equipmentqualification-121207095652-phpapp01
-
Upload
abd-al-rahmman-al-qatanani -
Category
Documents
-
view
215 -
download
0
Transcript of equipmentqualification-121207095652-phpapp01
-
7/27/2019 equipmentqualification-121207095652-phpapp01
1/29
Equipment Qualification Fit for Intended Use
IVT18th Annual Validation Week
October, 2012
Presented By:
-
7/27/2019 equipmentqualification-121207095652-phpapp01
2/29
Agenda
Equipment Qualification TerminologyIntended Use - User RequirementsMaintaining the Qualified State Interactive ExerciseBonus Material
2IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
3/29
Terminology
Risk Assessment- Determines the ability/likely hood that thesubject equipment can impact product quality, efficacy, patientor care provider safety.
Commissioning - The purpose of Commissioning is toestablish confidence that the equipment or system is safe andfunctional and that it meets established requirements and
specifications. For equipment or systems with a direct orindirect affect on product quality, commissioning establishes that
the equipment or system is ready for turnover to qualification
and validation. Turnover at the end of commissioning also
places the equipment or system under formalized changecontrol. For projects where formal FAT, SAT, or Commissioningactivities are not performed, those activities must be completed
during the Qualification phases.
3IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
4/29
Terminology (cont.)
Factory Acceptance Test (FAT)The purpose of FAT is to establish confidence that the equipment or system is tested to the
extent possible at the manufacturers facility and that it is ready for shipment and installation
at the operational site. The extent of testing is agreed with the manufacturer in advance and
is documented in a test plan or protocol. FAT activities may include:
Verification that the equipment or system has been constructed in conformance
with the Purchase Order and other Engineering specifications.Safety issues and concerns have been addressed if applicable (e.g. Safety
Assessment).
Any software associated with the equipment or system has been verified for
proper installation and security.
The equipment will perform the specified operations as designed and
documented
Any issues or concerns are addressed by the vendor prior to shipment andacceptance by the customer.
All required drawings, documents, cut-sheets, sequence of operations, etc. are
properly documented and delivered by the vendor.
Reference to documented results in the FAT may be appropriate for subsequent
qualification activities if it was planned, executed, and documented to a sufficient
level to do so.
4IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
5/29
Terminology (cont.)
Site Acceptance Test (SAT)The purpose of SAT is to establish confidence that the equipment or system has been built to design
specifications, assembled, and debugged by the manufacturer at the operational site, and that it isready for turnover to the customer for acceptance. The extent of testing is agreed with themanufacturer in advance and is documented in a test plan or protocol. Once the SAT is approved
the customer owns the equipment.
Typically the SAT is a repeat* of the FAT along with testing for anything that was discovered,repaired, redesigned, etc. during or after the FAT.
SAT activities may include:
Visual and or other inspections to ensure no damage occurred during shipment.
Reassembly if the equipment had to be shipped in pieces due to size or other issues
Verification that the equipment or system has been constructed in conformance with the
Purchase Order and other Engineering specifications.
Any software associated with the equipment or system has been verified for properinstallation and security.
Start up and running with the site utilities to ensure the equipment operates the sameas at the FAT
All required drawings, documents, cut sheets, sequence of operations are complete andappropriate from the vendor.
*Reference to documented results in the SAT may be appropriate for subsequent
qualification activities if it was planned, executed, and documented to a sufficient level to do so.
5IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
6/29
Terminology (cont.)
Installation Qualification Documentation of objective evidenceshowing that the equipment has been installed according to
specifications (manufacturers recommendations)
Operational Qualification - Documentation of objective evidenceshowing that the equipment operates according to specifications (User
Guide, User Requirements)
6IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
7/29
Whats the difference between Validation and
Qualification?
Validation means confirmation by examination and
provision of objective evidence that specified requirements
have been fulfilled. (CFR 21 Part 820.3 (z))
Qualification
Not defined by FDA Subset of validation Provides documented evidence that the subject
equipment has been installed per specification
(manufacturer's recommendations) and will attain and
maintain critical process parameters repeatedly andreliably.
