Exhibit C- Project Assignment Page 1 of 4
EXHIBIT C
GUARANTEED MAXIMUM PRICE
TO THE CONTINUING CONTRACT FOR
CONSTRUCTION MANAGEMENT SERVICES/RFQ #18-Q-091-DR
BY AND BETWEEN
THE SCHOOL BOARD OF BREVARD COUNTY, FLORIDA
2700 Judge Fran Jamieson Way
Viera, Florida 32940-6601
Phone: (321) 631-1911
Fax: (321) 633-4646
AND
CORE CONSTRUCTION SERVICES OF FLORIDA, LLC
FOR THE CONSTRUCTION OF:
SCHOOL: Astronaut High School
PROJECT: CTE Welding Lab
Exhibit C- Project Assignment Page 2 of 4
ARTICLE 1. GUARANTEED MAXIMUM PRICE (GMP)
1.1.1 Guaranteed Maximum Price (GMP): Construction Manager guarantees that it shall not exceed a Guaranteed Maximum Price (GMP) of Five Hundred Forty-One Thousand, Four Hundred Eighty-Five Dollars and Fifty-Nine Cents ($541,485.59) for the identified Sub-Project. 1.2 Basis of the GMP: 1.2.1 Construction Documents: The Scope of Work for the GMP shall be as defined in the
Construction Documents, prepared by CDE Company, titled Astronaut High School CTE Welding Lab and dated November 20, 2019.
1.2.2 List of Contract Documents attached as Exhibit C-1. 1.2.3 Exceptions, Clarifications and Exclusions: The Scope of Work defined in the Contract
Documents shall be modified and/or clarified as shown in attached Exhibit C-2. 1.2.4 Truth-In-Negotiation: The Construction Manager certifies that the wage rates and other
factual unit costs supporting the compensation are accurate, complete and current at the time of execution of each Sub-Project of which this certificate is a part. The original price and any additions thereto shall be adjusted to exclude any significant sums by which the Owner determines the Sub-Project amount was increased due to inaccurate, incomplete or non-current wage rates and other factual unit costs and that such original Sub-Project adjustments shall be made within one year following the end of the Agreement.
ARTICLE 2. PROJECT TIME 2.1 Substantial Completion Date: Substantial Completion of the Work as defined in Article 6.1.2 of the
General Conditions to the Continuing Contract for Construction Management Services shall be achieved by July 31, 2020.
2.2 Final Completion Date: Final Completion for the Work as defined in Article 6.1.3 of the General Conditions to the Continuing Contract for Construction Management Services shall be achieved by September 30, 2020.
2.3 Project Schedule: Attached to this Amendment will be a schedule identifying the above noted completion times and intermediate milestone dates estimated for the Project. The proposed schedule shall be integrated into the Construction Manager's CPM Schedule upon approval of its Guaranteed Maximum Price Amendment.
ARTICLE 3. CONSTRUCTION MANAGEMENT FEE 3.1 Construction Management Fee: The Construction Management Fee for the Project shall be either
a ☒Lump Sum or ☐Not-To-Exceed Fee (Check Correct Type – Reference Sub-Project Work Request (Exhibit B) which identifies the Fee type) of Twenty-Four Thousand, Four Dollars and Forty Cents ($24,004.40).
Exhibit C- Project Assignment Page 3 of 4
ARTICLE 4. REIMBURSABLE GENERAL CONDITIONS COSTS 4.1 General Conditions: General Conditions costs for the Project shall not exceed Sixty-Three
Thousand, Seven Hundred Four Dollars and Seventy Cents ($63,704.70). General Conditions costs shall be reimbursed at actual cost. General Condition costs shall be in compliance with the General Conditions to the Construction Management Contract (Exhibit A) and are identified in the attached document, prepared by the Construction Manager titled GMP Report for Astronaut High School CTE Welding Lab and dated January 8, 2020.
