Faster Projects, On-time,
with Team HarmonyAn introduction to Critical Chain Project
Management
presented by: Joe Cooper
Tokyo, Japan – 6 February 2017
![Page 2: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/2.jpg)
Gartner on CCPM
• “Like may concepts, CCPM was ahead of its time. However, with the proliferation of digitization and the shortage of technical resources, the world may very well be ready for CCPM.” – Gartner
• “Anyone who is working on projects and is concerned about on-time delivery should care about CCPM. Therefore, those who should care include CIOs, PMO leaders, portfolio managers, program managers, and project managers. – Gartner
![Page 3: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/3.jpg)
Do you have these project problems?
Low Team Morale & Low-trust environments
Missed delivery dates: late projects
Excessive project durations: reduced return on investment (ROI)
Nonproductive multitasking
Uncertainty in task estimates
High amounts of work in progress
![Page 4: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/4.jpg)
Key Concepts Covered
Focus versus Multitasking
50/50 versus 95% Estimates
Buffer to protect project delivery date
TRUST
![Page 5: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/5.jpg)
Additional Details
•Each concept covered includes “Adoption Nuggets”:
• Practical tips for team member engagement
• Methods to gain senior leadership support
• Acceleration techniques from the field
![Page 6: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/6.jpg)
Focus versus Multitasking
50/50 versus 95% Estimates
Buffer to protect project delivery date
TRUST
![Page 7: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/7.jpg)
Multitasking Example
Volunteer Needed
![Page 8: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/8.jpg)
1 A I2 B II3 C III4 D IV5 E V6 F VI7 G VII8 H VIII9 I IX10 J X
1 A I2 B II3 C III4 D IV5 E V6 F VI7 G VII8 H VIII9 I IX10 J X
40 42 44 7 14 22
P1 P2 P3 P1 P2 P3
Multitasking Example
![Page 9: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/9.jpg)
Multitasking vs. Focus
Multitasking
Focus
P1: A B C D E F G H I J
P2:
P3:
48 days
A B C D E F G H I J 50 days
A B C D E F G H I J 52 days
P1: D E F G H I J
P2:
P3:
20 days
D E F G H I J 28 days
D E F G H I J 36 days
B CA
B CA
B CA
![Page 10: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/10.jpg)
Summary
Context switching
creates a loss of productivity, an increase in stress, and a decrease in
quality
“Focus” allows most tasks (or
projects) to complete
faster and with better quality
Even the tasks (or projects)
that start later, finish earlier
Time to Market and Return on
Investment improve
significantly
![Page 11: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/11.jpg)
Adoption Nuggets
• Use the multitasking game with teams and senior leadership to gain understanding and buy-in.
• Empower team members to call out times they may be pulled into multitasking.
• Find PM’s who are confident enough to “yield” to other PM’s for team member focus – lead by example.
![Page 12: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/12.jpg)
Focus versus Multitasking
50/50 versus 95% Estimates
Buffer to protect project delivery date
TRUST
![Page 13: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/13.jpg)
Which estimate would you give?
95% likely or 50% likely?
![Page 14: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/14.jpg)
Task duration probabilityP
roba
bilit
y
Duration
10% confidence 50% confidence 95% confidence
2 days 5 days 12 days
.20
.40
.60
.80
1.0
![Page 15: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/15.jpg)
Student Syndrome
No progress Panic Work!
Start task Deadline
![Page 16: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/16.jpg)
Parkinson’s Law
• Work expands to fill the time allotted
• Reliable estimators
• Padding will be cut next time
• Keep working/testing
• Heavily padded task durations become a self-
fulfilling prophesy, even when the work is
completed early.
![Page 17: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/17.jpg)
Summary
50/50 creates better
results than 95%
estimates
Teams become
more engaged
and trust is built
Student syndrome is significantly
reduced
Parkinson’s law is
significantly reduced
![Page 18: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/18.jpg)
Adoption Nuggets
• Address the need for everyone to be “busy”.
• Teams enjoy the stretch goal of 50/50 estimates, but they have to trust they will not be criticized for being late – It’s OK to be late!!
• Share the optimistic, pessimistic, and most-likely scenario to help teams provide 50/50.
• Be careful if other projects are not operating in this way.
![Page 19: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/19.jpg)
Focus versus Multitasking
50/50 versus 95% Estimates
Buffer to protect project delivery date
TRUST
![Page 20: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/20.jpg)
Protecting the project commitment
Task 1’ Hidden Padding Task 2’ Hidden
Padding Task 3’ Hidden Padding Task 4’ Hidden
Padding
Task 1 Task 2 Task 3 Task 4 Project BufferX
![Page 21: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/21.jpg)
Task 1’ Hidden Padding Task 2’ Hidden
Padding Task 3’ Hidden Padding Task 4’ Hidden
Padding
Task 1 Task 2 Task 3 Task 4
Task 1’ Task 2’ Task 3’ Task 4’ Project BufferTime
Saved
Protecting the project commitment
![Page 22: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/22.jpg)
Task 1’ Hidden Padding Task 2’ Hidden
Padding Task 3’ Hidden Padding Task 4’ Hidden
Padding
Task 1 Task 2 Task 3 Task 4
Task 1’ Task 2’ Task 3’ Task 4’ Project BufferTime
Saved
Protecting the project commitment
![Page 23: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/23.jpg)
Buffer Consumption
![Page 24: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/24.jpg)
Focus Management Attention
.Project G .Project E
.Project F
.Project D
.Project B
.Project C
Project A.
Program / Portfolio Buffer
![Page 25: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/25.jpg)
Summary
Project buffer protects what
is really important –the project
The buffer can be built
using the task padding we
removed
A buffer equal to 50%
of the new project
duration is a good start
Projects in red or yellow can receive priority and
management attention
![Page 26: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/26.jpg)
Adoption Nuggets
• Help sponsors to understand 50/50 so they can appreciate project buffers – and not cut them!
• Help teams to see how the buffer chart provides a sense of urgency – they don’t always have to be in a state of crisis.
• Reiterate how buffers help to prioritize team member’s focus and management attention.
![Page 27: Faster Projects, On-time, with Team Harmony Projects, On-time, with Team Harmony An introduction to Critical Chain Project Management presented by: Joe Cooper ... • Padding will](https://reader031.fdocuments.us/reader031/viewer/2022030506/5ab3f5e97f8b9a156d8b71e5/html5/thumbnails/27.jpg)
Thank you!