ESCRI-SA Battery Energy Storage System Dalrymple North...On Wednesday 29 April 2020 at 08:29,...
Transcript of ESCRI-SA Battery Energy Storage System Dalrymple North...On Wednesday 29 April 2020 at 08:29,...
ESCRI-SA Battery Energy Storage System
Dalrymple NorthESCRI-SA Knowledge Sharing Reference Group
Meeting # 6 - 16 September 2020
Dalrymple
North
ESCRI-SA
Battery
Energy
Storage
System
(BESS)
2
ESCRI-SA Dalrymple BESS
Project UpdateESCRI-SA Knowledge Sharing Reference Group
16 September 2020
Outline
▪ Project Update
▪ 6 Monthly Operational Report
▪ ElectraNet Perspective
▪ AGL Perspective
▪ Reflections on the impact of ESCRI-SA (ElectraNet, AGL, Advisian, ARENA)
▪ Q&A
▪ Acknowledgements
4
Project scope and objectives
5
1. Gain practical experience and learnings from the application of grid connected utility
scale battery storage as an enabler of large scale intermittent renewable energy on an
interconnected system
2. Demonstrate that utility scale battery storage can effectively provide network reliability
and security services alongside market services
3. Demonstrate network ownership of battery storage and commercial appropriate
separation of provision of regulated services and competitive energy market services
4. Demonstrate “seamless” islanded operation with 100% renewable generation following
transmission outages
Scope: Nominal 30 MW, 8 MWh lithium-ion battery
Heywood interconnector
Melbourne
Adelaide
Location at the edge of NEM
6
• Connection at 33 kV at Dalrymple
substation on Yorke Peninsula – land
available
• Opportunity to reduce expected
unserved energy under islanding
conditions (max demand is about 8 MW
but on average need about 3 MW for 2
hours)
• Site is close to the 91 MW Wattle Point
Wind Farm – provides opportunity for
battery to support islanded operation
with the wind farm and 2 MW of local
rooftop solar, following network outages
Utility scale BESS near the end of a long radial line in proximity to a wind farm
ESCRI-SA
132 kV single
circuit line
Wattle Point wind farm
Adelaide
Integration at ElectraNet’s Dalrymple substation
7
66 km25 km
Dalrymple BESS30 MW / 8 MWh
Dalrymple substation
132 kV
33 kV
Wattle Point Wind Farm 91 MW(55 x Vestas V82 directly
coupled induction generators)
Load/DER-1 .. 8 MW
Images (left to right): Wind farm: Flickr https://www.flickr.com/photos/daveclarkecb/BESS: ElectraNetBESS and substation: Courtesy Google Maps
Upstream grid
BESS building
BESS and Dalrymple substation
Services provided
to customers and
NEM participants
ElectraNetowns battery &
provides regulated
services
ARENAgrant part
funding
Regulated services
Reduced unserved energy
Fast frequency response
Competitive market
servicesFCAS
Market caps
Commercial arrangements
8
Assets and
operation
Funding and
commercials
Operational
control
Availability
Guarantee
Benefits Payments
Operating
Principles
ESCRI BESS
Providing both regulated and competitive market services
AGL leases battery
from ElectraNet
and is battery
operator
EPC/ D&C contract and 12-year maintenance agreement awarded to Consolidated
Power Projects (CPP) following extensive procurement process
Reflection on Project Outcomes and
Knowledge Sharing Deliverables
Project Outcomes - Achieved
10
Outcome Comment
Demonstrate the deployment and operation of a large
scale BESS to deliver a combination of network and
market benefits
Achieved. The BESS entered commercial operation on
14 December 2018
Demonstrate a contracting and ownership model to
maximise the value of a BESS
Achieved. Wattle Point wind farm integration allows AGL
use of BESS MWh capacity between 10% – 90%
Test the regulatory treatment for the ownership of
large-scale BESS by regulated transmission network
service providers
Achieved. The AER has accepted ElectraNet's proposed
regulatory treatment of the BESS at Dalrymple
Provide price discovery for the deployment of a
large-scale grid connected BESS
