FAA Update Airports Program

23
Presented to: By: Date: Federal Aviation Administration FAA Update Airports Program Western-Pacific Region Association of California Airports Arlene B. Draper September 13, 2013

description

FAA Update Airports Program. Western-Pacific Region. Association of California Airports. Arlene B. Draper. September 13, 2013. FAA Update. FY12 Program Highlights AIP Performance Metric Inactive Grants Are You Ready for FY14? Safety Initiatives Geo Balancing. - PowerPoint PPT Presentation

Transcript of FAA Update Airports Program

Page 1: FAA Update Airports Program

Presented to:

By:

Date:

Federal AviationAdministrationFAA Update

Airports Program

Western-Pacific Region

Association of California Airports Arlene B. Draper

September 13, 2013

Page 2: FAA Update Airports Program

2Federal AviationAdministration

FAA Update

FAA Update• FY12 Program Highlights• AIP Performance Metric• Inactive Grants• Are You Ready for FY14?• Safety Initiatives• Geo Balancing

Page 3: FAA Update Airports Program

3Federal AviationAdministration

FAA Update

FY12 AIP Projects Funded (Western-Pacific Region)

$0

$20

$40

$60

$80

$100

$120

Environmental /Planning $7M

Roads/Fencing$12M

Other $14M Navaids /Equipment $16

Building/Terminal$41M

Noise $45M Taxiway $76M Apron $78M Runway Rehab$86M

Improve RSA$102M

Total: $470M

Page 4: FAA Update Airports Program

4Federal AviationAdministration

FAA Update

AIP Funding for FY10/11/12

$255M

$44M

$76M

$24M

$77M

$238M

$55M

$86M

$33M

$49M

$263M

$42M

$78M

$44M $43M

$0

$50

$100

$150

$200

$250

$300

CA NV AZ HI PAC

FY-10 FY-11 FY-12

Page 5: FAA Update Airports Program

5Federal AviationAdministration

FAA Update

AIP Performance Metric

By September 30th, grant disbursement rate should be as follow:

FY12 grants - 60%

FY11 grants - 81%

FY10 grants - 91%

FY09 grants - 96%

FY08 and older grants, close them.

Page 6: FAA Update Airports Program

6Federal AviationAdministration

FAA Update

OMB Target Balance Vs. Actual Regional Balance

Grant Year FY12 FY11 FY10 FY09

Target for July 43%Grant Balance

20%Grant Balance

10% Grant Balance

4% Grant Balance

AWP 64%Behind by $99M

20% 6%Ahead: $23M

2%Ahead by $6M

AAL 48% 12% 10% 4%   

ACE 32% 14% 6% 2%   

AEA 40% 14% 10% 1%   

AGL 40% 11% 5% 3%   

ANE 43% 13% 9% 1%   

ANM 30% 7% 3% 1%   

ASO 41% 23% 8% 2%   

ASW 42% 20% 4% 2%

Note: Data is as of September 10, 2013.

Page 7: FAA Update Airports Program

7Federal AviationAdministration

FAA Update

Grant Payment Behind Schedule

Page 8: FAA Update Airports Program

8Federal AviationAdministration

FAA Update

Note: Data is as September 10, 2013.

State > 6 Months > 9 Months > 12 Months

Arizona 7 13 15

California 18 32 6

Nevada 3 3 5

Hawaii 1 5 1

Pacific Islands 1 1 0

Total: 30 54 27

Grants with No Payments

Page 9: FAA Update Airports Program

9Federal AviationAdministration

FAA Update

Inactive Grants(No Payments > 9 Months)

• FAA needs to explain to DOT reasons for keeping inactive grants open.

• Grant condition requires sponsors to complete projects without undue delay.

• Sponsors with inactive grants will be considered as elevated risk. (required additional documentation).

• Grant inactivity is a factor in considering future AIP grants with state apportionment and discretionary funding.

• FAA may pursue unilateral closeouts for inactive grants.

Page 10: FAA Update Airports Program

10Federal AviationAdministration

FAA Update

Important Dates for FY14

Events Due Dates

Environmental (FONSI, ROD, or CAT EX) December 2013

Application December 2013

Solicit Bids or Declare Carryover May 1

Grant Offers (approximate) June 15

Grant Execution (approximate) July 15

Page 11: FAA Update Airports Program

11Federal AviationAdministration

FAA Update

Are You Ready for FY14?

By 12/31/13 you have:

Planning complete

Project on an approved ALP

FAA environmental complete (FONSI, ROD, or submission of extraordinary circumstance form)

Airspace review and approval complete

Design complete and project ready for bid

Page 12: FAA Update Airports Program

12Federal AviationAdministration

FAA Update

Airport Environmental• Every AIP/PFC funding approval and Airport

Layout Plan approval requires environmental analysis under the National Environmental Policy Act.

