Airports GIS | Update

22
1 Federal Aviation Administration Airports GIS | Airport Engineering and Planning in the NextGen World January 26, 2011 https://airports-gis.faa.gov/ Airports GIS | Update Presented to | Nebraska Aviation Symposium January 2011 Robert Bonanni, National Resource, AAS-101 Date | Wednesday: January 26, 2011

description

Airports GIS | Update. Presented to | Nebraska Aviation Symposium January 2011 Robert Bonanni, National Resource, AAS-101 Date | Wednesday: January 26, 2011. Why Did FAA Create Airports GIS?. Improve Efficiencies Airports, FAA, consultants Single, authoritative, accessible data source - PowerPoint PPT Presentation

Transcript of Airports GIS | Update

Page 1: Airports GIS | Update

1 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Update

Presented to | Nebraska Aviation Symposium January 2011

Robert Bonanni, National Resource, AAS-101

Date | Wednesday: January 26, 2011

Page 2: Airports GIS | Update

2 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Why Did FAA Create Airports GIS? Improve Efficiencies

‣ Airports, FAA, consultants‣ Single, authoritative, accessible data source

Reduce Costs to all Stakeholders Improve Safety

‣ Increased need for real-time data accuracy Support New Initiatives – Next Generation of Air

Transportation (NextGen)‣ A repository of airport information (not just survey data)

A true paradigm shift in the way we do business… in the right direction

Page 3: Airports GIS | Update

3 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS

othermodulesother

modules

PlanningModulePlanning

Module

AirportsGIS

AirportsGIS

O U T P U T

Survey Data Collection

Airports GIS at a High Level

NFDC | eNASR data

Remote Sensing

Ground Surveys

$ $$ $

Natl Flt Procedures data

iOE/AAA data

electronic ALP Module

eNOTAMs Module *

NAVAIDS records/data **

Airport Design Module **

139 Inspections Module **

Misc Financial Modules **

Compatible Land Use Module **

Misc Engineering Modules **

Misc Environmental Modules **

Aerial Photos

Airport Planning

5010/NASR Data *

Airport Ops | NOTAMS *

Data | Other Agencies **

New Tech | LiDAR/GPS **Data Transformation

Reduced Redundancy

Reduced Costs

* In Development | ** Planned

I N P U T

Data Standards• Collection• Input

AC150/ 5300-16,-17,-18

Page 4: Airports GIS | Update

4 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | End State

Other Modules

PlanningModule

AirportsGIS

FAA LOBs

Agencies

Industry

Airports

APPLY PUBLISHUSECOLLECT STORECHECK

DATA COLLECTION SYSTEM DEPLOYMENT

Page 5: Airports GIS | Update

5 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Reality/Today

PlanningModule

AirportsGIS

FAA LOBs

Airports

APPLY PUBLISHUSECOLLECT STORECHECK

Development/Deployment Perspective: ATMs; PCs; FAX; Internet; e-mail; mobile phones; Google Earth

Page 6: Airports GIS | Update

6 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | FY09-10 Accomplishments Emphasis on Survey Standards (Advisory Circulars) and Airports GIS website

‣ 800+ projects in the system (includes LPV/WAAS) Airports GIS Programming (software, website, modules)

‣ Completed electronic ALP proof-of-concept (Sept 2009)‣ Transitioned from AIM to ARP (Fall 2010)‣ Deployed -18B schema templates (DWG, DGN, and SHP)

Outreach (on-going) and Training‣ Deployed web-based training (IDLE), FAQs, and Airports GIS Help Desk‣ ACC, ACI, AAAE, FAA conferences and workshops‣ Initiated: external training (ACC); internal training (6 Regions by end of CY10)

Initiated robust data collection/input efforts‣ Phase I – 7 Airports (SW and SO Regions); Phase II – 30 Airports (All Regions)‣ Increasing emphasis on Airports GIS deliverable for all projects‣ AIP Grant/PFC requirement to incorporate on virtually all projects‣ Obstruction surveys, construction projects, noise contours, land acquisition‣ “Tiger Team” deployed to reduce data verification delays

Issued Working Draft Guidance (see National Planning Website)‣ Strategic Plan created and in review (includes preliminary BCA results)‣ Transition Policy in review (target for implementation in Jan)

