people.
Monitoring and evaluation reports submitted.
8.3.2 Source of Information/Data Collection Methods
Performance monitoring of the ARAP will be integrated into the overall project management to
ensure that ARAP activities are synchronized with all project implementation activities. Various
methods will be used to monitor progress against the milestones established in the ARAP, such
as:
Interviews of random sample of affected people, using open-ended discussions to
assess their knowledge and concerns regarding the displacement, their entitlement
and rehabilitation measures;
Up-date of baseline survey within 18 months of displacement;
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
65
Case studies of grievances.
Information will be collected and compiled in the quarterly narrative status and compensation
disbursement reports.
8.3.3 Responsibility for Data Collection, Analysis and Reporting
The FPMU/SPIU ARAP Management team supported by other departments will have primary
responsibility for the implementation of all internal monitoring activities. Designated staff will
collect relevant data in a standardized format.
8.3.4 Frequency/Audience of Reporting
Performance monitoring reports for the FPMU/SPIU ARAP management team will be prepared
at regular intervals (weekly), beginning with the commencement of any activities related to
resettlement, including income restoration. These reports will summarize information that is
collected and compiled in the quarterly narrative status and compensation disbursement
reports and highlight key issues that have arisen. As a result of the monitoring of inputs,
processes, outputs and outcomes of ARAP activities, project management will be advised of
necessary improvements in the implementation of the ARAP.
8.4 Impact Monitoring
Impact monitoring assesses the effectiveness of the ARAP and its implementation in meeting
the needs of the affected population. FPMU/SPIU will commission social and economic impact
monitoring studies in consultation with the external and independent Panel of Experts including
the Federal Ministry of Environment and the Enugu State Ministry of the Environment. Results will
be reviewed by FPMU/SPIU ARAP management team as well as by the Panel. The results of
impact studies as well as internal monitoring efforts will be available through the regular
information outlets of FPMU/SPIU. Impact monitoring will enable FPMU/SPIU to do the following:
Verify internal performance monitoring; and
Identify adjustments in the implementation of the ARAP, as required.
FPMU/SPIU will include the affected persons in all phases of impact monitoring, including the
identification and measurement of baseline indicators. One baseline has already been
established through the preliminary socio-economic studies of the population and area
affected by the project. Impact monitoring will also review consultation and grievance
mechanism outputs such as the types of grievances identified and the outcomes.
8.4.1 Type of Information/Data Collected
In order to measure the project impact and to assess the effectiveness of project impact
mitigation measures, FPMU/SPIU will evaluate various categories of quantitative economic,
public health and social indicators at the individual level as appropriate.
In addition to quantitative indicators, impact monitoring will be supplemented by the use of
qualitative indicators to assess client satisfaction and the satisfaction of the affected people
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
66
with the choices that they have made in re-establishing themselves. Tracking this data will allow
FPMU/SPIU to determine the following types of information:
• The extent to which quality of life and livelihood has been restored; and
• Whether Project Affected Persons have experienced any hardship as a result of the project.
8.4.2 Source of Information/Data Collection Methods
Impact monitoring data will be collected at appropriate intervals through qualitative and
quantitative surveys, and include a review of grievance mechanism outputs. FPMU/SPIU intends
to directly consult with the affected populations through regular public meetings.
8.4.3 Responsibility for Data Collection, Analysis and Reporting
FPMU/SPIU ARAP team will have primary responsibility for the implementation of all internal
monitoring activities. Designated staff will collect and review relevant data in a standardized
format.
8.4.4 Frequency/Audience of Reporting
Impact monitoring data will be reported to the ARAP management team and relevant
external agencies annually, or more frequently as required. The monitoring will continue for six
months beyond the completion of displacement process.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
67
9.0 RESETTLEMENT BUDGET AND FINANCING
Budgetary provisions have been made in the proposed rural road project to ensure that the mitigation
commitments, including compensation and the monitoring programs are fully implemented. FPMU/SPIU shall
make direct payments to all project affected persons and this will be done after an audit of eligible PAPs
would have been carried out. This audit is a physical verification exercise to further confirm the actual
number of PAPs by requesting them to appear physically for identification, to confirm the number of PAPs
that are still alive as of the time of compensating them, to check against multiple registration and to issue
them identification cards. In a case, where a PAP is demised as of the time the compensation would be paid,
their biological off-springs will be identified and paid the deceased’s compensation. The overall budget for
the resettlement action plan is presented in Table 9.1.
Table 9.1: ARAP Budget for Enugu State RAMP Roads
#.
Location/Description
Unit
Quantity
Rates
(NGN)
Total Amount
(NGN)
1.0
UMUANIAGU (OZALLA) Community on Road #13
1.1
4,500 Square Metre of Cassava Farmland @ Umuaniagu
SQ.M
4,500
925.926
4,166,667.00
1.2
Major Traditional Religious Shrine @ Umuaniagu
Nos.
3
250,000
750.000.00
1.3
Baskets of Cassava Lost to Road Encroachment
Nos.
281
1,500
421,500.00
1.4
Palm Trees Lost to Road Encroachment
Nos.
63
18,000
1,134,000.00
1.5
Other Valuable Trees Lost to Road Encroachment
Nos.
54
15,000
810,000.00
Sub-Total for Umuaniagu Community on Road #13 N7,282,167.00
#.
Location/Description
Unit
Quantity
Rates
(NGN)
Total Amount
(NGN)
2.0
OJOR Community on Road #12
2.1
Virgin Land @ Ojor
SQ.M
3,600
925.926
3,333,333.60
2.2
Major Traditional Religious Shrine @ Umuaniagu
Nos.
3
250,000
750,000.00
2.3
Minor Traditional Religious Shrine @ Umuaniagu
Nos.
40
2,000
80,000.00
2.4
Cassava Farmland @ Ojor
SQ.M
1,200
925.926
1,111,111.20
2.6
Baskets of Cassava Lost to Road Encroachment
Nos.
75
1,500
112,500.00
2.7
Relocation of Community Transformer
LS
750,000.000
3.0 Sub-Total for Ojor Community on Road #12 N6,136,944.53
4.0 Total for Umuaniagu and Ojoo Communities N13,419,111.53
5.0 Cost for Impact Monitoring (5% of 4.0) N670,955.58
6.0 Sub-Total N14,090,067.11
7.0 Contingency (5% of 6.0) N704,503.36
Total ARAP Cost Estimate for Enugu RAMP ROAD PROJECTS
N14,794,570.47
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
68
10.0 IMPLEMENTATION SCHEDULES
10.1 Introduction
To ensure an effective and successful implementation of the expropriation/compensation
program there is the need to put in place an efficient system of planning and coordination. In
order to achieve this objective, public consultations have been organized with the various
stakeholders and other relevant government agencies, at the commencement and other
stages of project.
The implementation schedule for this ARAP covers the periods from the preparation of the
ARAP to the conclusion of the proposed rural road construction to the completion and the
time that the road will be fully available to full use. It is important to note that the procedure in
the schedule starting from notification of the PAPs before their displacement through
compensation and resettlement will be carried out in phases to synchronize with the various
phases of the project. The ARAP Implementation schedule defines the duration and timing of
the key milestones and tasks. The major component tasks for the schedule include:
Preparation of ARAP
Consultation and Disclosure of ARAP
Final Investment Decision and effectiveness of Credit
Formation of Project Implementation Committee
Education and awareness creation about ARAP procedures and compensation
payment
Notification of PAPs prior to the activities that will affect them
Space Acquisition and Compensation.
Commencement of project operations.
Grievance Redress Measures
Monitoring and evaluation, including baseline update
The implementation schedule for major activities relating to both permanent and temporary
structures is presented in Table 10.1.
Table 10.1 shows the implementation schedule, this however will be developed in further details
and timeline after the World Bank Review and Final Investment Decision.
