Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link, CCT Date: March 14, 2012 Subject: Tiger Grant Pedestrian Walkway and Parking Garage- Conceptual, Rough Order of Magnitude Cost Estimate Estimate Overview This Cost Estimate is based on the provided drawings and sketches for the Pedestrian Walkway/ Parking Garage project located in Cleveland, Ohio. The documents were received by URS Pittsburgh Cost Estimating Department between 03/06/2012 and are dated 03/14/2012. In addition, other details and clarifications provided by the client and/or design team are incorporated. Estimate Purpose Conceptual Estimate With conceptual estimating methods, the independent variables used in the estimating algorithm are generally something other than a direct measure of the units of the item being measured. They usually involve simple or complex modeling (or factoring) based on conferred or statistical relationships between costs and other, typically design-related, parameters. Often the cost estimating relationships used in conceptual estimating methods are somewhat subject to conjecture. Conceptual Estimating Using PACES Parametric Cost Engineering System (PACES) software is a cost engineering tool used to assist with the development of planning and budgeting facility and infrastructure construction and renovation costs. PACES is an integrated PC- based software system that prepares parametric cost estimates for new facility construction, renovation, and life cycle cost analysis. PACES uses pre-engineered model parameters and construction criteria to accurately predict construction costs with limited design information. PACES is a parametric cost-estimating system for conventional construction projects and is targeted to government and conventional construction estimators. Predefined and documented engineering relationships link the primary parametrics to detailed engineering quantities. Quantities and most model assumptions can be changed by users. PACES estimates are recognized by the Congressional Budget Office as accurate up to the 35% design stage, and they have been validated to be within 7 1/2% of final, actual costs. If needed, estimates can be refined at later stages of design. The database used is the Army Corps of Engineers Unit Price Book. Conceptual estimating methods that were used in the preparation of the cost estimate are:

Transcript of Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost...

Page 1: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Estimate Memorandum/ Basis of Estimate

To: Mary Ann Lasch, FASLA From: Eric Link, CCT Date: March 14, 2012 Subject: Tiger Grant Pedestrian Walkway and Parking Garage- Conceptual,

Rough Order of Magnitude Cost Estimate

Estimate Overview

This Cost Estimate is based on the provided drawings and sketches for the Pedestrian Walkway/ Parking Garage

project located in Cleveland, Ohio. The documents were received by URS Pittsburgh Cost Estimating Department

between 03/06/2012 and are dated 03/14/2012. In addition, other details and clarifications provided by the client

and/or design team are incorporated.

Estimate Purpose

Conceptual Estimate

With conceptual estimating methods, the independent variables used in the estimating algorithm are generally

something other than a direct measure of the units of the item being measured. They usually involve simple or

complex modeling (or factoring) based on conferred or statistical relationships between costs and other, typically

design-related, parameters. Often the cost estimating relationships used in conceptual estimating methods are

somewhat subject to conjecture.

Conceptual Estimating Using PACES

Parametric Cost Engineering System (PACES) software is a cost engineering tool used to assist with the development

of planning and budgeting facility and infrastructure construction and renovation costs. PACES is an integrated PC-

based software system that prepares parametric cost estimates for new facility construction, renovation, and life cycle

cost analysis. PACES uses pre-engineered model parameters and construction criteria to accurately predict

construction costs with limited design information.

PACES is a parametric cost-estimating system for conventional construction projects and is targeted to government

and conventional construction estimators. Predefined and documented engineering relationships link the primary

parametrics to detailed engineering quantities. Quantities and most model assumptions can be changed by users.

PACES estimates are recognized by the Congressional Budget Office as accurate up to the 35% design stage, and they

have been validated to be within 7 1/2% of final, actual costs. If needed, estimates can be refined at later stages of

design. The database used is the Army Corps of Engineers Unit Price Book.

Conceptual estimating methods that were used in the preparation of the cost estimate are:

Page 2: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Eric Link 03/14/2012 Page 2

• Capacity Factor Method: A capacity factored estimate is one in which the cost of a new facility is derived

from the cost of a similar facility with known (but usually different) capacity. This method relies on the non-

linear relationship between capacity and cost.

• Ratio or Factor Methods: Ratio or factored estimating methods are used in situations where the total cost of

an item or facility can be reliably estimated from the cost of a primary component. For example these

methods are commonly used when estimating the cost of specialized process equipment that makes up the

significant portion of the total project cost.

• The Parametric Method: A parametric model is a mathematical representation of cost relationships that

provides a logical and predictable correlation between the physical or functional characteristics of a project

and its resultant cost. A parametric estimate is developed using cost estimating relationships and other

estimating functions that provide logical and repeatable relationships between independent variables, such as

design parameters or physical characteristics; and the dependent variable, cost.

