Facilities Modernization ProgramFunded by Measure B
Project Report
November 21, 2011
PROJECT PROGRESS REPORTChild Development Center
Project Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates
Project Update:• Project is complete.• Project is in Warranty Period.
Occupancy Spring 2011
LAS POSITAS COLLEGENovember 21, 2011
PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)
Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction
Project Update:• Project is complete.• We are in Warranty Period.• DSA Closeout is in progress.
Occupancy: 04/2011
LAS POSITAS COLLEGENovember 21, 2011
PROJECT PROGRESS REPORTScience Building, Phase II
Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc
Project Update:• Interior/Exterior framing on first and second floors are being completed.• Exterior insulation is being installed. • Plumbing installation is continuing on first and second floors.• Electrical and Data installation is continuing at first and second floors.• Roofing on High Roof is complete, Low roof is 85% complete.• Storefront installation will start week of Nov 28, 2011.
Occupancy: 09/2012
LAS POSITAS COLLEGENovember 21, 2011
PROJECT PROGRESS REPORTStudent Services & Central Administration
Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction
Project Update:• GFRC installation erection complete, plumbing and lining remain.• Mechanical, Electrical, Plumbing rough in continues.• Interior wall partitions underway, exterior framing 50% complete.
Occupancy: Spring 2013
LAS POSITAS COLLEGENovember 21, 2011
PROJECT PROGRESS REPORTCampus Boulevard Phase I-III
Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: TBD
Project Update:• 100% Design review completed, final design schedule for December 2011.
Design Re-Start: 04/2011DSA Permit Approval: 02/2012Construction Start: 03/2012Occupancy: TBD
LAS POSITAS COLLEGENovember 21, 2011
PROJECT PROGRESS REPORTPhotovoltaic System Phase II
Project Team: Design Build Contractor: Cupertino Electric Inc.Construction Manager: Parsons Brinckerhoff
Project Update:• Fencing Completed.• Racking System completed and ready for Array installation.• PV Arrays installation will start week of November 28, 2011.• Inverters and Transformer install Mid December 2011.
Occupancy: January 2012