Feasibility Report for Increase in Production of Nadidih Iron...

26
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine Page 1 | 26 Ecomen Laboratories Pvt. Ltd. 1.0EXECUTIVE SUMMARY: Nadidih Iron & Manganese Mine, covering an area of 121.405 ha of M/s Feegrade & Co. (P) Ltd. is in operation since 1961. The site is at a distance of 25km from Barbil and is well connected by an all-weather metal road. In pursuance to section 8-A (6) of MMDR Amendment Act, 2015, the mining lease period has been extended up to 31/03/2020 by execution of a Supplementary Lease Deed on 02.05.2015 over an area of 121.405 hectares. The lease area of 121.405 ha comprises 89.870 ha of forest land (PF+KF+DLC) and 31.535 ha of non-forest land. Stage-II Forest clearance for an area of 39.309 ha has been accorded by MoEF, Govt. of India vide letter no. 8(21)26/2003-FCE dated 16 /03/2006 and 45.118 ha of additional forest & deemed DLC forest land for mining and allied activities (including 8.036 ha of forest land for safety zone) vide F. No. 8-68/2011-FC dt. 30/10/2013.The lessee had applied for surrender of 5.443 ha forest land which is under process. At present, the production of the mine is restricted to excavation of Iron ore (ROM) from mine and dry screening & crushing of iron ore. These crushing & screening produce processed ore of +55% and -55% Fe. The overall objective of the project for grant of Environmental Clearance is to meet the following: Increase in production of Iron Ore from 2.88 million TPA ROM Iron ore to 6.0 million TPA (ROM) and dry processing of iron ore of 1.451 million TPA. Total handling will be 7.451 million TPA& 1.451 million TPA dry crushing/screening of low grade ore from old stack/dumps. The mine was accorded Environmental Clearance vide order no. J-11015/136/2012-IA.II (M) dated 10.04.2015 for 2.88 million TPA ROM and dry processing of 4.571 million TPA of low grade iron reworking of old dumps thus total handling of 7.451 million TPA and installation of wet beneficiation plant of 1.142 million TPA capacity and production of 0.0036 million TPA of Manganese ore. Installation of wet beneficiation plant of 1.142 million TPA capacity has been deleted by Ministry of Environment, Forests and Climate Change vide letter no. J- 11015/136/2012-IA.II (M) dated 09.11.2015.

Transcript of Feasibility Report for Increase in Production of Nadidih Iron...

Page 1: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 1 | 26 Ecomen Laboratories Pvt. Ltd.

1.0 EXECUTIVE SUMMARY:

Nadidih Iron & Manganese Mine, covering an area of 121.405 ha of M/s

Feegrade & Co. (P) Ltd. is in operation since 1961. The site is at a distance of

25km from Barbil and is well connected by an all-weather metal road. In

pursuance to section 8-A (6) of MMDR Amendment Act, 2015, the mining lease

period has been extended up to 31/03/2020 by execution of a Supplementary

Lease Deed on 02.05.2015 over an area of 121.405 hectares. The lease area of

121.405 ha comprises 89.870 ha of forest land (PF+KF+DLC) and 31.535 ha of

non-forest land. Stage-II Forest clearance for an area of 39.309 ha has been

accorded by MoEF, Govt. of India vide letter no. 8(21)26/2003-FCE dated 16

/03/2006 and 45.118 ha of additional forest & deemed DLC forest land for

mining and allied activities (including 8.036 ha of forest land for safety zone)

vide F. No. 8-68/2011-FC dt. 30/10/2013.The lessee had applied for surrender

of 5.443 ha forest land which is under process.

At present, the production of the mine is restricted to excavation of Iron ore

(ROM) from mine and dry screening & crushing of iron ore. These crushing &

screening produce processed ore of +55% and -55% Fe. The overall objective

of the project for grant of Environmental Clearance is to meet the following:

Increase in production of Iron Ore from 2.88 million TPA ROM Iron ore to 6.0

million TPA (ROM) and dry processing of iron ore of 1.451 million TPA. Total

handling will be 7.451 million TPA& 1.451 million TPA dry crushing/screening

of low grade ore from old stack/dumps. The mine was accorded Environmental

Clearance vide order no. J-11015/136/2012-IA.II (M) dated 10.04.2015 for

2.88 million TPA ROM and dry processing of 4.571 million TPA of low grade

iron reworking of old dumps thus total handling of 7.451 million TPA and

installation of wet beneficiation plant of 1.142 million TPA capacity and

production of 0.0036 million TPA of Manganese ore. Installation of wet

beneficiation plant of 1.142 million TPA capacity has been deleted by Ministry

of Environment, Forests and Climate Change vide letter no. J-

11015/136/2012-IA.II (M) dated 09.11.2015.

Page 2: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 2 | 26 Ecomen Laboratories Pvt. Ltd.

Total handling of iron ore will be 7.451 million TPA to get 5.90 million TPA

of processed iron ore of grade +55 % and balance of grade – 55 % (Refer

Exhibit No.1). The ROM, accumulated mineral rejects & wastes from

Nadidih Iron & Manganese Mines will be hauled through trucks/dumpers to

dry processing plants. After processing, the finished iron ore will be carried

to the Railway siding and loaded into Rail wagons and dispatched mainly to

the steel, pelletisation, sponge, sinter plants throughout India and also to

port for export. In the project, due care is taken for optimum use of

natural resources and their conservation and this will continue further. The

company has the electricity permission of total 213 KVA from WESCO, a

power holding company of State Govt. of Odisha. There are also 02

standby generators of total capacity 140 KVA for support.