Achieved. Price discovery provided for capital
expenditure. Reporting on operational performance and
market revenue in Operational Reports
Highlight and address technical and regulatory
barriers in the deployment of large scale batteries
Achieved. Regulatory treatment accepted and BESS
registered by AEMO
Knowledge Sharing Portal
▪ ARENA knowledge sharing commitments
□ Project delivering substantial knowledge sharing
benefits to stakeholders
▪ Real-time data
▪ Data downloads
▪ Reports
▪ Presentations
▪ Knowledge Sharing Reference Group
□ Agendas
□ Minutes
11
www.escri-sa.com.au
Portal usage
12
14/12/18 to
14/06/19
14/06/19 to
14/12/19
14/12/19 to
14/06/20Total
Page views 1241 799 683 2723
Unique page
views984 666 592 2242
Average time
on page1:54 2:14 3:04 2:13
Number of
report/
presentation
downloads
76 47 46 169
Number of
data
downloads
230 103 57 390
Knowledge Sharing Deliverables
13
Deliverable Requirement Actual
Establish Knowledge Sharing Reference Group, hold
regular meetings6 6
Technical Open Days (Site visit) 2 2
Web portal with knowledge sharing material, including
operational data1 1
Formal knowledge sharing reports 7 5
Other reports and technical articles - 2
Presentation at industry conferences 6 9
Direct engagement with other industry participants
(national and international)- 6
Transfer of portal information to ARENA 1 Future
Dalrymple
North
ESCRI-SA
Battery
Energy
Storage
System
(BESS)
14
ESCRI-SA Ongoing Performance
6 Monthly Operational ReportESCRI-SA Knowledge Sharing Reference Group
16 September 2020
Outline
▪ General asset performance and metrics
▪ What O&M is occurring
▪ Safety performance and observations
▪ System events and incidents
▪ R2 model validation
16
Key Metrics – First 18 months of operation
17
Key Performance Metric
Value for reporting
period
(14/12/18 – 14/06/19)
Value for reporting
period
(14/06/19 – 14/12/19)
Value for reporting
period
(14/12/19 – 14/06/20)
Average BESS Availability 98.01% 97.35% 98.93%
Total Energy Consumed 1,370 MWh 2,006 MWh 1499 MWh
Total Energy Exported 160 MWh 768 MWh 198 MWh
Average auxiliary load and losses (%
of 30 MW rated capacity)2.19% 2.25% 2.35%
Number of Charge and Discharge
Cycles (per BOA definition)2 4 1
BESS Charging Cost $120,000 $101,000 $76,000
BESS Discharge Revenue $116,000 $97,000 $102,000
FCAS Revenue $1.33m $3.73m $15.6m
General Operational Issues to manage
▪ Availability
▪ Air conditioning
▪ Inverters & batteries
▪ Communications
▪ SCADA alarms
18
What O&M is occurring
▪ Routine
□ Site / housekeeping
□ Air conditioners
□ CO2 fire system
□ Diesel generator
□ Inverter maintenance
▪ Corrective (some common items)
□ Air conditioners
□ Communication alarms
□ Nuisance alarms
□ Security system
▪ Specific items
19
Air conditioners
▪ Since last update, all the 4 additional air conditioners have all been installed. This occurred early in this
reporting period. Reliability of the A/C has also improved.
▪ Work has mainly focussed on ducting, the idea is to produce an even cool airflow directly in front of the
inverters, rather that trying to cool the actual room.
▪ We will remove the old ducting and replace this with more directed solution.
▪ This has been done on one unit as a trial and the remaining units will be completed in early November.
▪ After this further adjustment of the A/C controls may be needed by Mitsubishi and adjustment of
temperature sensors on the inverters by ABB.
▪ Intent is conduct a high ambient temperature full discharge test when conditions allow (during Summer).
20
Ducting - old
21
Ducting - new
22
ESCRI-SA
PCS100
BESS
Modules
23
Inverters & Control System(s)
▪ “Reboot” issue
□ There remains an issue with the controller firmware that is causing a lock up and requires a reboot every approx.
100 days. This was thought to have been fixed, however this occurred again. ABB want to try a firmware update to
resolve.