10.2 Plan Preparation
Development of the formal ARAP was carried out in May, 2012 with socio-economic surveys in
the field. Prior to the survey, SPIU had consultations with the relevant stakeholders of project
areas to inform them of the project and its purpose and benefits. Public disclosure of the final
document and restitution will be concluded in July, 2012 subsequent to review by World Bank
authorities before the final investment decision.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
69
Table 10.1: Schedule for Implementation of the Major Activities Major Activities Months
1 2 3 4 5 6 7 8 9 10 11 12
Preparation of ARAP
Consultation and Disclosure of ARAP
Final Investment Decision and Effectiveness of Credit
Formation of Project Implementation Committee
Education and awareness creation about ARAP
procedures and compensation payment
Notification of PAPs prior to the activities that will
affect them
Payment for compensation for Acquisition, Relocation
etc
Commencement of Construction Activities
Grievance Redress Measures
Monitoring and Evaluation
Completion Report Writing
10.3 Consultation and Disclosure
Consultations with stakeholders, was initiated very early with preliminary meetings with local
government chairmen and community groups. To date, RAMP/SPIU have conducted series of
consultations.
Broad ranges of stakeholders, including state and local authorities, traditional ruling authorities,
non-governmental organizations, Community-based Organizations, youth organizations and
trade unions in the project areas have been contacted. The consultations were aimed at
identifying the best ways to mitigate the impacts the project is likely to have on the affected
people.
FPMU/SPIU alongside the Consultant conducted open consultations with the PAPs to inform
them of the proposed road projects and the need for some of them to either shift or get
relocated away from the Right of Way (RoW) of the proposed route.
Disclosure of the ARAP continues with the public consultation process by communicating the
plan for implementation of RoW acquisition and relocation assistance, as well as monitoring
and evaluation of the mitigation measures.
10.4 RoW Acquisition and Construction
RoW acquisition activities will be synchronized with the project construction. Specific RoW
acquisition negotiations and contract preparation began in April, 2012 following the survey of
the quantity of RoW occupied and their valuation.
As part of the negotiations it will be emphasised that the acquisition of properties will be
aligned with the construction schedule. Though the final schedule for construction is not yet in
place, however, it is envisaged that site work will commence in January, 2013 after payment of
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
70
compensation. The commencement date of the schedule for the project is dependent on the
final investment decision (FID). Construction activities are expected to occur over a 1-month
period after commencement.
10.5 Monitoring and Evaluation
These activities will occur over the construction period and will continue for approximately 4
months following completion of the construction phase.
10.6 Update of the Baseline Data
Based on the monitoring and evaluation of the impact of the project on the PAP population,
an update of the baseline date will be produced to assess the overall impact of the project on
the population along the project route.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
71
11.0 DISCLOSURE
This Abbreviated Resettlement Action Plan will be disclosed in Nigeria by the FPMU which will
make copies available at its head offices and on its website and copies distributed to the
project affected persons, the press, palaces of traditional rulers and the offices of the Local
Government Areas overseeing these zones on August 15, 2012. The World Bank will also
disclose this Abbreviated Resettlement Action Plan electronically through its website prior to
processing the project.
The following process will be used to disclose the ARAP:
FPMU will place the ARAP in designated places and at least through the construction
phase. In Nigeria, these will consist of Local Government Area headquarters in the two
intervention areas, Enugu State Government secretariat, palaces of traditional rulers,
Federal Ministry of Environment, FPMU office, SPIU office and any other public place as
directed by the World Bank.
FPMU/SPIU will run public advertisement in the electronic media on the availability of
the ARAP report in designated places.
FPMU will advise its public relations and legal units to maintain contact with the relevant
Ministries, other public agencies, local representatives and communities.
Furthermore, during project implementation, the ARAP consultant and the SPIU State
Coordinator will prepare and conduct information and stakeholders program in the project
areas.
The main objectives are to:
1. inform and explain the entitlement policy and various options to the affected people
(APs) prior to financial assistance;
2. socially prepare the affected persons for relocation;
3. help counter rumors and prevent unnecessary distress;
4. bring clarity on issues that might be raised by the affected persons about their
entitlements and benefits through question-and-answer sessions;
5. solicit help from local government administration, Traditional rulers, community groups,
and others and encourage their participation in RAP implementation; and
6. attempt to ensure that vulnerable groups understand the process and their needs are
specifically taken into consideration.
Moreover, participation of project-affected people is also ensured through their involvement in
various local committees such as Resettlement Advisory Committees and Grievances Redress
Committees. FPMU/SPIU will establish and continuously maintain an ongoing interaction with
the affected persons to identify problems and undertake remedial/mitigation actions.
According to the requirements of the World Bank, the ARAP must be submitted for their review.
Once approved for public disclosure purposes, the ARAP will be made available via the World
Bank Info Shop. In addition, short brochures will be printed and distributed to inform people of
the ARAP implementation arrangements.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
72
Annex 1A: List of PAPs Consulted in Umuaniagu (Ozalla) Community (on Road #13)
#.
Name of PAP @ Umuaniagu
Occupation
Contact Telephone
Number
Gender 1 Amos Nwogbodo Farmer 08058497579 Male
2 Simeon Nwogbodo Farmer Male 3 Ebuka Nwogbodo Farmer Male 4 Onyechi Okeke Farmer Male 5 Okonkwo Ozoma Farmer 07032200064 Male 6 Jonadha Atu Farmer Male 7 Chinwe Uba Nwogbodo Farmer Male 8 Josephine Okonkwo Farmer 08160283271 Female
9 Zina Nwogbodo Farmer Female 10 Josephine Nwogbodo Farmer 08060096141 Female 11 Osita Okeke Farmer 08060960253 Male 12 Sylvester Okeke Farmer 08060960253 Male 13 Joseph Nwogbodo Farmer 08060096141 Male 14 Ndidi Nwogbodo Farmer 08105864916 Female 15 Roseline Nwogbodo Farmer Female 16 Venatus Nwogbodo Trader 08105864916 Male 17 Linus Onyia Farmer 07068794122 Male 18 Josephine Onyia Farmer 08038519200 Female
19 Uchenna Onyia Farmer Male
20 Felicia Onyia Farmer Female
21 Anthony Chukwu Farmer Male 22 Nwankwo Ogbodo Farmer 07032200064 Male 23 Amuche Chukwu Farmer Female
24 Godwin Ogbodo Farmer 08062916936 Male 25 Onyekachi Nwogbodo Farmer Male 26 Simeon Nwafor Trader Male 27 Godwin Nwogbodo Farmer 08058497579 Male 28 Mabel Chukwu Farmer 08035598110 Female
29 Sunday Okoye Farmer 08035958828 Male 30 Felix Ani Farmer 08037377548 Male 31 Ebuka Nwogbodo Farmer Male 32 Chukwuma Okeke Farmer 08160283271 Male 33 Afamu Ogbodo Farmer Male 34 Okwudili Ani Farmer Male 35 Cyril Ogbodo Farmer 08036230190 Male 36 Nwafor Ogbodo Farmer Male 37 Ujo Ude Farmer Female 38 Bridget Nwankwo Farmer Female 39 Chinyere Okeke Farmer Female 40 Martha Atu Farmer Female 41 Nworie Ofor Ogbodo Farmer Female 42 Theresa Ogbodo Farmer Female 43 Caroline Chika Trader 08031388530 Female 44 Eucheria Nweke Farmer 08185400560 Female 45 Faith Nwogbodo Farmer 08035958828 Female 46 Susan Ude Trader Female 47 Rosemary Nwachukwu Trader Female
48 Esther Ude Farmer 08036230190 Female 49 Monica Agu Farmer 08185400560 Female
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
73
50 Cordelia Nwafor Trader Female 51 Josephine Nwanneche Farmer 08064650910 Female 52 Catherine Ani Police Officer 08034788224 Female 53 Patricia Okonkwo Farmer Female 54 Amuche Chukwu Farmer Female 55 Roseline Ude Farmer Female 56 Maria Dons-Ude Farmer Female 57 Comfort Atu Farmer Female 58 Angelina Okoroafor Farmer Female 59 Uche Atu Farmer Female 60 Monica Nwatu Farmer Female 61 Comfort Aneke Farmer Female 62 Okonkwo Caroline Farmer Female
63 Okonkwo Josephine Farmer 08062916936 Female
64 Paul Nwafor Trader 07059747888 Male
65 Francis Okonkwo Farmer 08035598110 Male
66 Micheal Nwachukwu Farmer 08037377548 Male
67 Christiana Igwe Farmer 08130140411 Female
68 Jude Agu Kingsley Trader 08031388530 Male
69 Roseline Ogbodo Farmer 08036230190 Female
70 Sam Ngene Farmer 08064650910 Male
71 Joseph Ogbodo Police Officer 08034788224 Male
72 Gladys Nwogbodo Farmer Female
73 Ibuka Nwafor Farmer Male
74 Oscar Okeke Farmer Male
75 Kelechi Okeke Trader Female
76 Onyinye Okeke Trader Female
77 Cletus Nwogbodo Farmer Male
78 Ogbeani Onyia Farmer Male
79 Judith Nwogbodo Trader Female
80 Chinwe Onyia Trader Female
81 Benedict Okeke Farmer Male
82 Ozoma Okonkwo Trader Male
83 Caroline Okonkwo Trader Female
84 Josephine Okonkwo Trader Female
85 Monica Nwafor Trader Female
86 Nzekwe Ani Farmer Male
87 Mabel Ani Trader Female
88 Ngbeke Nwafor Farmer Male
89 Florence Ogbodo Trader Female
90 Clement Nweke Trader Male
91 Bernard Igwe Farmer Male
92 Nwogodo Onyia Farmer Male
93 Comfort Onyia Trader Female
94 Rebecca Onyia Trader Female
95 Anieke Chukwu Farmer Male
96 Chukwu Nonso Chukwu Farmer Male
97 Amosile Chukwu Farmer Female
98 Sunday Okore Farmer Male
99 Ndubuisi Ogbodo Trader Male
100 Ugochukwu Agu Trader Male
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
74
Annex 1B: List of PAPs Consulted in Ojor Community (on Road #12)
#.
