Transcript of Fabrication Progress for LHC Superconducting Crab Cavities April 17, 2015.
- Slide 1
- Fabrication Progress for LHC Superconducting Crab Cavities April 17, 2015
- Slide 2
- Outer conductor halves 4 halves in QA 2 Double Quarter-Wave
- Slide 3
- 3 Top cake pans 2 in QA Double Quarter-Wave
- Slide 4
- 4 Bottom cake pans 2 in QA
- Slide 5
- Double Quarter-Wave 5 Cake pan assemblies
- Slide 6
- 6 Bowls Complete Ready for NbTi tuner attachment welds Double Quarter-Wave
- Slide 7
- 7 Cake pan & bowl stackup Double Quarter-Wave
- Slide 8
- 8 Outer conductor halves 4 in QA RF Dipole
- Slide 9
- 9 Small HOM Box Side Port 2 in QA (4 halves)
- Slide 10
- 10 End cap: Niobium stamping in progress RF Dipole
- Slide 11
- 11 FPC & HOM Box Port Halves Waiting for finalization of end cap prototype RF Dipolecopper prototypes
- Slide 12
- 12 Bowl: Machined copper for stackup RF Dipolecopper prototypes
- Slide 13
- 13 Stiffener: Machined for stackup RF Dipolecopper prototypes
- Slide 14
- 14 Bowl Stiffener Outer Conductor