NAVFAC MIDLANT FEAD MCAS Cherry Point 2019 Facilities Outlook Southeast Region Federal Construction, Infrastructure and Environmental Summit 24 October 2019 Ericka Bishop Supervisory Contract Specialist Marine Corps Installations-East/ Marine Corps Air Station Cherry Point 1

Transcript of FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF...

Page 1: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT

FEAD MCAS Cherry Point2019 Facilities Outlook

Southeast Region Federal Construction, Infrastructure and Environmental Summit24 October 2019

Ericka BishopSupervisory Contract SpecialistMarine Corps Installations-East/Marine Corps Air Station Cherry Point

1

Page 2: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT2

FEAD MCAS Cherry Point

Base loading (Mil/Dependents & Civ APF + NAF) = 22,801Airspace and Operations: 24/7

• 9,145 Sq Miles of National and Special Use Airspace• 22 VFR / 10 IFR Airports• Total operations in FY17 = 144,873 Aircraft• Aerial Port of Embarkation (APOE): (FY-18)

• 344 Flights; 26,555 Pax: 3995 Short-Tons2d Marine Aircraft Wing aboard Cherry Point:

• 6,115 of 13,857 Marines, 61 AircraftFRCEAST:

• Military: 35• APF Employees: 3,748• Contractors: 219

Naval Health Clinic:• Military: 241• APF Employees: 118• Contractors: 90• Population Served: 20,000

Center of Naval Aviation Technical Training (CNATT):• Command & Staff 123• Students FY19 2,049

Cape Hatteras

Kinston

Jacksonville

Wilmington

Page 3: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT3

FEAD MCAS Cherry Point

3

Bombing Targets 9 and 11• 12 scored targets (fixed)• Water borne moving targets• Aviation and small boat target engagement

Outlying/Auxiliary Landing Fields (OLF)• Aviation Support Mission Tasks• Military Operations in Urban Terrain (MOUT)

Facility (OLF Atlantic only)• Non-live fire

Special Use Airspace (SUA)/

ATC Assigned Airspace (ATCAA)

• R5306 to 17,999’ MSL• Neuse ATCAA FL180-230• Burner ATCAA FL180-290• Razor Talon ATCAA FL290-500

Electronic Threat Systems

• Covers Cherry Point SUA and Offshore WarningArea (W-122)

• Integrated Tactical Combat Training System (Virginia to Florida)

• 24 threat capabilities, fixed and mobile

OLF Atlantic MOUT

ALF Bogue Field

OLF Oak Grove

Bombing Target 9

(BT-9)

Bombing Target 11

(BT-11)

Page 4: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT4

Facilities Mission

Mission: To provide garrison facilities, infrastructure, housing, and environmental support to enable operational forces, supported commands, and others associated with MCAS Cherry Point to complete their mission.

Functions:• Facilities Planning and

Engineering• Military Construction

(MILCON)• Real Property Maintenance• Real Property Accountability• Housing and Billeting

Management• Real Estate

• Environmental Compliance• Conservation• Pollution Prevention• Utilities Management• Management of Contractor

Provided Services• Geospatial Information

System (GIS)

Page 5: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT5

FY11 Bachelor Enlisted Quarters (P136)FY16 Airfield Security Upgrades (P222)FY19 F35 Flightline Utilities Upgrade (P235)FY19 F35 Hangar, Para Loft Facility (P199)FY20 ATC Tower/ AirOps (P228)FY20 Training & Simulator Facility (P204)FY20 Phys Sec Upgrades - Slocum Rd (P134)FY20 PMO/H&HS & MWHS-2 HQ (P162) HFLOFY20 Station Academic Facility (P254) HFLOFY20 BT-11 Range Operations Center (P246) HFLO (NS)FY20 Motor Communication/Comm Shop (P130) HFLOFY20 Fire Stations (P142) HFLOFY22 F35 Flightline Utilities Upgrade, Phase II (P239)FY22 MALS Maint Facility/MAG-HQ (P226) FY22 F35 Hangar & Parking Garage (P197)FY22 Runway Improvements (P206)FY22 Vertical Landing Pad Improvements (P205)FY22 Support Equipment Storage (P202)FY23 GSE Shop (P207)FY23 Indoor Fitness Facility (P658)FY23 2D LAAD Battery Maint & HQTRS Facility (P258)FY23 Atlantic Field Security (P080)FY24 F-35 LHA Deck/FOB (P210)FY24 F-35 Hangar (P200)FY24 MACS-2 Tactical Air & Operations Center (P129)

NS

Total of $1.17B in execution, planning, or

programming

FY23 FY24 FY25FY16 FY17 FY18 FY20 FY21 FY22 FY27FY26

VMFA (x2)

VMAQ-4 VMAQ-3 VMAQ-2VMAQT-1 VMAT-203

VMA-223VMA-231

FY19

VMFA VMFA VMFA (x2)Start Construction

End ConstructionRevision Date: 6/13/2019

VMA-542

FIRST AIRCRAFT ARRIVAL

SUNDOWNTRANSITON

Non-Hurricane MILCON Plan

Page 6: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT6

Acquisition Tools• MCAS Cherry Point Current AQ Tools:

– Mini MACC– Mechanical MACC– General MACC– Roofing MACC

• Due to limited demand, NAVFAC ML reach-back is used for local DB MACC requirements.