Name of PAP @ Ojor
Occupation
Contact Telephone
Number
Gender
1. HRH Igwe Emmanuel Umunna Farmer 08087321717 Male
2. Olisaemeka Ogugua Farmer 08087321717 Male
3. Izualor Umunna Farmer 08087321717 Female
4. Pius Ogugua Farmer 08087321717 Male
5. Oriyibo Mokwugwu Farmer 08087321717 Male
6. Oriizoba Ogwawonwa Farmer 08087321717 Male
7 Okuata Okeji Farmer 08087321717 Male
8 Christopher Eze Farmer 08087321717 Male
9 Ngbakwo Okeji Farmer 08087321717 Male
10 Onwuma Egwuma Farmer 08087321717 Male
11 Mercy Udeka Farmer 08087321717 Female
12 Obanakwu Itado Farmer 08087321717 Male
13 Mary Nwabozie Farmer 08087321717 Female
14 John Ugbagi Farmer 08087321717 Male
15 Odemane Ugwonwa Farmer 08087321717 Male
16 Chika Anyanwu Farmer 08087321717 Male
17 Hygeinus Egwuma Farmer 08087321717 Male
18 Elizabeth Ejike Farmer 08087321717 Female
19 Godwin Anyanwu Farmer 08087321717 Male
20 Odenigbo Nnalue Farmer 08087321717 Male
21 Virginia Anyanwu Farmer 08087321717 Female
22 Regina Okeke Farmer 08087321717 Female
23 Ozene Madubom Farmer 08087321717 Male
24 Oranu Nweke Farmer 08087321717 Male
25 Angelina Chidokwe Farmer 08087321717 Female
26 Nnonye Chidokwe Farmer 08087321717 Female
27 Afuluenu Uchonwu Farmer 08087321717 Female
28 Gloria Uchonwu Farmer 08087321717 Female
29 Nkiru Ude Farmer 08087321717 Female
30 Ibegwu Shiran Farmer 08087321717 Female
31 Blessing Okagbue Farmer 08087321717 Female
32 Ifeanyiwa Okagbue Farmer 08087321717 Female
33 Beatrice Okagbue Farmer 08087321717 Female
34 Fidelia Okoye Farmer 08087321717 Female
35 Ugochukwu Okoye Farmer 08087321717 Female
36 Mathew Egwuda Farmer 08087321717 Male
37 Ibanugo Onwude Farmer 08087321717 Female
38 Roseline Nnalue Farmer 08087321717 Female
39 Mathew Nweke Farmer 08087321717 Female
40 Gabriel Ejike Farmer 08087321717 Male
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
75
Annex 1C:List of PAPs, their Affected Structures and Compensation: UMUANIAGU Village
#.
Name of PAP @ Umuaniagu
Gender
Types of Property Estimated Cost (NGN)
Land (M
2)
Cassava (Baskets)
Palm Trees
Other Trees
Major Shrine
Minor Shrine
1 Amos Nwogbodo Male 45.00 2.81 45,881.67
2 Simeon Nwogbodo Male 45.00 2.81 2 81,881.67
3 Ebuka Nwogbodo Male 45.00 2.81 45,881.67
4 Onyechi Okeke Male 45.00 2.81 1 63,881.67
5 Okonkwo Ozoma Male 45.00 2.81 45,881.67
6 Jonadha Atu Male 45.00 2.81 5 4 195,881.67
7 Chinwe Uba Nwogbodo Male 45.00 2.81 45,881.67
8 Josephine Okonkwo Female 45.00 2.81 45,881.67
9 Zina Nwogbodo Female 45.00 2.81 45,881.67
10 Josephine Nwogbodo Female 45.00 2.81 3 99,881.67
11 Osita Okeke Male 45.00 2.81 18 315,881.67
12 Sylvester Okeke Male 45.00 2.81 1 63,881.67
13 Joseph Nwogbodo Male 45.00 2.81 24 2 3 1,257,881.67
14 Ndidi Nwogbodo Female 45.00 2.81 45,881.67
15 Roseline Nwogbodo Female 45.00 2.81 45,881.67
16 Venatus Nwogbodo Male 45.00 2.81 2 81,881.67
17 Linus Onyia Male 45.00 2.81 4 105,881.67
18 Josephine Onyia Female 45.00 2.81 45,881.67
19 Uchenna Onyia Male 45.00 2.81 1 60,881.67
20 Felicia Onyia Female 45.00 2.81 45,881.67
21 Anthony Chukwu Male 45.00 2.81 2 75,881.67
22 Nwankwo Ogbodo Male 45.00 2.81 45,881.67
23 Amuche Chukwu Female 45.00 2.81 45,881.67
24 Godwin Ogbodo Male 45.00 2.81 45,881.67
25 Onyekachi Nwogbodo Male 45.00 2.81 45,881.67
26 Simeon Nwafor Male 45.00 2.81 2 3 126,881.67
27 Godwin Nwogbodo Male 45.00 2.81 1 63,881.67
28 Mabel Chukwu Female 45.00 2.81 45,881.67
29 Sunday Okoye Male 45.00 2.81 1 63,881.67
30 Felix Ani Male 45.00 2.81 1 63,881.67
31 Ebuka Nwobodo Male 45.00 2.81 45,881.67
32 Chukwuma Okeke Male 45.00 2.81 1 63,881.67
33 Afamu Ogbodo Male 45.00 2.81 45,881.67
34 Okwudili Ani Male 45.00 2.81 45,881.67
35 Cyril Ogbodo Male 45.00 2.81 18 15 594,881.67
36 Nwafor Ogbodo Male 45.00 2.81 1 63,881.67
37 Ujo Ude Female 45.00 2.81 45,881.67
38 Bridget Nwankwo Female 45.00 2.81 45,881.67
39 Chinyere Okeke Female 45.00 2.81 45,881.67
40 Martha Atu Female 45.00 2.81 45,881.67
41 Nworie Ofor Ogbodo Female 45.00 2.81 45,881.67
42 Theresa Ogbodo Female 45.00 2.81 45,881.67
43 Caroline Chika Female 45.00 2.81 45,881.67
44 Eucheria Nweke Female 45.00 2.81 45,881.67
45 Faith Nwogbodo Female 45.00 2.81 45,881.67
46 Susan Ude Female 45.00 2.81 45,881.67
47 Rosemary Nwachukwu Female 45.00 2.81 45,881.67
48 Esther Ude Female 45.00 2.81 45,881.67
49 Monica Agu Female 45.00 2.81 45,881.67
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
76
50 Cordelia Nwafor Female 45.00 2.81 45,881.67
51 Josephine Nwanneche Female 45.00 2.81 45,881.67
52 Catherine Ani Female 45.00 2.81 45,881.67
53 Patricia Okonkwo Female 45.00 2.81 45,881.67
54 Amuche Chukwu Female 45.00 2.81 45,881.67
55 Roseline Ude Female 45.00 2.81 45,881.67
56 Maria Dons-Ude Female 45.00 2.81 45,881.67
57 Comfort Atu Female 45.00 2.81 45,881.67
58 Angelina Okoroafor Female 45.00 2.81 45,881.67
59 Uche Atu Female 45.00 2.81 45,881.67
60 Monica Nwatu Female 45.00 2.81 45,881.67
61 Comfort Aneke Female 45.00 2.81 45,881.67
62 Okonkwo Caroline Female 45.00 2.81 45,881.67
63 Okonkwo Josephine Female 45.00 2.81 45,881.67
64 Paul Nwafor Male 45.00 2.81 45,881.67
65 Francis Okonkwo Male 45.00 2.81 45,881.67
66 Micheal Nwachukwu Male 45.00 2.81 45,881.67
67 Christiana Igwe Female 45.00 2.81 45,881.67
68 Jude Agu Kingsley Male 45.00 2.81 45,881.67