• Action choices include:– A simple Categorical Exclusion with no further action

required– A Categorical Exclusion that requires a review of

possible extraordinary circumstances– An Environmental Assessment (EA)– An Environmental Impact Statement (EIS)

• We also are the FAA focal point for:– Title 14, CFR, Part 150, Airport Noise Compatibility

Planning– Title 14, CFR, Part 161, Notice of Approval of Airport

Noise and Access Restrictions

Page 13: FAA Update Airports Program

13Federal AviationAdministration

FAA Update

FY14 Environmental Deadline

Environmental documents should be completed by December 31, 2013

• Finding of No Significant Impact (FONSI) for Environmental Assessment (EA)

• Record of Decision (ROD) for Environmental Impact Statement (EIS)

• Submission of extraordinary circumstance form to support categorical exclusions.

Page 14: FAA Update Airports Program

14Federal AviationAdministration

FAA Update

Vehicle Pedestrian Deviations• We have already exceeded last years rate of Vehicle/Pedestrian Runway Incursions. Last

year we experience a significant reduction. We need your increased focus on this as we close FY 13 and begin FY 14.

Recommendations to Airport Operators:1.Train and re-train your staff who drive on the airport.2.Train and re-train your tenants.3.Make sure your tenants provide proper escorts for vehicles and pedestrians they give access. (There should be consequences for not doing so.)4.Conduct outreach/training for local Law Enforcement and First Responders (Airports are a different environment).5.Ensure Perimeter Fencing, access controls, and cautionary signage are maintained.6.“Change the Gate Code” regularly. If you have not done so recently, do it NOW!

Page 15: FAA Update Airports Program

15Federal AviationAdministration

FAA Update

Airport Capital Improvement Plan (ACIP)

• All proposed ACIP work elements must be reflected on an FAA Approved ALP.

• Your ACIP can include all AIP eligible projects for the 1-5 year planning time frame.

• Your ACIP should be properly sequenced.

• Expectation for AIP funding should be realistic. The ADO will only support justified projects.

Page 16: FAA Update Airports Program

16Federal AviationAdministration

FAA Update

3 Year Before Construction

• Scope the project

• Identify funding sources (AIP/PFC/State/Local)

• Identify NAVAIDS that might be affected

• Identify type of environmental review expected (CatEX, EA, EIS).

• Determine if ALP or Exhibit A needs updating

• Identify if Benefit Cost Analysis is appropriate

Page 17: FAA Update Airports Program

17Federal AviationAdministration

FAA Update

2 Year Before Construction

• Select consultant

• Initiate – Environmental review (CatEX, EA)

– Update ALP, Exhibit A, BCA

• Refine work scope and cost estimate

• Coordinate– NAVAIDS

– Instrument Approach Procedure

– Airspace, Air Traffic

Page 18: FAA Update Airports Program

18Federal AviationAdministration

FAA Update

1 Year Before Construction

• Solidify project scope

• Develop 90% plans and specification

• Update /revised cost estimates

• Finalize ALP update environmental review, BCA

• Review project schedule with FAA

• Be ready to accept grant the following year (based on bids)

Page 19: FAA Update Airports Program

19Federal AviationAdministration

FAA Update

National ADO Initiatives

• Geographic Balancing (Geo-balancing)– National redistribution of resources to better serve our

customers

– New Phoenix ADO to serve AZ and NV• Phoenix office will initially report to LAX ADO

– LAX and SFO ADOs will exclusively serve California

• National SOPs under development to create consistency among ADOs

Page 20: FAA Update Airports Program

20Federal AviationAdministration

FAA Update

Phoenix Field Office

• Office opened on November 19, 2012

• Currently operating as Phoenix Field Office

• Current staff: 1) Assistant Manager, 1) Program Specialist, 2) Planners, and 2) Engineers, 1) Environmental Protection Specialist, 1) Lead Engineer

• Phoenix ADO, when established, will also serve Nevada.

Page 21: FAA Update Airports Program

21Federal AviationAdministration

FAA Update

• Talk to us.

• Talk early.

• Plan ahead.

• Stay abreast of current regulation and guidance.

• Please talk to us before an issue becomes a problem!

Summary

Page 22: FAA Update Airports Program

22Federal AviationAdministration

FAA Update

Contact InformationMark McClardy, Division Manager

Western-Pacific Region (310) 725-3600

Mia Ratcliff, ManagerPlanning and Programming Branch (310) 725-3610

Brian Armstrong, ManagerSafety and Standards Branch (310) 725-3620

David Cushing, ManagerLos Angeles Airports District Office (310) 725-3644

Mike N Williams, Assistant ManagerPhoenix Field Office (602) 379-3021

Robin Hunt, ManagerSan Francisco Airports District Office (650) 827-7601

Ron Simpson, ManagerHonolulu Airports District Office (808) 541-1232

Page 23: FAA Update Airports Program

23Federal AviationAdministration

FAA Update

Questions?