Page 7: Airports GIS | Update

7 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | FY2011 Priorities Implement Transition Policy and finalize Strategic Plan Business Case (and tie-in with other LOBs) Data Collection

‣ Complete Phase I pilot program; marked progress on Phase II‣ Fund additional robust data collection projects at high priority locations

Address Growing Pains >>> see next slide‣ Streamline data verification process (review: plans; control; imagery; data)‣ Improve website software and project flow (project/partial vs. airport-centric)‣ Complete deployable eALP module precursors (programming; beta-testing)‣ Incorporate lessons learned from pilot projects into Advisory Circulars (for

updating in FY2012) and programming Outreach and Training (on-going)

‣ Integrated Distance Learning Environment (IDLE)‣ Continue additional internal/external workshops and outreach efforts‣ Explanation of ROIs to airport community (from FAA field personnel)‣ Begin planning for resident training course at FAA Academy

Page 8: Airports GIS | Update

8 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Addressing Immediate ChallengesAPPLY PUBLISHUSECOLLECT STORECHECK

AirportsGIS

FAA LOBs

Airports

Enhanced dataverification process

ImprovedWeb Portal

Cost Drivers; Timing

eALPbeta

TransitionPolicy (forall Airportcategories)

Page 9: Airports GIS | Update

9 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS Transition Policy | Premise Airports GIS ACs were applied too broadly too quickly Estimated 4,000 projects per year (staff is already very busy) One size of requirement does not fit all project types Industry and FAA have a steep learning curve Airports GIS system and processes not ready to handle demand ACs have kinks that need to be worked outTransitioning is the key to realizing program (and NextGen) benefits Program requirements need to be transitioned in practically Phased in to airports by size and relevance to NAS Enforce compliance as appropriate by project Improve awareness, education and support

Page 10: Airports GIS | Update

10 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Transition Policy | Proposed Next Steps1. Initiate/enforce requirements when there is a “triggering event”

‣ Any change to safety critical data, such as:• New or lengthened runway• Instrument procedure design

‣ Master Plan / eALP update

2. Then phase in (by relevance to NAS)‣ Large/Medium Hubs: Now (FY10-11)‣ Small/Non Hubs: 1 year (FY12)‣ Top Non Primary: 2 years (FY13)‣ Middle Tier GA: 3 Years (FY14)‣ Lower Tier GA: 4 Years (FY15)

Meanwhile, encourage the use of CADD standards identified in -18

draft Transition Policy | 2½ pages• 67 comments from the field!• 11 comments from APP-1/AAS-1

Page 11: Airports GIS | Update

11 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Transition Policy | draft TimelineFY10 FY11 FY12 FY13 FY14 FY15

IDLESupport

Awareness

Outreach &Education

APP Policy

Revise AC-18New Tech

Prioritized Verification

“Right-Size”requirements

Data Verification(where necessary)

B

Large & Medium Hub AirportsSmall and Non Hub Airports

Top Non-PrimaryMiddle Tier GA*

Other GA*Phase In by

Airport Hub Size and Relevance

Unless Triggering Event&

Encourage CAD ComplianceA

CToday

Appox. level of effort

Page 12: Airports GIS | Update

12 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Working Draft Policy | Potential Near-Term Updates Update to incorporate adoption of Transition Policy Identify data required (or optional) by project type Define where data is relevant and collected Update changes to data verification process

‣ NGS only verifies data for procedure design‣ FAA/airport verifies data for planning and identification

Reevaluate accuracy requirements Enable the use of more cost effective technology

(satellite and LiDAR)

Consider Field sentiment | enable the Regions to “right size” the requirements to their specific project needs

Page 13: Airports GIS | Update

13 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Looking Forward | eALP Transition

2011-2012 2015 +

‣ Airports GIS data collection and submittal

‣ Sponsor/FAA access to data through Airports GIS

‣ Legacy ALP (paper or PDF)‣ Legacy ALP coordination

and approval process

‣ Airports GIS data collection and submittal

‣ Sponsor/FAA access to data through Airports GIS

‣ Electronic Signatures (submittal and approval)

‣ eALP (geo-referenced PDF) with legacy ALP review and approval process

‣ Airports GIS data collection and submittal

‣ Sponsor/FAA access to data through Airports GIS

‣ Electronic eALP submittal‣ Electronic eALP review and

approval through Airports GIS

‣ Geo-referenced PDF (for use outside Airports GIS)

Today End StateNear Term

2012-2015

Limited e-Capability Optimized EfficiencyIncreasing Efficiency

Page 14: Airports GIS | Update

14 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Lessons Learned / Using Airports GIS | DFW

DFW: LIVE Parking Status DFW: Flight Track Analysis

Page 15: Airports GIS | Update

15 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Business Case Analysis (BCA) The FAA Office of Airports is preparing a Business Case Analysis for Airports

GIS.

