Evaluation ToR

25
UXO Sector Evaluation June – July 2008 Findings and Recommendations Dr Maligna Saignavongs Director NRA

description

UXO Sector Evaluation June – July 2008 Findings and Recommendations Dr Maligna Saignavongs Director NRA. Evaluation ToR. - PowerPoint PPT Presentation

Transcript of Evaluation ToR

Page 1: Evaluation  ToR

UXO Sector EvaluationJune – July 2008

Findings and Recommendations

Dr Maligna Saignavongs Director NRA

Page 2: Evaluation  ToR

Evaluation ToR

1. Evaluate progress of the UXO Sector against the 3 objectives of

the National Strategic Plan. Also examine the National Strategic Plan and make recommendations for revisions;

2. Evaluate whether the structure of the UXO Sector is correct and if the NRA is providing effective leadership, governance and coordination as stipulated in Part IV, Institutional Arrangements of the National Strategic Plan;

3. Evaluate the efficiency and effectiveness of UXO Lao and the progress achieved against its strategy; and

4. Review and assess the effectiveness of Government and donor support provided to the UXO Sector and the implementation of the National Strategic Plan.

Page 3: Evaluation  ToR

1. Community Awareness: “UXO/Mine Risk Education (MRE) teams will visit and deliver MRE training to all impacted communities in Lao PDR and UXO/mine accidents will be reduced ….. not exceeding 100 persons/year”; 2. Survey and Clearance: “All agricultural areas considered to be ‘high priority’ will be cleared, as well as a sizeable portion of other areas identified as ‘medium priority’ – for a total of no less than 18,000 hectares of land cleared by UXO Lao alone”;

3. Victim Assistance: “A national database on Mine/UXO accidents will be developed …. to feed into the prioritization of clearance and MRE tasks. The specific needs of survivors of UXO/mine accidents ….. will be factored in all national/local public health initiatives”;

3 Objectives of the Safe Path Forward

Page 4: Evaluation  ToR

The Evaluation was very detailed and has made many recommendations.

Recommendations can be accepted or not.

Accepted recommendations need to be implemented.

Page 5: Evaluation  ToR

1. The use of scoping results as the basis for planning 2. The need for greater emphasis on roving tasks and responsiveness 3. The need for development of a simple system of priority setting that addresses development and poverty reduction priorities 4. The development of new types of targets, given the shift in emphasis to roving tasks  5. An explanation of funding policies and mechanisms for the sector 6. The definition of an exit or handover strategy for the NRA and UXO Lao residual functions.

The Next Strategic PlanRecommendations

Page 6: Evaluation  ToR

Evaluation Recommendation or Issue 1: Scoping

Page 7: Evaluation  ToR

Scoping

• 1.1 – 1.6 Agreed

– The Evaluation Team designed a method to identify the scope of work required to clear all contaminated land that is financially “worth” clearing in 47 poorest districts. It is suggested that this exercise is revised and re-run

– The programme cannot be limited to the clearance of

paddy land…... The scoping exercise is a complex undertaking and should not be underestimated as there are many variables that need to be agreed and many data-sets that are not accurate.

Page 8: Evaluation  ToR

Evaluation Recommendation or Issue 2: The UXO Sector

Page 9: Evaluation  ToR

UXO Sector

• 2.1 – Not agreed (restructuring the sector for 2 pillars).

• 2.2 – linked to 2.1.• 2.3 – Agreed.• 2.4 – A new prioritisation system should be

developed.• 2.5 & 2.6 – Agreed. QA expansion should be planned

but 5 % is not feasible.• 2.7 & 2.8 & 2.9 – Agreed.• 2.10 – Not agreed – too soon to transition.

Page 10: Evaluation  ToR

Evaluation Recommendation or Issue 3: The Next Strategic Plan

Page 11: Evaluation  ToR

Next Strategic Plan

• 3.1 – Agreed. Integrate next plan into NSEDP timing

• 3.2 – Not agreed. As discussed earlier the UXO Sector should remain based on the 3 pillars of VA, MRE and Clearance.

