Feasibility Report for Increase in Production of Nadidih Iron...
Transcript of Feasibility Report for Increase in Production of Nadidih Iron...
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 1 | 26 Ecomen Laboratories Pvt. Ltd.
1.0 EXECUTIVE SUMMARY:
Nadidih Iron & Manganese Mine, covering an area of 121.405 ha of M/s
Feegrade & Co. (P) Ltd. is in operation since 1961. The site is at a distance of
25km from Barbil and is well connected by an all-weather metal road. In
pursuance to section 8-A (6) of MMDR Amendment Act, 2015, the mining lease
period has been extended up to 31/03/2020 by execution of a Supplementary
Lease Deed on 02.05.2015 over an area of 121.405 hectares. The lease area of
121.405 ha comprises 89.870 ha of forest land (PF+KF+DLC) and 31.535 ha of
non-forest land. Stage-II Forest clearance for an area of 39.309 ha has been
accorded by MoEF, Govt. of India vide letter no. 8(21)26/2003-FCE dated 16
/03/2006 and 45.118 ha of additional forest & deemed DLC forest land for
mining and allied activities (including 8.036 ha of forest land for safety zone)
vide F. No. 8-68/2011-FC dt. 30/10/2013.The lessee had applied for surrender
of 5.443 ha forest land which is under process.
At present, the production of the mine is restricted to excavation of Iron ore
(ROM) from mine and dry screening & crushing of iron ore. These crushing &
screening produce processed ore of +55% and -55% Fe. The overall objective
of the project for grant of Environmental Clearance is to meet the following:
Increase in production of Iron Ore from 2.88 million TPA ROM Iron ore to 6.0
million TPA (ROM) and dry processing of iron ore of 1.451 million TPA. Total
handling will be 7.451 million TPA& 1.451 million TPA dry crushing/screening
of low grade ore from old stack/dumps. The mine was accorded Environmental
Clearance vide order no. J-11015/136/2012-IA.II (M) dated 10.04.2015 for
2.88 million TPA ROM and dry processing of 4.571 million TPA of low grade
iron reworking of old dumps thus total handling of 7.451 million TPA and
installation of wet beneficiation plant of 1.142 million TPA capacity and
production of 0.0036 million TPA of Manganese ore. Installation of wet
beneficiation plant of 1.142 million TPA capacity has been deleted by Ministry
of Environment, Forests and Climate Change vide letter no. J-
11015/136/2012-IA.II (M) dated 09.11.2015.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 2 | 26 Ecomen Laboratories Pvt. Ltd.
Total handling of iron ore will be 7.451 million TPA to get 5.90 million TPA
of processed iron ore of grade +55 % and balance of grade – 55 % (Refer
Exhibit No.1). The ROM, accumulated mineral rejects & wastes from
Nadidih Iron & Manganese Mines will be hauled through trucks/dumpers to
dry processing plants. After processing, the finished iron ore will be carried
to the Railway siding and loaded into Rail wagons and dispatched mainly to
the steel, pelletisation, sponge, sinter plants throughout India and also to
port for export. In the project, due care is taken for optimum use of
natural resources and their conservation and this will continue further. The
company has the electricity permission of total 213 KVA from WESCO, a
power holding company of State Govt. of Odisha. There are also 02
standby generators of total capacity 140 KVA for support.
There is a mine camp within the ML area having about 132 nos. of
residential quarters for its employees of different categories. The social
infrastructure adjacent to the project area includes a health centre and one
Primary School. As a part of CSR activities the Company has undertaken
the construction works of School buildings, boundary wall for Schools &
Temples, club houses in villages, digging of ponds in nearby villages and
bore wells. Such type of work will continue in future. The entire
infrastructure related facilities for traffic and transportation for the mine
are already available. So, there is no new proposal for the same.
The estimated project cost is Rs.200Crores. As regards the economic
viability of the project, this Iron & Manganese mine supplies iron ore to the
steel, pelletisation, sponge, sinter plants of India and also for Export. The
production cost is very favourable than the market price.
The per capita consumption of steel is increasing with the economic
development of people in the World. There is positive market demand of
steel at present and more production of steel is required to bridge the gap
between demand and supply to achieve sustainable development. Hence,
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 3 | 26 Ecomen Laboratories Pvt. Ltd.
the capacity expansion of this mine will meet the urgency of iron ore in
domestic as well as international market. The State will also earn more
revenue from the increased iron ore production and can utilize in its
developmental plans. The capacity expansion plan will also create direct
and indirect employment opportunity for the local youths that will help to
minimize the unemployment problem as well as all around development of
the surrounding area.
2.0 INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION:
District & State: Sundargarh, Odisha
Sub-division: Koira
Village : Nadikasira & Rengalbeda
P.O. Guali
GPS reading
210 58’ 20.15” to 210 57’ 23.35”
850 14’ 58.34” to 850 15’ 34.84”
Name of Lessee:
M/s. Feegrade & Co. Pvt. Ltd. It is a Private Limited Company, under the Indian Companies Act, 1956.