ARTICLE 5. LIQUIDATED DAMAGES 5.1 Substantial Completion: Construction Manager shall pay Owner One Thousand Dollars ($1,000.00)
as liquidated damages for each day that Substantial Completion extends beyond the Substantial Completion Date.
5.2 Final Completion: Construction Manager shall pay Owner Five Hundred Dollars ($500.00) as liquidated damages for each day that Final Completion extends beyond the Final Completion Date.
ARTICLE 6. PROJECT REPRESENTATIVES 6.1 Owner’s Representative: Owner designates the individual listed below as its Owner’s
Representative to provide direct interface with Construction Manager with respect to Owner’s responsibilities:
Art Johnson, Owner’s Project Manager. 6.2 Construction Manager's Representative: Construction Managerdesignates the individual listed
below as its Construction Manager's Representative to provide direct interface with Owner with respect to Construction Manager's responsibilities:
Saravanan Sathya, Construction Manager's Project Manager.
(REMAINDER OF PAGE INTENTIONALLY LEFT BLANK)
January 8, 2020
Mr. Arthur C. Johnson
Project Manager
Brevard Public Schools
Office of Facilities Management Services
1254 S. Florida Avenue
Rockledge, FL 32955
Re: GMP Report for Astronaut High School CTE Welding Lab
Dear Mr. Johnson,
We are pleased to submit our GMP Astronaut High School CTE Welding Lab. This estimate is
based on the plans and specifications prepared by Schenkel Shultz Architecture & CDE
Company Engineering for Architecture dated November 26, 2019.
CORE Construction’s GMP Estimate Total: $541,485.59
A general description of the work included in the GMP Base Bid scope is listed below:
Architectural
• Perform selective demolition of existing conditions.
• Provide new metal stud framing and drywall.
• Install new frames and doors.
• Paint exposed above ceiling conditions, walls, columns, frames and doors.
• Install new acoustical ceiling tile system in the newly constructed CCTV room.
• Replace existing floor coating with new epoxy floor coating.
Structural
• Construct mechanical pad with CMU wall and black vinyl chain-link gate to house new
fume exhaust system.
• Paint new CMU wall to match adjacent conditions.
Electrical
• Perform selective demolition of existing conditions.
• Reinstall existing speakers and projector.
• Provide new LED light fixtures.
• Provide new fire alarm shutdown replay for welding exhaust system.
• Provide new emergency disconnect switch as indicated.
• Provide new circuit breakers as indicated.
• Provide VFD for welding exhaust equipment.
• Add receptacles for technology. Provide circuits for the receptacles and connect to new
panels.
• Provide electrical support for HVAC equipment renovation work.
Mechanical
• Perform selective demolition of existing conditions.
• Provide new fume exhaust system.
• Provide new compressed air system.
• Provide new chilled water air handling unit.
• Provide new supply air and outside air ductwork.
• Provide new balancing damper.
• Provide new thermostat.
Included in this GMP Report you will find the following documents enclosed:
1. Project Description
2a. GMP Estimate Schedule of Values
2b. Schedule Cost Item Breakdown
3. Bid Recap Summary
4. General Conditions
5. General Requirements
6. Summary of Allowances
7. Assumptions and Exclusions
8. Milestone Schedule Dates
9. Enumeration of Documents
10. Anticipated ODP Value – Forthcoming
We look forward to a successful and enjoyable project together. Thank you for this opportunity,
please do not hesitate to contact me directly with any questions or comments.
Respectfully submitted,
Joshua Gray
Preconstruction Manager
CORE Construction Services of Florida, LLC
Astronaut High School
CTE Welding Lab
PROJECT DESCRIPTION
Astronaut High School is part of the Brevard Public School system and is located at 800 War
Eagle Blvd, Titusville, FL 32796. The campus was originally constructed in 1972.
