1 WATER CORPORATION OF ODISHA OFFICE OF THE MANAGING DIRECTOR, WATCO Ground Floor, Unnati Bhawan H.B. Colony, Satyanagar, Bhubaneswar-751007, Odisha, India Telefax: +91-674-2391444 E Mail: [email protected], [email protected] Expression of Interest (EOI) Invited From Consultancy Firms in the field of Preparation of Feasibility Report/DPR and Providing PMC services for implementation of 24X7 Water Supply Systems March 2020

Transcript of Expression of Interest (EOI) Invited

Page 1: Expression of Interest (EOI) Invited

1

WATER CORPORATION OF ODISHA OFFICE OF THE MANAGING DIRECTOR, WATCO

Ground Floor, Unnati Bhawan H.B. Colony, Satyanagar, Bhubaneswar-751007,

Odisha, India Telefax: +91-674-2391444

E Mail: [email protected], [email protected]

Expression of Interest (EOI) Invited

From Consultancy Firms in the field of Preparation of Feasibility

Report/DPR and Providing PMC services for implementation

of 24X7 Water Supply Systems

March 2020

Page 2: Expression of Interest (EOI) Invited

2

CONTENTS

S. NO. CONTENTS PAGE NO.

1 Disclaimer 3

2 EOI 4-5

3 EOI Document 6-9

4 Annexures 10-38

Page 3: Expression of Interest (EOI) Invited

3

Disclaimer

This EOI Document has been prepared by Managing Director WATCO, Odisha, Bhubaneswar solely for the purpose of gathering valuable information and inputs from experienced and reputed consultancy firms having consistent and outstanding track record in the field of preparation of Feasibility report/DPR and providing PMC services for implementation of 24X7 water supply systems in India/abroad. This is a knowledge sharing exercise for going to the subsequent stage of EOI process.

The information contained in this EOI document (the “EOI”) or subsequently provided to the Consultancy Firms, whether verbally or in documentary or any other form by or on behalf of WATCO or any of their employees or advisors, is provided to Consultancy Firms on the terms and conditions set out in this EOI and such other terms and conditions subject to which such information is provided.

This EOI is neither a bid nor an agreement and is neither an offer nor invitation by

“WATCO” to the Consultancy Firms. The purpose of this EOI, is to provide interested

Consultancy Firms with information that may be useful to them, for sharing credible and valuable information related to their experience, expertise and success stories in the field of preparation of Feasibility Reports/DPRs together with providing PMC services for implementation of 24X7 water supply systems in India/abroad and presenting the same through interactive session during Video Conference pursuant to this EOI.

The issue of this EOI does not imply that “WATCO” is bound to select any of the

participating consultancy firm for the upcoming consultancy assignments nor is an indication in any way of their qualification at the EOI stage. The Consultancy firm shall bear all its costs associated with or relating to the preparation and submission of its EOI including but not limited to preparation, copying, postage, delivery fees, expenses associated with any demonstrations or presentations which may be required by “WATCO” or any other costs

incurred in connection with or relating to its EOI. All such costs and expenses will remain with the consultancy firm and “WATCO” shall not be liable in any manner whatsoever for the

same or for any other costs or other expenses incurred by a consultancy firm in preparation or submission of the EOI.

*****

Page 4: Expression of Interest (EOI) Invited

4

WATER CORPORATION OF ODISHA

OFFICE OF THE MANAGING DIRECTOR, WATCO Ground

Floor, Unnati Bhawan

Near Satyanagar Fly Over Bridge, Bhubaneswar-751001,

Odisha, India

Telefax: +91-674-2391444

E Mail: [email protected], [email protected]

EOI Identification No MD, WATCO-02- 19/20 Dated:20.03.2020

WATCO No.679 Date:20.03.2020

EXPRESSION OF INTEREST (EOI)

The MANAGING Director, WATCO, Bhubaneswar on behalf of the Governor of Odisha invites Expression of Interest (EOI) in conformity with the detailed EOI document, from experienced and reputed consultancy firms for the purpose of gathering valuable information and inputs in the field of preparation of Feasibility report/DPR and providing PMC services for implementation of 24X7 water supply systems in India/abroad. The EOI can be downloaded from WATCO website www.watcoodisha.in and completed document can be sent by E-mail/hard copy as per details provided in the EOI document. Processing fee of Rs.5000/- shall be deposited as provided in the EOI document.

