equipmentqualification-121207095652-phpapp01

download equipmentqualification-121207095652-phpapp01

of 29

Transcript of equipmentqualification-121207095652-phpapp01

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    1/29

    Equipment Qualification Fit for Intended Use

    IVT18th Annual Validation Week

    October, 2012

    Presented By:

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    2/29

    Agenda

    Equipment Qualification TerminologyIntended Use - User RequirementsMaintaining the Qualified State Interactive ExerciseBonus Material

    2IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    3/29

    Terminology

    Risk Assessment- Determines the ability/likely hood that thesubject equipment can impact product quality, efficacy, patientor care provider safety.

    Commissioning - The purpose of Commissioning is toestablish confidence that the equipment or system is safe andfunctional and that it meets established requirements and

    specifications. For equipment or systems with a direct orindirect affect on product quality, commissioning establishes that

    the equipment or system is ready for turnover to qualification

    and validation. Turnover at the end of commissioning also

    places the equipment or system under formalized changecontrol. For projects where formal FAT, SAT, or Commissioningactivities are not performed, those activities must be completed

    during the Qualification phases.

    3IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    4/29

    Terminology (cont.)

    Factory Acceptance Test (FAT)The purpose of FAT is to establish confidence that the equipment or system is tested to the

    extent possible at the manufacturers facility and that it is ready for shipment and installation

    at the operational site. The extent of testing is agreed with the manufacturer in advance and

    is documented in a test plan or protocol. FAT activities may include:

    Verification that the equipment or system has been constructed in conformance

    with the Purchase Order and other Engineering specifications.Safety issues and concerns have been addressed if applicable (e.g. Safety

    Assessment).

    Any software associated with the equipment or system has been verified for

    proper installation and security.

    The equipment will perform the specified operations as designed and

    documented

    Any issues or concerns are addressed by the vendor prior to shipment andacceptance by the customer.

    All required drawings, documents, cut-sheets, sequence of operations, etc. are

    properly documented and delivered by the vendor.

    Reference to documented results in the FAT may be appropriate for subsequent

    qualification activities if it was planned, executed, and documented to a sufficient

    level to do so.

    4IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    5/29

    Terminology (cont.)

    Site Acceptance Test (SAT)The purpose of SAT is to establish confidence that the equipment or system has been built to design

    specifications, assembled, and debugged by the manufacturer at the operational site, and that it isready for turnover to the customer for acceptance. The extent of testing is agreed with themanufacturer in advance and is documented in a test plan or protocol. Once the SAT is approved

    the customer owns the equipment.

    Typically the SAT is a repeat* of the FAT along with testing for anything that was discovered,repaired, redesigned, etc. during or after the FAT.

    SAT activities may include:

    Visual and or other inspections to ensure no damage occurred during shipment.

    Reassembly if the equipment had to be shipped in pieces due to size or other issues

    Verification that the equipment or system has been constructed in conformance with the

    Purchase Order and other Engineering specifications.

    Any software associated with the equipment or system has been verified for properinstallation and security.

    Start up and running with the site utilities to ensure the equipment operates the sameas at the FAT

    All required drawings, documents, cut sheets, sequence of operations are complete andappropriate from the vendor.

    *Reference to documented results in the SAT may be appropriate for subsequent

    qualification activities if it was planned, executed, and documented to a sufficient level to do so.

    5IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    6/29

    Terminology (cont.)

    Installation Qualification Documentation of objective evidenceshowing that the equipment has been installed according to

    specifications (manufacturers recommendations)

    Operational Qualification - Documentation of objective evidenceshowing that the equipment operates according to specifications (User

    Guide, User Requirements)

    6IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    7/29

    Whats the difference between Validation and

    Qualification?

    Validation means confirmation by examination and

    provision of objective evidence that specified requirements

    have been fulfilled. (CFR 21 Part 820.3 (z))

    Qualification

    Not defined by FDA Subset of validation Provides documented evidence that the subject

    equipment has been installed per specification

    (manufacturer's recommendations) and will attain and

    maintain critical process parameters repeatedly andreliably.