There is a mine camp within the ML area having about 132 nos. of

residential quarters for its employees of different categories. The social

infrastructure adjacent to the project area includes a health centre and one

Primary School. As a part of CSR activities the Company has undertaken

the construction works of School buildings, boundary wall for Schools &

Temples, club houses in villages, digging of ponds in nearby villages and

bore wells. Such type of work will continue in future. The entire

infrastructure related facilities for traffic and transportation for the mine

are already available. So, there is no new proposal for the same.

The estimated project cost is Rs.200Crores. As regards the economic

viability of the project, this Iron & Manganese mine supplies iron ore to the

steel, pelletisation, sponge, sinter plants of India and also for Export. The

production cost is very favourable than the market price.

The per capita consumption of steel is increasing with the economic

development of people in the World. There is positive market demand of

steel at present and more production of steel is required to bridge the gap

between demand and supply to achieve sustainable development. Hence,

Page 3: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 3 | 26 Ecomen Laboratories Pvt. Ltd.

the capacity expansion of this mine will meet the urgency of iron ore in

domestic as well as international market. The State will also earn more

revenue from the increased iron ore production and can utilize in its

developmental plans. The capacity expansion plan will also create direct

and indirect employment opportunity for the local youths that will help to

minimize the unemployment problem as well as all around development of

the surrounding area.

2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION:

District & State: Sundargarh, Odisha

Sub-division: Koira

Village : Nadikasira & Rengalbeda

P.O. Guali

GPS reading

210 58’ 20.15” to 210 57’ 23.35”

850 14’ 58.34” to 850 15’ 34.84”

Name of Lessee:

M/s. Feegrade & Co. Pvt. Ltd. It is a Private Limited Company, under the Indian Companies Act, 1956.

Name of the Corporate Office Name of Registered Office

M/s. Feegrade& Co. Pvt. Ltd. M/s. Feegrade& Co. Pvt. Ltd. At/P.O.-Chaibasa 8-A, Express Tower

Dist.-.West Singhbhum 42-A, Shakespeare Sarani Jharkhand-833201 Kolkota-700017

Ph. 06582-256861 Ph-033-22813751

Fax-06582-256442 Fax-033-22815380

Nadidih Iron & Manganese Mine over an area of 121.405 ha of M/s

Feegrade& Co. (P) Ltd. is under operation since 1961. Nadidih Iron &

Manganese Mine was operated manually in the beginning. But at present,

the mining operation is mechanized with production of 2.88 million TPA

ROM and dry processing of 4.571 million TPA of low grade iron reworking

of old dumps having total handling capacity of 7.451 million TPA and

production of Manganese ore of 0.0036 million TPA. At present, it is

proposed to increase the production capacity of the mine from 2.88 million

TPA of ROM iron ore to 6.0million TPA ROM iron ore and dry

Page 4: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 4 | 26 Ecomen Laboratories Pvt. Ltd.

crushing/screening of 1.451 million TPA for reworking of old dumps/stacks

for up gradation of low grade recovered from screening of ROM ore and dry

screening of low grade ore. There will be no change in total handling of

material which will be 7.451 million TPA and also there will be no change in

production quantity of Manganese. The ROM ore produced by the

excavation of quarry generally consisted of blue dust, lump iron ore, etc.

This iron ore will be produced by developing up to 9metre benches in the

quarry. The benches will be developed by using different mining

machineries like excavator, tippers, rock breakers, deep hole drilling &

blasting etc. After excavation, ROM iron ore will be processed through in-

pit mobile crushing & screening units.

2.1 Identification of Project & Project Proponent (in case of mining project, a copy of mining lease/letter of intent should be given) :

The project aims for grant of EC to meet the following objectives:

It is proposed to increase the production capacity of the mine from 2.88

million TPA ROM iron to 6.0 million TPA of ROM iron ore and dry processing

of 1.451 million TPA for reworking of old dumps/stacks (total handling will

be 7.451 million TPA). Supplementary Lease deed for this mine has been

executed by the State Govt. of Odisha on 02.05.2015 up to 31.03.2020 as

per The Mines and Minerals (Development and Regulation) Amendment

Act, 2015 dated 26.03.2015 Section 8A (6) states that the period of Lease

granted before the date of Commencement of the Mines and Minerals

(Development and Regulation)Amendment Act, 2015 where mineral is

used for other than captive purpose, shall be extended and be deemed to

have been extended up to a period ending on 31st March, 2020 with effect

from the date of expiry of the period of renewal last made or till the

completion of renewal period, if any or a period of fifty years from the date

of grant of such lease, whichever is later (Copy of Supplementary

Lease deed is enclosed)

Page 5: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 5 | 26 Ecomen Laboratories Pvt. Ltd.