The existing campus is being renovated to include a Welding Lab to support Brevard Public
Schools initiative to provide technical education to its students. The design for the CTE Welding
Lab was based on CDE Company’s CTE Welding Lab Estimate provided September 16, 2019. This
GMP is based on the plans and specifications provided by Schenkel Shultz Architecture & CDE
Company Engineering for Architecture dated November 26, 2019.
This project consists of a complete remodel of an existing classroom space to function as a
welding lab. The renovation includes the construction of a new outdoor mechanical area to
house the new fume exhaust system. The new fume exhaust system will work in tandem with the
twelve welding booths to ensure adequate ventilation while the welding booths are in use. The
interior renovation includes the removal of the existing acoustical ceiling tile system, the
demolition of interior walls, and construction of a new CCTV space in the neighboring
classroom. The exposed above ceiling components will be painted a uniform black, and new
interior walls and doors will be constructed to house hand tools and student projects. The HVAC
and electrical systems will be updated to accommodate the additional equipment and expanded
area of use.
1/8/2020
DIV. DESCRIPTION TOTAL
1 General Requirements 20,791.80
1a Final Cleaning 1,169.00
2a Demolition 15,800.00
3a Concrete 36,686.00
4a Masonry -
5a Metals -
6a Architectural Woodwork (PLAM Cabinets) -
7a Waterproofing & Joint Sealants -
7b Roofing, Gutters, DS, Fascia, Soffit -
7c Fireproofing -
8a Doors, Frames & Hardware 7,139.00
8b Storefronts, Windows & Glazing -
9a Drywall Patching Allowance 16,806.00
9b Stucco -
9c Acoustical Ceilings & Panels -
9d Carpet & Vinyl Flooring 30,450.00
9e Tile -
9f Painting Allowance 26,100.00
21a Fire Sprinklers 6,325.00
22a Plumbing -
23a HVAC 106,259.00
23b Test & Balance 2,685.00
23c Fume Hood Exhaust System & Equipment 122,833.00
26a Electrical 57,000.00
31a Sitework & Sod Allowance -
A TOTAL ALL DIVISIONS 451,969.80
B General Conditions 26,195.96
C Design Construction Administration -
D General Liability (.402% of Total All Divisions & GCs) 1,922.23
E TOTAL COST OF WORK 480,087.99
F CM FEES - [5% of (G)] 24,004.40
G CM Contingency (5%) 22,598.49
H Subcontractor Default Insurance [1.489%] 6,402.83
I Builder's Risk - [0.90% of (A)] 4,067.73
J SUBTOTAL PROPOSED GMP (E+F+G+H+I) 537,161.44
K Bond - 0.805% of GMP Subtotal 4,324.15
L TOTAL PROPOSED GMP (J+K) 541,485.59
CORE Construction Services of Florida, LLC
Schedule of Values
Brevard Public Schools
Astronaut High School CTE Lab
GMP Estimate
1 of 1
Astronaut High School CTE LabDetailed Estimate - Astronaut High School
EXISTING CONDITIONS 15,800 02-1000 DEMOLITION 15,800
1 Demolition of Existing Conditions 1 LS 15,800.00 15,800
LANDSCAPING & SITE AMENITIES 1,926.00 32-7100 FENCES & GATES 1,926.00
1 Vinyl Chainlink Fence @ New Mechanical Area 1 LS 1,926.00 1,926.00
BUILDING STRUCTURE 36,686.00 03-3000 CONCRETE 36,686.00
1 Concrete, CMU, & Stucco @ New Mechanical Area 1 LS 36,686.00 36,686.00