Name of the Corporate Office Name of Registered Office
M/s. Feegrade& Co. Pvt. Ltd. M/s. Feegrade& Co. Pvt. Ltd. At/P.O.-Chaibasa 8-A, Express Tower
Dist.-.West Singhbhum 42-A, Shakespeare Sarani Jharkhand-833201 Kolkota-700017
Ph. 06582-256861 Ph-033-22813751
Fax-06582-256442 Fax-033-22815380
Nadidih Iron & Manganese Mine over an area of 121.405 ha of M/s
Feegrade& Co. (P) Ltd. is under operation since 1961. Nadidih Iron &
Manganese Mine was operated manually in the beginning. But at present,
the mining operation is mechanized with production of 2.88 million TPA
ROM and dry processing of 4.571 million TPA of low grade iron reworking
of old dumps having total handling capacity of 7.451 million TPA and
production of Manganese ore of 0.0036 million TPA. At present, it is
proposed to increase the production capacity of the mine from 2.88 million
TPA of ROM iron ore to 6.0million TPA ROM iron ore and dry
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 4 | 26 Ecomen Laboratories Pvt. Ltd.
crushing/screening of 1.451 million TPA for reworking of old dumps/stacks
for up gradation of low grade recovered from screening of ROM ore and dry
screening of low grade ore. There will be no change in total handling of
material which will be 7.451 million TPA and also there will be no change in
production quantity of Manganese. The ROM ore produced by the
excavation of quarry generally consisted of blue dust, lump iron ore, etc.
This iron ore will be produced by developing up to 9metre benches in the
quarry. The benches will be developed by using different mining
machineries like excavator, tippers, rock breakers, deep hole drilling &
blasting etc. After excavation, ROM iron ore will be processed through in-
pit mobile crushing & screening units.
2.1 Identification of Project & Project Proponent (in case of mining project, a copy of mining lease/letter of intent should be given) :
The project aims for grant of EC to meet the following objectives:
It is proposed to increase the production capacity of the mine from 2.88
million TPA ROM iron to 6.0 million TPA of ROM iron ore and dry processing
of 1.451 million TPA for reworking of old dumps/stacks (total handling will
be 7.451 million TPA). Supplementary Lease deed for this mine has been
executed by the State Govt. of Odisha on 02.05.2015 up to 31.03.2020 as
per The Mines and Minerals (Development and Regulation) Amendment
Act, 2015 dated 26.03.2015 Section 8A (6) states that the period of Lease
granted before the date of Commencement of the Mines and Minerals
(Development and Regulation)Amendment Act, 2015 where mineral is
used for other than captive purpose, shall be extended and be deemed to
have been extended up to a period ending on 31st March, 2020 with effect
from the date of expiry of the period of renewal last made or till the
completion of renewal period, if any or a period of fifty years from the date
of grant of such lease, whichever is later (Copy of Supplementary
Lease deed is enclosed)
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 5 | 26 Ecomen Laboratories Pvt. Ltd.
2.2 Brief description of nature of the project:
Nadidih Iron & Manganese Mine is an operating mine with a capacity to
produce2.88 million TPA ROM and dry processing of 4.571 million TPA of
low grade iron reworking of old dumps, total handling of 7.451 million TPA,
installation of wet beneficiation plant of 1.142 million TPA and production
of 0.0036 million TPA Manganese ore granted Environmental Clearance
vide order no. J-11015/136/2012-IA.II (M) dated 10.04.2015. Installation
of wet beneficiation plant 1.142 million TPA capacity has been deleted by
Ministry of Environment, Forests and Climate Change vide letter no. J-
11015/136/2012-IA.II (M) dated 09.11.2015.At present, the ROM ore
produced in the mine are subjected to dry crushing& screening. The
produced iron ore fines are exported as well as dispatched or sent to
domestic pelletisation/sinter plants. The sized ore are dispatched to
domestic market either through road or through Rail head. The lessee has
already got the necessary permissions from Govt. authorities to fulfill the
demand supply gap of iron ore. Now, it is proposed to enhance the
production of the mine from 2.88 million TPA ROM iron ore to 6.0 million
TPA ROM iron ore and dry processing which include crushing and screening
of low grade ore of 1.451 million TPA having total handling 7.451 million
TPA to get 5.90 million TPA of processed iron ore of grade +55 % and
balance of grade – 55 % Fe.
2.3 Need for the project and its importance to the country and the
region:
Due to market demand of iron ore for domestic steel, sponge and
pelletisation and sinter industry and to meet the export demand, the
project proponent wishes to increase the production capacity of iron ore of
the mines by handling of 7.451 million TPA iron ore i.e., 6.0 million TPA
ROM iron ore and dry crushing and screening of 1.451 million TPA from old
stacks/dumps ROM iron ore. The Govt. will earn more revenue and more
job opportunities will be created. Besides more indirect employment will be
generated through handling of material, transportation, etc. which will
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 6 | 26 Ecomen Laboratories Pvt. Ltd.
result in economic improvement of the people in the locality. Many people,
apart from the above will get other avenues for livelihood, which will help,
in improving the economic and social status of the people in the area.