Last date & time for EOI download : 30.03.2020 up to 5.00 PM

Last date and time for submission of EOI document : 03-04-2020 up to 5.00PM

Date of Video Conference Meeting : will be intimated to eligible firms after 03.04.2020

Name & Address of the Officer Inviting EOI:

Managing Director, WATCO, OFFICE OF THE MANAGING DIRECTOR, WATCO Ground Floor, Unnati Bhawan H.B. Colony, Satyanagar, Bhubaneswar-751007, Odisha, India Telefax: +91-674-2391444, E Mail: [email protected], [email protected]

Sd/- Managing Director, WATCO

Copy to:-

1. Copy along with soft copy forwarded to the Deputy Director (Advt.) and Deputy Secretary to Govt., Information & Public Relation Deptt., Odisha, Bhubaneswar for information with a request to arrange immediate publications of the “Expression of

Page 5: Expression of Interest (EOI) Invited

5

Interest” (EoI)” for one day in 1 (one) English National News Paper all editions in addition to one leading Oriya daily. It is requested to ensure the publication of above EoI notice on or before 23.03.2020. The payment for publishing the same in the above

mentioned newspapers will be borne by this office, if the same cannot be borne by the I&PR Deptt. Copies of the newspapers featuring publication of the notice may please be sent to this office for necessary action. Encl: As above

2. Principal Secretary cum Chairman, WATCO, Bhubaneswar for favour of kind information.

3. Engineer-in-chief, PH, Odisha for favour of kind information.

4. Copy with Soft Copy of the EoI forwarded to the PMC WATCO, Bhubaneswar for display in the WATCO website http:www.watcoodisha.in on or before

23.03.2020.

Sd/- Managing Director, WATCO

Page 6: Expression of Interest (EOI) Invited

6

WATER CORPORATION OF ODISHA

OFFICE OF THE MANAGING DIRECTOR, WATCO Ground

Floor, Unnati Bhawan

H.B. Colony, Satyanagar, Bhubaneswar-751007,

Odisha, India

Telefax: +91-674-2391444 E Mail: [email protected], [email protected]

EXPRESSION OF INTREST (EOI)

WATCO invites Expression of Interest (EOI) from reputed, experienced and eligible consultancy firms having consistent and outstanding track record in the field of preparation of Feasibility report/DPR and providing Project Management Consultancy (PMC) services for implementation of 24X7 water supply systems in India/abroad, solely for the purpose of gathering valuable information, inputs and learning experience for utilizing the same in the next level of bidding process.

The Odisha Mineral Bearing Areas Development Corporation (OMBADC) has

sanctioned funds for providing 24X7 water supply system in selected 14 urban

local bodies of Odisha which are presently served with the intermittent water

supply. The primary objectives of providing 24X7 water supply are: 1) It is

reliable: 24x7 water supply reduces the time and money spent by citizens to

store water 2) Pressurized system, thus eliminates chances of pollution, 3).

Continuous water supply thus helps keep water clean and safe for consumers.

The salient features of existing water supply systems in these ULBs is attached at

Annexure-I and II.

Successful Implementation of the 24X7 water supply system would require

selection of expert and experienced consultancy farms having consistent and

outstanding track record in the field of providing PMC services from concept to

commissioning of 24X7 water supply systems in India/abroad. The PMC services

broadly encompass preparation of feasibility report/DPR , bid process

management for selection of civil contractor, project management services during

construction, commissioning and during 1st year of O&M of the project. It is

therefore absolutely necessary to scan through the market to know about

experience, expertise and success stories of the consultancy firms who have

provided consultancy services and steered successful implementation of 24X7

water supply systems in Indian towns and abroad.

Page 7: Expression of Interest (EOI) Invited

7

Expression of Interest therefore, is called by this notice from Consultancy Firms in

the field of Preparation of Feasibility Report/DPR and Providing PMC services

for implementation of 24X7 Water Supply Systems, to understand the potential

available in the market of such firms, learning about their experience and

expertise in having provided PMC services for successful execution and

commissioning of 24X7 water supply projects both in towns of India and abroad so

as to enable WATCO to formulate proper RFP document for selection of the

right type of consultancy firms to ensure successful implementation of the 24X7

water supply projects in the 14 ULBs.

A. Eligibility criteria and document submission requirement for participating in the EOI:

1. The Consultancy firms registered in India as per companies act and operational successfully for the last 10 years and registered under the taxation authorities of India(GST/IT) and having outstanding track record in the area of design and PMC services with special focus on 24X7 water supply system both in Indian towns and abroad demonstrating robust performance consistently in India. Company profile including Copies of MOA, registration certificates to be submitted.

2. Consultancy firms with average annual turnover of Rs.30 crores in last 5 years.

Copies of balance sheets to be furnished.

3. The Consultancy firm must have carried out (as a single entity) at least One work of Detailed Engineering, Design or PMC of 24 X 7 water supply works in India Internationally of cities / with at least 3 No. projects of 3000 connections.

OR

The Consultancy firm must have carried out (as a single entity) at least Three work of Detailed Engineering, Design or PMC of 24 X 7 water supply works in India or Internationally of cities / Towns of at least 1 (One) Lakh population. Experience certificates from the Government authorities from appropriate level shall be furnished justifying the above experience.

4. The Consultancy firm must not have been blacklisted or debarred or suspended from bidding in tendering process (either as single entity or as partner of JV) by any Govt. /Semi govt. Authority, Funding Agencies like World Bank/ADB/ JICA etc.) at the time of bidding. The debarred period shall not be valid at the time of bidding.