69 Roseline Ogbodo Female 45.00 2.81 45,881.67
70 Sam Ngene Male 45.00 2.81 45,881.67
71 Joseph Ogbodo Male 45.00 2.81 45,881.67
72 Gladys Nwoggodo Female 45.00 2.81 45,881.67
73 Ibuka Nwafor Male 45.00 2.81 45,881.67
74 Oscar Okeke Male 45.00 2.81 45,881.67
75 Kelechi Okeke Female 45.00 2.81 45,881.67
76 Onyinye Okeke Female 45.00 2.81 45,881.67
77 Cletus Nwogodo Male 45.00 2.81 45,881.67
78 Ogbeani Onyia Male 45.00 2.81 45,881.67
79 Judith Nwogbodo Female 45.00 2.81 45,881.67
80 Chinwe Onyia Female 45.00 2.81 45,881.67
81 Benedict Okeke Male 45.00 2.81 45,881.67
82 Ozoma Okonkwo Male 45.00 2.81 45,881.67
83 Caroline Okonkwo Female 45.00 2.81 45,881.67
84 Josephine Okonkwo Female 45.00 2.81 45,881.67
85 Monica Nwafor Female 45.00 2.81 45,881.67
86 Nzekwe Ani Male 45.00 2.81 45,881.67
87 Mabel Ani Female 45.00 2.81 45,881.67
88 Ngbeke Nwafor Male 45.00 2.81 45,881.67
89 Florence Ogbodo Female 45.00 2.81 45,881.67
90 Clement Nweke Male 45.00 2.81 45,881.67
91 Bernard Igwe Male 45.00 2.81 45,881.67
92 Nwogbodo Onyia Male 45.00 2.81 19 11 552,881.67
93 Comfort Onyia Female 45.00 2.81 45,881.67
94 Rebecca Onyia Female 45.00 2.81 45,881.67
95 Anieke Chukwu Male 45.00 2.81 45,881.67
96 Chukwu Nonso Chukwu Male 45.00 2.81 45,881.67
97 Amosile Chukwu Female 45.00 2.81 45,881.67
98 Sunday Okore Male 45.00 2.81 45,881.67
99 Ndubuisi Ogbodo Male 45.00 2.81 45,881.67
100 Ugochukwu Agu Male 45.00 2.81 45,881.67
Total ARAP Cost Estimate for Umuaniagu Community on Road #13 N7,282,167.00
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
77
Annex 1D:List of PAPs, their Affected Structures and Compensation: OJOR Village
#.
Name of PAP @ Ojor
Gender
Types of Property
Estimated Cost (NGN)
Land (M
2)
Cassava (Baskets)
Community Land (M
2)
Transf
-ormer Major Shrine
Minor Shrine
1. HRH Igwe Emmanuel
Umunna
Male
3,600
1
4,083,333.6
2. Olisaemeka Ogugua Male 3 8 766,000.00
3. Izualor Umunna Female 8 16,000.00
4. Pius Ogugua Male 8 16,000.00
5. Oriyibo Mokwugwu Male 8 16,000.00
6. Oriizoba Ogwawonwa Male 8 16,000.00
7 Okuata Okeji Male 35.294 2.206 35,988.63
8 Christopher Eze Male 35.294 2.206 35,988.63
9 Ngbakwo Okeji Male 35.294 2.206 35,988.63
10 Onwuma Egwuma Male 35.294 2.206 35,988.63
11 Mercy Udeka Female 35.294 2.206 35,988.63
12 Obanakwu Itado Male 35.294 2.206 35,988.63
13 Mary Nwabozie Female 35.294 2.206 35,988.63
14 John Ugbagi Male 35.294 2.206 35,988.63
15 Odemane Ugwonwa Male 35.294 2.206 35,988.63
16 Chika Anyanwu Male 35.294 2.206 35,988.63
17 Hygeinus Egwuma Male 35.294 2.206 35,988.63
18 Elizabeth Ejike Female 35.294 2.206 35,988.63
19 Godwin Anyanwu Male 35.294 2.206 35,988.63
20 Odenigbo Nnalue Male 35.294 2.206 35,988.63
21 Virginia Anyanwu Female 35.294 2.206 35,988.63
22 Regina Okeke Female 35.294 2.206 35,988.63
23 Ozene Madubom Male 35.294 2.206 35,988.63
24 Oranu Nweke Male 35.294 2.206 35,988.63
25 Angelina Chidokwe Female 35.294 2.206 35,988.63
26 Nnonye Chidokwe Female 35.294 2.206 35,988.63
27 Afuluenu Uchonwu Female 35.294 2.206 35,988.63
28 Gloria Uchonwu Female 35.294 2.206 35,988.63
29 Nkiru Ude Female 35.294 2.206 35,988.63
30 Ibegwu Shiran Female 35.294 2.206 35,988.63
31 Blessing Okagbue Female 35.294 2.206 35,988.63
32 Ifeanyiwa Okagbue Female 35.294 2.206 35,988.63
33 Beatrice Okagbue Female 35.294 2.206 35,988.63
34 Fidelia Okoye Female 35.294 2.206 35,988.63
35 Ugochukwu Okoye Female 35.294 2.206 35,988.63
36 Mathew Egwuda Male 35.294 2.206 35,988.63
37 Ibanugo Onwude Female 35.294 2.206 35,988.63
38 Roseline Nnalue Female 35.294 2.206 35,988.63
39 Mathew Nweke Female 35.294 2.206 35,988.63
40 Gabriel Ejike Male 35.294 2.206 35,988.63
Total ARAP Cost Estimate for Ojor Community on Road #12
N6,136,944.53
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
78
Annex 2A:MINUTES OF THE CONSULTATION AND NOTIFICATION MEETING
ON THE PROPOSED UNTH-ENUGUAGU NDIAGU-UMUANIAGU-OBE AMURI ROAD (11.88kM) HELD
IN UMUANIAGU (OZALLA) ON THE 29TH MAY, 2012 AT 10.00AM
1.0 ATTENDANCE
i. Chairman, Mr. Joseph Nwogbodo (Community Head)
ii. Engr. Fidelis Nweke, SPIU State Coordinator, Enugu State
iii. Dr. Shakirudeen Odunuga, Pheman Peniel Consultants Ltd
iv. Engr . Bidemi Bello, Pheman Peniel Consultants Ltd
v. Engr. S. Igwuodo, SPIU, Enugu State
vi. Engr. Nsiegbunam, SPIU State, Enugu State
vii. 51 Female PAPs (See Table 5.1)
viii. 49 Male PAPs (See Table 5.1)
2.0 OPENING
The meeting commenced at about 10.00am with Engr F. Nweke introducing members of the
team present. Mr. Joseph Nwogbodo, who is a community/family head and Chairman of the
meeting led the PAPs in introducing themselves one after the other.
3.0 MEETING OBJECTIVES
Project Description: The intentions of FPMU/RAMP and the objectives of RAMP to upgrade the
rural road network in Enugu State and particularly the construction of the
11.88kM long UNTH-Enuguagu Ndiagu-Umuaniagu-Obe- Amuri Road on
the side of which their community lies was explained by Engr. Fidelis
Nweke. He made the PAPs to understand the need for their participation
in the realization of the objectives of the project and continued
consultation towards the success of the project. He pointed out that the
project may involve relocation of some properties the RoW of the
proposed route.