▪ Some battery banks “going flat”/off target dispatch
□ Over time as particular inverter groups experience slightly different temperature derating, the battery banks’ SOC
will tend to diverge. This will eventually require ABB to equalise charge on Powerstores (1/12th) or cause a trip on
low charge
□ ElectraNet or AGL do not have the ability to individually equalise charge
▪ Inverter failures
□ We had 2 inverter failures during this reporting period
□ Also replaced a handful of inverter cooling fans
24
Batteries
25
Batteries
▪ Guaranteed remaining battery MWh capacity (annual)
▪ This is determined by an annual charge discharge test.
▪ Prior to a test being conducted Samsung should conduct routine maintenance equalisation and
calibration of SOC being conducted prior. At that stage Samsung was not able to attend site to conduct
this work due to COVID-19 restrictions.
▪ An indicative charge discharge test was conducted by CPP in April 2020.
▪ Indications from this test are the energy capacity was slightly short.
▪ Samsung equalisation work has been completed in Aug 2020.
▪ Plan to re-conduct test soon with the correct test methodology.
▪ No battery rack failures in this reporting period.
26
Safety performance and observations
Safety Incidents
▪ The Dalrymple North BESS site is predominately unmanned
▪ Apart from corrective maintenance, routinely there would only be site attendance 1 to 2 days a month
▪ There were zero safety incidents reported during the third six months of commercial operation
▪ This includes near miss or Lost Time Injuries
▪ Maintenance is undertaken via formalised safety procedures (SWMS/JSA managed by MSP)
Safety Notice – Fire system
▪ If a fire is detected, an audible signal will be triggered and all personnel that may be present in the
inverters or batteries room should evacuate immediately the building
▪ The fire suppression will then be activated 60 seconds later
▪ ElectraNet control centre will be notified and protocols exist as to how the fire brigade would intervene
27
System Events – First 18 months
▪ 21 operational system events:
▪ sixteen of these events were single-line trips or a frequency event
▪ The other 5 events were more significant and led to the BESS supplying load to
prevent or reduce the duration of an unserved energy event
▪ High-speed data recordings from Power System Performance Monitor (PSPM)
confirmed the BESS successfully rode through the fault or responded as
required
28
ESCRI-SA BESS Operating in Islanding Condition
Unplanned outages from 14 December 2019 – 14 June 2020
Unplanned outages
Over the past six months, from 14 December 2019
– 14 June 2020, the Dalrymple BESS responded to
several unplanned outages due to various reasons.
These unplanned outages are listed below:
▪ On 20 December 2019 at 13:52, the Ardrossan West –
Dalrymple 132 kV line successfully reclosed following a single
phase – ground fault resulting in the Dalrymple BESS
supplying the local load for a short period of time
▪ On 31 January 2020 at 17:59, the Ardrossan West –
Dalrymple 132 kV line successfully reclosed following a single
phase – ground fault resulting in the Dalrymple BESS
supplying the local load for a short period of time, and
▪ On 29 April 2020, inadvertent trips at Dalrymple due to tests
at the Wattle Point Wind Farm resulted in the Dalrymple
BESS supplying the local load for periods of time
30
31
▪ On 20 December 2019 at 13:52, the Ardrossan West - Dalrymple 132kV line tripped and successfully
reclosed following a single phase to ground fault caused by lightning. The Dalrymple local supply
remained connected and supplied by the Dalrymple BESS until re-synchronisation at 13:55
Ardrossan West – Dalrymple 132 kV line trip
32
▪ On Wednesday 29 April 2020 at 08:29, Dalrymple 132/33/11kV TF1 and TF2 inadvertently tripped due to
tests at the Wattle Point Wind Farm. The Dalrymple load was successfully supplied from the BESS and
operated in islanded mode for 14 minutes until attempting to re-synchronise at 08:43
▪ The BESS then tripped. Load was restored within minutes from the transmission network.
