FAA Update Airports Program
description
Transcript of FAA Update Airports Program
Presented to:
By:
Date:
Federal AviationAdministrationFAA Update
Airports Program
Western-Pacific Region
Association of California Airports Arlene B. Draper
September 13, 2013
2Federal AviationAdministration
FAA Update
FAA Update• FY12 Program Highlights• AIP Performance Metric• Inactive Grants• Are You Ready for FY14?• Safety Initiatives• Geo Balancing
3Federal AviationAdministration
FAA Update
FY12 AIP Projects Funded (Western-Pacific Region)
$0
$20
$40
$60
$80
$100
$120
Environmental /Planning $7M
Roads/Fencing$12M
Other $14M Navaids /Equipment $16
Building/Terminal$41M
Noise $45M Taxiway $76M Apron $78M Runway Rehab$86M
Improve RSA$102M
Total: $470M
4Federal AviationAdministration
FAA Update
AIP Funding for FY10/11/12
$255M
$44M
$76M
$24M
$77M
$238M
$55M
$86M
$33M
$49M
$263M
$42M
$78M
$44M $43M
$0
$50
$100
$150
$200
$250
$300
CA NV AZ HI PAC
FY-10 FY-11 FY-12
5Federal AviationAdministration
FAA Update
AIP Performance Metric
By September 30th, grant disbursement rate should be as follow:
FY12 grants - 60%
FY11 grants - 81%
FY10 grants - 91%
FY09 grants - 96%
FY08 and older grants, close them.
6Federal AviationAdministration
FAA Update
OMB Target Balance Vs. Actual Regional Balance
Grant Year FY12 FY11 FY10 FY09
Target for July 43%Grant Balance
20%Grant Balance
10% Grant Balance
4% Grant Balance
AWP 64%Behind by $99M
20% 6%Ahead: $23M
2%Ahead by $6M
AAL 48% 12% 10% 4%
ACE 32% 14% 6% 2%
AEA 40% 14% 10% 1%
AGL 40% 11% 5% 3%
ANE 43% 13% 9% 1%
ANM 30% 7% 3% 1%
ASO 41% 23% 8% 2%
ASW 42% 20% 4% 2%
Note: Data is as of September 10, 2013.
7Federal AviationAdministration
FAA Update
Grant Payment Behind Schedule
8Federal AviationAdministration
FAA Update
Note: Data is as September 10, 2013.
State > 6 Months > 9 Months > 12 Months
Arizona 7 13 15
California 18 32 6
Nevada 3 3 5
Hawaii 1 5 1
Pacific Islands 1 1 0
Total: 30 54 27
Grants with No Payments
9Federal AviationAdministration
FAA Update
Inactive Grants(No Payments > 9 Months)
• FAA needs to explain to DOT reasons for keeping inactive grants open.
• Grant condition requires sponsors to complete projects without undue delay.
• Sponsors with inactive grants will be considered as elevated risk. (required additional documentation).
• Grant inactivity is a factor in considering future AIP grants with state apportionment and discretionary funding.
• FAA may pursue unilateral closeouts for inactive grants.
10Federal AviationAdministration
FAA Update
Important Dates for FY14
Events Due Dates
Environmental (FONSI, ROD, or CAT EX) December 2013
Application December 2013
Solicit Bids or Declare Carryover May 1
Grant Offers (approximate) June 15
Grant Execution (approximate) July 15
11Federal AviationAdministration
FAA Update
Are You Ready for FY14?
By 12/31/13 you have:
Planning complete
Project on an approved ALP
FAA environmental complete (FONSI, ROD, or submission of extraordinary circumstance form)
Airspace review and approval complete
Design complete and project ready for bid
12Federal AviationAdministration
FAA Update
Airport Environmental• Every AIP/PFC funding approval and Airport
Layout Plan approval requires environmental analysis under the National Environmental Policy Act.