Project Objectives: The key objectives of the proposed road project, the safeguard issues
involved and how some farmlands, plantations and community structures
have been identified for resettlement action plan were presented to the
Chairman and the PAPs. He made the audience to appreciate that the
project is a World Bank-assisted one which requires that adequate
compensation should be paid to all those who are going to either be
displaced or relocated.
Dr. Odunuga further reiterated that FPMU would embark on the project
and has also identified the people that the project will affect and what
could be done to address the potential negative impacts of the project.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
79
He mentioned that all parties including members of Umuaniagu
community would be involved in the execution and management of the
proposed project before and during and after construction.
He made them to understand that being identified PAPs they would be
compensated for any loss of land, farm produce, shrines and structures in
accordance with the guidelines of the World Bank and the Federal Ministry
of the Environment. He further presented the list and extent of and led the
meeting to confirm and approve the landed property, farmlands, shrines
and structures which his team has identified.
Deliberations, Approval
and Confirmation: Extensive consultations on the level of impacts the proposed road would
have on the PAPs and their properties were made by the audience. Both
men and women from different families asked pertinent questions and
sought clarifications on the types of impact, mitigation measures,
resettlement action plans, compensation and the construction
programme and type to be adopted. Both Engr. Nweke and Dr. Odunuga
provided answers to their questions and allayed their fears of not being
compensated.
An inspection of the identified landed properties, farmland, shrines and
structures that will be affected by the proposed project was carried out
jointly by the PAPs and the project.
Based on this inspection exercise, the following properties were confirmed
by the PAPs for either relocation or acquisition.
i. Three (3Nos.)Major Shrines on the RoW of the propject road
ii. Cassava Farmland of an area of 4,500 Square metres.
iii. 281 Baskets of Cassava to be harvested from the cassava farmland
iv. 63 Oil Palm Trees
v. 54 Other Economic Trees
The Chairman presented the outcome of the exercise to the house and
the whole house (all the PAPs) further confirmed and approved the above
five items for either relocation or acquisition for the proposed project road.
Compensation: The consultation process progressed into valuation and compensation. Dr.
Odunuga explained the need for the PAPs to come to an agreeable
compensation rates uner the resettlement action plan. After adequate
deliberation, the PAPs and the project team agreed on the following rates
for compensation.
Shrine: N250,000 for the relocation of a shrine
Cassava Farmland: N925.926 per square metre
Harvested Cassava: N1,500 per basket
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
80
Oil Palm Tree: N18,000 per tree
Other Trees: N15,000 per tree
The Chairman presented the outcome of the exercise to the house and
the whole house (all the PAPs) further confirmed and approved the above
compensation rates for either relocation or acquisition for the proposed
project road.
4.0 CLOSING
The Chairman commended the efforts of FPMU/SPIU and the World Bank for bringing
development projects to their area and promised and promised to give full cooperation
towards the success of the project.
The meeting came to a close at 1.30pm, Nigerian time.
SIGNED SIGNED
Mr. Joseph Nwobodo Dr. Shakirudeen Odunuga
Community Head Pheman Peniel Consultants Ltd
SIGNED
Engr. Fidelis Nweke
State Coordinator, SPIU, Enugu State
Pix 2A-1: PAPs and Project Team @ Umuaniagu
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
81
Pix 2A-2: Women Group (PAPs) at Umuaniagu
Pix 2A-3: Men Group (PAPs) at Umuaniagu
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
82
Annex 2B: MINUTES OF THE CONSULTATION AND NOTIFICATION MEETING
ON THE PROPOSED ADANI-ASABA-IGGA-OJOR ROAD (9.94kM) HELD IN OJOR ON THE 30TH MAY,
2012 AT 11.00AM
1.0 ATTENDANCE
i. Chairman, HRH. Igwe Emmanuel Umunna (Community Head)
ii. Engr. Fidelis Nweke, SPIU State Coordinator, Enugu State
iii. Dr. Shakirudeen Odunuga, Pheman Peniel Consultants Ltd
iv. Engr . Bidemi Bello, Pheman Peniel Consultants Ltd
v. Engr. S. Igwuodo, SPIU, Enugu State
vi. Engr. Nsiegbunam, SPIU State, Enugu State
vii. 20 Female PAPs (See Table 5.2 for more details)
viii. 20 Male PAPs (See Table 5.2 for more details)
2.0 OPENING
The meeting commenced at about 10.00am with Engr F. Nweke introducing members of the
team present. HRH. Igwe Emmanuel Umunna, who is the community/family head and
Chairman of the meeting, led the PAPs in introducing themselves one after the other.
3.0 MEETING OBJECTIVES
Project Description: Engr. F. Nweke explained the intentions of FPMU/RAMP and the objectives
of RAMP to upgrade the rural road network in Enugu State and particularly
the construction of the 9.94kM long Adani-Asaba-Igga-Ojor Road on the
side of which their community lies. He made the PAPs to understand the
need for their participation in the realization of the objectives of the
project and continued consultation towards the success of the project. He
pointed out that the project may involve relocation of some properties
the RoW of the proposed route.
Project Objectives: Dr. Odunuga explained the key objectives of the proposed road project,
the safeguard issues involved and how some farmlands, plantations and
community structures have been identified for resettlement action plan to
the Chairman and the PAPs. He made the audience to appreciate that
the project is a World Bank-assisted one which requires that adequate
compensation should be paid to all those who are going to either be
displaced or relocated.
Dr. Odunuga further reiterated that FPMU would embark on the project
and has also identified the people that the project will affect and what
could be done to address the potential negative impacts of the project.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
83
He mentioned that all parties including members of Ojor community would
be involved in the execution and management of the proposed project
before and during and after construction.
He made them to understand that being identified PAPs they would be
compensated for any loss of land, farm produce, shrines and structures in
accordance with the guidelines of the World Bank and the Federal Ministry
of the Environment. He further presented the list and extent of and led the
meeting to confirm and approve the landed property, farmlands, shrines
and structures which his team has identified.
Deliberations, Approval
and Confirmation: The whole audience was engaged in extensive consultations on the level
of impacts the proposed road would have on the PAPs and their
properties. Both men and women from different families asked pertinent
questions and sought clarifications on the types of impact, mitigation
measures, resettlement action plans, compensation and the construction
programme and type to be adopted. Both Engr. Nweke and Dr. Odunuga
provided answers to their questions and allayed their fears of not being
compensated.
The meeting rose and carried out an inspection of the identified landed
properties, farmland, shrines and structures that will be affected by the
proposed project.
Based on this inspection exercise, the following properties were confirmed
by the PAPs for either relocation or acquisition.
i. Three (3Nos.)Major Shrines on the RoW of the project road
ii. Forty (40Nos.)Minor Shrines on the RoW of the project road
iii. Cassava Farmland of an area of 1,200 Square metres.
iv. Virgin land of an area of 3,600 Square metres.
v. 75 Baskets of Cassava to be harvested from the cassava farmland
vi. A Transformer to be shifted
The Chairman presented the outcome of the exercise to the house and
the whole house (all the PAPs) further confirmed and approved the above
five items for either relocation or acquisition for the proposed project road.
Compensation: The consultation process progressed into valuation and compensation. Dr.
Odunuga explained the need for the PAPs to come to an agreeable
compensation rates under the resettlement action plan. After adequate
deliberation, the PAPs and the project team agreed on the following rates
for compensation.
Major Shrine: N250,000 for the relocation of a shrine
Minor Shrine: N2,000 for the relocation of a shrine
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
84
Cassava Farmland and Virgin Land: N925.926 per square metre
Harvested Cassava: N1,500 per basket
Transformer: N75,000 for relocation
The Chairman presented the outcome of the exercise to the house and
the whole house (all the PAPs) further confirmed and approved the above
compensation rates for either relocation or acquisition for the proposed
project road.
4.0 CLOSING
The Chairman commended the efforts of FPMU/SPIU and the World Bank for bringing
development projects to their area, thanked the PAPs for honouring the invitation to and
participating meaningfully in the consultation and promised to give full support towards the
advancement of the project to realisation.
The meeting came to a close at 3.00pm, Nigerian time.