+

Project Request/ Long Range Planning Estimate

Similar Industry Terms for this Level of Estimate: Feasibility, Top Down, Capacity Factored

Accuracy Range: -50% to +100%

AACE Estimate Classification: Class 5

Development: The project request/long-range planning estimates will be developed using information gathered from

the client and/or design team. The estimate is compiled to determine the Preliminary Design Report and Capital

Budget. The estimate is built using capacity factored modules based on comparative historical data. Statistical data is

collected and compiled and a relative algorithmic curve was established for each of the project. The cost curves are

incorporated in the statistical module and applied to the project. The estimate is defined by the module and is adjusted

by the estimator to incorporate complexities anticipated with the project. This “adjustment” will relies on the

collective experience of the Estimating Group. The estimate is presented in Capacity Factored Units with lines

encoded into Work Breakdown Structure.

Planning Level Design Estimate

Similar Industry Terms for this Level of Estimate: Rough Order of Magnitude, Budget, Scope Development, Concept

Study

Accuracy Range: -30% to +50%

AACE Estimate Classification: Class 4

Development: The planning level design estimates are developed using information gathered from the client and/or

design team. This estimate is developed when an initial construction budget is required. The accuracy of the planning

level design estimate depends on several factors including the level of project definition, the quality of past historical

cost data used in development, and the judgment and experience of the Estimating Group. The estimates will be

organized is organized by a Work Breakdown Structure with estimate lines coded in the CSI Masterformat 2004

classification system.

Estimate Contingencies/ Markups

• Contractor’s Overhead: This is the cost of doing business. The Estimating Group calculates this percentage

by gauging the amount of annual construction work of the contractor performing the work, on the particular

project size and complexity, as well as the knowledge of what historically has been used on similar project of

this type.

• Contractor’s Profit: This includes the cost amount as compensation for risk and efforts to undertake and

complete the project. This percentage is based directly on economic conditions for local construction

Page 3: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Eric Link 03/14/2012 Page 3

industry, the individual contractor’s overhead costs, and their perception of the risk of losing money on the

project.

• Design Contingency: As the design progresses through the project design life cycle, a percentage is typically

added to the estimate to account for uncertainties inherent in the estimating process. This percentage is

anticipated by the estimator as the relative stability of the design documents, project scope, and assumptions

upon which the estimate is based are assessed. The design contingency percentage should decrease as the

design life cycle progresses. The design contingency percentage calculates off of the raw capital cost in the

estimate. Items typically covered by design contingency are:

• Design that may not be complete enough to determine final quantities at the time of

estimate preparation.

• Some items may defy precise quantification as to what is required to be estimated.

• Some items to be quantified that are generally computed by factors for other conceptual

methods.

• Mid-Project Escalation: This is a provision for an increase in the cost of equipment, material, and labor

above the costs specified in the contract, due to continuing price changes over time. The Estimating Group

trends market conditions to temper and forecast escalation percentages.

• Construction Contingency: The construction contingency amount relies upon the technical ability of the

estimator or the estimating team, and is used in the estimate to deal with the uncertainties inherent in the

project design process. It is the responsibility of the estimator to assess all of the documents used to

assemble the estimate to verify completeness and accuracy. From this assessment, the estimator will

formulate the project contingency amount for the estimate. The project contingency amount is applied using

a percentage variable that calculates off of the initial construction raw costs, plus markups and escalation.

Construction contingency is a factor added to the estimate to account for the estimators anticipated overrun

of the estimate due to the following:

• Errors and omissions in the design process.

• Design that may not be complete enough to determine final quantities at the time of

estimate preparation.

• Labor productivity variability.

• Labor availability, skills, and productivity that may vary from the fact originally assumed.

• Estimator assumed change orders that may be inherent within the project design.

Estimating Team

Leonard Calianno, CEP

Manager of Pre- Construction Services

412-503-4691 (Direct)

412-298-1605 (Cell)

[email protected]

Role in estimate: QA/QC

Eric Link, CCT

Senior Cost Estimator

412-503-4647 (Direct)

412-320-1109 (Cell)

[email protected]

Role in estimate: Pedestrian Walkway, Parking Garage (Capacity Factor Portion)

Page 4: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Eric Link 03/14/2012 Page 4

Russell Link, CCT

Cost Estimator

412-503-4624 (Direct)

[email protected]

Role in estimate: Parking Garage (PACES/ Parametric Portion)

Page 5: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Conceptual Cost Estimate - Rough Order of Magnitude