    Typically done as part of a larger validation effort. May support multiple validation efforts. (see slide #26)

    IVT Validation Week - October, 2012 7

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    8/29

    Getting Started

    Validation TeamThe Project Leader is responsible to form a multi-functional team to

    plan and oversee the validation activities. A team approach

    assures that the validation processes are well thought out, theprotocols are comprehensive, and that the final packages are well

    documented and easy to follow. Members of the validation team

    could include representatives from or personnel with expertise in:

    Quality Assurance (must be a member of all validation teams) Engineering Manufacturing Others depending on facility organization and equipment/product

    types:o Laboratoryo Technical Serviceso Research & Developmento Regulatory Affairs

    IVT Validation Week - October, 2012 8

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    9/29

    Getting Started

    For all phases described, the Project Team must:

    Determine what, how and when to verify/measure. Determine how many to verify/measure, i.e. statistical

    significance.

    Define acceptance/rejection criteria. Identify required documentation. The division of responsibilities and activities must be

    determined by the Project Team based on the Risk

    Assessment to provide a high degree of assurance that

    the equipment under test is suitable for its intended

    purpose.

    IVT Validation Week - October, 2012 9

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    10/29

    Intended Use

    User Requirements - A stand alone document that iscommon for computer systems. For equipment User

    Requirements come from many sources.

    Commercial Off The Shelf (COTS) equipment, they usuallytake the form of Owners Manual or Users Guides. Maybe a

    Request for Quote (RFI) if the equipment is custom.Other sources:

    Set up sheetsDesign of ExperimentParameter Limit Values

    Environmental requirements and/or constraintsManufacturers installation guide

    Regardless of their origin they form the basis for your Risk

    Assessments and Acceptance criteria

    IVT Validation Week - October, 2011 10

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    11/29

    Risk Assessment

    CONDUCTING RISK ASSESSMENT

    A risk assessment must be performed for all validations anddetermines the documentation deliverables.

    The risk assessment will determine the validation parameters of the

    overall equipment or system and the required functions.The assessment must also analyze the potential failure and faultmodes of the equipment or system to determine if the design is

    appropriate and to gauge the relative level of validation testing and

    need for external safeguards.

    Risk assessment must be conducted using methods appropriate to

    the scope and nature of the validation project.The conclusions of the risk assessment process may be included in

    a project Validation Plan, in individual protocols, or in a separatedocument.

    IVT Validation Week - October, 2012 11

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    12/29

    EQUIPMENT QUALIFICATIONREQUIREMENTS

    The following GAMP V Model (Figure 1) demonstrates the

    traceable approach to equipment qualification

    IVT Validation Week - October, 2012 12

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    13/29

    Dont forget the software!

    Conducting GxP AssessmentAll equipment systems must be assessed for their impact to patient

    safety, product quality and data integrity. This assessment will be

    accomplished by following SOP-MD-2010411, GXP Assessment

    System Categorization.

    IVT Validation Week - October, 2012 13

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    14/29

    Validation Requirements Based on GxPAssessment

    Each piece of computerized equipment or computerized systemdetermined as GxP as a result of the GxP assessment is assigned

    a criticality per SOP-XYZ based on the use and application of theequipment with rationale.

    Equipment criticality is assessed by performing risk assessment

    directly on equipment or through process and/or product.

    All equipment systems determined as GxP related are categorized

    as Non-configured, Configured, or Custom.

    IVT Validation Week - October, 2012 14

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    15/29

    IVT Validation Week - October, 2011 15

    Category Description Examples Requirements

    Non-Computerized Process impact equipment withno computerized component

    o Molding toolso Manual Presso Solvent Dispensers

    o Product Risk Assessmento Equipment Identificationo Risk based test against process identified

    parameters

    Non-ConfiguredRun-time parameters may beentered and stored, but the

    software cannot be configuredto suit the business process.

    o Firmware based applicationso COTS Software/equipmento Instruments

    o Abbreviated life cycle approacho Abbreviated (i.e. equipment specifications or

    manuals)o Installation Qualification and version controlo Risk-based approach to supplier assessmento Version controlo Risk-based test against (for simple systems

    regular calibration may substitute for testing)o Verify procedures are in place for maintaining

    compliance and fitness for intended use

    ConfiguredSoftware that can beconfigured by the user to meet

    the specific needs of the usersbusiness/manufacturing

    process. Software code is not

    altered.