B. Technical Meeting cum presentation through Video Conferencing

Consulting firms qualifying the eligibility criteria shall be invited to participate in the Technical Meeting cum presentation trough Video conferencing to be held and date will be intimated in due course to eligible firms. The Video Conferencing details shall be intimated to the eligible firms by E-mail. The firms /their authorized technical team shall make a detailed presentation to cover the followings and participate in the

Page 8: Expression of Interest (EOI) Invited

8

interactive session with the technical team of WATCO/PHEO:

1. Company profile and credentials including financial and technical capability. 2. Organizational profile with resources available etc. 3. Present work load and status of the assignments 4. All completion certificates they have to demonstrate their capability including

past performance records in the field of 24X7 water supply systems in Indian towns/abroad.

5. Design and PMC experience in implementation of 24X7 water supply systems including success stories and failures, technology experience in 24X7 water supply systems etc. May also indicate on various software and hardwares, used by them.

6. Approach and methodology which they may conceive for doing a 24X7 water supply project from concept to commissioning.

7. Any other information they may like to share.

Each Manufacturer will be given 30 (thirty) minutes time for their presentation. They may share the hard copy and soft copy of the presentation by E mail before the Video-conferencing date.

C. SUBMISSION OF EOI:-

The EOI shall be submitted on line along with the documents cited above at clause A under eligibility criteria and non-refundable processing fees of Rs.5,000/- (Rupees Five thousand only) through electronic submission ( E-mail as well as hard copy by courier/registered post before the scheduled date of submission) as under:

The Consultancy Firm shall submit the processing fee amount electronically on or before the last date and time of the bid in Account Number 35406572672 at State Bank of India, HOD Branch, Bhubaneswar (IFSC /RTGS code No SBIN0010249) through the firm’s banker. Since the amount is less than Rs.one lac the same may be remitted through NEFT. EOI number shall be inserted before the beneficiary name and date & time of closing of bid should be inserted either before the Firm’s address or Firm’s name as shown below

Account No. ………

Beneficiary Name/in favour of ‹EOI No.›/ ‹Item No.› WATCO

Consultancy Firm’s name ‹Date and time of closing› Consultancy Firm’s name

Address ‹Consultancy Firm’s address›

i) The firm must upload the scanned copy of RTGS/NEFT customer confirmation

in place of DD/Pay order along with the EOI document before the date and time of closing of the receipt of the EOI. If processing fee is transferred through online Banking, confirmation receipt indicating transaction number should be mentioned.

v) Processing fee received without complying with above instructions shall be

liable for rejection.”

Page 9: Expression of Interest (EOI) Invited

9

The EOI shall be received on stipulated date & in time. After scrutinizing the same, the EOIs confirming to the aforesaid criteria of processing fee and fulfilling the eligibility requirements shall be treated as 'Responsive' & it shall be communicated to them, about the date of technical presentation as mentioned in EOI. Consultancy Firms qualifying the eligibility requirement receiving intimation shall only attend the Video Conference based technical presentation meeting. The processing fee above is nonrefundable and nontransferable. EOI shall be submitted both through [email protected],

[email protected] (soft copy) and hard copy by speed post in the address given below:

To The Managing Director,

OFFICE OF THE MANAGING DIRECTOR, WATCO Ground

Floor, Unnati Bhawan, H.B. Colony, Satyanagar, Bhubaneswar-751007,

Odisha, India, Telefax: +91-674-2391444, E Mail: [email protected], [email protected]

Sd/-

Managing Director WATCO, Odisha, Bhubaneswar

Page 10: Expression of Interest (EOI) Invited

10

Annexure-I: Salient Information on population, coverage etc.

Sr. ULB Name -

District

P.H

Division

Popula

tion as

per

2011

Censu

s

Total

No of

wards

Coverage of

Wards

House Service

Connection

Stand

Posts

In use

Hand

pumps

and

Tube

Wells

No. Full Part Presen

t

Ongoin

g

connect

ions

1 Rourkela - Sundargarh

Rourkel

a

275121 40 23 17 29039 21063 1003 1839

2 Biramitrapur -

Sundargarh

33442 11 7 4 808 4738 113 311

3 Sundargarh -

Sundargarh

45036 19 11 8 3782 3997 123 321

4 Rajgangpur-

Sundargarh

51362 20 10 10 1900 5023 167 347

5 Baripada -

Mayurbhanj

Baripada 109743 28 25 3 12639 3200 456 367

6 Karanjia -

Mayurbhanj

22865 15 12 3 2210 1000 117 155

7 Rairangpur -

Mayurbhanj

25516 15 15 0 3066 801 173 230

8 Udala -

Mayurbhanj

13152 12 10 2 1221 2428 100 116

9 Anandapur -

Kendujhar

Keonjar 39585 16 15 1 2798 5192 386 360

10 Barbil -

Kendujhar

66540 15 11 4 2100 8813 139 38

11 Champua -

Kendujhar

10394 13 6 7 922 1276 8 131

12 Joda -

Kendujhar

46631 14 12 2 1021 6594 145 32

13 Keonjhar -

Keonjhar

60590 21 16 5 5708 6567 167 363

14 VyasaNagar- Jajpur

Cuttack Division-

II

48911 26 14 12 6812 567 250 127

Page 11: Expression of Interest (EOI) Invited

11

Status of urban water supply in Rourkela Water supply status as on 31.03.2019

Sl No.