2.2 Brief description of nature of the project:

Nadidih Iron & Manganese Mine is an operating mine with a capacity to

produce2.88 million TPA ROM and dry processing of 4.571 million TPA of

low grade iron reworking of old dumps, total handling of 7.451 million TPA,

installation of wet beneficiation plant of 1.142 million TPA and production

of 0.0036 million TPA Manganese ore granted Environmental Clearance

vide order no. J-11015/136/2012-IA.II (M) dated 10.04.2015. Installation

of wet beneficiation plant 1.142 million TPA capacity has been deleted by

Ministry of Environment, Forests and Climate Change vide letter no. J-

11015/136/2012-IA.II (M) dated 09.11.2015.At present, the ROM ore

produced in the mine are subjected to dry crushing& screening. The

produced iron ore fines are exported as well as dispatched or sent to

domestic pelletisation/sinter plants. The sized ore are dispatched to

domestic market either through road or through Rail head. The lessee has

already got the necessary permissions from Govt. authorities to fulfill the

demand supply gap of iron ore. Now, it is proposed to enhance the

production of the mine from 2.88 million TPA ROM iron ore to 6.0 million

TPA ROM iron ore and dry processing which include crushing and screening

of low grade ore of 1.451 million TPA having total handling 7.451 million

TPA to get 5.90 million TPA of processed iron ore of grade +55 % and

balance of grade – 55 % Fe.

2.3 Need for the project and its importance to the country and the

region:

Due to market demand of iron ore for domestic steel, sponge and

pelletisation and sinter industry and to meet the export demand, the

project proponent wishes to increase the production capacity of iron ore of

the mines by handling of 7.451 million TPA iron ore i.e., 6.0 million TPA

ROM iron ore and dry crushing and screening of 1.451 million TPA from old

stacks/dumps ROM iron ore. The Govt. will earn more revenue and more

job opportunities will be created. Besides more indirect employment will be

generated through handling of material, transportation, etc. which will

Page 6: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 6 | 26 Ecomen Laboratories Pvt. Ltd.

result in economic improvement of the people in the locality. Many people,

apart from the above will get other avenues for livelihood, which will help,

in improving the economic and social status of the people in the area.

2.4 Demand-Supply Gap:

The Indian Steel industry has entered into new development stage from

2005-06, riding high on the resurgent economy and rising demand of steel.

Rapid rise in production has resulted India to become the 5th largest

producer of steel. It is estimated that, India’s steel consumption will

continue to grow at nearly 16% rate annually, fueled by the demand of

construction project. The National Steel Policy envisaged steel production

to reach 110 million tonnes by 2020. So, considering these huge demands

of iron ore for steel industries, the supply is not sufficient. So, this project

is important for partial fulfilling of demand.

2.5 Imports Vs. Indigenous Production:

To minimize the growing import of steel, it is necessary to increase the

indigenous production of steel in India. For this it is necessary to produce

more iron ore as raw material. The expansion of the project will partially

meet the demand of raw materials for our upcoming steel industry.

2.6 Export Possibilities:

China & Japan being the 1st& 2nd crude steel producers of World, depend

partly on India for iron ore as raw material. India is the 3rd largest iron ore

provider to China’s steel industry. So there is always an export possibility

of iron ore from this mine.

2.7 Domestic/Export markets:

The sized iron ore from this mine has demand in domestic steel & sponge

industry. During production of lump iron ore, fines of iron ore will be

Page 7: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 7 | 26 Ecomen Laboratories Pvt. Ltd.

generated automatically, this iron ore fines are exported to China as well

as supplied to domestic pelletisation/sinter plants.

2.8 Employment Generation (direct & indirect) due to the project: Manpower:

Existing& Proposed:

As in this mine total handling will remain same as 7.451 million TPA and

there is change in ROM production only there may by opportunity for direct

employment of total 426 people and indirect employment of 400 people.

So, 826 people will get engagement due to enhancement of the project.

Existing Proposed

Graduate Mining Engineer 2 2

Diploma Mining Engineer 1 1

Geologist 1 1

Surveyor 1 1

Other Officers 12 14

Mine worker for manual sorting &

sizing

171 209

Operator for mining machineries 158 198

Total 346 426

Besides direct employment, many more persons are benefited through

indirect employment as contract jobs, which are mainly extended to the

local tribes.

3.0 .PROJECT DESCRIPTION:

3.1 Type of project including interlinked and interdependent projects,

if any:

In Nadidih mine, ROM iron ore will be produced from the mine by

mechanized method of excavation of the quarry by excavator, tipper, deep

hole drilling, blasting, rock breakers, etc. ROM ore is further processed by

dry crushing, screening.

Page 8: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 8 | 26 Ecomen Laboratories Pvt. Ltd.

3.2 Location (map showing general location, specific location and

project boundary & project site layout with coordinates):

District & State : Sundargarh, Odisha

Sub-division : Koira

Village

P.O.

: Nadikasira, Rengalbeda

Guali

GPS reading

210 58’ 20.15” to 210 57’ 23.35”

850 14’ 58.34” to 850 15’ 34.84”

Location map showing general location, specific location and project

boundary is attached herewith as Plate No.1.

3.3 Details of alternate sites considered and the basis of selecting the

proposed site, particularly the environmental considerations gone

into should be highlighted:

It is already a running mine.