    o LIMSo SCADAo Spreadsheetso Simple Human Machine

    Interfaces(HMI)Note: specific examples of the above

    system types may contain

    substantial custom elements.

    o Life cycle approacho Risk-based approach to supplier assessmento Demonstrate supplier has an adequate Quality

    Management Systemo Some life cycle documentation (DS) retained by

    supplier.o Installation Qualification against Design

    Qualificationo Operational Qualification against Functional

    Specificationo Performance Qualification against .o Version controlo Risk-based testing to demonstrate application

    works as designed.o Verify procedures are in place for maintaining

    compliance and fitness for intended use

    Custom Software custom designed andcoded to suit the businessprocess.

    o Internally and externallydeveloped IT applications

    o Internally and externallydeveloped process control

    applicationsCustom ladder logic

    Same as for configurable, plus:oMore rigorous supplier assessment.oPossible supplier auditoPossession of full life cycle documentationoDesign and source code review

    Computer System Validation requirements

    Some Examples

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    16/29

    Installation Qualification (IQ)

    The purpose of the IQ is to establish by objective evidence

    that the equipment as installed or modified. For equipment

    qualifications, an IQ should contain these minimum

    requirements.

    IVT Validation Week - October, 2012 16

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    17/29

    Installation Qualification

    Purpose Scope Equipment descriptiono Boundaries ancillary equipment

    Environment Critical Utilities Drawings Preventive Maintenanceo Spare Parts

    Product Contacto Cleaning procedureso Materials of construction Product Contact

    17IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    18/29

    IVT Validation Week - October, 2012 18

    Section Requirement/Content

    Purpose State the equipment needs to be qualified

    Scope State whether the installation is for

    o New equipment oro Modifying previous qualified equipment

    Equipment/

    System Description

    Describe what the equipment does, how it is used, what process/products use it, and its basic design features

    Supplier Vendor certification and safety feature verification

    Equipment Components Identify and briefly describes each major component of the subject equipment Define the system/equipment boundaries with other systems or equipment Ancillary equipment used in conjunction with the equipment being qualified should be identified as appropriate

    Utilities Utilities required to operate the equipment should be identified

    Construction, Installation andRequirements

    Specify the cleaning procedures that must be executed after the equipment is installed Document that the cleaning procedures have been successfully executed and completed

    Supporting Documentation List supporting documentation that may be used to identify or operate the equipment such as EngineeringTurnover Packages, Purchase Orders, or Equipment Manuals

    Maintenance Programs Establish maintenance procedure Include a listing of any preventive maintenance activities

    Spare/Change Parts Provide a list of spare parts and change parts, if applicable, required for system operation, including a description ofthe part and part number of reference

    Drawings List and include in the qualification protocol for the system drawings used to support the IQ

    Testing and Acceptance Criteria Acceptance criteria must be approved by the site designate review board or project team prior to executing anyIQ

    Define the test procedure; IQ testing must be designed to confirm that the equipment is installed in accordancewith manufacturers recommendation or document justification for exceptions

    Define the acceptance criteria; for an IQ this is usually a Pass/Fail resultDiscrepancies Discuss and justifies events per required deviation or exception procedure

    Summary and Conclusion Summarize IQ test results, which demonstrate that the equipment was installed correctly Provide a conclusion on whether the equipment installation is acceptable

    Installation Qualification (IQ)

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    19/29

    Installation Qualification (IQ)

    The IQ will document that the required design feature have

    been properly installed. The number of design features can

    vary from a few to any number of design features. Design

    features are dependent upon the complexity of the

    equipment.The following slide contains examples of various designfeatures that may be considered.

    IVT Validation Week - October, 2011 19

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    20/29

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    21/29

    Operational Qualification (OQ)

    User Guides/Manuals Critical Process Parameters Environment Critical Utilities

    21IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    22/29

    Operational Qualification (OQ)

    At minimum the OQ must include and/or address the items

    in this section. Statistical tools such as design experiment

    and/or response surface design should be applied to

    optimize equipment and process performance.

