Facilities Modernization Program Funded by Measure B Project Report. April 19, 2010. PROJECT PROGRESS REPORT College Center for the Arts. LAS POSITAS COLLEGE April 19, 2010. Project Team: Architect : John Sergio Fisher & Associates Construction Manager : Parsons Brinckerhoff - PowerPoint PPT Presentation

Transcript of Facilities Modernization Program Funded by Measure B Project Report

  • Facilities Modernization ProgramFunded by Measure BProject ReportApril 19, 2010

  • PROJECT PROGRESS REPORTCollege Center for the ArtsProject Team: Architect: John Sergio Fisher & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: C. Overaa & Co

    Project Update: The exterior siding, stucco and windows are 99% complete. The interior of the building is 97% complete in segment "B" which is the facility offices and the rehearsal rooms. The Black Box Theater and the Main Auditorium infrastructure elements are continuing and will be completed this month. The final concrete walk ways and ramp around the building and the Amphitheater are 98% complete. The total project is 95% complete.

    Occupancy Fall Semester 2010LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTChild Development CenterProject Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates

    Project Update: Exterior plaster complete on all buildings. Installation of sheetrock continues in building B and has started in building C. Rough grading for the OLEs has begun.

    OccupancySpring 2011LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)

    Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

    Project Update: Underground & electrical utilities are continuing.

    Occupancy: 10/2010LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTCollier Creek Storm Water OutfallProject Team: Engineer of Record: SandisConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

    Project Update: Storm Drain and Retaining wall installation is complete. Backfill at retaining wall is on going.

    Occupancy: 04/2010LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTScience Building, Phase IIProject Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: TBD

    Project Update: Added space for 4 classrooms on second floor. Site layout and floor plan finalized. Projected submittal to DSA in March 2010.

    Occupancy: Fall 2012LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTStudent Services & Central AdministrationProject Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: TBD

    Project Update: 60% design documents were submitted in April DSA submittal planned for August 2010, This project will participate in the new DSA Collaborative Process.

    Occupancy: Fall 2012LAS POSITAS COLLEGEApril 19, 2010

  • PROJECT PROGRESS REPORTCampus Boulevard Phase I-IIIProject Team: Architect: RHAA Construction Manager: Parsons BrinckerhoffContractor: TBD

    Project Update: Design stopped to coordinate with SSA design concepts.

    Occupancy: Fall 2011LAS POSITAS COLLEGEApril 19, 2010

    *