Typically done as part of a larger validation effort. May support multiple validation efforts. (see slide #26)
IVT Validation Week - October, 2012 7
-
7/27/2019 equipmentqualification-121207095652-phpapp01
8/29
Getting Started
Validation TeamThe Project Leader is responsible to form a multi-functional team to
plan and oversee the validation activities. A team approach
assures that the validation processes are well thought out, theprotocols are comprehensive, and that the final packages are well
documented and easy to follow. Members of the validation team
could include representatives from or personnel with expertise in:
Quality Assurance (must be a member of all validation teams) Engineering Manufacturing Others depending on facility organization and equipment/product
types:o Laboratoryo Technical Serviceso Research & Developmento Regulatory Affairs
IVT Validation Week - October, 2012 8
-
7/27/2019 equipmentqualification-121207095652-phpapp01
9/29
Getting Started
For all phases described, the Project Team must:
Determine what, how and when to verify/measure. Determine how many to verify/measure, i.e. statistical
significance.
Define acceptance/rejection criteria. Identify required documentation. The division of responsibilities and activities must be
determined by the Project Team based on the Risk
Assessment to provide a high degree of assurance that
the equipment under test is suitable for its intended
purpose.
IVT Validation Week - October, 2012 9
-
7/27/2019 equipmentqualification-121207095652-phpapp01
10/29
Intended Use
User Requirements - A stand alone document that iscommon for computer systems. For equipment User
Requirements come from many sources.
Commercial Off The Shelf (COTS) equipment, they usuallytake the form of Owners Manual or Users Guides. Maybe a
Request for Quote (RFI) if the equipment is custom.Other sources:
Set up sheetsDesign of ExperimentParameter Limit Values
Environmental requirements and/or constraintsManufacturers installation guide
Regardless of their origin they form the basis for your Risk
Assessments and Acceptance criteria
IVT Validation Week - October, 2011 10
-
7/27/2019 equipmentqualification-121207095652-phpapp01
11/29
Risk Assessment
CONDUCTING RISK ASSESSMENT
A risk assessment must be performed for all validations anddetermines the documentation deliverables.
The risk assessment will determine the validation parameters of the
overall equipment or system and the required functions.The assessment must also analyze the potential failure and faultmodes of the equipment or system to determine if the design is
appropriate and to gauge the relative level of validation testing and
need for external safeguards.
Risk assessment must be conducted using methods appropriate to
the scope and nature of the validation project.The conclusions of the risk assessment process may be included in
a project Validation Plan, in individual protocols, or in a separatedocument.
IVT Validation Week - October, 2012 11
-
7/27/2019 equipmentqualification-121207095652-phpapp01
12/29
EQUIPMENT QUALIFICATIONREQUIREMENTS
The following GAMP V Model (Figure 1) demonstrates the
traceable approach to equipment qualification
IVT Validation Week - October, 2012 12
-
7/27/2019 equipmentqualification-121207095652-phpapp01
13/29
Dont forget the software!
Conducting GxP AssessmentAll equipment systems must be assessed for their impact to patient
safety, product quality and data integrity. This assessment will be
accomplished by following SOP-MD-2010411, GXP Assessment
System Categorization.
IVT Validation Week - October, 2012 13
-
7/27/2019 equipmentqualification-121207095652-phpapp01
14/29
Validation Requirements Based on GxPAssessment
Each piece of computerized equipment or computerized systemdetermined as GxP as a result of the GxP assessment is assigned
a criticality per SOP-XYZ based on the use and application of theequipment with rationale.
Equipment criticality is assessed by performing risk assessment
directly on equipment or through process and/or product.
All equipment systems determined as GxP related are categorized
as Non-configured, Configured, or Custom.
IVT Validation Week - October, 2012 14
-
7/27/2019 equipmentqualification-121207095652-phpapp01
15/29
IVT Validation Week - October, 2011 15
Category Description Examples Requirements
Non-Computerized Process impact equipment withno computerized component
o Molding toolso Manual Presso Solvent Dispensers
o Product Risk Assessmento Equipment Identificationo Risk based test against process identified
parameters
Non-ConfiguredRun-time parameters may beentered and stored, but the
software cannot be configuredto suit the business process.
o Firmware based applicationso COTS Software/equipmento Instruments
o Abbreviated life cycle approacho Abbreviated (i.e. equipment specifications or
manuals)o Installation Qualification and version controlo Risk-based approach to supplier assessmento Version controlo Risk-based test against (for simple systems
regular calibration may substitute for testing)o Verify procedures are in place for maintaining
compliance and fitness for intended use
ConfiguredSoftware that can beconfigured by the user to meet
the specific needs of the usersbusiness/manufacturing
process. Software code is not
altered.