    IVT Validation Week - October, 2012 22

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    23/29

    IVT Validation Week - October, 2012 23

    Section Requirement/Content

    Purpose State the equipment needs to be qualified

    Scope State whether the installation is foro New equipment oro Modifying previous qualified equipment

    Equipment/System Description Describe what the equipment does, how it is used, what process/products use it, and its basic design features

    If above fully described in the IQ, then a reference to the IQ is acceptable

    Operational Qualification Pre-requisites Verify all IQ tests have been completed prior to execution of operational qualification or that any IQ testing not yet completedhas been identified in a protocol exception report as non-critical for OQ testing to begin

    Test Equipment Calibration Verification A completed record of qualified test equipment and approved materials that is used during protocol execution List calibration date and next due date

    Standard Operating Procedures Establish operating, maintenance, setup and/or cleaning procedures for the equipment Procedure(s) shall be approved and effected before or by end of OQ is completed

    Alarm/Control Challenges Identify and challenge critical alarms associated equipment/system. Note: In some cases, the alarm studies may bedeferred to an overriding operating system, such as Building Management System or equivalent

    Challenge the equipment/system operator controls and indicators such as controllers not challenged as part of aseparate software validation package and buttons, lamps, switches, etc. that are used for control or monitoring of the

    equipment

    Operating Parameters Verify the key and critical process parameters (some equipment may not have critical process parameters) Verify the operating ranges and acceptance criteria for each parameterNotes:

    Software parameters must also be considered; separate computer validation protocol can be used to address thisRationale and Sampling Locations Provide rationale for:

    Qualification approach takenSample size rationaleSelected test conditionsCritical parameters

    Testing and Acceptance Criteria Define the test range for each critical process parameter for verificationo The testing range typically brackets the operating range to ensure equipment is qualified with extra security;

    e.g., if temperature operating range is 50C to 100C, then the test range should be 40C to 110C

    The process will be challenged at the extremes of the critical process parameters wherever possible. The number of test runs needs to be statistically justified and it may be depending on the complexity of the equipment

    Test Result Documentation Summarize test results and confirms the acceptance criteria

    Discrepancies Discuss and justifies discrepancies

    Summary and Conclusion Summarize equipment OQ results and provide a conclusion on whether the equipment operation is acceptable

    Operational Qualification (OQ)

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    24/29

    Operational Qualification (OQ)

    Equipment Employed for Multiple Products

    When equipment is employed for multiple products, one may consider using

    theproven acceptable range (PAR) approach. The establishment of PAR

    to include operating and control parameters represents much of what

    process validation is all about. The function of PAR is to include and

    validate all corresponding control and operating ranges at the same time.

    The following is an example of equipment that employing three products or

    molds, for which temperature is one of the critical process control

    variables.

    The objective to challenge the operating range should test on the lowest

    and highest proven acceptable limits.

    IVT Validation Week - October, 2012 24

    Product A Product B Product COperating 90 -110 85 - 100 100 - 120

    Control 85 - 115 80 - 105 105 - 125Proven Acceptable 80 - 120 75 - 110 100 - 130

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    25/29

    Maintaining the Qualified State

    Training Preventive Maintenanceo Spare Parts List

    Calibration Change Control Re-Qualification

    25IVT Validation Week - October, 2012

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    26/29

    Re-Qualification

    Re-Qualification Review

    The validation status of qualified equipment must bereviewed to determine whether it continues to operate in a

    qualified state. With the exception of those processes that

    are subject to regulatory requirements regarding timespecific intervals for periodic re-qualification, the change

    control process is appropriate to determine re-qualification

    requirements to maintain the validated state.

    As part of the Change Control process, a validationassessment will be completed for each change to

    determine and document any potential validation impact

    and any actions deemed appropriate to ensure the

    validation status is maintained including the possibility of re-

    qualification. IVT Validation Week - October, 2012 26

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    27/29

    Documentation Strategies

    IVT Validation Week - October, 2012 27

    IOQ

    IQ OQ

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    28/29

    Interactive Stuff

    Participants develop an equipment qualification protocol

    IVT Validation Week - October, 2012 28

  • 7/27/2019 equipmentqualification-121207095652-phpapp01

    29/29

    BONUS Material

    Mold Validation Procedure Forms

    Production Equipment and Process validation ProcedureGxP Assessment Procedure

    IVT Validation Week - October, 2012 29