08-2000 DOORS, TRIM, & HARDWARE 7,139.00
1 New Doors, Frames, & Hardware @ Welding Lab & CCTV Lab 1 LS 7,139.00 7,139.00
FINISHES 74,525.00 09-2000 METAL FRAMING & DRYWALL 16,806.00
1 New Metal Stud Framing & Drywall 1 LS 16,806.00 16,806.00
2 ACT System @ CCTV Room -
09-6000 FLOORING 30,450.00
1 Preparing Existing Surface for New Epoxy Floor Coating 1 LS 4,000.00 4,000.00
2 New Epoxy Floor Coating @ CTE Welding Lab 1 LS 26,450.00 26,450.00
09-9000 PAINTING 26,100.00
1 Paint Walls, Exposed Deck, Doors & Frames @ CTE Lab 1 LS 26,100.00 26,100.00
2 Paint CMU Wall @ New Mechanical Area - -
09-9990 FINAL CLEANING 1,169.00
1 Final Cleaning 1 LS 1,169.00 1,169.00
MEP SYSTEMS 294,217.00 21-1000 FIRE SPRINKLER SYSTEM 6,325.00
1 Install New Heads on Existing Fire Sprinkler Systems @ CTE Lab 1 LS 6,325.00 6,325.00
22-1000 PLUMBING -
1 Included with Mechanical Scope 1 LS -
23-8000 HVAC 230,892.00
1 Full HVAC Scope Plans & Specs 1 LS 106,259.00 106,259.00
2 Test & Balance Allowance 1 LS 1,800.00 1,800.00
3 Lincoln Exhaust System 1 LS 122,833.00 122,833.00
26-1000 ELECTRICAL 57,000.00
1 Full Electrical Scope per Plans & Specs 1 LS 57,000.00 57,000
GRAND TOTAL 430,293.00$
UNIT COST TOTAL COST
CODEDESCRIPTION QUANTITY UNIT
PAGE 1 OF 1
SCHOOL
CM
BID OPENING DATE
A/E
DIV NO. BIDDERS
LEVELED BID
AMOUNT
1A
Kings Service Solutions, LLC 1,169.00$
Daisy Fresh Commercial Cleaning, Inc. 3,050.00$
2A
MGM Contracting Inc. 16,500.00$
EE&G 16,992.00$
Creative Environmental Services, Inc. 15,800.00$
Environmental Construction, Inc. NO BID
3A
Central Florida Construction Walls 37,824.00$
MGM Contracting, Inc. 36,686.00$
Liberty Concrete & Forming 47,114.00$
Don Kings Concrete, Inc. NO BID
8A
C&S Supply Orlando 7,139.00$
A.G. Mauro 8,453.00$
Performance Door & Hardware NO BID
9A
Architectural Drywall Systems, Inc. 19,335.00$
MGM Contracting, Inc. 16,806.00$
Horus Construction Services, Inc. 25,401.00$
Mader Southeast, Inc. NO BID
Ramm Drywall Paint & Stucco NO BID
9D
AJ Flooring 35,294.00$
Pro Flooring Systems 32,237.00$
Hot Spray Industrial Coatings, Inc. 30,450.00$
Spectra Contract Flooring NO BID
9F
Hot Spray Industrial Coatings, Inc. 36,645.00$
MGM Contracting, Inc. 26,100.00$
Steve Harper Painting, Inc. 9,800.00$
Jerry Jackson Painting NO BID
21A
VSC Fire & Security 7,986.00$
Titan Fire Systems, LLC 6,325.00$
22A
General Mechanical Included Below
Ferran Mechanical Included Below
W.W. Gay Mechanical Contractor, Inc. NO BID
Hill York NO BID
23A
General Mechanical 106,259.00$
Ferran Mechanical 198,330.00$
W.W. Gay Mechanical Contractor, Inc. NO BID
Hill York NO BID
23B
Bay to Bay 1,800.00$
Air Balance Unlimited 2,685.00$
Richard Flanders 4,500.00$
Southern Independent Testing Agency 3,350.00$
23C
Lincoln Electric 122,833.00$
DIVISION DESCRIPTION
FINAL CLEANING
DEMOLITION
CONCRETE
FIRE SPRINKLERS
TEST & BALANCE
PAINTING
HVAC
PLUMBING
FUME HOOD EXHAUST SYSTEM & EQUIPMENT
Astronaut High School CTE Welding Lab
Schenkel Shultz Architecture / CDE Company
Core Construction Service of FL
December 12, 2019
DOORS, FRAMES & HARDWARE
DRYWALL
EPOXY FLOORING
Miller Electric NO BID