• AQ Tools in Work:– Airfield IDIQ - $5M– Mechanical/Electrical/Plumbing MACC – $240M (Target Award

Nov 2019)– General Construction MACC – $249M (Target Award Jan 2020)– Maintenance & Repair MACC – $40M

• Replaces lost construction capacity from BOS (BTO)– Civil/Paving MACC - $95M (Target Award Feb 2020)– Painting/ Flooring MACC - $10M (Target Award Apr 2020)

Page 7: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT7

Acquisition Tools, Cont

• Acquisition tool decision process includes:– Complexity, Size, Risk, Mission Impact, Schedule– CPARS

• A/E IDIQ Contracts: – Two (2) for DBB Projects– Planned Architectural IDIQ – scheduled award for Sep 19’– Planned MEP IDIQ– Planned Civil/Structural IDIQ

Page 8: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT8

FY20 NORTH CAROLINAOPPORTUNITIES

Fund Source Project Number Description Location

FSRM 6861538 Repair Concrete Footing for speaker Pole, Parade Grounds, Bldg 1 MCAS Cherry Point

FSRM 6858885 Repair Grit System, IWTP MCAS Cherry Point

FSRM 6693241 Replace Badly Corroded Water Lines MCAS Cherry Point

FSRM 6682326 E911 Street Sign Replacement MCAS Cherry Point

FSRM 6827495 Replace Water Fountain Playground # 8 MCAS Cherry Point

FSRM 6759754 Replace Broken Water Line Inside Masonry Wall RM137, 139 MCAS Cherry Point

FSRM 6714173 Repair Manifold leak on Generator, HQ, Bldg 1 MCAS Cherry Point

FSRM 6893113 Replace Deluge Sprinkler Alarm Valves and Piping VMAT 203 MCAS Cherry Point

FSRM 6735834 Repair Sidewalk MCAS Cherry Point

FSRM 6895127 Replace Lift Station Atlantic Field MCAS Cherry Point

FSRM 6768131 Replace Metal Grates on Collection Ring MCAS Cherry Point

FSRM 6725643 Repair HVAC BT-11 9014 9022 MCAS Cherry Point

FSRM 6844836 Replace Roll Up Door In Warehouse, MCX MCAS Cherry Point

FSRM 6661889 Repair Heaters in Cooler Doors MCAS Cherry Point

FSRM 6825225 Replace Hoist Building 3998 MCAS Cherry Point

FSRM 6653698 Repaint Floor in Aerial Port MCAS Cherry Point

FSRM 6844738 AE-Repair Bridges MCAS Cherry Point MCAS Cherry Point

FSRM 6825483 Replace 2" Sewer Line from Tee to Lift Station MCAS Cherry Point

Page 9: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT9

FY20 NORTH CAROLINAOPPORTUNITIES

FSRM 6844329 Replace Electrical Outlets & Wire Ordinance Pier MCAS Cherry Point

FSRM 6838993 Replace Inside Left Front Sliding Door Operator MCAS Cherry Point

FSRM 6844721 Repair Erosion Around Magzine, Ordance, MCAS Cherry Point MCAS Cherry Point

FSRM 6814207 Install Railing Around Primary Clarifier MCAS Cherry Point

FSRM 6767630 Repair Broken Water Line Inside Masonry Wall MCAS Cherry Point

FSRM 6878999 Replace Damaged Section of Bay Door, 2DLAAD, Maint Bay MCAS Cherry Point

FSRM 6807069 Repair Sewer Line, Behind Post Office on 2nd Ave, 209180 MCAS Cherry Point

FSRM 6747446 Repair Underground Steam Main Bldg 219 MCAS Cherry Point

FSRM 6809481 Install Actuators on Yard Valves MCAS Cherry Point

FSRM 6689333 Renovate Lift Station #6 MCAS Cherry Point

FSRM 6856713 Install 4 Clean Outs, Mess Hall, Kitchen Bldg. 3451 MCAS Cherry Point

FSRM 6818858 Install Electrical Outlets STAG 6 Comm Ceneter MCAS Cherry Point

FSRM 6816418 Repaint Warm Up Area 2 MCAS Cherry Point

FSRM 6461930 Replace Secondary Feed Water Supply Piping AE MCAS Cherry Point

FSRM 6646038 Repair Fire Water Main Low Pressure AE MCAS Cherry Point

FSRM 6470853 Construct Separate Male and Female Crew Quarters MCAS Cherry Point

FSRM 6900720 Repair Main Steam Leak Parking Lot 137 MCAS Cherry Point

FSRM 6863724 Repair Front Door and Frame, MCCS Military Clothing, Bldg 3918 MCAS Cherry Point

FSRM 6846905 Replace Missing Ceiling Tiles MCAS-2 Bldg 4402 and 3918 BX MCAS Cherry Point

Page 10: FEAD MCAS Cherry Point2 NAVFAC MIDLANT FEAD MCAS Cherry Point Base loading (Mil/Dependents & Civ APF + NAF) = 22,801 Airspace and Operations: 24/7 • 9,145 Sq Miles of National and

NAVFAC MIDLANT10

Questions?