3.4 Size of magnitude of operation:

The project cost of Nadidih Iron & Manganese Mine is Rs200Crores. It

involves mining of ROM Iron ore, dry crushing & screening of ROM ore to

produce processed iron ore of + 55% and -55% Fe. The processed iron ore

will be produced by processing of excavated ROM iron ore& processing of

low grade iron ore and waste.

At present production capacity of the mine is 2.88 million TPA ROM iron ore

and dry processing of 4.571 million TPA of low grade iron reworking of old

dumps having total handling of 7.451 million TPA. After expansion ROM

production of the mine will increase from 2.88 million TPA ROM iron ore to

6.0 million TPA ROM iron ore and dry processing will reduce from 4.571

million TPA to 1.451 million TPA of low grade iron ore by reworking of old

dumps/stacks.

Page 9: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 9 | 26 Ecomen Laboratories Pvt. Ltd.

3.5 Project description with process details (a schematic diagram/flow

chart showing the project layout, components of the project, etc.

should be given):

The mining method of Nadidih Iron & Manganese Mine will be fully

mechanized to handle 7.451million TPA of iron ore to produce

5.90million TPA processed iron ore of + 55% grade. The conventional

opencast mining with mechanized drilling with 110mm dia drill machine,

deep hole blasting, excavation by excavator of capacity 2.6 m3bucket

capacity and stacking by loader of capacity 1.2 m3. Excavator of

capacity 1.6 m3 /1.5 m3 will be used for feeding the crushing &

screening unit. ROM iron ore will then be processed through dry

crushing &screening units. To prevent generation of fugitive dust during

transportation of ore through trucks/dumpers, static water sprinklers

have been installed along the haul road within the mine for a length of

5.04 km. Besides that water is also been sprinkled through water

tankers of different capacities.

3.6 Raw Material required along with estimated Quantity, likely

source, marketing area of final products, mode of Transport of

raw material & finished product.

It is a mining project to produce iron ore. Low grade iron ore from this

mine will be processed to get saleable ore. There is no need of any raw

material from outside agency.

Iron Ore is having a very good market in India & abroad. So after

production it is immediately saleable to beneficiation plant/sinter/ sponge

and steel industry present in Odisha, Jharkhand, M.P., Chhattisgarh and

other parts of India. China, Korea & Japan are the major buyers from

abroad.

Within the Mine both Iron Ore & Waste Materials will be transported

through tippers of capacity 20 MT. The sized Iron Ore and Fine are

transported to railway sidings at Barsuan, Rengra, Barbil, Bolani etc.

through Tippers of capacity 10 MT or 20 MT. From railway siding, Iron Ore

Page 10: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 10 | 26 Ecomen Laboratories Pvt. Ltd.

is transported to buyer’s destination or port by rake. Sometimes Iron Ore is

also supplied to the Seaport by trucks from the mines through road.

3.7 Resources optimization/recycling and reuse envisaged in the

project, if any, should be briefly outlined.

As discussed earlier the low grade ore will be crushed and screened for

optimal use of iron ore.

3.8 Availability of water its source, Energy/Power requirement and

source:

Water requirement:

In Nadidih Iron & Manganese Mine water is required for different

operational purpose and also for domestic purpose.

The water requirement as per EC accorded on 10.04.2015 is 2566.6

KLPD (Surface water 2340.38KLPD, Ground water 226.22 KLPD)

including 1599 KLPD for Wet Beneficiation plant. The water is sourced

from Karo River.

Since in the new proposal Beneficiation plant is not there the water

requirement is 993.5 KLPD only (surface water 767.5 KLPD, ground

water 226 KLPD). 520.06 KLPD approval for surface water &226 KLPD

approval for ground water is already there.

For drawl of balance surface water (247.44KLPD), is under process to

the concerned authority.

Energy power requirement:

The machineries will be operated either through electricity or through H.S.D.

details are given below.

(1) Electricity requirement: The electricity is supplied to the project by

WESCO through 2 nos. transformers of total capacity 213 KVA inside

leasehold. There is also requirement of transformers with total capacity

of 350 KVA.

Page 11: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 11 | 26 Ecomen Laboratories Pvt. Ltd.

(2) Details of Generator: 2 nos. of generators of total capacity 140 KVA

exist. There is a further requirement of generator of capacity 400 KVA.

(3) H.S.D. requirement: Present requirement of H.S.D is 1192006

Liters/year. For the envisaged increase in production total H.S.D.

requirement will be around2292000Liters/year.

3.9 Quantity of waste to be generated and scheme for their

management.

Solid Waste Management:

The waste materials of Nadidih Mines are mainly laterite, lateritic Iron

ore, BHQ, BHJ, shale, alluvial soil etc. Total 8300748 m3 of waste

material exists at present. It is expected that 2671588 m3 of waste will

be generated up to the end of the life of the mine. 309248 m3waste

materials of this mine will be dumped in and balance part of the waste

material will be used for backfilling of exhausted quarry.

Previously, the grade of waste material was considered as below 58%

Fe, but at present the grade of waste material is fixed as below 45%. So,

the old waste of Nadidih mines at present are considered as low grade

non-saleable ore.

(1) The waste dumping sites are proposed to be surrounded by

retaining wall and garland drain.

(2) The waste dumps are proposed to be formed by making terraces of

height of 8m to 12m, width 8 m to 12 m and ultimate slope of 370

to 400.