Data and conclusions from the Business Case Analysis will be used to further guide the development and implementation processes of Airports GIS based on a review of the eALP Pilot Program and general lessons learned.

We also want to better understand the full potential use of the data collected as part of the Airports GIS program, including internal and external FAA uses, and data that will be used in support of NextGen. For example, the Business Case Analysis will be used to provide financial data for the FAA’s Investment Analysis of its Aeronautical Information Management (AIM).

‣ AIM is the FAA source for collecting, validating, storing, maintaining, and disseminating aeronautical data concerning the United States and its territories to support real-time aviation activities.

Page 16: Airports GIS | Update

16 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Business Case Analysis | NextGen Airport GIS provides accurate and up-to-date maps of airport facilities

and equipment that is essential to NextGen systems and capabilities. As a result, Airports GIS is a key enabler for NextGen implementation.

FAA office of Airports (ARP) is supporting the development of such a NextGen capability through the collection, formatting, and uploading of airport and aeronautical data as specified in the Airport Surveying-GIS Program.

Because Airports GIS is part of NextGen, the Benefit Case Analysis must follow the general guidelines of the FAA Acquisition Management Policy (AMP) and Financial Investment Process. The BCA is being prepared in parallel to the Investment Analysis being conducted for AIM.

Page 17: Airports GIS | Update

17 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Business Case Analysis | Capabilities Key system capabilities/data to be assed in the BCA:

‣ Improved Collaboration: Immediately share comments and questions with FAA, airport, and consultant stakeholders for more efficient and effective resolution.

‣ Thorough Analysis: Measure heights, distances, and clearances of runways, taxiways, obstacles and other features in comparison with design standards.

‣ Access to Multiple Sources of Information: Gain one-stop access to a variety of airport mapping, operations, financial, and other data sources.

‣ Better Decisions: interpret information and make decisions (e.g. flight procedure minimums, protected critical areas, modifications to standards, and other safety determinations) faster and with greater confidence because data is consistently presented, current, comprehensive, and assured to be the required quality.

Page 18: Airports GIS | Update

18 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | How will GIS help us do our job better and how often will we use Airports GIS data?

Grant Review and Approval Project Eligibility Requirements Compatible Land Use Master Plans/ALP Obstruction Evaluation (OE)

Database/Airspace Determination

Runway Safety Area Determination

• Airports GIS will provide data to support airport construction, land-use planning, environmental compliance, categorical exclusions, recording of NAVAID records, 3-D visualization, and integration into other GIS efforts.

• Think about how we currently refer to geospatial data/maps related to: Environmental/NEPA Design Review Conformity to Plans and

Specifications (As-Builts) Safety and Construction Phasing Compliance/Grant Obligations Land Acquisition

Page 19: Airports GIS | Update

19 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

NextGen | Can you see the connection to Airports GIS data?

Page 20: Airports GIS | Update

20 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

NextGen | Can you see the connection to Airports GIS data?

Page 21: Airports GIS | Update

21 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Airports GIS | Measure and Quantify the Benefits

Our focus can shift from processing data to using data to make informed decisions in a more timely manner. ‣ Primary benefactors

• External | Airport Sponsors• External | Airport Consultants (primarily A&E firms)• Internal | ARP personnel• Internal | Other FAA Lines of Business

‣ Types of benefits• Efficiency Benefits (i.e. Time/Cost Savings)• Effectiveness Benefits

Page 22: Airports GIS | Update

22 Federal AviationAdministration

Airports GIS | Airport Engineering and Planning in the NextGen WorldJanuary 26, 2011 https://airports-gis.faa.gov/

Thank You: Questions Welcome!