Name of the Urban Local Body : Rourkela

1 Population as per census 2011 : 275121

2 Projected Population for 2019 : 322772

3 Source of water supply

(a) Surface Source : River Brahmani & Koel

(b) Ground Source (Production wells) : 0 4 Present demand of water supply (in MLD) : 50.03

5 Present level of water supply (in MLD) : 56.2

6 Present rate of supply (in LPCD) : 174

7 Ward wise coverage information 0

(a) Total number of wards: : 40

(b) Fully covered : 23

(c) Partly covered : 17

(d) Uncovered : 0

8 Total number of House connections : 29039

9 Total number of Stand posts : 1003

10 Total number of running Hand pump tube Wells : 1839

Page 12: Expression of Interest (EOI) Invited

12

Name of the ULB: ___________Rourkela___________

Infrastructure

S No.

Details of infrastructure

Existing as on

31.03.2019

Ongoing / To be completed under

Action Plan 2019-20

(Infrastructure

to be added during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with yield in MLD

2. No. of intake wells

Nil

4 Nos

Nil

1 No (AMRUT)

Nil

5 Nos

2 Treatment -

WTPs with capacity in MLD

6 Nos – 79.50 MLD

1 No - 5.00 MLD (AMRUT)

84.50 MLD

3 Storage - ESRs – No.s with capacity

10 Nos- 5.40 ML

(3 Nos-1.43 MLAMRUT 12 Nos-7.00 ML-UIDSSMT 1 No- 0.90 ML-OMBADC 7 Nos- 5.50 ML-SP)

23 Nos 14.83 ML

20.23 ML

4 Storage - GSR/OGR/GLSRs-

No.s with capacity

21 Nos –

18.19 ML

(5 Nos- 2.00 ML-AMRUT 11 Nos-5.00 ML UIDSSMT 2 Nos - 1.00 ML- SP)

18 Nos- 8.00 ML

26.19 ML

5 Distribution – Length of pipeline

in km

288.28 K.M

( 95.24 KM-AMRUT 186.47 KM- UIDSSMT 130.00 KM-SP)

416.71 K.M

704.99 K.M

6 Rising Main –

Length of pipeline in km

25.05 K.M

17.07 KM-AMRUT

12.34 KM-UIDSSMT 29.41 K.M

54.46 K.M

7 House hold connections

29,039 Nos 21,063 Nos 50,102 Nos

Page 13: Expression of Interest (EOI) Invited

13

Status of urban water supply in Sundargarh Water supply status as on 31.03.2019

Sl No.

Name of the Urban Local Body : Sundargarh

1 Population as per census 2011 : 45036

2 Projected Population for 2019 : 55419

3 Source of water supply

(a) Surface Source : River “IB”

(b) Ground Source (Production wells) : 0 4 Present demand of water supply (in MLD) : 8.59

5 Present level of water supply (in MLD) : 5.39

6 Present rate of supply (in LPCD) : 97

7 Ward wise coverage information 0

(a) Total number of wards: : 19

(b) Fully covered : 11

(c) Partly covered : 8

(d) Uncovered : 0

8 Total number of House connections : 3782

9 Total number of Stand posts : 123

10 Total number of running Hand pump tube Wells : 321

Page 14: Expression of Interest (EOI) Invited

14

Name of the ULB: ____Sundargarh__________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action Plan 2019-20

(Infrastructure to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source –

No. of Production wells with yield in MLD

No. of intake wells

Nil

1 No

Nil

Nil

Nil

1 No

2 Treatment - WTPs with

capacity in MLD

2 Nos - 4.50

MLD

1 No - 7.50 MLD

(DMF)

12.00 MLD

3 Storage -

ESRs – No.s with capacity

2 Nos 0.425 ML

(1 No- 0.090 ML-

SDPDS 3 Nos-1.08 ML DMF)

4 Nos – 1.17 ML

1.595 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

1 Nos- 2.65 ML

1 No - 0.650 ML (DMF)

3.300 ML

5 Distribution – Length of pipeline in km

31.71 K.M

(92.93 KM (DMF) 33.218 KM (SDPDS)

126.148 K.M

157.858

K.M

6 Rising Main –

Length of pipeline in km

2.10 K.M

5.57 KM (DMF)

4.07 KM (SDPDS) 9.64 K.M

11.74 K.M

7 House hold

connections

3782 Nos 3997 Nos

7779 Nos

Page 15: Expression of Interest (EOI) Invited

15

Status of urban water supply in Rajgangpur Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Rajgangpur

1 Population as per census 2011 : 51362

2 Projected Population for 2019 : 51963

3 Source of water supply

(a) Surface Source : Nakti Nalla

(b) Ground Source (Production wells) : 0 4 Present demand of water supply (in MLD) : 8.05