(3) Any rain cuts developed in old dump slopes are proposed to be

leveled and maintained properly by planting saplings and grass.

(4) Garland drains at the toe of the dump are proposed to be

connected with a series of settling tanks which will allow the

settling of silt in it. The silt free water will ultimately go out of the

lease hold. The garland drain will have check weirs/waffle wall at

regular interval to check flow of silt/debris

Page 12: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 12 | 26 Ecomen Laboratories Pvt. Ltd.

(5) The dead slope of the dump is to be covered by plantation. The

dump slopes where plantations are already completed are

proposed to be maintained properly.

(6) Coir matting is also proposed on the dead dump slope.

4.0 SITE ANALYSIS:

4.1 Connectivity:

Nadidih Iron & Manganese Mine is located in Sundargarh district of Odisha.

The area is about 5kms north-east of Koira. The area is situated on the

main road of Barbil-Koira-Rourkela road, which passes through the south-

eastern side of the lease hold area. The nearest town is Barbil which is at a

distance of 25 km (by road) & Tata Nagar is about 176kms away from

road. The Barbil town is connected by road with major cites of India

including, Bhubaneswar, Paradeep (port), Kolkata.

Koira is the nearest town which provides the facilities of a Hospital, Bank,

Police Station, Post Office, Telephonic Communication, a high school&

College. Barsuan, Banspani, Roxy & Barbil are the nearest railway stations

which also have siding for ore transport. Nearest airport is at Tanto of

Barbil which is at a distance of 17 km from the lease area.

4.2 Land Form, Land use & Land ownership:

Land Form:

The area is a gentle undulated area. Within the total lease area of

121.405 hectares, 31.535 hectares is non-forest land, 48.652 hectare

Khesra forest & P.F. land &41.218 hectare of DLC forest land.

Land Use:

Existing land use pattern:

Sl.

No.

Category Existing Land use

pattern (Ha)

1 Area to be excavated 42.7

2 Over burden/dump 20.394

3 Mineral storage 7.421

4 Infrastructure & mine camp 1.783

5 Roads 5.246

Page 13: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 13 | 26 Ecomen Laboratories Pvt. Ltd.

6 Green belt 7.540

7 Mineral processing plant 3.75

8 Mine Camp 1.522

9. Unutilised 31.049(within which

5.443 ha forest area

under surrender)

Total 121.405

Land ownership:

a) PF &Khesra Forest – 48.652 hectares is forest land belong to Government.

b) D.L.C Forest – 41.218 hectares is forest land belong to Government. c) Non forest land- 31.535 hectares is Government Non-Forest Land.

N.B. The lessee had applied for surrender of 5.443 ha of forest land which is

under process with concerned statutory authority.

4.3 Topography (along with map):

The area is undulating terrain with a few hillocks, the highest one is RL

615m above MSL. The minimum ground level RL is 528m. The top of the

hill is more or less flat. Southern flank of the hill is more slanting in

comparison to the northern portion. The south-eastern corner of the area

shows a minor trough filled up with recent alluvial sediments. The area is

devoid of any nala or water shed. However, the Karo River which flows

along the north-western boundary of the area provides water throughout

the year to the inhabitants. 10 km. radius map of the mine lease area is

enclosed as Plate No.2.

4.4 Major land use categories of the area in 10 km radius

Sl. No. Category Area (in ha) % of the Study

area

1 Mining Area 2636.00 8.39

2 Agricultural 540.00 1.72

3 Forest Land 17203.00 54.79

4 Waste Land 10031.00 31.95

5 Water bodies 990.00 3.15

Total 31400.00 100

Distance of the nearest park/Sanctuary etc.

a) Kathmala R.F. - 2.9 km SSW

b) Mendhamaruni R.F. - 1.0 km SE

Page 14: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 14 | 26 Ecomen Laboratories Pvt. Ltd.

c) Karo R.F. - adjacent W

d) Sidhamath R.F. - 7.8 km E

e) Uliburu - 3.6 km N

f) Torha RF - 5.0 km W

There is no National Park or Sanctuary in 10 km radius of mining lease area.

4.5 Existing Infrastructure:

The infrastructure of the lease area partly within the lease and partly outside

the lease. The details are given below:

Sl.

No.

Quarter No.

1 Manager Bungalow Duplex (3-bed

room)

1

2 G+2 (Three bedroom) 6

3 Type-II (Two bedroom) 22

4 Type-I (Two bedroom) 67

5 Guest House 1

6 Club 1

Total 98

There are another 34 nos. of small quarters for mine worker also.

Other Details are:

Sl. No.

Quarter No.

1 One office building 1

2 Chemical Laboratory 1

3 One diesel pump 1

4 One security barrack 1

5 Two D. G. room 2

6 One Rest shelter 2

7 Five nos. of weigh bridge 6

8 One magazine 1

9 One drinking water tank 1

10 New dispensary building 1

11 Mechanical workshop 1

Page 15: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 15 | 26 Ecomen Laboratories Pvt. Ltd.

Explosive Magazine Capacity:

Sl. No.

Name of Explosives

Capacity

1 Class-II 470 kg

2 Class-6 (Div.3) 7000 nos.

3 Class-6 (Div.1) 3000 m

4 Class-6 (Div.2) 3000 m

To avoid blasting the lessee is using rock breaker at present.