3/14/2012

Item Code Description Quantity UOM Unit Cost Total Cost

1 Pedestrian Walkway LS $8,039,000.00

1.01 General Conditions 1 LS $748,000.00 $748,000.00

1.02 Earthwork 1 LS $291,000.00 $291,000.00

1.03 Pier Foundations 1 LS $960,000.00 $960,000.00

1.04 Bridge Piers 1 LS $820,000.00 $820,000.00

1.05 Pier Cross Girders 1 LS $110,000.00 $110,000.00

1.06 Walkway Box Beams 1 LS $362,000.00 $362,000.00

1.07 Walkway Deck 1 LS $862,000.00 $862,000.00

1.08 Walkway Topping Slab 1 LS $235,000.00 $235,000.00

1.09 Masonry Work 1 LS $468,000.00 $468,000.00

1.10 Guard Railings @ Masonry Walls 1 LS $205,000.00 $205,000.00

1.11 Ramp to Science Center Area 1 LS $750,000.00 $750,000.00

1.12 Enclosed Walkway 1 LS $1,900,000.00 $1,900,000.00

1.13 Miscellaneous Site Demo 1 LS $180,000.00 $180,000.00

1.14 Miscellaneous Utility Work 1 LS $50,000.00 $50,000.00

1.15 Miscellaneous RR Track Work 1 LS $98,000.00 $98,000.00

2 Parking Garage - 4 Level LS $27,921,084.00

2.01 Substructure 1 LS $634,507.00 $634,507.00

2.02 Superstructure 1 LS $15,401,619.00 $15,401,619.00

2.03 Exterior Closure 1 LS $1,235,947.00 $1,235,947.00

2.04 Roofing 1 LS $9,941.00 $9,941.00

2.05 Interior Construction 1 LS $260,981.00 $260,981.00

2.06 Interior Finishes 1 LS $54,616.00 $54,616.00

2.07 Conveying System 1 LS $106,903.00 $106,903.00

2.08 Plumbing System 1 LS $857,074.00 $857,074.00

2.09 HVAC System 1 LS $1,560,947.00 $1,560,947.00

2.10 Fire Protection System 1 LS $1,593,569.00 $1,593,569.00

2.11 Electrical Systems 1 LS $2,784,979.00 $2,784,979.00

2.12 Sitework 1 LS $3,420,001.00 $3,420,001.00

$35,960,084.00

2.00% $719,201.68

$36,679,285.68

12.00% $3,961,362.85

$40,640,648.53

5.00% $2,032,032.43

$42,672,680.96

10.00% $4,267,268.10

$46,939,949.06

3.00% $1,408,198.47

7.00% $3,285,796.43

7.00% $3,285,796.43

$54,919,740.40

$37,551,959.24

$46,939,949.06

$56,327,938.87

Sub Total

General Contractor Overhead and Profit

Sub Total

Design Contingency

Project: Tiger Grant Pedestrian Bridge and Parking Garage

Location: Cleveland Ohio

Sub Total

Escalation to 2013

Sub-Contractor Overhead and Profit (Assumes 90% Subs @

15%)

Sub Total

High End Construction Cost (Assumes +/- 20% Level Of

Accuracy For Conceptual Estimate)

Total Construction Cost

Low End Construction Cost (Assumes +/- 20% Level Of

Accuracy For Conceptual Estimate)

Total Construction Cost

Construction Contingency (Reserved For Change Orders)

Total Capital Cost

Administrative Fees

Design Fees

Page 6: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Conceptual Cost Estimate - Rough Order of Magnitude