SIGNED SIGNED
HRH Igwe Emmanuel Umunna Dr. Shakirudeen Odunuga
Community Head Pheman Peniel Consultants Ltd
SIGNED
Engr. Fidelis Nweke
State Coordinator, SPIU, Enugu State
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
85
Pix 2B-1: PAPs and Project Team
Pix 2B-2: Transformer at Ojor
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
86
Pix 2B-3: A Minor Shrine at Ojor.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
87
ANNEX 3A: RELOCATION OF A MAJOR SHRINE: Procedure and Costs
A3.1 Procedures for Relocation of a Major Shrine
The high priest will supernaturally consult with the gods and the ancestral spirits behind the
shrine and its particular location. This will take seven days or more depending on the time of
response of the gods. The high priest would have to persistently intercede on behalf of the
community. This intercession will involve sacrifices to appease the spirits of the gods behind
the deity. The gods will not ordinarily accept to be shifted going by traditions but with
consistent intercession the prayers of the high priest may be accepted with a high cost of items
of sacrifice such as goats, tubers of yam, palm oil, fowls, assorted drinks, kolanuts, pepper etc..
The source of power of the high priest is not what anybody can ask him to divulge as divulging
such information on power and incantations is an abomination and an infringement on the
authority of the cult order he subscribes to. There are some personal sacrifices the high priest
must carry out on himself by himself in order to spiritually fortify himself against reprisals and
other spiritual attacks that might come upon him and his family as a result of venturing into an
unusual exercise of this nature. Therefore, this process is at the risk of the high priest’s life. For this
aspect of the procedure to relocate the shrine the high priest will offer sacrifices with items such
as are listed above. He will also be without food for seven days and sleep alone in the shrine at
his current location for as long as it takes for the sacrifice to be accepted by the gods without
having his bath or being exposed to daylight. He must neither sleep with his wives nor
communicate with any human being during this period of appeasement.
After, the appeasement must have been accepted by the gods, the high priest will come out
of the shrine, make a clarion call to all members of the community to gather around him, pour
libations, release a spotless white cock into the air and the community will erupt in joyful
celebration as this is a sign that the proposal to shift the shrine has been accepted by the gods
and there will be no evil repercussion on any member of the community.
Thereafter, the high priest will select seven men from the community who belong to the order
of the cult of the shrine and who he will sanctify to embark on the relocation exercise. These
seven men will be fortified spiritually by the high priest and they must not have had any sexual
contact with any woman or their wives seven days prior to the day the shrine will be relocated.
The exercise will be carried at midnight of a major market day under the cover of darkness and
when the shrines and their objects of worship are being moved, no member of the community
must come out for any reason and if anybody does, the repercussion will be very severe. The
person might die within forty days of this error or be spiritually attacked with a sickness that he
will nurse for the rest of his existence on earth.
Once the relocation has been successfully achieved, the high priest will invite the traditional
ruler and the entire community to worship at the new shrine and to celebrate with their
personal items of food and drinks.
No written documentation on the above processes are available with the Enugu State Ministry
of Culture and Tourism. These processes are the exclusive preserve of the traditional religious
institution of the community. They were obtained as oral tradition from the traditional ruler of
each community.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
88
3A.2 Cost Estimation for Major Shrine Relocation
The high priest is the only authorized person to collect the compensation for the relocation of
the shrine.
3A.2.1 Items for Sacrifice
a) 7 He-goats @ N15,000 = N105,000
b) 49 Tubers of Yam @N200 (7 Tubers of Yam per day) =N9,800
c) 21 Gallons of Palm Oil @ N1,000 (3 Gallons of Palm Oil per day) = N11,000
d) 21 Fowls @ N800 (3 Fowls per day) = N16,800
e) 21Nos Assorted Drinks @ N500 (3Nos. Assorted Drinks per day)= N10,500
f) Firewood = N2,000
g) Kolanut = N2,000
Sub-total: Items of Sacrifice: N157,100
3A.2.2 Others
a) Fee to the High Priest = N35,000
b) Fee to 7 men = N25,000
c) Honour Fee to the Oldest Man in the Community = N5,000
d) Honour Fee to the Oldest Woman in the Community = N3,000
e) Cost of Preparing a new site for the Shrine = N2,900
f) Cost of Dismantling the Make-shift Surround of the Shrine = N2,000
g) Cost of Erecting a new Make-shift Surround for the Shrine = N20,000
Sub-total: Others: N92,900
3A.2.3 Total Estimated Cost for Shrine Relocation: N250,000 (Two hundred and fifty thousand
Naira only)
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
89
ANNEX 3B: RELOCATION OF A MINOR SHRINE: Procedure and Costs
Minor shrines are personal shrines belonging to individuals for the purpose of personal contact
with their gods. They do not have permanent locations or physical structures like the major
shrines and can be moved from place to place depending on the interests of the owners. They
are usually in form of a calabash by the road side with sacrifice items inside or a piece of cloth
tied to the bottom of a tree.
To move this type of shrine, the owner will identify a new location outside the RoWs of the
roads, prepare the place, pour libation, chant some incantations and move the shrine.
No written documentation on the above processes are available with the Enugu State Ministry
of Culture and Tourism. These processes are the exclusive preserve of the traditional religious
institution of the community. They were obtained as oral tradition from the traditional ruler of
each community.
3B.1 Cost Estimation for the Relocation of a Minor Shrine
3B.1.1 Items for Sacrifice
4Nos Assorted Drinks @ N500= N2,000
Sub-total: Items of Sacrifice: N2,000
3A.1.2 Total Estimated Cost for Shrine Relocation: N2,000 (Two thousand Naira only)
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
90
ANNEX 4: GRASSROOT ORGANISATIONS IN AFFECTED COMMUNITIES
Umuaniagu Ozalla Women Organisation
Umuaniagu Ozalla Youth Association
Umuaniagu Ozalla National Union of Road Transport Workers
Umuaniagu Ozalla Market Women Association
Umuaniagu Ozalla Farmers Association
Traditional Ruler of Umuaniagu
Nkanu East Local Government
Nkanu West Local Government
Enugu South Local Government
Ojor Women Association
Ojor Youth Development Association
Ojor National Union of Road Transport Workers
Ojor Market Women Association
Ojor Farmers Association
Traditional Ruler of Ojor
Uzo Uwani Local Government
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
91
ANNEX 5:
TERMS OF REFERENCE (TOR) ON CONSULTANCY SERVICES FOR THE DETAILED ENGINEERING, SAFEGUARDS
STUDIES AND PREPARATION OF BIDDING DOCUMENTS FOR PRIORITIZED ROADS IN ENUGU STATE UNDER
RAMP II
1.0.0. INTRODUCTION
The Federal Ministry of Agriculture and Rural Development has received a Project Preparatory Advance
(PPA) from the World Bank and a Project Preparation Fund from the French Development Agency (AFD)
towards the cost of the preparing the Rural Access and Mobility Project II (RAMP II), and intends to apply
part of the proceeds for Consultancy Services for the preparation of Detailed Engineering Studies, Social
and Environmental Safeguards Studies and Bidding Documents for Prioritized Roads in four (4) selected
states.
1.0.1 Project Background
Nigeria’s rural transport infrastructure has been identified as a crucial component for the economic
development of the country by linking the rural communities to the urban areas. Most of the rural roads
are in poor condition, and impose significant cost to the national economy especially to the agricultural
activities due to increased vehicle operating costs and travel times. As a result of this, the Federal
Government of Nigeria (FGN) has given priority to the provision of adequate transport facilities to meet
the needs of the rural population.
To achieve this, a National Policy on Rural Travel and Transport Programme (RTTP) was prepared by the
Federal Government as an integral part of the National Transport Policy. The Federal Ministry of
Agriculture and Rural Development (FMARD) is responsible for the overall coordination of the RTTP in the
country through the Federal Project Management Unit (FPMU). The proposed RAMP is to be guided by
and will be supporting the implementation of the RTTP. The Federal Government of Nigeria, through the
Federal Ministry of Finance, requested the assistance of donors in financing the implementation of RTTP.
The successful implementation of the first phase of the project in Kaduna and Cross River States paved
way for the expansion of the project under RAMP 2 to cover additional four (4) states and additional
Eight (8) states will be prepared for an eventual future scaling up in the project.