Page 16: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 16 | 26 Ecomen Laboratories Pvt. Ltd.

4.6 Soil Quality:

Soil may be defined as a mixture of rock and mineral material with the

organic matter. Soil is the net result of the action of climate and

organisms especially plant on the earth crust. The pH of soil is normal

ranging from 6.25 – 7.22, average nitrogen values are in medium to

high range (355.45 – 566.32 kg/ha), average potassium value is also in

the range of medium to high (120 – 280 kg/ha).However the average

phosphorus value are low (2.87 – 4.51 kg/ha). The maximum value of

total heterotrophs, azotobacter, actinomycetes & yeast were 7.8 x 105,

6.4 x 104, 1.2 x 104& 6.2 x 105 respectively.

4.7 Climatic condition:

The area is characterized by extreme climate with very hot (42 °C)

summer and very cold winter (4°C) winter. It experiences tropical and

humid climate. The summer is very hot and dry starting from March and

continues till end of May or early June. The rainy season lasts from early

June to end of September. October and November are the post monsoon

months followed by cold winter which lasts till end of February.

a) Temperature:

The area experiences a wide variation in temperature in respect of both

day and night and seasonal. Generally winter starts from late November

and continues till mid of February. December is the coldest month. The

temperature goes up to maximum of 41.50C in June and comes down to

a minimum of 7.90C in December. Data pertaining to temperature

variation for the year 2007 is shown in Table no.1.

Table No. 1.

Month

Temperature ºC Relative Humidity

Max Min Morning Evening

Jan 32.3 8.5 67 51

Feb 31.5 11.2 75 49

Mar 37 13.3 69 38

Apr 40.3 17.4 60 33

May 40 19 70 53

Page 17: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 17 | 26 Ecomen Laboratories Pvt. Ltd.

Jun 41.5 20.4 76 75

Jul 33 22.4 84 82

Aug 32.6 21 87 83

Sep 31.9 21.4 89 88

Oct 32.6 15.2 73 64

Nov 31.5 12 75 66

Dec 30.3 7.9 67 55

Source: IMD, Bhubaneswar.

b) Humidity

In general air is dry except in monsoon period. Monthly mean relative

humidity varies from 33 to 89 %. In morning (8.30hrs) it varies from 60

to 89 % (Average 74.33%) while in evening it varies from 33 to 88 %.(

Average 61.4%). The Relative Humidity data is shown in Table no. 1.

c) Rainfall

The rainfall data collected from Keonjhar are shown in Table No.2.

MONTHLY RAINFALL RECORDED AT KEONJHAR

(2006-2008)

Table No. 2

MONTH 2006 2007 2008

January Nil 3.1 62.6

February Nil 90.1 6.6

March 21.1 25.1 9.2

April 35.7 42.4 30.8

May 152.9 88.9 103.6

June 177.8 288.4 570.8

July 317.9 454.9 303.6

August 545.6 436.8 293.4

September 285.5 396.6 362.7

October 38.2 27.5 15.4

November 34.8 66.6 2.7

December Nil Nil Nil

Total

Annual Rainfall

1609.5 1920.4 1761.4

Source - Meteorological Centre, Keonjhar

Page 18: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 18 | 26 Ecomen Laboratories Pvt. Ltd.

d) Wind

The prominent wind directions at Keonjhar are from south west and north

east. The variation in velocity ranges from 0 to 20 km per hour are common in

this area. The directions become predominant from North West during May to

October. The dry winds of the northern plains are not common here.

However, higher wind speeds may be present for a short period before the

rains, during May and June. These periods are quite short, lasting not more

than an hour. Dust storms and hurricanes are rare in this area.

5.0 PLANNING BRIEF:

5.1 Planning concept (type of Industries, facilities, transportation

etc.) Town and country planning/Development authority

classification.

It is an Iron and manganese Ore mine project and in operation for more

than six decades to produce Iron Ore.

The lessee has made arrangement for quarters, drinking water, school

van, ambulance, medical dispensary etc. for all the workers of the mine.

Both waste material & Ore are transported within the mine through

tippers of capacity 35 MT& 20 MT. The processed Iron ore are

transported through tippers to different railway sidings away from the

lease hold. The nearest railway siding is Rengra, Barsuan, Bolani &

Barbil. From the railway siding, through railway wagons, Iron Ore is

transported to buyer’s destination inside or outside Odisha or to the

nearby seaport at Paradeep or Haldia for export.

The lessee has a mine camp in the area equipped with all the facilities

like water supply, electric supply, dish antenna, mobile communication

tower, sewage treatment plant, medical dispensary, ambulance, etc.

5.2 Population Projection:

For the existing production of 2.88 million TPA ROM iron ore and dry

processing of 4.571 million TPA from reworking of old dumps/stacks

Page 19: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 19 | 26 Ecomen Laboratories Pvt. Ltd.

290total worker are directly & indirectly employed. For the proposed

production target 80 nos. of worker will be employed additionally. Within

the lease hold area 98families are staying permanently within the mine

camp.