2.4 Demand-Supply Gap:
The Indian Steel industry has entered into new development stage from
2005-06, riding high on the resurgent economy and rising demand of steel.
Rapid rise in production has resulted India to become the 5th largest
producer of steel. It is estimated that, India’s steel consumption will
continue to grow at nearly 16% rate annually, fueled by the demand of
construction project. The National Steel Policy envisaged steel production
to reach 110 million tonnes by 2020. So, considering these huge demands
of iron ore for steel industries, the supply is not sufficient. So, this project
is important for partial fulfilling of demand.
2.5 Imports Vs. Indigenous Production:
To minimize the growing import of steel, it is necessary to increase the
indigenous production of steel in India. For this it is necessary to produce
more iron ore as raw material. The expansion of the project will partially
meet the demand of raw materials for our upcoming steel industry.
2.6 Export Possibilities:
China & Japan being the 1st& 2nd crude steel producers of World, depend
partly on India for iron ore as raw material. India is the 3rd largest iron ore
provider to China’s steel industry. So there is always an export possibility
of iron ore from this mine.
2.7 Domestic/Export markets:
The sized iron ore from this mine has demand in domestic steel & sponge
industry. During production of lump iron ore, fines of iron ore will be
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 7 | 26 Ecomen Laboratories Pvt. Ltd.
generated automatically, this iron ore fines are exported to China as well
as supplied to domestic pelletisation/sinter plants.
2.8 Employment Generation (direct & indirect) due to the project: Manpower:
Existing& Proposed:
As in this mine total handling will remain same as 7.451 million TPA and
there is change in ROM production only there may by opportunity for direct
employment of total 426 people and indirect employment of 400 people.
So, 826 people will get engagement due to enhancement of the project.
Existing Proposed
Graduate Mining Engineer 2 2
Diploma Mining Engineer 1 1
Geologist 1 1
Surveyor 1 1
Other Officers 12 14
Mine worker for manual sorting &
sizing
171 209
Operator for mining machineries 158 198
Total 346 426
Besides direct employment, many more persons are benefited through
indirect employment as contract jobs, which are mainly extended to the
local tribes.
3.0 .PROJECT DESCRIPTION:
3.1 Type of project including interlinked and interdependent projects,
if any:
In Nadidih mine, ROM iron ore will be produced from the mine by
mechanized method of excavation of the quarry by excavator, tipper, deep
hole drilling, blasting, rock breakers, etc. ROM ore is further processed by
dry crushing, screening.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 8 | 26 Ecomen Laboratories Pvt. Ltd.
3.2 Location (map showing general location, specific location and
project boundary & project site layout with coordinates):
District & State : Sundargarh, Odisha
Sub-division : Koira
Village
P.O.
: Nadikasira, Rengalbeda
Guali
GPS reading
210 58’ 20.15” to 210 57’ 23.35”
850 14’ 58.34” to 850 15’ 34.84”
Location map showing general location, specific location and project
boundary is attached herewith as Plate No.1.
3.3 Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental considerations gone
into should be highlighted:
It is already a running mine.
3.4 Size of magnitude of operation:
The project cost of Nadidih Iron & Manganese Mine is Rs200Crores. It
involves mining of ROM Iron ore, dry crushing & screening of ROM ore to
produce processed iron ore of + 55% and -55% Fe. The processed iron ore
will be produced by processing of excavated ROM iron ore& processing of
low grade iron ore and waste.
At present production capacity of the mine is 2.88 million TPA ROM iron ore
and dry processing of 4.571 million TPA of low grade iron reworking of old
dumps having total handling of 7.451 million TPA. After expansion ROM
production of the mine will increase from 2.88 million TPA ROM iron ore to
6.0 million TPA ROM iron ore and dry processing will reduce from 4.571
million TPA to 1.451 million TPA of low grade iron ore by reworking of old
dumps/stacks.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 9 | 26 Ecomen Laboratories Pvt. Ltd.
3.5 Project description with process details (a schematic diagram/flow
chart showing the project layout, components of the project, etc.
should be given):
The mining method of Nadidih Iron & Manganese Mine will be fully
mechanized to handle 7.451million TPA of iron ore to produce
5.90million TPA processed iron ore of + 55% grade. The conventional
opencast mining with mechanized drilling with 110mm dia drill machine,
deep hole blasting, excavation by excavator of capacity 2.6 m3bucket
capacity and stacking by loader of capacity 1.2 m3. Excavator of
capacity 1.6 m3 /1.5 m3 will be used for feeding the crushing &
screening unit. ROM iron ore will then be processed through dry
crushing &screening units. To prevent generation of fugitive dust during
transportation of ore through trucks/dumpers, static water sprinklers
have been installed along the haul road within the mine for a length of
5.04 km. Besides that water is also been sprinkled through water
tankers of different capacities.