26A
Giles Electric 5,700.00$
Grassland Electrical 105,450.00$
Boys Electrical Contractors, LLC NO BID
Carter Electric Co. Inc. NO BID
32A
KMG Fence, LLC 3,250.00$
Straight Up Fence, Inc. 1,926.00$
All-Rite Fence 3,781.00$
ELECTRICAL
FENCE & GATES
GENERAL CONDITIONS
1/6/2020
Loaded Total
Rate Hrs Total
Description Quantity Unit Hrs/Wk $/Hr Hrs $
PROJECT MANAGEMENT
Project Oversight (8hr/week) 10.00 week 2.00 93.45 20.00 1,869.00
Project Manager (10.hr/week) 11.00 week 10.00 81.82 110.00 9,000.20
Assistant Project Manager (20hr/week) 10.00 week 5.00 43.91 50.00 2,195.50
Project Coordinator (12hr/week) 11.00 week 4.00 27.72 44.00 1,219.68
Project Accountant (12hr/week) 11.00 week 4.00 43.07 44.00 1,895.08
Superintendent (10hr/week) 11.00 week 10.00 51.45 110.00 5,659.50
Assistant Superintendent (24hr/week) 10.00 week 10.00 43.57 100.00 4,357.00
TOTAL GENERAL CONDITIONS 478.00 26,195.96
ASTRONAUT HIGH SCHOOL CTE WELDING LAB
CORE CONSTRUCTION
UNIT COSTS
GENERAL REQUIREMENTS
Labor
$
Material
$
Sub
$
Equip
$
Labor
$
Material
$
Sub
$
Equip
$
FIELD OFFICE - - - - -
Drinking Water (Use School Facilities) - - - - -
Temporary Toilets (Use School Facilities) - - - - -
OFFICE EQUIPMENT - 250 - - 250
Copy / Fax Machine (Lease) - 350 - - - - -
Office supplies 1.0 250 - 250 - - 250
COMPUTER EQUIPMENT - 540 - 1,279 1,819
Field Computers & IT ($1.39/MH) 1.39 920 - - - 1,279 1,279
Wireless Internet Card (3 months) 3.0 180.00 - 540 - - 540
TELEPHONE SYSTEM - 312 - - 312
Cellular Telephones (QTY 2 @ $52/mo) 3.0 104.00 - 312 - - 312
POSTAGE & COURIER - 100 - - 100
Monthly Charges 2.0 50.00 - 100 - - 100
ASTRONAUT HIGH SCHOOL SCHOOL
CORE CONSTRUCTION
Description Qty Unit Costs Total Costs General
Requirements
Total
$
GENERAL REQUIREMENTS
Labor
$
Material
$
Sub
$
Equip
$
Labor
$
Material
$
Sub
$
Equip
$
ASTRONAUT HIGH SCHOOL SCHOOL
CORE CONSTRUCTION
Description Qty Unit Costs Total Costs General
Requirements
Total
$
DRAWINGS - - 1,305 - 1,305
Drawings for CM 3 185 - - 555 - 555
As Built Drawings & Training DVD 1 250 - - 250 - 250
O&M & Closeout Docs 1 500 - - 500 - 500
PROJECT VEHICLES - - - 1,956 1,956
Automobile & Fuel (1 Vehicles - at
$163/WK)
12.0 163 - - - 1,956 1,956
SAFETY & SECURITY - 200 2,000 - 2,200
First Aid Supplies / Kit 1 100.00 - 100 - - 100
Hard Hats/Safety Glasses/Harness/etc. 1.0 100 - 100 - - 100
Temporary Fencing Panels 400 5.00 - - 2,000 - 2,000
GENERAL LABOR & CLEANING 4,100 4,450 1,100 - 9,650
Daily Cleaning & General Purpose
Labor (Per Week)
8 200.00 1,600 - - - 1,600
General Labor for Moving BPS FF&E 1 2,500.00 400.00 2,500 400 - - 2,900
Dumpsters / Dump Charges 10 405.00 - 4,050 - - 4,050
Final Cleaning 1 1,100 - - 1,100 - 1,100
JOB SIGNS - 150 - - 150
Safety/ Directional Signs 1 150.00 - 150 - - 150
MISCELLANEOUS - 1,250 1,800 - 3,050
Small Tools & Supplies 1.0 250.00 - 250 - - 250
GENERAL REQUIREMENTS
Labor
$
Material
$
Sub
$
Equip
$
Labor
$
Material
$
Sub
$
Equip
$
ASTRONAUT HIGH SCHOOL SCHOOL
CORE CONSTRUCTION
Description Qty Unit Costs Total Costs General
Requirements
Total
$
Protection of Existing Surfaces,