5 Present level of water supply (in MLD) : 3.2

6 Present rate of supply (in LPCD) : 62

7 Ward wise coverage information 0

(a) Total number of wards: : 20

(b) Fully covered : 10

(c) Partly covered : 10

(d) Uncovered : 0

8 Total number of House connections : 1900

9 Total number of Stand posts : 167

10 Total number of running Hand pump tube Wells : 347

Page 16: Expression of Interest (EOI) Invited

16

Name of the ULB: ________Rajgangpur______________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with

yield in MLD 2. No. of intake

wells

Nil

Nil

Nil

1 No (DMF)

Nil

1 No

2 Treatment - WTPs with capacity in MLD

1 No - 6.00

MLD

1 No - 6.50 MLD

(DMF)

12.50 MLD

3 Storage - ESRs – No.s with

capacity

1 No- 0.225

ML

4 Nos – 1.56 ML

(DMF)

1.785 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

3 Nos- 0.225 ML

1 No- 2.00 ML (DMF)

2.675 ML

5 Distribution – Length of pipeline

in km

21.32 K.M

91.446 K.M (DMF)

112.766

K.M

6 Rising Main – Length of pipeline in km

25.95 K.M

6.485 K.M (DMF)

32.435

K.M

7 House hold connections

1900 Nos 5023 Nos

6923 Nos

Page 17: Expression of Interest (EOI) Invited

17

Status of urban water supply in Biramitrapur Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Biramitrapur

1 Population as per census 2011 : 33442

2 Projected Population for 2019 : 37056

3 Source of water supply

(a) Surface Source : “B” Quarry & Kanshabahal

Quarry (b) Ground Source (Production wells) : 0 4 Present demand of water supply (in MLD) : 5.74

5 Present level of water supply (in MLD) : 2.16

6 Present rate of supply (in LPCD) : 58

7 Ward wise coverage information 0

(a) Total number of wards: : 11

(b) Fully covered : 7

(c) Partly covered : 4

(d) Uncovered : 0

8 Total number of House connections : 808

9 Total number of Stand posts : 113

10 Total number of running Hand pump tube Wells : 311

Page 18: Expression of Interest (EOI) Invited

18

Name of the ULB: ___Biramitrapur___________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with

yield in MLD 2. No. of intake

wells

Nil

Nil

Nil

1 No

Nil

1 No

2 Treatment - WTPs with capacity in MLD

1 No -0.50

MLD

1 No -7.00 MLD

(DMF)

7.50 MLD

3 Storage - ESRs – No.s with

capacity

Nil

2 Nos- 1.50 ML

(DMF)

1.50 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

3 Nos – 0.33

ML

1 No -0.70 ML

(DMF)

1.03 ML

5 Distribution – Length of pipeline

in km

11.15 K.M

32.59 K.M (DMF)

43.74 K.M

6 Rising Main – Length of pipeline in km

7.50 K.M

23.57 K.M (DMF)

31.07 K.M

7 House hold connections

808 Nos 4738 Nos

5546 Nos

Page 19: Expression of Interest (EOI) Invited

19

Status of urban water supply in Baripada Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Baripada

1 Population as per census 2011 : 109743

2 Projected Population for 2019 : 123364

3 Source of water supply

(a) Surface Source : River Chipat

(b) Ground Source (Production wells) : 75 4 Present demand of water supply (in MLD) : 19.12

5 Present level of water supply (in MLD) : 17.34

6 Present rate of supply (in LPCD) : 141

7 Ward wise coverage information 0

(a) Total number of wards: : 28

(b) Fully covered : 25

(c) Partly covered : 3

(d) Uncovered : 0

8 Total number of House connections : 12639

9 Total number of Stand posts : 456

10 Total number of running Hand pump tube Wells : 367

Page 20: Expression of Interest (EOI) Invited

20

Name of the ULB: ___Baripada___________________

Infrastructure

S No.

Details of infrastructure

Existing as on 31.03.2019

Ongoing / To be completed during

Action Plan 2019-20

(Infrastructure to

be added during

2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of Production

wells with yield in MLD

75 nos 13.04 MLD

_

75 nos 13.04 MLD

2. No. of intake wells

_ 1 no taken up under BSRJ which is

scheduled to be completed in 2020-21

1 no

2 Treatment -

WTPs with capacity in MLD

1no - 9 MLD 1 no of 16 MLD

capacity taken up under BSRJ which is scheduled to be

completed in 2020-21

2 nos

25.0 MLD

3 Storage - ESRs – No.s with

capacity

3nos - 0.9 ML 6 nos - 4.70 ML capacity taken up

under BSRJ which is scheduled to be completed in 2020-

21

9 nos 5.60 ML

4 Storage - GSR/OGR/GLSRs- No.s

with capacity

12 nos 2.90 ML

4 Nos-1.575 MLD 16 nos 4.475 MLD

5 Distribution – Length of pipeline in km

142.41KM 122.64KM 265.05 KM

6 Rising Main – Length of pipeline in km

3.79Km 25.13KM 28.92 KM

7 House hold connections

12639 nos 3200 nos 15839 nos

Page 21: Expression of Interest (EOI) Invited

21

Status of urban water supply in Rairangpur Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Rairangpur

1 Population as per census 2011 : 25516

2 Projected Population for 2019 : 28891

3 Source of water supply

(a) Surface Source : River Khadkhai.