3.6 Raw Material required along with estimated Quantity, likely
source, marketing area of final products, mode of Transport of
raw material & finished product.
It is a mining project to produce iron ore. Low grade iron ore from this
mine will be processed to get saleable ore. There is no need of any raw
material from outside agency.
Iron Ore is having a very good market in India & abroad. So after
production it is immediately saleable to beneficiation plant/sinter/ sponge
and steel industry present in Odisha, Jharkhand, M.P., Chhattisgarh and
other parts of India. China, Korea & Japan are the major buyers from
abroad.
Within the Mine both Iron Ore & Waste Materials will be transported
through tippers of capacity 20 MT. The sized Iron Ore and Fine are
transported to railway sidings at Barsuan, Rengra, Barbil, Bolani etc.
through Tippers of capacity 10 MT or 20 MT. From railway siding, Iron Ore
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 10 | 26 Ecomen Laboratories Pvt. Ltd.
is transported to buyer’s destination or port by rake. Sometimes Iron Ore is
also supplied to the Seaport by trucks from the mines through road.
3.7 Resources optimization/recycling and reuse envisaged in the
project, if any, should be briefly outlined.
As discussed earlier the low grade ore will be crushed and screened for
optimal use of iron ore.
3.8 Availability of water its source, Energy/Power requirement and
source:
Water requirement:
In Nadidih Iron & Manganese Mine water is required for different
operational purpose and also for domestic purpose.
The water requirement as per EC accorded on 10.04.2015 is 2566.6
KLPD (Surface water 2340.38KLPD, Ground water 226.22 KLPD)
including 1599 KLPD for Wet Beneficiation plant. The water is sourced
from Karo River.
Since in the new proposal Beneficiation plant is not there the water
requirement is 993.5 KLPD only (surface water 767.5 KLPD, ground
water 226 KLPD). 520.06 KLPD approval for surface water &226 KLPD
approval for ground water is already there.
For drawl of balance surface water (247.44KLPD), is under process to
the concerned authority.
Energy power requirement:
The machineries will be operated either through electricity or through H.S.D.
details are given below.
(1) Electricity requirement: The electricity is supplied to the project by
WESCO through 2 nos. transformers of total capacity 213 KVA inside
leasehold. There is also requirement of transformers with total capacity
of 350 KVA.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 11 | 26 Ecomen Laboratories Pvt. Ltd.
(2) Details of Generator: 2 nos. of generators of total capacity 140 KVA
exist. There is a further requirement of generator of capacity 400 KVA.
(3) H.S.D. requirement: Present requirement of H.S.D is 1192006
Liters/year. For the envisaged increase in production total H.S.D.
requirement will be around2292000Liters/year.
3.9 Quantity of waste to be generated and scheme for their
management.
Solid Waste Management:
The waste materials of Nadidih Mines are mainly laterite, lateritic Iron
ore, BHQ, BHJ, shale, alluvial soil etc. Total 8300748 m3 of waste
material exists at present. It is expected that 2671588 m3 of waste will
be generated up to the end of the life of the mine. 309248 m3waste
materials of this mine will be dumped in and balance part of the waste
material will be used for backfilling of exhausted quarry.
Previously, the grade of waste material was considered as below 58%
Fe, but at present the grade of waste material is fixed as below 45%. So,
the old waste of Nadidih mines at present are considered as low grade
non-saleable ore.
(1) The waste dumping sites are proposed to be surrounded by
retaining wall and garland drain.
(2) The waste dumps are proposed to be formed by making terraces of
height of 8m to 12m, width 8 m to 12 m and ultimate slope of 370
to 400.
(3) Any rain cuts developed in old dump slopes are proposed to be
leveled and maintained properly by planting saplings and grass.
(4) Garland drains at the toe of the dump are proposed to be
connected with a series of settling tanks which will allow the
settling of silt in it. The silt free water will ultimately go out of the
lease hold. The garland drain will have check weirs/waffle wall at
regular interval to check flow of silt/debris
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 12 | 26 Ecomen Laboratories Pvt. Ltd.
(5) The dead slope of the dump is to be covered by plantation. The
dump slopes where plantations are already completed are
proposed to be maintained properly.
(6) Coir matting is also proposed on the dead dump slope.
4.0 SITE ANALYSIS:
4.1 Connectivity:
Nadidih Iron & Manganese Mine is located in Sundargarh district of Odisha.
The area is about 5kms north-east of Koira. The area is situated on the
main road of Barbil-Koira-Rourkela road, which passes through the south-
eastern side of the lease hold area. The nearest town is Barbil which is at a
distance of 25 km (by road) & Tata Nagar is about 176kms away from
road. The Barbil town is connected by road with major cites of India
including, Bhubaneswar, Paradeep (port), Kolkata.