o LIMSo SCADAo Spreadsheetso Simple Human Machine
Interfaces(HMI)Note: specific examples of the above
system types may contain
substantial custom elements.
o Life cycle approacho Risk-based approach to supplier assessmento Demonstrate supplier has an adequate Quality
Management Systemo Some life cycle documentation (DS) retained by
supplier.o Installation Qualification against Design
Qualificationo Operational Qualification against Functional
Specificationo Performance Qualification against .o Version controlo Risk-based testing to demonstrate application
works as designed.o Verify procedures are in place for maintaining
compliance and fitness for intended use
Custom Software custom designed andcoded to suit the businessprocess.
o Internally and externallydeveloped IT applications
o Internally and externallydeveloped process control
applicationsCustom ladder logic
Same as for configurable, plus:oMore rigorous supplier assessment.oPossible supplier auditoPossession of full life cycle documentationoDesign and source code review
Computer System Validation requirements
Some Examples
-
7/27/2019 equipmentqualification-121207095652-phpapp01
16/29
Installation Qualification (IQ)
The purpose of the IQ is to establish by objective evidence
that the equipment as installed or modified. For equipment
qualifications, an IQ should contain these minimum
requirements.
IVT Validation Week - October, 2012 16
-
7/27/2019 equipmentqualification-121207095652-phpapp01
17/29
Installation Qualification
Purpose Scope Equipment descriptiono Boundaries ancillary equipment
Environment Critical Utilities Drawings Preventive Maintenanceo Spare Parts
Product Contacto Cleaning procedureso Materials of construction Product Contact
17IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
18/29
IVT Validation Week - October, 2012 18
Section Requirement/Content
Purpose State the equipment needs to be qualified
Scope State whether the installation is for
o New equipment oro Modifying previous qualified equipment
Equipment/
System Description
Describe what the equipment does, how it is used, what process/products use it, and its basic design features
Supplier Vendor certification and safety feature verification
Equipment Components Identify and briefly describes each major component of the subject equipment Define the system/equipment boundaries with other systems or equipment Ancillary equipment used in conjunction with the equipment being qualified should be identified as appropriate
Utilities Utilities required to operate the equipment should be identified
Construction, Installation andRequirements
Specify the cleaning procedures that must be executed after the equipment is installed Document that the cleaning procedures have been successfully executed and completed
Supporting Documentation List supporting documentation that may be used to identify or operate the equipment such as EngineeringTurnover Packages, Purchase Orders, or Equipment Manuals
Maintenance Programs Establish maintenance procedure Include a listing of any preventive maintenance activities
Spare/Change Parts Provide a list of spare parts and change parts, if applicable, required for system operation, including a description ofthe part and part number of reference
Drawings List and include in the qualification protocol for the system drawings used to support the IQ
Testing and Acceptance Criteria Acceptance criteria must be approved by the site designate review board or project team prior to executing anyIQ
Define the test procedure; IQ testing must be designed to confirm that the equipment is installed in accordancewith manufacturers recommendation or document justification for exceptions
Define the acceptance criteria; for an IQ this is usually a Pass/Fail resultDiscrepancies Discuss and justifies events per required deviation or exception procedure
Summary and Conclusion Summarize IQ test results, which demonstrate that the equipment was installed correctly Provide a conclusion on whether the equipment installation is acceptable
Installation Qualification (IQ)
-
7/27/2019 equipmentqualification-121207095652-phpapp01
19/29
Installation Qualification (IQ)
The IQ will document that the required design feature have
been properly installed. The number of design features can
vary from a few to any number of design features. Design
features are dependent upon the complexity of the
equipment.The following slide contains examples of various designfeatures that may be considered.
IVT Validation Week - October, 2011 19
-
7/27/2019 equipmentqualification-121207095652-phpapp01
20/29
-
7/27/2019 equipmentqualification-121207095652-phpapp01
21/29
Operational Qualification (OQ)
User Guides/Manuals Critical Process Parameters Environment Critical Utilities
21IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
22/29
Operational Qualification (OQ)
At minimum the OQ must include and/or address the items
in this section. Statistical tools such as design experiment
and/or response surface design should be applied to
optimize equipment and process performance.