Furniture, & Equipment
1.0 1,000.00 - 1,000 - - 1,000
Final ASBUILT Survey 1.0 1,800 - - 1,800 - 1,800
TOTAL GENERAL REQUIREMENTS 4,100 7,352 6,205 3,235 20,791.80
Astronaut High School CTE LabSUMMARY OF ALLOWANCES 1/6/2020
9a Drywall Patching
All labor, materials, and equipment for patching drywall or
drywall finishes above ceiling & damages as a result of new
installations.
16,806
9f Painting
All labor, materials, and equipment for painting the new
mechanical area & any newly installed pipe/conduit,
miscellaneous paint patches from demolition, and exposed duct
above ceiling.
26,100
Allowances Total: 42,906
All allowance numbers are inclusive of material, sales tax, delivery, stocking, labor, and equipment for installation, protection of work and
cleanup for that portion of work unless otherwise noted.
# ALLOWANCE DESCRIPTIONALLOWANCE
AMOUNT
Astronaut High School – CTE Welding Lab
JANUARY 6, 2020
Assumptions, Clarifications, & Exclusions
General Assumptions
• This proposal does not include any costs for building permit, mechanical/electrical/plumbing permits.
• This proposal assumes there will be no students or faculty in construction areas for summer school
activities for the duration of the summer recess.
• This proposal assumes the CM will have access to an existing office or portable to be used as a
construction office for the duration of the summer recess.
• This proposal includes State and County taxes as applicable and does not discount for anticipated
Owner Direct Purchases.
• This proposal assumes the new ceiling tile and grid in areas where it may need to be replaced will not
achieve a perfect match to the existing grid.
• This proposal assumes the existing utilities (electrical, water, & sanitary) will be available for use during
construction at no cost to the CM or the project. All utility consumption costs to be By Owner.
• This proposal includes Owner’s rights to salvage any materials or equipment prior to the start of
construction.
Specific Exclusions to Proposal
• Asbestos Abatement
• Lead Paint Abatement
• Any LEED standards or certifications.
• This proposal does not include any temporary air or dehumidification at the Classrooms or Cafeteria
Area.
• Final cleaning services in Mechanical Areas. Mechanical Areas will be turned over in the condition in
which they are received.
• Any work to the covered walkways.
• Any repairs to doors, hardware, windows, or exterior sealants not explicitly included with the
predefined scope of work.
• Any ADA or Life Safety modifications.
• Any perimeter/entry fencing or gates.
• Any upgrades or installations to building access controls or security.
• Any sitework unless it is being restored due to damage from new work put in place.
• FF&E - Furniture, Fixtures, and Equipment.
• Any underground chiller pipe replacement.
• Preconstruction test and balance reports on existing HVAC systems and equipment.
• Storing or relocating off site any existing materials/equipment planned for demolition or replacement.
• Any architectural repairs other than those included with the predefined scope of work.