Inadvertent trips at Dalrymple
ESCRI-SA BESS Responding to System Events
Transmission single-line trips or a frequency event
ESCRI-SA BESS Performance During System Events
Over the past six months, from 14 December 2019 – 14 June 2020, six transmission network fault events
were relevant to the Dalrymple BESS, summarised below:
▪ On 20 December 2019 at 13:52, the Ardrossan West – Dalrymple 132 kV line successfully reclosed following a single phase – ground
fault
▪ On 13 January 2020 at 2:19, a CT failure at the Waterloo substation resulted in tripping various element in the Mid-North region
▪ On 31 January 2020 at 13:54, the collapse of a number of steel transmission towers on the Moorabool – Mortlake and Moorabool –
Haunted Gully 500 kV lines resulted in these lines tripping and remaining unavailable for service, effectively islanding South Australia
from the NEM
▪ On 31 January 2020 at 17:59, the Ardrossan West – Dalrymple 132 kV line successfully reclosed following a single phase – ground fault
▪ On 7 February 2020 at 11:44, the Munno Para – Blyth West 275 kV line successfully reclosed following a single phase – ground fault
▪ On 7 February 2020 at 12:26, the Clare North - Brinkworth 132kV line tripped and locked out following a 3 phase – ground fault
34
Current Transformer failure at the Waterloo substation (1/2)
▪ On the 13th January 2020 at 2:19:32, catastrophic failure of S phase CT 7022 at Waterloo resulted in
operation of the Waterloo South Bus Zone protection and CB7022 CB Fail protection. This resulted in
tripping of Waterloo TF5, Waterloo South Bus, Waterloo-Hummocks line and Hummocks TF1 (CB failed).
Dalrymple BESS response due to this fault are shown below.
35
36
Current Transformer failure at the Waterloo substation (2/2)
Clare North - Brinkworth 132kV line trip (1/2)
▪ On 7 February 2020 at 12:26, the Clare North - Brinkworth 132kV line tripped
and locked out following a three phase to ground fault. The Dalrymple BESS
successfully rode through the fault as shown in the graphs below.
37
38
Clare North - Brinkworth 132kV line trip (2/2)
▪ On 31 January 2020 at 13:54, the collapse of a
number of steel transmission towers on the Moorabool
– Mortlake and Moorabool – Haunted Gully 500 kV
lines resulted in these lines tripping and remaining
unavailable for service.
▪ South Australia and parts of Victoria, including
Mortlake Power Station and APD (Alcoa Portland),
were islanded from the NEM.
▪ Prior to the time when the double circuit tripped, SA
was exporting approximately 515 MW. SA system
demand was approximately 2648 MW. There were 7
conventional generators online at the time in SA, with a
total output of 1559 MW.
39
South Australia islanding from the NEM (1/2)
▪ Dalrymple BESS response due to this over-frequency
event is illustrated in the graphs to the right.
▪ Power flow on the Heywood interconnector and frequency
measured at South East substation are illustrated in the
graph below.
40
South Australia islanding
from the NEM (2/2)
ESCRI-SA BESS R2 model validation
42
Traditional Connection application process
I. Finalise initial R1 model package (PSSE, PSCAD &
Power factory)
II. Finalise generator performance standard (GPS)
III. Finalise customer performance standard (CPS)
IV. Commissioning tests (hold point test)
V. Submit final R2 model package
ESCRI islanding
- Model validation for islanding tests (PSCAD)
- Islanding tests with loads
- Islanding tests with wind farm and loads
- Black start tests
+
R2 model validation process
Single set of parameters required for seamless transition from grid connected to islanded operation
Issues raised from R2 test
▪ Major: Power system modelling guideline non-compliant
□ Voltage and reactive power responses from simulation models in voltage control mode are outside the 10% band
requirement for S5.2.5.13 assessment
− No limiter operation
− Limiter operation
□ ( primary control mode is power factor)
▪ Minor: Model fixing
□ Better alignment of PSSE and PSCAD models, especially with inertia response/ overload capability response
□ Long PSCAD model initialisation time
43
44
Voltage at 33 kV Reactive power at 33 kV
30 MW discharge with + 5% voltage step – Improved performance with new model
R2 test performance
45
System frequency at 33 kV Active power response from ESCRI at 33 kV
SA islanded
R2 system event performance - 31 January 2020PSSE model does not
have the islanded
operation functionality
Very good actual performance vs. PSSE & PSCAD model alignment
Thank you
Hugo Klingenberg
Laurie Antal
Viet Trinh
Fida Rafi