5.3 Tentative Land use planning (breakup along with green belt

etc.):

Heads Conceptual

Land use

Area to be excavated 58.613

Overburden/Dump 27.889

Mineral Storage 7.421

Infrastructure 2.137

Roads 4.246

Green Belt + plantation 12.134

Mineral processing Plant 2.0

Mine Camp 1.522

Non mineralized forest area for surrender

5.443

Total 121.405

5.4 Assessment of Infrastructure demand (physical & social) :

Amenities/Facilities:

As it is an operating mine, all the amenities/facilities arrangement are

already present. At present it is only necessary to enhance the

arrangement as per the proposed target production.

6.0 PROPOSED INFRASTRUCTURE:

6.1 Industrial Area (Processing Area):

The area is a mechanized opencast Iron Mine which is under operation

for more than six decades. For existing production of 2.88 million TPA

ROM iron ore and dry processing of 4.571 Million TPA of low grade of old

dumps/stacks. The mine is already well equipped with different

infrastructure. As the total handling remains same as 7.451 million TPA

(6.0 million TPA ROM ore excavation & 1.451 million TPA from reworking

of low grade ore & dump), the above infrastructure will be used with

little addition of some machineries.

Page 20: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 20 | 26 Ecomen Laboratories Pvt. Ltd.

6.2 Residential Area (non-processing area):

Details of existing infrastructure and residential area are already given.

No further infrastructure is necessary, except few new quarters are

proposed to be developed in the area. Other workers will be local

residents. The capacity of water reservoir and electric supply

substation/generator is also proposed to be improved.

6.3 Green Belt:

At present 7.540hectares of area is present as green belt as safety zone.

At the end of the plan period total approximately12.134hectares of area

will be converted to green belt and plantation. At the end of life of the

mine approximately 41.789 hectare of exhausted quarry will be back

filled and covered with plantation and 16.824 ha area will come under

bench plantation.

6.4 Social Infrastructure:

Road:

The lessee maintains the village roads on regular basis. At places

constructed blacktop road/CC road as per the requirement. Wherever

required, arrangements have been made for water sprinkling through

tankers to suppress the dust. Apart from these, other social

infrastructure like village electrification, supply of DG set, supply of

transformer, construction of socio-cultural mandaps, renovation of

anganwadi center, construction of bathing ghats, Maintenance of street

light, construction of drains have also been done. The lessee spent Rs

approximately Rs. 2.45 crore till the year 2015 and Rs. 1.74 crore in the

year 2015-16 for the same.

Education:

Initiatives like construction & renovation of class rooms in schools,

construction of boundary wall, kitchen, toilet, construction of double

storied library building, hostel building, supply of book stacks,

electrification of schools, financial assistance to school teachers, supply

of desk-benches, furniture and teaching aid &equipment’s, play

Page 21: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 21 | 26 Ecomen Laboratories Pvt. Ltd.

equipment’s to schools, uniform and study materials to students, etc.

have been undertaken for promotion of education. The lessee spent

approximately Rs. 71 lakh till the year 2015 and Rs.47 lakh in the year

2015-16 for the same.

Sports & Culture:

Initiatives like organizing sports tournaments, supply of sports materials,

financial assistance to sports associations, players, organizing inter

village sports tournaments etc. have been undertaken for promotion of

sports.

Towards promotion of culture, financial assistance for organizing cultural

programmes, supply of furniture to different cultural organizations are

also being done to sustain our culture.

The lessee spent approximately Rs.2 lakh till the year 2015 and Rs. 1

lakh in the year 2015-16 for the same.

Health care:

Equipped dispensary with doctor and paramedical staffs, ambulance and

free medicine facility provided to all nearby villagers. Apart from these,

initiatives like, Sprinkling of insecticide wherever necessary, time to time

supply of mosquito nets to villagers, distribution of blankets, financial

assistance for organizing health camps, renovation of staff quarters of

CHC, construction of doctors quarters, extension of PHC and male and

female ward, construction of toilet with water storage tank for tribal

house hold, financial assistance for treatment, financial assistance to red

cross society are also being done.

For provision of drinking water, piped water supply is being done at

villages through RCC/ PVC overhead storage tanks and pipeline

connection at places through bore wells with submersible pump and at

some places bore well with hand pumps, financial assistance for village

committee for potable drinking water etc.

The lessee spent approximately Rs.3.8 crore till the year 2015 and Rs.

18 lakh in the year 2015-16 for the same.

Page 22: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 22 | 26 Ecomen Laboratories Pvt. Ltd.

Sustainable livelihood:

Assistance for livelihood generation like mushroom cultivation,

construction of SHG centre, distribution of fruit bearing saplings,

vegetable seeds, financial assistance for development of kitchen garden

and organizing Environmental awareness programmes have also been

done.

6.5 Connectivity:

The area is well connected with Joda, Barbil, and Koira by all-weather

well maintained road. As this is a mining belt, transport vehicles are

more than public transport vehicle. Tippers of capacity 10 MT & 20 MT

are used for transportation of Iron ore to railway siding within and

outside the lease area. Sized Iron ore, natural fines etc. are transported

from the railway siding to nearby seaport at Paradeep, Haldia etc.

through railway rake. From seaport, Iron ore fines are exported to China

etc.

6.6 Drinking Water Management:

The lessee has made the proper arrangement of drinking water to the

lease hold and also in the area around the lease hold. The lessee

arranged water supply system for all the workers present in the lease

hold. Deep bore well fitted with submersible pumps, water supply pipe,

RCC/PVC tanks are provided within as well as outside the lease hold.