(b) Ground Source (Production wells) : 29 4 Present demand of water supply (in MLD) : 4.48

5 Present level of water supply (in MLD) : 3.32

6 Present rate of supply (in LPCD) : 115

7 Ward wise coverage information 0

(a) Total number of wards: : 15

(b) Fully covered : 15

(c) Partly covered : 0

(d) Uncovered : 0

8 Total number of House connections : 3066

9 Total number of Stand posts : 173

10 Total number of running Hand pump tube Wells : 230

Page 22: Expression of Interest (EOI) Invited

22

Name of the ULB: ______Rairangpur________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To

be completed during Action Plan 2019-20

(Infrastructure to be added

during 2019-

20)

Total

1 2 3 4 5

[3]+[4]

1 Source – 1. No. of Production

wells with yield in MLD

29 nos 1.65MLD

-

29 nos 1.65MLD

2. No. of intake wells

2 nos 3.0 MLD

- 2 nos 3.0 MLD

2 Treatment - WTPs with capacity in MLD

1 no 3.00MLD

- 1 no 3.0 MLD

3 Storage -

ESRs – Nos with capacity

1 no

0.227 ML

- 1 no

0.227 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

6nos 1.456 MLD

- 6nos 1.456 MLD

5 Distribution – Length of pipeline in

km

74.46KM - 74.46KM

6 Rising Main –

Length of pipeline in km

4.55Km - 4.55Km

7 House hold connections

3066 nos 801 nos 3867 nos

Page 23: Expression of Interest (EOI) Invited

23

Status of urban water supply in Udala Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Udala

1 Population as per census 2011 : 13152

2 Projected Population for 2019 : 14446

3 Source of water supply

(a) Surface Source : River Sono.

(b) Ground Source (Production wells) : 7 4 Present demand of water supply (in MLD) : 2.24

5 Present level of water supply (in MLD) : 1.97

6 Present rate of supply (in LPCD) : 136

7 Ward wise coverage information 0

(a) Total number of wards: : 12

(b) Fully covered : 10

(c) Partly covered : 2

(d) Uncovered : 0

8 Total number of House connections : 1221

9 Total number of Stand posts : 100

10 Total number of running Hand pump tube Wells : 116

Page 24: Expression of Interest (EOI) Invited

24

Name of the ULB: ______Udala________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed during Action Plan 2019-20

(Infrastructure to be added

during 2019-20)

Total

1 2 3 4 5

[3]+[4]

1 Source – 1. No. of Production

wells with yield in

MLD

7 nos 0.89 MLD

5 nos 0.32 MLD

12 nos 1.21 MLD

2. No. of intake wells

1No 1.5 ML

_

1No 1.5 ML

2 Treatment - WTPs with capacity in

MLD

1No 1.5 MLD

_

1No 1.5 MLD

3 Storage -

ESRs – Nos with capacity

1no

0.10 ML

_

1No

0.10 ML

4 Storage - GSR/OGR/GLSRs- Nos with capacity

5nos 0.94 ML

_

1No 0.94 ML

5 Distribution – Length of pipeline in km

53.45 Km _

53.45 Km

6 Rising Main –

Length of pipeline in km

1.60 Km _

1.60 Km

7 House hold connections

1221 nos 2428 nos 3649 nos

Page 25: Expression of Interest (EOI) Invited

25

Status of urban water supply in Karanjia Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Karanjia

1 Population as per census 2011 : 22865

2 Projected Population for 2019 : 24080

3 Source of water supply

(a) Surface Source : River Deo.

(b) Ground Source (Production wells) : 15 4 Present demand of water supply (in MLD) : 3.73

5 Present level of water supply (in MLD) : 2.09

6 Present rate of supply (in LPCD) : 87

7 Ward wise coverage information 0

(a) Total number of wards: : 15

(b) Fully covered : 12

(c) Partly covered : 3

(d) Uncovered : 0

8 Total number of House connections : 2210

9 Total number of Stand posts : 117

10 Total number of running Hand pump tube Wells : 155

Page 26: Expression of Interest (EOI) Invited

26

Name of the ULB: ______Karanjia________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed during Action Plan 2019-

20

(Infrastructure to be added during

2019-20)

Total

1 2 3 4 5

[3]+[4]

1 Source – 1. No. of Production

wells with yield in MLD

15 nos 1.13 MLD

02 nos 0.10 MLD

17 nos 1.23 MLD

2. No. of intake wells 1No 1.5 MLD

_ 1No 1.5 MLD

2 Treatment -

WTPs with capacity in MLD

1no

1.50 MLD

_ 1No

1.5 MLD

3 Storage - ESRs – No.s with capacity

_ _ _

4 Storage - GSR/OGR/GLSRs- No.s

with capacity

6nos 1.36 ML

_ _

5 Distribution – Length of pipeline in

km

50.4 3 Km _ 50.43 Km

6 Rising Main – Length of pipeline in km

3.20 Km _ 3.20Km

7 House hold connections

2210 nos 1000 nos 3210 nos

Page 27: Expression of Interest (EOI) Invited

27

Status of urban water supply in Keonjhar Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Keonjhar