The four states that were selected based on the Country Partnership Strategy (CPS) State Governance
criteria and the technical readiness criteria are:
1. Adamawa
2. Enugu
3. Niger
4. Osun
The second phase of the project (RAMP II) includes the following three (3) components:
Component 1: Rehabilitation of Rural and State Roads - This component would finance rehabilitation
works for an indicative 500km of rural roads and state roads in each of the initial four states as well as the
related design studies and external supervision activities. The prioritization of roads is based on the
following principles:
Road Classification: The project considers mostly local government and state roads link.
Federal roads are excluded.
State of Roads: Links that are inaccessible due to impassable terrain (collapse or
damage culverts, marshy areas) and difficult topographical terrain. The project focuses
on recreation of basic access and on roads in poor state.
Traffic: The project focuses on roads with current average daily vehicle traffic (AADT) of
less than 50 vehicles per day (vpd).
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
92
Connectivity: The project prioritized feeder roads that link to paved state and federal
roads. To major market places, to areas of medium to high agricultural and mining
production potentials.
Environmentally sensitive areas: The project in as much as possible avoids creating
access to protected areas (national parks; protected forests) to minimize the risk of
excessive logging, illegal hunting, forest clearing (cut and slash burning) for agriculture
and to protect Plant and animal.
The road works will include earthworks, laterite materials, construction of new pipe and box culverts as
well as repairs and extension of existing culverts.
Horizontal Alignments: The improved link will follow existing road alignment. Minor deviations
(short cuts) will be permitted for track reopened to vehicle traffic.
Vertical Alignments: They will follow essentially the existing topography. Only in sections of
excessive gradients minor cuts and fills will be considered. In sections liable to flooding and
marshy areas the road embankment will be raised to a minimum height of + 0.5 m above
maximum water level. Crossing of zones consisting of subsoils of insufficient strengths (e.g CBR <
10: clayey soils). If these zones are limited in length, building up of road embankments on
geotextiles shall be preferred to soil replacement. If such crossings are excessive in length,
alternative and more cost efficient horizontal alignments shall be sought (ridge road).
Components 2: Roads Maintenance and Local Development – This components would finance road
maintenance activities on rehabilitated roads and support state mechanisms for maintenance funding.
The models to be use in the maintenance mechanism involve community-based approach to among
others.
Components 3: Capacity Building and Project Administration – This components would finance
Institutional Strengthening activities at state level as well as project administration costs. The components
would be split in two subcomponents:
Subcomponents 3.1 (capacity building and project administration in the initial four states will be
implemented by the State Project Implementation Units (SPIU).
Subcomponents 3.2 (institutional strengthening for other participating states and Federal Project
Management Unit (FPMU) project management costs) would be implemented by the FPMU. This
component could also address capacity building at federal level to improve the sector strategy.
If each of the four selected states, about 200 km of rural roads have been prioritized, based on the
outcome of prioritization studies as well as on the conclusions from a revalidation study. The proposed
assignment aims at preparing the detailed engineering and safeguards studies and the bidding
documents for the rehabilitation works on 158.64 km of rural roads in Enugu State, packaged in three
clusters. The assignment also includes a conditional tranche for an additional cluster packaging 44.81 km
of rural roads’ rehabilitation works. The complete list of prioritized roads is provided below.
1.0.2. Understanding the Rural Access and Mobility Project (RAMP) and the Federal Project
Management Unit (FPMU)
The “Rural Access and Mobility Project (RAMP)” emerged from the RTTP as the rural transport strategy to
support the implementation of the National Policy on Rural Travel and Transport (NPRTT). RAMP is being
implemented in selected States, while the RTTP which is broader in scope is the umbrella of the Federal
Government designed to take RAMP to all the States of the Federation. Under this arrangement the role
of the Federal Government is to coordinate, support the States and ensure the implementation of the
policy while the responsibility for implementation of the projects rests with the States.
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
93
1.0.3. Objective of RAMP 2
The objective of RAMP 2 is to provide rural communities with improved access to social services and
economic opportunities, and to enhance the capacity of relevant government institutions to better
manage rural transport infrastructure. The indicative objective is to rehabilitate about 500km of rural
roads per initial participating state. Road standards will be determined as part of the road design studies,
with proper economic justification. Considering traffic levels observed on rural roads in Enugu state
(current average daily vehicle traffic (AADT) of less than 50 vehicles per day (vpd) and typical current
motorcycle traffic of 50 to 100 cycles per day), it is expected that the RAMP-2 project will rehabilitate
existing roads, without any paving/asphalt treatment involved.
The list of the prioritized roads in Enugu State is detailed below:
Cluster
Description: Intervention Areas and Road Links
Distance
(KM)
1.
UDI Intervention Area
Rd 32 Umuabi-Ehuhe Achi Road 9.48km
Rd 36 Abor Road 4.46km
Rd 37 Egede – Awhum Road 6.50km
Rd 39 St. Mary Ngwo – Nsude Road: 6.25km
EZEAGU/OJI RIVER Intervention Area
Rd 41 Ugwuoba – Nkwere Inyi- Inyi Road 19.88km
Rd 42 Isu Abaraji – Akpugo Eze – Inyi Market Road 12.69km
Total for Cluster #1 59.26kM
2.
NKANU EAST/NKANU WEST/ENUGU SOUTH Intervention Area
Rd 13 UNTH – Enuguagu Ndiagu-Umuaniagu–Obe – Amuri Road 11.88km
Rd 18 Mbogodo – Obinagu Uwani Akpugo – Ihuokpara Road 15.0km
ANINRI/AWGU Intervention Area
Rd 23 Mamaku-Awangbidi-Nkwe-Ezere-Isochi Road 9.28km
Rd 24 Uhueze Nenwe – Nomeh – Mburubu – Nara Road 21.00km
Total for Cluster #2 57.16kM
3.
IZI UZO Intervention Area
Rd 3 Neke – Umualor Road 16.84km
Rd 5 Neke – Mbu – Ogbodo Aba – Obollo Eke Road 25.38km
Total for Cluster #3 42.22kM
4.
UZO UWANI Intervention Area
Rd 9a Ukpabi – Nimbo – Ugbene Ajima – Eziani Road 28.62km
Rd 9b Ikwuoka –Amagu – Ajuona – Akabusiyi – Obimo Road 6.25km
Rd 12 Adani – Asaba – Igga - Ojo Road 9.94km
Total for Cluster #4 44.81kM
Grand Total
203.45kM
1.0.4 Objective of the Services:
The objective of the consultancy services is to carry out detailed engineering design including cost
estimates as well as environmental and social studies and to prepare the bidding documents for
prioritized rural road rehabilitation works in the state of Enugu.
The assignment will therefore involve survey of the roads, soil and materials testing, detailed Engineering
design, drainage structure design, preparation of detailed working drawings and bidding documents as
well as Bill of Engineering Measurement and Evaluation (BEME) and confidential cost estimate. It will also
include Environmental and Social Impact Assessment (ESIA) for the selected road rehabilitation works –
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
94
together with the associated Environmental Management Plan, and, whenever needed, a Resettlement
Action Plan (RAP).
One set of studies and bidding documents will have to be prepared for each of the three prioritized
clusters of roads in Enugu State, for respectively 59.26 km, 57.16 km and 42.22 km of roads. A third cluster
is included, as a conditional tranche, for 44.81 km of additional roads.
2.0.0. SCOPE OF SERVICES:
For each of the three clusters of rural roads (as well as possibly on the fourth cluster included as a
conditional tranche to the proposed assignment), the Consultant will prepare the following set of studies
(five copies to be provided for each document):
(a) Preparation of detailed road inventory and collection of road condition data.
(b) Full topographic survey of the road using Total station and GPS over a width of 6m on either side
of the center line. In addition to the data required for preparation of plan and profile drawings of
the road, the topographic survey shall provide information on the presence of housing units,
commercial and administrative buildings, trees, entrances to roadside properties, watercourses
and any other features that will affect the design of the rehabilitation works. The Consultant shall
carry out the necessary detailed topographic surveys for the road in order to establish the
accurate centerline. The centerline shall then be set out, cross-sectioned, with vertical controls
established where this has not already been done. The allowable tolerance of the survey and
leveling should be of the order of 0.01%. The Coordinates of all intersection points shall be tied to
the National Survey Grid and all levels related to the National Bench Marks. All survey data shall
be stored in AutoCAD compatible format (DWG/DXF) or equivalent and shall be compatible with
the software used for detailed road design.