Koira is the nearest town which provides the facilities of a Hospital, Bank,
Police Station, Post Office, Telephonic Communication, a high school&
College. Barsuan, Banspani, Roxy & Barbil are the nearest railway stations
which also have siding for ore transport. Nearest airport is at Tanto of
Barbil which is at a distance of 17 km from the lease area.
4.2 Land Form, Land use & Land ownership:
Land Form:
The area is a gentle undulated area. Within the total lease area of
121.405 hectares, 31.535 hectares is non-forest land, 48.652 hectare
Khesra forest & P.F. land &41.218 hectare of DLC forest land.
Land Use:
Existing land use pattern:
Sl.
No.
Category Existing Land use
pattern (Ha)
1 Area to be excavated 42.7
2 Over burden/dump 20.394
3 Mineral storage 7.421
4 Infrastructure & mine camp 1.783
5 Roads 5.246
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 13 | 26 Ecomen Laboratories Pvt. Ltd.
6 Green belt 7.540
7 Mineral processing plant 3.75
8 Mine Camp 1.522
9. Unutilised 31.049(within which
5.443 ha forest area
under surrender)
Total 121.405
Land ownership:
a) PF &Khesra Forest – 48.652 hectares is forest land belong to Government.
b) D.L.C Forest – 41.218 hectares is forest land belong to Government. c) Non forest land- 31.535 hectares is Government Non-Forest Land.
N.B. The lessee had applied for surrender of 5.443 ha of forest land which is
under process with concerned statutory authority.
4.3 Topography (along with map):
The area is undulating terrain with a few hillocks, the highest one is RL
615m above MSL. The minimum ground level RL is 528m. The top of the
hill is more or less flat. Southern flank of the hill is more slanting in
comparison to the northern portion. The south-eastern corner of the area
shows a minor trough filled up with recent alluvial sediments. The area is
devoid of any nala or water shed. However, the Karo River which flows
along the north-western boundary of the area provides water throughout
the year to the inhabitants. 10 km. radius map of the mine lease area is
enclosed as Plate No.2.
4.4 Major land use categories of the area in 10 km radius
Sl. No. Category Area (in ha) % of the Study
area
1 Mining Area 2636.00 8.39
2 Agricultural 540.00 1.72
3 Forest Land 17203.00 54.79
4 Waste Land 10031.00 31.95
5 Water bodies 990.00 3.15
Total 31400.00 100
Distance of the nearest park/Sanctuary etc.
a) Kathmala R.F. - 2.9 km SSW
b) Mendhamaruni R.F. - 1.0 km SE
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 14 | 26 Ecomen Laboratories Pvt. Ltd.
c) Karo R.F. - adjacent W
d) Sidhamath R.F. - 7.8 km E
e) Uliburu - 3.6 km N
f) Torha RF - 5.0 km W
There is no National Park or Sanctuary in 10 km radius of mining lease area.
4.5 Existing Infrastructure:
The infrastructure of the lease area partly within the lease and partly outside
the lease. The details are given below:
Sl.
No.
Quarter No.
1 Manager Bungalow Duplex (3-bed
room)
1
2 G+2 (Three bedroom) 6
3 Type-II (Two bedroom) 22
4 Type-I (Two bedroom) 67
5 Guest House 1
6 Club 1
Total 98
There are another 34 nos. of small quarters for mine worker also.
Other Details are:
Sl. No.
Quarter No.
1 One office building 1
2 Chemical Laboratory 1
3 One diesel pump 1
4 One security barrack 1
5 Two D. G. room 2
6 One Rest shelter 2
7 Five nos. of weigh bridge 6
8 One magazine 1
9 One drinking water tank 1
10 New dispensary building 1
11 Mechanical workshop 1
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 15 | 26 Ecomen Laboratories Pvt. Ltd.
Explosive Magazine Capacity:
Sl. No.
Name of Explosives
Capacity
1 Class-II 470 kg
2 Class-6 (Div.3) 7000 nos.
3 Class-6 (Div.1) 3000 m
4 Class-6 (Div.2) 3000 m
To avoid blasting the lessee is using rock breaker at present.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 16 | 26 Ecomen Laboratories Pvt. Ltd.
4.6 Soil Quality:
Soil may be defined as a mixture of rock and mineral material with the
organic matter. Soil is the net result of the action of climate and
organisms especially plant on the earth crust. The pH of soil is normal
ranging from 6.25 – 7.22, average nitrogen values are in medium to
high range (355.45 – 566.32 kg/ha), average potassium value is also in
the range of medium to high (120 – 280 kg/ha).However the average
phosphorus value are low (2.87 – 4.51 kg/ha). The maximum value of
total heterotrophs, azotobacter, actinomycetes & yeast were 7.8 x 105,
6.4 x 104, 1.2 x 104& 6.2 x 105 respectively.