Astronaut High School – CTE Welding Lab
JANUARY 6, 2020
• Any stripping or waxing or polishing of existing floors.
• Any new flooring or tile outside of the predefined scope of work unless damaged/disturbed as a result
of new installations.
Astronaut High School
CTE Welding Lab
MILESTONE SCHEDULE DATES
OWNER DELIVERABLE: DATE
CM GMP SUBMISSION 12/18/2019
CM/BPS GMP FINALIZED (SUBMIT TO BOARD AGENDA) 1/8/2020
BPS BOARD APPROVAL OF GMP 1/28/2020
BPS PROJECT NTP 1/29/2020
CM SUBMIT LONG LEAD SUBMITTALS 2/12/2020
CM/EOR APPROVE LONG LEAD SUBMITTALS 2/26/2020
CM/BPS ODP PROCESSED FOR LONG LEAD EQUIPMENT 3/18/2020
CM/BPS ISSUE PO FOR LONG LEAD EQUIPMENT 3/19/2020
CM EARLY PREP WORK / CONTROLS 4/30/2020
CM LONG LEAD EQUIPMENT PROCUREMENT / DELIVERY 5/27/2020
CM BEGIN CONSTRUCTION 6/1/2020
CM SUBSTANTIAL COMPLETION 7/31/2020
Milestone dates above are for the base bid scope of work only. CM assumes that
Commissioning, performed under Brevard Public Schools, will occur after Substantial
Completion.
PROJECT NAME: Astronaut High School CTE Welding Lab
Drawing Description Current Set
ADDENDUM
#1
ADDENDUM
#2
GENERAL INFORMATION DRAWING LIST
G-001 COVER SHEET AND INDEX 20-Nov-19
ARCHITECTURAL DRAWING LIST
AS100 SCOPE LOCATION PLAN 20-Nov-19
AD101 FIRST FLOOR DEMOLITION PLAN 20-Nov-19
AD102 DEMOLITION PHOTOS 20-Nov-19
A101 FIRST FLOOR PLAN 20-Nov-19
A141 REFLECTED CEILING PLAN 20-Nov-19
A201 EXTERIOR ELEVATIONS 20-Nov-19
A202 WELDING EQUIPMENT PHOTOS 20-Nov-19
A301 BUILDING SECTIONS 20-Nov-19
STRUCTURAL DRAWING LIST
S-001 STRUCTURAL ABBREVIATIONS, LEGEND AND NOTES 20-Nov-19
S-100 STRUCTURAL PLAN 20-Nov-19
MECHANICAL DRAWING LIST
M-001 MECHANICAL ABBREVIATIONS, LEGENDS AND NOTES 20-Nov-19
MD-101 HVAC PLAN - DEMO 20-Nov-19
M-101 HVAC PLAN - NEW 20-Nov-19
M-601 SCHEDULES AND DETAILS 20-Nov-19
M-701 CONTROLS 20-Nov-19
PLUMBING DRAWING LIST
P-101 PLUMBING PLAN 20-Nov-19
P-102 COMPRESSED AIR PLAN 20-Nov-19
FIRE PROTECTION DRAWING LIST
FP-100 FIRE PROTECTION PLAN 20-Nov-19
ELECTRICAL DRAWING LIST
E-001 ELECTRICAL ABBREVIATIONS, LEGENDS AND NOTES 20-Nov-19
E-100 LIGHTING PLANS 20-Nov-19
E-200 POWER PLANS 20-Nov-19
E-300 SYSTEMS PLANS 20-Nov-19
E-400 PANELBOARD SCHEDULES 20-Nov-19
DIVISION SPECIFICATION DESCRIPTION DATE
2 EXISTING CONDITIONS
02 41 19 SELECTIVE DEMOLITION 20-Nov-19
3 CONCRETE
03 20 00 CONCRETE REINFORCING 20-Nov-19
03 30 00 CAST-IN PLACE CONCRETE 20-Nov-19
4 MASONRY
04 05 13 MASONRY MORTARING 20-Nov-19