(c) Geometric design following existing profile, except where safety factors necessitate some
adjustments. Road standards will follow standards and practices in Nigeria for rural roads (6
meters platform + 2 x 1 meter sides + 2 x 0.5 meter for drainage or as directed by the FPMU). The
horizontal alignment of the road centerline, tangent points and other critical points shall be fully
defined relative to stations on the baseline by coordinates and offsets suitable for setting out the
centerline. All points shall be coordinated to the National Survey Grid. Cross-sections shall be
taken along the length of the road centerline at 25 meter intervals and at any changes in the
topography. The vertical alignment shall take into account the design standard adopted while
minimizing the earth works required. There shall be coordination between horizontal and vertical
alignment to the extent possible. Consideration shall be given to road safety standards. The
design shall incorporate all the environmental aspects identified in the ESMF report. The
Consultant shall investigate whether there will be any other possible impacts on the environment
and make proposals for remedial measures. Engineering analysis shall be undertaken using the
results of the soils and materials tests to determine the gradients of the slopes, compaction
requirements,, and other engineering factors dictated by available natural materials.
(d) Geotechnical and materials surveys and tests, including soil sampling and testing at appropriate
intervals, as necessary for completion of the design, but also identification, sampling and testing
of materials from borrow pits, as well as any other geotechnical and soils investigations and
testing necessary for final design. The consultant shall make a detailed soil investigation over the
road alignment to identify the various soil types. These include: (i) Tests to identify and evaluate
the soundness of subgrade, subbase, base course and pavement layer materials including the
following investigation procedures. The sampling interval for sub-grade shall not be more than
500m, pits shall not be less than 1m deep; (iii) Specific tests to determine suitability of materials for
compliance to FMW Specifications which will include: particle size distribution and determination
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
95
of Atterberg limits for the purpose of soil classification; Compaction/ density / moisture
relationship/ maximum dry density; CBR; the expansiveness of proposed embankment
construction materials; and other tests as proposed by the consultant. The CBR tests and
moisture-density relationship tests on samples shall not be more 500 metre intervals and (iii) As
needed, hard rock samples obtained from quarries.
(e) Investigation of the hydrolic and drainage efficiency of existing bridges, fords, river crossings, river
training, culverts, retaining walls and roadside drainage facilities, including examination of scour,
erosion, drainage and flood characteristics along the road. The consultant shall prepare
hydraulic recommendation considering the following: (i) The catchment area, run-off coefficient,
hydraulic slope, design flood discharge and water elevation for the appropriate return period in
accordance with national manuals shall be determined for drainage structures requiring major
rehabilitation works; (ii) Cross-sections and gradients of watercourses shall be surveyed to
determine the proper drainage sizes ( Pipe size, type, locations etc). Erosion protection of the
structure and slopes must be determined; and (iii) The hydraulics report will provide the necessary
hydrologic and hydraulic analysis to complete the design. Contents of the report shall follow the
guidance in the FMW Drainage Design Manual.
(f) Detailed inspection and dimensioning of existing and proposed bridges, fords, river crossings, river
training culverts, retaining walls and roadside drainage facilities. Detailed designs shall be
prepared for all drainage structures having spans of 10 meters or greater. Structures of less than
10 meters shall be specified as standard type structures, which shall be fully designed.
(g) Preliminary and final plans and drawings of the roads, typical cross-section, horizontal and
vertical alignments of the roads, involving the calculation of material layers’ thicknesses,
considering the composition or existing and forecast traffic, as calculated from traffic survey and
analysis to be carried out by the Consultant. The Consultant shall prepare the following plans for
the project using a format agreed with the FPMU: (i) Plans and profiles to scale 1:2000 and 1:200,
respectively: showing natural ground levels, horizontal and vertical curve details, drainage
structures, cross-sections, side drains, etc. Details of drainage and bridge rehabilitation, location
of bench marks and survey beacons, contour lines superimposed on plans and other relevant
information on the format specified by FPMU; (ii) Typical and other necessary cross sections to
scale 1:25 and 1:50 respectively: showing all details of road cross sections in cuts and fills, side
drains; layers thickness; camber and super elevation; pavement widening; (iii) The road cross
sectional drawings at 25m interval to scale 1:25; (iv) Cross-sections to scale 1:200: showing details
of all types of drainage structures with inlet and out let details and any necessary protection
works; (v) Soils plans: showing the characteristics of soils at various sections of the road and plans
showing locations of borrow and quarry sites; (vi) River channel profiles (cross-section;scale:1/100-
1/250) of the present and potential crossing points marked with high water, flood water, and low
water level and also showing the details of any protection measures of the banks and river
training; and (vii) Structural details of the larger-scale drainage, hydraulic structure and culverts (if
any) (scale: 1/10-1/50).
(h) Economic analysis using HDM-4 or the Road Economic Decision (RED) model, based on cost
estimates and traffic projections, or any other economic evaluation methodology authorized by
the FPMU and the World Bank/AFD.
(i) Environmental and Social Impact Assessment (ESIA) in line with World Bank Operational Policy
OP4.01to identify, quantify and to the extent possible monetize the likely negative and positive
environmental and social impacts of the proposed road work, and suggest the required
mitigating measures (Environmental Management Plan, EMP) to be implemented to avoid these
negative impacts. As needed, the ESIA and the EMP will also include “chance find procedures”
ARAP Report Enugu State RAMP 2 06/2012 Pheman Peniel Consultants Ltd
96
as per the World Bank Operational Policy for Physical Cultural Resources (OP/BP 4.11). The ESIA
shall among others: (i) Recommend an appropriate Institutional structure for safeguard in the
rural roads that will guarantee sustainable safeguard measures system; (ii) Explore the possibilities
for community-based safeguard approach and the Capacity Building needs of the relevant
stakeholders; and (iii) Explore and recommend alternative safeguard measures/models.
(j) As needed, Resettlement Action Plan (RAP) or Abbreviated Resettlement Action Plan (ARAP) in
line with World Bank Operational Policy OP4.12, to ensure that the eventual Project Affected
Persons (PAPs) are adequately compensated or provided assistance. However, it is not
anticipated that land acquisition or resettlement will be undertaken as all project physical
activities would be carried out at on the existing right of way (ROW).
(k) Preparation of a road maintenance strategy for the selected roads with a description of
maintenance activities to be performed in the next 5 years following the completion of the
rehabilitation works, an estimate of the maintenance cost and a simulation of the roads’ life
cycle with and without maintenance. The strategy will explore the option of involving the
communities living aside from the roads in performance the needed routine maintenance
activities.
(l) Preparation of bill of quantities (BOQ) based on the various items of work to be executed and in
accordance with the drawings and the technical specifications. The items in the BOQ shall
correspond to the work items specified in the technical specifications. The calculated quantities
for the construction shall be based on the final design drawings. The earthworks quantities shall
be derived from calculations based on the field cross-sections taken along the road centerline in
accordance with accepted methods of measurement, which shall be agreed with the
Government. The Consultant shall carry out all the works necessary for the detailed design of the
proposed works, for the estimation of quantities to an accuracy of +/- 10% of final quantities as
measured on completion of the works; excluding any approved variations of the contract.
(m) Development of a Confidential Unit price analysis for each work item and a Confidential Cost
Estimate for the contract package as a whole. In order to make a fair and reasonable estimate
of the cost of the project, the Consultant shall prepare a unit price analysis of each item using
basic cost elements (labor, materials, equipment, tools, overheads, on-site costs, profit, etc.) He
shall show separately the cost of all taxation (direct or indirect). In addition, the cost of
supervision of construction by a Consultant shall be analyzed on a unit price basis and included
in the overall cost estimates. The estimated financial cost resulting from this analysis shall be
accurate to within +/- 10%, and shall be compared with costs of previous projects or similar works
executed in the area or the Sub-Region. Should any differences be found, the causes shall be
identified and studies made to arrive at comparable market prices. The estimates for the
eventual right-of-way acquisition shall be made on the basis of the unit prices to be furnished by
the Government for each type of land and property utilization. The consultant shall provide all
back up calculations for the cost estimate for the client’s use.
(n) Preparation of Bidding Documents for the procurement of works. The Consultant shall prepare
bidding documents for the road rehabilitation works, following the applicable World Bank
procurement guidelines.