1 Population as per census 2011 : 60590

2 Projected Population for 2019 : 68767

3 Source of water supply

(a) Surface Source : Sanamachhakandana Dam

& Kanjhari Dam (b) Ground Source (Production wells) : 18 4 Present demand of water supply (in MLD) : 10.66

5 Present level of water supply (in MLD) : 9.53

6 Present rate of supply (in LPCD) : 139

7 Ward wise coverage information 0

(a) Total number of wards: : 21

(b) Fully covered : 16

(c) Partly covered : 5

(d) Uncovered : 0

8 Total number of House connections : 5708

9 Total number of Stand posts : 167

10 Total number of running Hand pump tube Wells : 363

Page 28: Expression of Interest (EOI) Invited

28

Name of the ULB: ________Keonjhar______________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action Plan 2019-20

(Infrastructure to be added

during 2019-

20)

Total

1 2 3 4 5

[3]+[4]

1 Source – 1. No. of

Production wells with yield in

MLD 2. No. of

intake wells

i. 18 no.s

0.90 MLD

ii.2 no.s 17.0 MLD

(No.s with yield)

ii. 18 no.s

0.90 MLD

ii.2 no.s 17.0 MLD

2 Treatment - WTPs with capacity in MLD

2 no.s 16.60 MLD

2 no.s 16.60 MLD

3 Storage -

ESRs – No.s with capacity

9 no.s

3.075 ML

9 no.s

3.075 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

24 no.s 6.875 ML

24 no.s 6.875 ML

5 Distribution –

Length of pipeline in km

130.23 32.94 163.17

6 Rising Main – Length of pipeline in km

63.99 63.99

7 House hold

connections

5708 6567 12275

Page 29: Expression of Interest (EOI) Invited

29

Status of urban water supply in Anandapur Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Anandapur

1 Population as per census 2011 : 39585

2 Projected Population for 2019 : 43686

3 Source of water supply

(a) Surface Source : 0

(b) Ground Source (Production wells) : 53 4 Present demand of water supply (in MLD) : 6.77

5 Present level of water supply (in MLD) : 4.17

6 Present rate of supply (in LPCD) : 95

7 Ward wise coverage information 0

(a) Total number of wards: : 16

(b) Fully covered : 15

(c) Partly covered : 1

(d) Uncovered : 0

8 Total number of House connections : 2798

9 Total number of Stand posts : 386

10 Total number of running Hand pump tube Wells : 360

Page 30: Expression of Interest (EOI) Invited

30

Name of the ULB: ____Anandapur__________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with

yield in MLD 2. No. of intake

wells

i. 32 no.s 3.29 MLD

(No.s with yield)

2 Treatment - WTPs with capacity in MLD

Nil

3 Storage - ESRs – No.s with

capacity

2 no.s 0.45 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

6 no.s 2.35 ML

5 Distribution – Length of pipeline

in km

79.99 5.52 85.51

6 Rising Main – Length of pipeline in km

4.86 0.09 4.95

7 House hold connections

2798 5192 7990

Page 31: Expression of Interest (EOI) Invited

31

Status of urban water supply in Joda Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Joda

1 Population as per census 2011 : 46631

2 Projected Population for 2019 : 54290

3 Source of water supply

(a) Surface Source : River Baitaranee

(b) Ground Source (Production wells) : 21 4 Present demand of water supply (in MLD) : 8.41

5 Present level of water supply (in MLD) : 5.63

6 Present rate of supply (in LPCD) : 104

7 Ward wise coverage information 0

(a) Total number of wards: : 14

(b) Fully covered : 12

(c) Partly covered : 2

(d) Uncovered : 0

8 Total number of House connections : 1021

9 Total number of Stand posts : 145

10 Total number of running Hand pump tube Wells : 32

Page 32: Expression of Interest (EOI) Invited

32

Name of the ULB: ____Joda__________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with

yield in MLD

2. No. of

intake wells

i. 21 no.s 0.63 MLD

i). 2 no’s 0.07

23 no’s 0.70 MLD

2 Treatment - WTPs with

capacity in MLD

1 no. 9.30 MLD

1 no. 9.30 MLD

3 Storage -

ESRs – No.s with capacity

1 no.

0.227 ML

1 no.

0.227 ML

4 Storage - GSR/OGR/GLSRs-

No.s with capacity

6 no.s 3.354 ML

6 no.s 3.354 ML

5 Distribution –

Length of pipeline in km

88.04 3.14

6 Rising Main – Length of pipeline

in km

12.50 12.50

7 House hold

connections

1021 6594 7615

Page 33: Expression of Interest (EOI) Invited

33

Status of urban water supply in Barbil Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Barbil

1 Population as per census 2011 : 66540

2 Projected Population for 2019 : 80615

3 Source of water supply

(a) Surface Source : River Karo

(b) Ground Source (Production wells) : 10 4 Present demand of water supply (in MLD) : 12.5

5 Present level of water supply (in MLD) : 3.82

6 Present rate of supply (in LPCD) : 47

7 Ward wise coverage information 0

(a) Total number of wards: : 15

(b) Fully covered : 11

(c) Partly covered : 4

(d) Uncovered : 0

8 Total number of House connections : 2100

9 Total number of Stand posts : 139

10 Total number of running Hand pump tube Wells : 38

Page 34: Expression of Interest (EOI) Invited

34

Name of the ULB: ____Barbil__________________

Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5 [3]+[4]

1 Source – 1. No. of

Production wells with

yield in MLD 2. No. of intake

wells

i. 10 no.s 0.72MLD

ii. 1no.