Water supply facilities are already provided to 19 no. of areas near to

the lease hold area. In future with the enhancement of project the lessee

will provide more & more water supply facilities to other villages also.

The lessee also planned rain water harvesting by collecting rain water in

exhausted quarry. It is also planned and implemented for rain water

harvesting by collecting rainwater on the roof of some of the houses of

camp for recharging purpose.

6.7 Sewerage System:

The mine camp of Iron Mine has a proper sewerage system to handle

domestic waste water. All the houses are connected with drains, through

Page 23: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 23 | 26 Ecomen Laboratories Pvt. Ltd.

which waste water usually is drained out. One sewage treatment plant of

100 KLD has already been installed in the camp area of the lease hold.

After necessary treatment of the domestic waste water, the waste is

used as manure and treated water used in plantation and haul road for

dust suppression. The green vegetable peels, instead of wasting, are

now used in “vermi-composting” units to produce vermin-compost

manure.

6.8 Industrial Waste Management:

This is a running mine and no industrial waste generated by this unit.

6.9 Solid Waste Management:

The waste materials of this Mine are mainly laterite, lateritic Iron Ore,

BHQ, BHJ, shale, Lateritic soil etc. The solid waste generated at present

will be dumped partly in preselected dump yards. Part of the dump will

be used for backfilling of the exhausted quarry also.

The details are discussed in item no. 3.9.

6.10 Power Requirement & Supply/Source:

Details of power requirement & supply are discussed in item no.3.8.

7.0 REHABILITATION & RESETTLEMENT (R & R) PLAN:

Not Applicable

8.0 PROJECT SCHEDULE & COST ESTIMATES:

Likely date of start of construction & likely date of completion (Time schedule

for the project to be given)

This is running mine.

8.1 Estimated Project cost along with analysis in terms of economic

Validity:

Total cost of proposed project is 200 Crores.

Page 24: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 24 | 26 Ecomen Laboratories Pvt. Ltd.

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION):

(Financial & Social benefits with special emphasis on the benefit

to the local people including tribal population, if any, in the

area.)

Nadidih Iron & Manganese Mine is a running iron mine with proposed

production target of 6.0 million TPA ROM of iron ore and dry processing

of 1.451 million TPA from reworking of old stacks/dumps. It is proposed

to enhance the production target to 5.90 million TPA of processed ore of

+ 55% grade. The increase is production will create some financial &

social benefit, which are as follows:

a) At present 290 nos. of people are benefitted. Due to the proposed

production enhancement, 80 nos. of people will further benefitted

directly.

b) With the enhancement of production, the revenue earned by the

Govt. in terms of Royalty.

c) The lessee will make further efforts for the following arrangement

for social welfare of the core zone as well as buffer zone.

i) Medical facilities: The mine management will arrange medical camps

in different villages. Occupational health study will be done in core zone.

For the purpose of malaria eradication proper steps will be taken which

includes sprinkling of bleaching power, fogging, distribution of mosquito

net etc. The existing dispensary having a pathological lab will take

medical care of the staff & villagers.

ii) Drinking Water:

Facility of drinking water to the core zone as well as buffer zone is available by

means of bore wells fitted with submersible pumps, construction of overhead

water tanks and supply of water through pipe line.

iii) Construction of culvert and bridges on the existing roads& repairing of

transport road.

iv) Construction of school building, remuneration to school teachers, supply of

reading materials to school children etc.

Page 25: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 25 | 26 Ecomen Laboratories Pvt. Ltd.

v) Arrangement of sports material for local villagers, promotion of sports &

tournament.

vi)Arrangement of Environmental awareness camp, distribution of saplings for

fruit bearing trees, construction of rain water harvesting ponds, roof top

rain water harvesting etc.

Thus, the project aims at social and economic growth of the surrounding

people.

Page 26: Feasibility Report for Increase in Production of Nadidih Iron ...environmentclearance.nic.in/writereaddata/Online/TOR/30...pit mobile crushing & screening units. 2.1 Identification

Feasibility Report for increase in Production of Nadidih Iron and Manganese mine

P a g e 26 | 26 Ecomen Laboratories Pvt. Ltd.

The Material balance chart for Iron ore (tentative) for Nadidih Iron & Mn Mine

1. Total handling: ROM Ore + Low grade ore from dump = 6.0 million tonne + 1.451million

tonne= 7.451 million tonne.

2. Total processed Iron ore (+55% Fe) = 5.4 million tonne + 0.5 million tonne = 5.9

million tonne

3. 1.551 million tonne of low grade ore (-55% Fe) will be directly despatched as per

markets requirement.

ROM Iron Ore from Mine

excavation

ROM Iron Ore from

Dump / Stack

containing low grade

ore

6.0 million tonne

1.451 million tonne

Dry processing

through mobile

screening / crushing

plant

Dry processing

through mobile

screening / crushing

plant

5.4 million tonne

1.551 million tonne

Low grade iron ore

0.6million tonne

Low grade iron ore

0.951million tonne

0.50 million

tonne

Direct despatch to

buyer’s destination

Despatchable as per buyer’s

requirement.

Direct despatch to

buyer’s destination