IVT Validation Week - October, 2012 22
-
7/27/2019 equipmentqualification-121207095652-phpapp01
23/29
IVT Validation Week - October, 2012 23
Section Requirement/Content
Purpose State the equipment needs to be qualified
Scope State whether the installation is foro New equipment oro Modifying previous qualified equipment
Equipment/System Description Describe what the equipment does, how it is used, what process/products use it, and its basic design features
If above fully described in the IQ, then a reference to the IQ is acceptable
Operational Qualification Pre-requisites Verify all IQ tests have been completed prior to execution of operational qualification or that any IQ testing not yet completedhas been identified in a protocol exception report as non-critical for OQ testing to begin
Test Equipment Calibration Verification A completed record of qualified test equipment and approved materials that is used during protocol execution List calibration date and next due date
Standard Operating Procedures Establish operating, maintenance, setup and/or cleaning procedures for the equipment Procedure(s) shall be approved and effected before or by end of OQ is completed
Alarm/Control Challenges Identify and challenge critical alarms associated equipment/system. Note: In some cases, the alarm studies may bedeferred to an overriding operating system, such as Building Management System or equivalent
Challenge the equipment/system operator controls and indicators such as controllers not challenged as part of aseparate software validation package and buttons, lamps, switches, etc. that are used for control or monitoring of the
equipment
Operating Parameters Verify the key and critical process parameters (some equipment may not have critical process parameters) Verify the operating ranges and acceptance criteria for each parameterNotes:
Software parameters must also be considered; separate computer validation protocol can be used to address thisRationale and Sampling Locations Provide rationale for:
Qualification approach takenSample size rationaleSelected test conditionsCritical parameters
Testing and Acceptance Criteria Define the test range for each critical process parameter for verificationo The testing range typically brackets the operating range to ensure equipment is qualified with extra security;
e.g., if temperature operating range is 50C to 100C, then the test range should be 40C to 110C
The process will be challenged at the extremes of the critical process parameters wherever possible. The number of test runs needs to be statistically justified and it may be depending on the complexity of the equipment
Test Result Documentation Summarize test results and confirms the acceptance criteria
Discrepancies Discuss and justifies discrepancies
Summary and Conclusion Summarize equipment OQ results and provide a conclusion on whether the equipment operation is acceptable
Operational Qualification (OQ)
-
7/27/2019 equipmentqualification-121207095652-phpapp01
24/29
Operational Qualification (OQ)
Equipment Employed for Multiple Products
When equipment is employed for multiple products, one may consider using
theproven acceptable range (PAR) approach. The establishment of PAR
to include operating and control parameters represents much of what
process validation is all about. The function of PAR is to include and
validate all corresponding control and operating ranges at the same time.
The following is an example of equipment that employing three products or
molds, for which temperature is one of the critical process control
variables.
The objective to challenge the operating range should test on the lowest
and highest proven acceptable limits.
IVT Validation Week - October, 2012 24
Product A Product B Product COperating 90 -110 85 - 100 100 - 120
Control 85 - 115 80 - 105 105 - 125Proven Acceptable 80 - 120 75 - 110 100 - 130
-
7/27/2019 equipmentqualification-121207095652-phpapp01
25/29
Maintaining the Qualified State
Training Preventive Maintenanceo Spare Parts List
Calibration Change Control Re-Qualification
25IVT Validation Week - October, 2012
-
7/27/2019 equipmentqualification-121207095652-phpapp01
26/29
Re-Qualification
Re-Qualification Review
The validation status of qualified equipment must bereviewed to determine whether it continues to operate in a
qualified state. With the exception of those processes that
are subject to regulatory requirements regarding timespecific intervals for periodic re-qualification, the change
control process is appropriate to determine re-qualification
requirements to maintain the validated state.
As part of the Change Control process, a validationassessment will be completed for each change to
determine and document any potential validation impact
and any actions deemed appropriate to ensure the
validation status is maintained including the possibility of re-
qualification. IVT Validation Week - October, 2012 26
-
7/27/2019 equipmentqualification-121207095652-phpapp01
27/29
Documentation Strategies
IVT Validation Week - October, 2012 27
IOQ
IQ OQ
-
7/27/2019 equipmentqualification-121207095652-phpapp01
28/29
Interactive Stuff
Participants develop an equipment qualification protocol
IVT Validation Week - October, 2012 28
-
7/27/2019 equipmentqualification-121207095652-phpapp01
29/29
BONUS Material
Mold Validation Procedure Forms
Production Equipment and Process validation ProcedureGxP Assessment Procedure
IVT Validation Week - October, 2012 29