3/14/2012

Item Code Description Quantity UOM Unit Cost Total Cost

1 Pedestrian Walkway LS $8,039,000.00

1.01 General Conditions 1 LS $748,000.00 $748,000.00

1.02 Earthwork 1 LS $291,000.00 $291,000.00

1.03 Pier Foundations 1 LS $960,000.00 $960,000.00

1.04 Bridge Piers 1 LS $820,000.00 $820,000.00

1.05 Pier Cross Girders 1 LS $110,000.00 $110,000.00

1.06 Walkway Box Beams 1 LS $362,000.00 $362,000.00

1.07 Walkway Deck 1 LS $862,000.00 $862,000.00

1.08 Walkway Topping Slab 1 LS $235,000.00 $235,000.00

1.09 Masonry Work 1 LS $468,000.00 $468,000.00

1.10 Guard Railings @ Masonry Walls 1 LS $205,000.00 $205,000.00

1.11 Ramp to Science Center Area 1 LS $750,000.00 $750,000.00

1.12 Enclosed Walkway 1 LS $1,900,000.00 $1,900,000.00

1.13 Miscellaneous Site Demo 1 LS $180,000.00 $180,000.00

1.14 Miscellaneous Utility Work 1 LS $50,000.00 $50,000.00

1.15 Miscellaneous RR Track Work 1 LS $98,000.00 $98,000.00

2 Parking Garage - 3 Level LS $22,545,591.00

2.01 Substructure 1 LS $495,248.00 $495,248.00

2.02 Superstructure 1 LS $12,021,339.00 $12,021,339.00

2.03 Exterior Closure 1 LS $964,687.00 $964,687.00

2.04 Roofing 1 LS $7,759.00 $7,759.00

2.05 Interior Construction 1 LS $203,702.00 $203,702.00

2.06 Interior Finishes 1 LS $42,629.00 $42,629.00

2.07 Conveying System 1 LS $83,440.00 $83,440.00

2.08 Plumbing System 1 LS $669,444.00 $669,444.00

2.09 HVAC System 1 LS $1,219,099.00 $1,219,099.00

2.10 Fire Protection System 1 LS $1,244,577.00 $1,244,577.00

2.11 Electrical Systems 1 LS $2,173,666.00 $2,173,666.00

2.12 Sitework 1 LS $3,420,001.00 $3,420,001.00

$30,584,591.00

2.00% $611,691.82

$31,196,282.82

12.00% $3,369,198.54

$34,565,481.36

5.00% $1,728,274.07

$36,293,755.43

10.00% $3,629,375.54

$39,923,130.98

3.00% $1,197,693.93

7.00% $2,794,619.17

7.00% $2,794,619.17

$46,710,063.24

$31,938,504.78

$39,923,130.98

$47,907,757.17

Total Capital Cost

Low End Construction Cost (Assumes +/- 20% Level Of

Accuracy For Conceptual Estimate)

Total Construction Cost

High End Construction Cost (Assumes +/- 20% Level Of

Accuracy For Conceptual Estimate)

Sub Total

General Contractor Overhead and Profit

Sub Total

Design Contingency

Total Construction Cost

Construction Contingency (Reserved For Change Orders)

Administrative Fees

Design Fees

Sub-Contractor Overhead and Profit (Assumes 90% Subs @

15%)

Project: Tiger Grant Pedestrian Bridge and Parking Garage

Location: Cleveland Ohio

Sub Total

Escalation to 2013

Sub Total

Page 7: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,

Project Actual Location Actual GSF Escalated GSF

Total Building Cost

- Cleveland $ -

2012

Building Cost Per

SF- Cleveland $ -

2012

Total Non-Building

Cost - Cleveland $ -

2012

Non-Building Cost

Per SF- Cleveland

$ - 2012

Total PROJECT

COST - Cleveland $

- 2012

Total Project Cost

Per SF- Cleveland

$ - 2012

Pensacola Regional Aiport FL- Other 537,170 370,000 $34,254,868.00 $92.58 $7,628,074.00 $20.62 $41,882,942.00 $113.20

Trump Taj Mahal Hotel Parking NJ- Atlantic City 883,800 370,000 $15,898,760.00 $42.97 $1,020,866.00 $2.76 $16,919,626.00 $45.73

Mercy Health Parking Garage PA- Pittsburgh 220,000 370,000 $20,750,277.00 $56.08 $1,488,920.00 $4.02 $22,239,197.00 $60.11

Trenton State College PK Structure NJ- Trenton 264,330 370,000 $10,678,745.00 $28.86 $1,002,701.00 $2.71 $11,681,446.00 $31.57

Parking Deck and Data Center AL- Birmingham 280,000 370,000 $48,426,049.00 $130.88 $4,037,218.00 $10.91 $52,463,267.00 $141.79

One Westside Parking Garage CA- Los Angles 292,656 370,000 $20,848,484.00 $56.35 $2,216,384.00 $5.99 $23,064,868.00 $62.34

Renaissance Parking Garage MA- Boston 301,000 370,000 $34,856,058.00 $94.21 $3,420,001.00 $9.24 $38,276,059.00 $103.45

Nova SE Health Parking Garage FL- Other 414,588 370,000 $14,434,117.00 $39.01 $4,630,455.00 $12.51 $19,064,572.00 $51.53

Tenth Street Place CA- Other 472,680 500,000 $38,801,429.00 $77.60 $4,343,964.00 $8.69 $43,145,393.00 $86.29

** All Costs are escalated to 2012 Cleveland Ohio $$ LOW $10,678,745.00 $28.86 $1,002,701.00 $2.76 $11,681,446.00 $31.57

MEDIAN $20,848,484.00 $56.35 $3,420,001.00 $8.69 $23,064,868.00 $62.34

AVERAGE $26,549,865.22 $68.73 $3,309,842.56 $8.61 $29,859,707.78 $77.33

HIGH $48,426,049.00 $130.88 $7,628,074.00 $20.62 $52,463,267.00 $141.79

SUMMARY

Page 8: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 9: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 10: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 11: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 12: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 13: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 14: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 15: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,
Page 16: Basis of Estimate Memorandum - Clevelandplanning.city.cleveland.oh.us/grants/tiger4/Cost Estimate...Estimate Memorandum/ Basis of Estimate To: Mary Ann Lasch, FASLA From: Eric Link,