Project : Fabrication Safety Shower and Eyewash for Sulfuric Acid Storage Fa Location : MVC Plant Site, Iligan City Owner : Mabuhay Vinyl Corporation Subject : BM and Cost Estimates BILL OF MATERIALS AND COST ESTIMATE A) MATERIALS ITEM NO. ITEM DESCRIPTION QTY UNIT UNIT COST MVC Owned materials TOTAL B) LABOR ITEM NO. ITEM DESCRIPTION QTY No of Days Rate/day 1 Skilled 1 12 342.00 2 Semi Skilled 1 12 312.00 3 Unskilled 269.00 TOTAL B) LABOR OVERHEAD ITEM NO. ITEM DESCRIPTION QTY No of Days OH/day 1 Skilled 1 12 75.24 2 Semi Skilled 1 12 68.64 3 Unskilled 59.18 TOTAL C) OTHER OVERHEAD ITEM NO. ITEM DESCRIPTION QTY No of Days Rate/day 1 Equipment Rental 2 Fixed Overhead (7%) 4 TOTAL SUMMARY Total Labor Cost Supervision Cost Profit Labor Overhead Other Overhead TOTAL 12%VAT TOTAL PROJECT COST SAY epared By: Approved: JVT LIÑAN ED PAGALING Project Staff Sr. IE

description

sample of fabrication of eyewash.

Transcript of Fabrication of Eyewash

Page 1: Fabrication of Eyewash

Project : Fabrication Safety Shower and Eyewash for Sulfuric Acid Storage Facility Location : MVC Plant Site, Iligan CityOwner : Mabuhay Vinyl CorporationSubject : BM and Cost Estimates

BILL OF MATERIALS AND COST ESTIMATEA) MATERIALSITEM NO. ITEM DESCRIPTION QTY UNIT UNIT COST AMOUNT

MVC Owned materials TOTAL

B) LABORITEM NO. ITEM DESCRIPTION QTY No of Days Rate/day AMOUNT

- 1 Skilled 1 12 342.00 4,104.00 2 Semi Skilled 1 12 312.00 3,744.00 3 Unskilled 269.00 -

TOTAL 7,848.00 B) LABOR OVERHEADITEM NO. ITEM DESCRIPTION QTY No of Days OH/day AMOUNT

1 Skilled 1 12 75.24 902.88 2 Semi Skilled 1 12 68.64 823.68 3 Unskilled 59.18 -

TOTAL 1,726.56 C) OTHER OVERHEADITEM NO. ITEM DESCRIPTION QTY No of Days Rate/day AMOUNT

1 Equipment Rental - 2 Fixed Overhead (7%) 910.56 4

TOTAL 910.56

SUMMARY Total Labor Cost 7,848.00 Supervision Cost 1,962.00

Profit 1,471.50 Labor Overhead 1,726.56 Other Overhead 910.56

TOTAL 13,918.62 12%VAT 1,670.23

TOTAL PROJECT COST 15,588.86 SAY 15,600.00