SAN MARCOS UNIFIED SCHOOL DISTRICT FEBRUARY 10, 2014 FACILITIES UPDATE GOVERNING BOARD MEETING

description

Facilities Update governing Board meeting. San marcos unified school district February 10, 2014. F acilities Update: In Construction. Woodland Park MS Modernization Project: Mar 2014* Modernize two (2) classrooms Remodel Administration Building - PowerPoint PPT Presentation

Transcript of Facilities Update governing Board meeting

Page 1: Facilities Update governing Board meeting

S A N M A R C O S U N I F I E D S C H O O L D I S T R I C T

F E B R U A R Y 1 0 , 2 0 1 4

FACILITIES UPDATEGOVERNING BOARD MEETING

Page 2: Facilities Update governing Board meeting

2

Facilities Update: In Construction

• Woodland Park MS Modernization Project: Mar 2014*• Modernize two (2) classrooms• Remodel Administration Building

• Twin Oaks HS Modernization Project: Completed• Remodel Administration Building

• Prop K: Technology Infrastructure Projects: • Mission Hills HS, La Costa Meadows ES, Paloma ES – Feb 2014*• Knob Hill ES, Richland ES, Twin Oaks ES, San Elijo MS – July 2014*

• NCREC – South: August 2014*• Professional Development and Centralized Kitchen

• Carrillo ES: Modernization Project: Apr 2014*• Modernize two (2) classrooms to add restrooms

*Note: Scheduled Completion Dates2/10/2014

Page 3: Facilities Update governing Board meeting

3

Facilities Update: Woodland Park MS

Classroom Modernization and

Expansion

2/10/2014

Page 4: Facilities Update governing Board meeting

4

Facilities Update: Woodland Park MSNew Restrooms

2/10/2014

Page 5: Facilities Update governing Board meeting

5

Facilities Update: Woodland Park MS

Student Support Services2/10/2014

Page 6: Facilities Update governing Board meeting

6

Facilities Update: Woodland Park MS

Conference Room and Student Support Services2/10/2014

Page 7: Facilities Update governing Board meeting

7

Facilities Update: Woodland Park MS

Student Support Services2/10/2014

Page 8: Facilities Update governing Board meeting

8

Facilities Update: Twin Oaks HS

Administrative and Student Support Services

Before

AFTER

2/10/2014

Page 9: Facilities Update governing Board meeting

9

Facilities Update: Twin Oaks HS

Administrative and Student Support Services2/10/2014

Page 10: Facilities Update governing Board meeting

10

Facilities Update: Twin Oaks HS

Administrative and Student Support Services2/10/2014

Page 11: Facilities Update governing Board meeting

11

Facilities Update: District-wide

I.T. Infrastructure Project• Phase 1: 4 campuses

• MHHS, DO, LCM, PAL • Feb. 2014 completion

• Phase 2: 4 campuses• Design complete• Bid February 2014• Complete July 2014• KH, RL, SEMS, TOES

• Working on E-rate projects (additional Federal funding)

2/10/2014

Page 12: Facilities Update governing Board meeting

12

Facilities Update: NCREC - South

Professional Development and Centralized Kitchen Project

• 3 Classrooms for Professional Development

• 1 Portable Kitchen (from San Marcos High School Temporary Campus)

2/10/2014

Page 13: Facilities Update governing Board meeting

13

Facilities Update: NCREC - South

2/10/2014

Page 14: Facilities Update governing Board meeting

14

Facilities Update: Carrillo ES Mod.

Existing

Remodel

2/10/2014

Page 15: Facilities Update governing Board meeting

15

Facilities Update: Carrillo ES Mod.

2/10/2014

Page 16: Facilities Update governing Board meeting

G O V E R N I N G B O A R D M E E T I N G

F E B R U A R Y 1 0 , 2 0 1 4

FACILITIES UPDATE:THANK YOU!