4.7 Climatic condition:
The area is characterized by extreme climate with very hot (42 °C)
summer and very cold winter (4°C) winter. It experiences tropical and
humid climate. The summer is very hot and dry starting from March and
continues till end of May or early June. The rainy season lasts from early
June to end of September. October and November are the post monsoon
months followed by cold winter which lasts till end of February.
a) Temperature:
The area experiences a wide variation in temperature in respect of both
day and night and seasonal. Generally winter starts from late November
and continues till mid of February. December is the coldest month. The
temperature goes up to maximum of 41.50C in June and comes down to
a minimum of 7.90C in December. Data pertaining to temperature
variation for the year 2007 is shown in Table no.1.
Table No. 1.
Month
Temperature ºC Relative Humidity
Max Min Morning Evening
Jan 32.3 8.5 67 51
Feb 31.5 11.2 75 49
Mar 37 13.3 69 38
Apr 40.3 17.4 60 33
May 40 19 70 53
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 17 | 26 Ecomen Laboratories Pvt. Ltd.
Jun 41.5 20.4 76 75
Jul 33 22.4 84 82
Aug 32.6 21 87 83
Sep 31.9 21.4 89 88
Oct 32.6 15.2 73 64
Nov 31.5 12 75 66
Dec 30.3 7.9 67 55
Source: IMD, Bhubaneswar.
b) Humidity
In general air is dry except in monsoon period. Monthly mean relative
humidity varies from 33 to 89 %. In morning (8.30hrs) it varies from 60
to 89 % (Average 74.33%) while in evening it varies from 33 to 88 %.(
Average 61.4%). The Relative Humidity data is shown in Table no. 1.
c) Rainfall
The rainfall data collected from Keonjhar are shown in Table No.2.
MONTHLY RAINFALL RECORDED AT KEONJHAR
(2006-2008)
Table No. 2
MONTH 2006 2007 2008
January Nil 3.1 62.6
February Nil 90.1 6.6
March 21.1 25.1 9.2
April 35.7 42.4 30.8
May 152.9 88.9 103.6
June 177.8 288.4 570.8
July 317.9 454.9 303.6
August 545.6 436.8 293.4
September 285.5 396.6 362.7
October 38.2 27.5 15.4
November 34.8 66.6 2.7
December Nil Nil Nil
Total
Annual Rainfall
1609.5 1920.4 1761.4
Source - Meteorological Centre, Keonjhar
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 18 | 26 Ecomen Laboratories Pvt. Ltd.
d) Wind
The prominent wind directions at Keonjhar are from south west and north
east. The variation in velocity ranges from 0 to 20 km per hour are common in
this area. The directions become predominant from North West during May to
October. The dry winds of the northern plains are not common here.
However, higher wind speeds may be present for a short period before the
rains, during May and June. These periods are quite short, lasting not more
than an hour. Dust storms and hurricanes are rare in this area.
5.0 PLANNING BRIEF:
5.1 Planning concept (type of Industries, facilities, transportation
etc.) Town and country planning/Development authority
classification.
It is an Iron and manganese Ore mine project and in operation for more
than six decades to produce Iron Ore.
The lessee has made arrangement for quarters, drinking water, school
van, ambulance, medical dispensary etc. for all the workers of the mine.
Both waste material & Ore are transported within the mine through
tippers of capacity 35 MT& 20 MT. The processed Iron ore are
transported through tippers to different railway sidings away from the
lease hold. The nearest railway siding is Rengra, Barsuan, Bolani &
Barbil. From the railway siding, through railway wagons, Iron Ore is
transported to buyer’s destination inside or outside Odisha or to the
nearby seaport at Paradeep or Haldia for export.
The lessee has a mine camp in the area equipped with all the facilities
like water supply, electric supply, dish antenna, mobile communication
tower, sewage treatment plant, medical dispensary, ambulance, etc.
5.2 Population Projection:
For the existing production of 2.88 million TPA ROM iron ore and dry
processing of 4.571 million TPA from reworking of old dumps/stacks
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 19 | 26 Ecomen Laboratories Pvt. Ltd.
290total worker are directly & indirectly employed. For the proposed
production target 80 nos. of worker will be employed additionally. Within
the lease hold area 98families are staying permanently within the mine
camp.
5.3 Tentative Land use planning (breakup along with green belt
etc.):
Heads Conceptual
Land use
Area to be excavated 58.613
Overburden/Dump 27.889
Mineral Storage 7.421
Infrastructure 2.137
Roads 4.246
Green Belt + plantation 12.134
Mineral processing Plant 2.0
Mine Camp 1.522
Non mineralized forest area for surrender
5.443
Total 121.405
5.4 Assessment of Infrastructure demand (physical & social) :
Amenities/Facilities:
As it is an operating mine, all the amenities/facilities arrangement are
already present. At present it is only necessary to enhance the
arrangement as per the proposed target production.