• Action choices include:– A simple Categorical Exclusion with no further action
required– A Categorical Exclusion that requires a review of
possible extraordinary circumstances– An Environmental Assessment (EA)– An Environmental Impact Statement (EIS)
• We also are the FAA focal point for:– Title 14, CFR, Part 150, Airport Noise Compatibility
Planning– Title 14, CFR, Part 161, Notice of Approval of Airport
Noise and Access Restrictions
13Federal AviationAdministration
FAA Update
FY14 Environmental Deadline
Environmental documents should be completed by December 31, 2013
• Finding of No Significant Impact (FONSI) for Environmental Assessment (EA)
• Record of Decision (ROD) for Environmental Impact Statement (EIS)
• Submission of extraordinary circumstance form to support categorical exclusions.
14Federal AviationAdministration
FAA Update
Vehicle Pedestrian Deviations• We have already exceeded last years rate of Vehicle/Pedestrian Runway Incursions. Last
year we experience a significant reduction. We need your increased focus on this as we close FY 13 and begin FY 14.
Recommendations to Airport Operators:1.Train and re-train your staff who drive on the airport.2.Train and re-train your tenants.3.Make sure your tenants provide proper escorts for vehicles and pedestrians they give access. (There should be consequences for not doing so.)4.Conduct outreach/training for local Law Enforcement and First Responders (Airports are a different environment).5.Ensure Perimeter Fencing, access controls, and cautionary signage are maintained.6.“Change the Gate Code” regularly. If you have not done so recently, do it NOW!
15Federal AviationAdministration
FAA Update
Airport Capital Improvement Plan (ACIP)
• All proposed ACIP work elements must be reflected on an FAA Approved ALP.
• Your ACIP can include all AIP eligible projects for the 1-5 year planning time frame.
• Your ACIP should be properly sequenced.
• Expectation for AIP funding should be realistic. The ADO will only support justified projects.
16Federal AviationAdministration
FAA Update
3 Year Before Construction
• Scope the project
• Identify funding sources (AIP/PFC/State/Local)
• Identify NAVAIDS that might be affected
• Identify type of environmental review expected (CatEX, EA, EIS).
• Determine if ALP or Exhibit A needs updating
• Identify if Benefit Cost Analysis is appropriate
17Federal AviationAdministration
FAA Update
2 Year Before Construction
• Select consultant
• Initiate – Environmental review (CatEX, EA)
– Update ALP, Exhibit A, BCA
• Refine work scope and cost estimate
• Coordinate– NAVAIDS
– Instrument Approach Procedure
– Airspace, Air Traffic
18Federal AviationAdministration
FAA Update
1 Year Before Construction
• Solidify project scope
• Develop 90% plans and specification
• Update /revised cost estimates
• Finalize ALP update environmental review, BCA
• Review project schedule with FAA
• Be ready to accept grant the following year (based on bids)
19Federal AviationAdministration
FAA Update
National ADO Initiatives
• Geographic Balancing (Geo-balancing)– National redistribution of resources to better serve our
customers
– New Phoenix ADO to serve AZ and NV• Phoenix office will initially report to LAX ADO
– LAX and SFO ADOs will exclusively serve California
• National SOPs under development to create consistency among ADOs
20Federal AviationAdministration
FAA Update
Phoenix Field Office
• Office opened on November 19, 2012
• Currently operating as Phoenix Field Office
• Current staff: 1) Assistant Manager, 1) Program Specialist, 2) Planners, and 2) Engineers, 1) Environmental Protection Specialist, 1) Lead Engineer
• Phoenix ADO, when established, will also serve Nevada.
21Federal AviationAdministration
FAA Update
• Talk to us.
• Talk early.
• Plan ahead.
• Stay abreast of current regulation and guidance.
• Please talk to us before an issue becomes a problem!
Summary
22Federal AviationAdministration
FAA Update
Contact InformationMark McClardy, Division Manager
Western-Pacific Region (310) 725-3600
Mia Ratcliff, ManagerPlanning and Programming Branch (310) 725-3610
Brian Armstrong, ManagerSafety and Standards Branch (310) 725-3620
David Cushing, ManagerLos Angeles Airports District Office (310) 725-3644
Mike N Williams, Assistant ManagerPhoenix Field Office (602) 379-3021
Robin Hunt, ManagerSan Francisco Airports District Office (650) 827-7601
Ron Simpson, ManagerHonolulu Airports District Office (808) 541-1232
23Federal AviationAdministration
FAA Update
Questions?