04 05 16 MASONRY GROUT 20-Nov-19
04 05 23 MASONRY ACCESSORIES 20-Nov-19
04 22 00 UNIT MASONRY 20-Nov-19
6 WOOD AND PLASTICS
06 10 53 MISCELLANEOUS ROUGH CARPENTRY 20-Nov-19
7 THERMAL AND MOISTURE PROTECTION
07 26 10 UNDERSLAB VAPOR BARRIER 20-Nov-19
07 92 00 JOINT SEALANTS 20-Nov-19
8 OPENINGS
08 12 13 HOLLOW METAL FRAMES 20-Nov-19
08 14 16 WOOD DOORS 20-Nov-19
08 41 13 ALUMINUM STOREFRONTS 20-Nov-19
9 FINISHES
09 22 16 NON-STRUCTURAL METAL FRAMING 20-Nov-19
09 24 00 CEMENT PLASTERING 20-Nov-19
09 29 00 GYPSUM BOARD 20-Nov-19
09 51 01 ACOUSTICAL CEILINGS 20-Nov-19
09 65 13 RESILIENT BASE 20-Nov-19
09 67 00 EPOXY FLOOR COATING 20-Nov-19
09 77 13 STRETCHED FABRIC WALL COVERING 20-Nov-19
09 91 00 PAINTING 20-Nov-19
Attachment C
Enumeration of Documents
Page 1 of 2
PROJECT NAME: Astronaut High School CTE Welding Lab
Drawing Description Current Set
ADDENDUM
#1
ADDENDUM
#2
Attachment C
Enumeration of Documents
10 SPECIALTIES
10 14 00 IDENTIFYING DEVICES 20-Nov-19
10 44 16 FIRE EXTINGUISHERS 20-Nov-19
22 PLUMBING
22 05 23. 12 BALL VALVES FOR PLUMBING PIPING 20-Nov-19
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT 20-Nov-19
22 11 16 DOMESTIC WATER PIPING 20-Nov-19
FIRE PROTECTION DRAWING LIST
FP-100 FIRE PROTECTION DRAWING PLAN 20-Nov-19
23 HEATING, VENTILATING AND AIR CONDITIONING
23 00 00 GENERAL MECHANICAL PROVISIONS 20-Nov-19
23 03 00 MECHANICAL IDENTIFICATION 20-Nov-19
23 05 00 BASIC MECHANICAL REQUIREMENTS 20-Nov-19
23 05 48 VIBRATION ISOLATION 20-Nov-19
23 05 93 TESTING, ADJUSTING AND BALANCING (HYDRONICS) 20-Nov-19
23 05 94 TESTING, ADJUSTING AND BALANCING (AIR SIDE) 20-Nov-19
23 07 00 MECHANICAL SYSTEMS INSULATION 20-Nov-19
23 07 13 DUCTWORK INSULATION 20-Nov-19
23 21 13 HYDRONIC PIPING 20-Nov-19
23 31 11 DUCTWORK AND ACCESSORIES 20-Nov-19
23 34 16 MODULAR AIR-HANDLING UNITS 20-Nov-19
23 62 00 PACKAGED COMPRESSED AIR - EQUIPMENT GENERAL 20-Nov-19
26 ELECTRICAL
26 00 10 BASIC ELECTRICAL REQUIREMENTS 20-Nov-19
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES 20-Nov-19
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS 20-Nov-19
26 05 29 HANGARS AND SUPPORTS FOR ELECTRICAL SYSTEMS 20-Nov-19
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS 20-Nov-19
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS 20-Nov-19
26 27 26 WIRING DEVICES 20-Nov-19
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS 20-Nov-19
32 EXTERIOR IMPROVEMENTS
32 31 13 CHAIN-LINK FENCES AND GATES 20-Nov-19
Page 2 of 2