6.0 PROPOSED INFRASTRUCTURE:
6.1 Industrial Area (Processing Area):
The area is a mechanized opencast Iron Mine which is under operation
for more than six decades. For existing production of 2.88 million TPA
ROM iron ore and dry processing of 4.571 Million TPA of low grade of old
dumps/stacks. The mine is already well equipped with different
infrastructure. As the total handling remains same as 7.451 million TPA
(6.0 million TPA ROM ore excavation & 1.451 million TPA from reworking
of low grade ore & dump), the above infrastructure will be used with
little addition of some machineries.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 20 | 26 Ecomen Laboratories Pvt. Ltd.
6.2 Residential Area (non-processing area):
Details of existing infrastructure and residential area are already given.
No further infrastructure is necessary, except few new quarters are
proposed to be developed in the area. Other workers will be local
residents. The capacity of water reservoir and electric supply
substation/generator is also proposed to be improved.
6.3 Green Belt:
At present 7.540hectares of area is present as green belt as safety zone.
At the end of the plan period total approximately12.134hectares of area
will be converted to green belt and plantation. At the end of life of the
mine approximately 41.789 hectare of exhausted quarry will be back
filled and covered with plantation and 16.824 ha area will come under
bench plantation.
6.4 Social Infrastructure:
Road:
The lessee maintains the village roads on regular basis. At places
constructed blacktop road/CC road as per the requirement. Wherever
required, arrangements have been made for water sprinkling through
tankers to suppress the dust. Apart from these, other social
infrastructure like village electrification, supply of DG set, supply of
transformer, construction of socio-cultural mandaps, renovation of
anganwadi center, construction of bathing ghats, Maintenance of street
light, construction of drains have also been done. The lessee spent Rs
approximately Rs. 2.45 crore till the year 2015 and Rs. 1.74 crore in the
year 2015-16 for the same.
Education:
Initiatives like construction & renovation of class rooms in schools,
construction of boundary wall, kitchen, toilet, construction of double
storied library building, hostel building, supply of book stacks,
electrification of schools, financial assistance to school teachers, supply
of desk-benches, furniture and teaching aid &equipment’s, play
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 21 | 26 Ecomen Laboratories Pvt. Ltd.
equipment’s to schools, uniform and study materials to students, etc.
have been undertaken for promotion of education. The lessee spent
approximately Rs. 71 lakh till the year 2015 and Rs.47 lakh in the year
2015-16 for the same.
Sports & Culture:
Initiatives like organizing sports tournaments, supply of sports materials,
financial assistance to sports associations, players, organizing inter
village sports tournaments etc. have been undertaken for promotion of
sports.
Towards promotion of culture, financial assistance for organizing cultural
programmes, supply of furniture to different cultural organizations are
also being done to sustain our culture.
The lessee spent approximately Rs.2 lakh till the year 2015 and Rs. 1
lakh in the year 2015-16 for the same.
Health care:
Equipped dispensary with doctor and paramedical staffs, ambulance and
free medicine facility provided to all nearby villagers. Apart from these,
initiatives like, Sprinkling of insecticide wherever necessary, time to time
supply of mosquito nets to villagers, distribution of blankets, financial
assistance for organizing health camps, renovation of staff quarters of
CHC, construction of doctors quarters, extension of PHC and male and
female ward, construction of toilet with water storage tank for tribal
house hold, financial assistance for treatment, financial assistance to red
cross society are also being done.
For provision of drinking water, piped water supply is being done at
villages through RCC/ PVC overhead storage tanks and pipeline
connection at places through bore wells with submersible pump and at
some places bore well with hand pumps, financial assistance for village
committee for potable drinking water etc.
The lessee spent approximately Rs.3.8 crore till the year 2015 and Rs.
18 lakh in the year 2015-16 for the same.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 22 | 26 Ecomen Laboratories Pvt. Ltd.
Sustainable livelihood:
Assistance for livelihood generation like mushroom cultivation,
construction of SHG centre, distribution of fruit bearing saplings,
vegetable seeds, financial assistance for development of kitchen garden
and organizing Environmental awareness programmes have also been
done.
6.5 Connectivity:
The area is well connected with Joda, Barbil, and Koira by all-weather
well maintained road. As this is a mining belt, transport vehicles are
more than public transport vehicle. Tippers of capacity 10 MT & 20 MT
are used for transportation of Iron ore to railway siding within and
outside the lease area. Sized Iron ore, natural fines etc. are transported
from the railway siding to nearby seaport at Paradeep, Haldia etc.
through railway rake. From seaport, Iron ore fines are exported to China
etc.
6.6 Drinking Water Management:
The lessee has made the proper arrangement of drinking water to the
lease hold and also in the area around the lease hold. The lessee
arranged water supply system for all the workers present in the lease
hold. Deep bore well fitted with submersible pumps, water supply pipe,
RCC/PVC tanks are provided within as well as outside the lease hold.