5.0 MLD

i). 10 no.s 0.72MLD

ii). 1no.

5.0 MLD

2 Treatment - WTPs with capacity in MLD

1 no. 5.0 MLD

3 Storage - ESRs – No.s with

capacity

Nil

4 Storage - GSR/OGR/GLSRs- No.s with capacity

6 no.s 3.05 ML

3 no’s 1.98 ML

9 no’s 5.03 ML

5 Distribution – Length of pipeline

in km

53.85 65.40 119.25

6 Rising Main – Length of pipeline in km

1.80

7 House hold connections

2100 8813 10913

Page 35: Expression of Interest (EOI) Invited

35

Status of urban water supply in Champua Water supply status as on 31.03.2019

Sl No.

Name of the Urban Local Body : Champua

1 Population as per census 2011 : 0

2 Projected Population for 2019 : 14380

3 Source of water supply

(a) Surface Source : River Baitaranee

(b) Ground Source (Production wells) : 15 4 Present demand of water supply (in MLD) : 2.23

5 Present level of water supply (in MLD) : 2.09

6 Present rate of supply (in LPCD) : 145

7 Ward wise coverage information 0

(a) Total number of wards: : 13

(b) Fully covered : 6

(c) Partly covered : 7

(d) Uncovered : 0

8 Total number of House connections : 922

9 Total number of Stand posts : 8

10 Total number of running Hand pump tube Wells : 131

Page 36: Expression of Interest (EOI) Invited

36

Name of the ULB: ____Champua__________________

Infrastructure

S

No.

Details of

infrastructure

Existing

as on 31.03.20

19

Ongoing / To

be completed under Action Plan 2019-20

(Infrastructure to be added during 2019-

20)

Total

1 2 3 4 5

[3]+[4]

1 Source – 1. No. of

Production wells with yield in MLD

2. No. of intake wells

i). 15 no.s 0.49

MLD

ii) 1 no. 3.0 MLD

i). 2 no’s 0.20

1 no. in progress to be completed in

2020-21

i). 17 no’s 0.69 ML

ii) 2 no.s

2 Treatment -

WTPs with capacity in MLD

1 no.

4.00 MLD to be completed in 2020-21

1 no.

4.00 MLD to be completed

in 2020-21

3 Storage -

ESRs – No.s with capacity

1 no.

0.80 ML

1 no.

0.80 ML

4 Storage - GSR/OGR/GLSRs- No.s with capacity

1 no. 0.60 ML

2 no’s 0.30 ML

3 no’s 0.90 ML

5 Distribution –

Length of pipeline in km

45.56 km 10.35 km 55.81 km

6 Rising Main – Length of pipeline in km

1.50 km 4.40 km 5.90 km

7 House hold

connections

922 1276 2198

Page 37: Expression of Interest (EOI) Invited

37

Status of urban water supply in Vyasanagar Water supply status as on 31.03.2019

Sl

No.

Name of the Urban Local Body : Vyasanagar

1 Population as per census 2011 : 48911

2 Projected Population for 2019 : 56737

3 Source of water supply

(a) Surface Source : Kharasrota River

(b) Ground Source (Production wells) : 34 4 Present demand of water supply (in MLD) : 8.79

5 Present level of water supply (in MLD) : 8.49

6 Present rate of supply (in LPCD) : 150

7 Ward wise coverage information 0

(a) Total number of wards: : 26

(b) Fully covered : 14

(c) Partly covered : 12

(d) Uncovered : 0

8 Total number of House connections : 6812

9 Total number of Stand posts : 250

10 Total number of running Hand pump tube Wells : 127

Page 38: Expression of Interest (EOI) Invited

38

Name of the ULB: ____Vyasanagar . Infrastructure

S

No.

Details of

infrastructure

Existing as

on 31.03.2019

Ongoing / To be

completed under Action

Plan 2019-20 (Infrastructure

to be added

during 2019-20)

Total

1 2 3 4 5

[3]+[4]

1 Source –

No. of Production wells with

yield in MLD

No. of intake wells

34 no’s – 5.99 ML

1 no. 2.50

- 34 no’s – 5.99 ML

1 no. 2.50

2 Treatment - WTPs with capacity in MLD

1 No. 1.50 MLD

1 No. 1.50 MLD

3 Storage - ESRs – No.s with

capacity

4 No.s 1.77 ML

4 No.s 1.77 ML

4 Storage -

GSR/OGR/GLSRs- No.s with capacity

5 No.s

3.40 ML

5 No.s

3.40 ML

5 Distribution – Length of pipeline in km

14.10 14.10

6 Rising Main – Length of pipeline in km

14.13 14.13

7 House hold connections

6812 399 7211