• 3.3 – Agreed but more aspects need to be included in the plan

Page 12: Evaluation  ToR

Evaluation Recommendation or Issue 4: The NRA & the NRA Office

Page 13: Evaluation  ToR

NRA 4.0 – Agreed – NRA should expand its Public Relations efforts• 4.1 – Not agreed – new legislation will follow with the CCM• 4.2 – Agreed - UXO clearance legislation is required

• 4.3 – Agreed in principle. A residual capacity needs designing soon.

• 4.4 – Partially agreed 4.5 – National Standards are approved 4.6 - Agreed – accreditation should be accelerated

Page 14: Evaluation  ToR

NRA

• 4.7 - QA is Agreed but 5% is too large to be feasible

• 4.8 –Agreed - Cost capture is a good idea • 4. 9 – Agreed – benchmarking is a good initiative but will depend on

funding

• 4.10 – Agreed – TA support should be better measured

• 4.11 – Agreed in principle – NRA should be cost conscious• 4.12 – Agreed in principle – NRA remains a UN project• 4.13 – Not agreed – NRA functions are in PM Decree

Page 15: Evaluation  ToR

Evaluation Recommendation or Issue 5: UXO Lao

Page 16: Evaluation  ToR

UXO LAO

• 5.1 – More emphasis on Roving Tasks - Accepted but not at expense of area clearance capacity.

• 5.2 & 5.3 - Agreed• 5.4 - Agreed in principle but requires capital investment that is

disproportionate to benefits• 5.5 - It is not practical for MRE Teams to operate with EOD

Roving Teams as they are in locations for no more than 1 day, so arranging and implementing MRE is not possible, especially if you wish to capture the target group.

Page 17: Evaluation  ToR

UXO LAO• 5.6 – Accepted

• 5.7 UXO Lao will follow any revised national priorities but it is not practical to move resources between provinces and 3 most impacted provinces have larger operations at present.

• 5.8 – 5.10 – Accepted• 5.11 UXO Lao strongly disagree with this recommendation. It

is based on the wrong perspective by the evaluation team.• 5.12 ETS should not be viewed as a prioritising tool per

se, as it is one option after desk assessment and general survey (other options are Clearance, roving or release)

Page 18: Evaluation  ToR

UXO LAO• 5.13 -5.15 – Accepted

• 5.16 UXO Lao would like to conduct this cost capture study and investigate ‘cost recovery’ operations provided this is approved by the Government.

• 5.17 – 5.18 – Accepted• 5.19 UXO Lao have no objection to a wider remit for the Auditors provided

it is practical and with in the scope of the UNDP NEX Audit ToR• 5.20 - Accepted

Page 19: Evaluation  ToR

Evaluation Recommendation or Issue 6: Government & Donor Support

Page 20: Evaluation  ToR

• 6.1- Agreed.

-MOFA has initiated a review process by setting up a reform committee

Streamlining MOU process

Page 21: Evaluation  ToR

Cash Contribution by the GOL

• 6.2–Agreed. – The GOL has been making in-kind contributions to the programme

and will continue to seek possibilities to increase both in-kind and cash contributions.

– The NRA submitted a funding request for the programme to the GOL.

– Funding for the long term capacity to deal with the residual threat will be discussed in the context of the strategy review process.

Page 22: Evaluation  ToR

Integration of UXO Action into Development

• 6.4 & 6.5 - Agreed in principle. – The cost of UXO clearance should be included in large scale

development project budgets. – Smaller poverty reduction and/or development projects

should be supported by a humanitarian UXO clearance operator without any charge if they have limited resources.

– Issuance of a guidance note (if not a stronger legislation) for development agencies on mainstreaming UXO clearance into their development projects will be further discussed.

Page 23: Evaluation  ToR

Residual Capacities for UXO Disposal

• 6.6 -Agreed in Principle. – The idea for a residual capacity needs

discussion with all stakeholders and direction from the NRA Board.

– A workshop to discuss options will be held to explore the options

Page 24: Evaluation  ToR

Harmonization/Coordination of Donor Support

• 6.3 & 6.7– Agreed.– Long-Term Capacity Development and TA

deployment plan will be formulated alongside the strategy review process

– A funding proposal for the UXO Sector is being developed and different funding modalities are being discussed with the NRA and MPI before being further discussed with donors.

Page 25: Evaluation  ToR

Thank YouAny Questions