Water supply facilities are already provided to 19 no. of areas near to
the lease hold area. In future with the enhancement of project the lessee
will provide more & more water supply facilities to other villages also.
The lessee also planned rain water harvesting by collecting rain water in
exhausted quarry. It is also planned and implemented for rain water
harvesting by collecting rainwater on the roof of some of the houses of
camp for recharging purpose.
6.7 Sewerage System:
The mine camp of Iron Mine has a proper sewerage system to handle
domestic waste water. All the houses are connected with drains, through
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 23 | 26 Ecomen Laboratories Pvt. Ltd.
which waste water usually is drained out. One sewage treatment plant of
100 KLD has already been installed in the camp area of the lease hold.
After necessary treatment of the domestic waste water, the waste is
used as manure and treated water used in plantation and haul road for
dust suppression. The green vegetable peels, instead of wasting, are
now used in “vermi-composting” units to produce vermin-compost
manure.
6.8 Industrial Waste Management:
This is a running mine and no industrial waste generated by this unit.
6.9 Solid Waste Management:
The waste materials of this Mine are mainly laterite, lateritic Iron Ore,
BHQ, BHJ, shale, Lateritic soil etc. The solid waste generated at present
will be dumped partly in preselected dump yards. Part of the dump will
be used for backfilling of the exhausted quarry also.
The details are discussed in item no. 3.9.
6.10 Power Requirement & Supply/Source:
Details of power requirement & supply are discussed in item no.3.8.
7.0 REHABILITATION & RESETTLEMENT (R & R) PLAN:
Not Applicable
8.0 PROJECT SCHEDULE & COST ESTIMATES:
Likely date of start of construction & likely date of completion (Time schedule
for the project to be given)
This is running mine.
8.1 Estimated Project cost along with analysis in terms of economic
Validity:
Total cost of proposed project is 200 Crores.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 24 | 26 Ecomen Laboratories Pvt. Ltd.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATION):
(Financial & Social benefits with special emphasis on the benefit
to the local people including tribal population, if any, in the
area.)
Nadidih Iron & Manganese Mine is a running iron mine with proposed
production target of 6.0 million TPA ROM of iron ore and dry processing
of 1.451 million TPA from reworking of old stacks/dumps. It is proposed
to enhance the production target to 5.90 million TPA of processed ore of
+ 55% grade. The increase is production will create some financial &
social benefit, which are as follows:
a) At present 290 nos. of people are benefitted. Due to the proposed
production enhancement, 80 nos. of people will further benefitted
directly.
b) With the enhancement of production, the revenue earned by the
Govt. in terms of Royalty.
c) The lessee will make further efforts for the following arrangement
for social welfare of the core zone as well as buffer zone.
i) Medical facilities: The mine management will arrange medical camps
in different villages. Occupational health study will be done in core zone.
For the purpose of malaria eradication proper steps will be taken which
includes sprinkling of bleaching power, fogging, distribution of mosquito
net etc. The existing dispensary having a pathological lab will take
medical care of the staff & villagers.
ii) Drinking Water:
Facility of drinking water to the core zone as well as buffer zone is available by
means of bore wells fitted with submersible pumps, construction of overhead
water tanks and supply of water through pipe line.
iii) Construction of culvert and bridges on the existing roads& repairing of
transport road.
iv) Construction of school building, remuneration to school teachers, supply of
reading materials to school children etc.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 25 | 26 Ecomen Laboratories Pvt. Ltd.
v) Arrangement of sports material for local villagers, promotion of sports &
tournament.
vi)Arrangement of Environmental awareness camp, distribution of saplings for
fruit bearing trees, construction of rain water harvesting ponds, roof top
rain water harvesting etc.
Thus, the project aims at social and economic growth of the surrounding
people.
Feasibility Report for increase in Production of Nadidih Iron and Manganese mine
P a g e 26 | 26 Ecomen Laboratories Pvt. Ltd.
The Material balance chart for Iron ore (tentative) for Nadidih Iron & Mn Mine
1. Total handling: ROM Ore + Low grade ore from dump = 6.0 million tonne + 1.451million
tonne= 7.451 million tonne.
2. Total processed Iron ore (+55% Fe) = 5.4 million tonne + 0.5 million tonne = 5.9
million tonne
3. 1.551 million tonne of low grade ore (-55% Fe) will be directly despatched as per
markets requirement.
ROM Iron Ore from Mine
excavation
ROM Iron Ore from
Dump / Stack
containing low grade
ore
6.0 million tonne
1.451 million tonne
Dry processing
through mobile
screening / crushing
plant
Dry processing
through mobile
screening / crushing
plant
5.4 million tonne
1.551 million tonne
Low grade iron ore
0.6million tonne
Low grade iron ore
0.951million tonne
0.50 million
tonne
Direct despatch to
buyer’s destination
Despatchable as per buyer’s
requirement.
Direct despatch to
buyer’s destination