Estimate File
description
Transcript of Estimate File
ITEMS Price per Unit TOTALTilestar 0.5 (mm)96.19 linear meter
667/m 64,158
15 pcs Spanish gutter 24” 765/pc 11,4757 pcs flashing gutter 24” 765/pc 5,3559 pcs ridge roll 16” 465/pc 4.18510 pcs Facia 12” 397/pc 3,9702 pcs Valley cover 6” 238/pc 476100m insulation foam 6000/roll 12,0000
Subtotal 101,619Accessories ( texscrew, blind rivets, sealant) 1,650Labor charge 18,000Freight and Handling 4,500Crating Charge 4,000
Subtotal 129,769Transport from Ormoc to Albuera 3,000
GRAND TOTAL 132,769
8 sheet textured lawanit 4,800Labor 3,500Repainting 12,000
Subtotal 20,30023 pcs Marine Plywood ¼” 9,890Labor Charge 6,500Painting Materials 32,000Labor Charge 18,000
Subtotal 86,690Glass/installation charge 12,000
GRAND TOTAL 98,690