Epc contractor management
-
Upload
herve-baron -
Category
Engineering
-
view
5.238 -
download
6
Transcript of Epc contractor management
![Page 1: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/1.jpg)
HERVE BARON
EPC Contractor management
Welcome to this presentation
It shows how to use The Guide1 to manage your EPC Contractor.
It is one thing to have a powerful tool. It is another to know how to use it!
Enjoy the ride! Hervé
1“The Oil & Gas Engineering Guide”, 2nd Edition, Editions Technip, 2015
![Page 2: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/2.jpg)
HERVE BARON
EPC Contractor management
A. KNOW each Engineering discipline and the overall process
B. UNDERSTAND the critical aspects
C. IMPLEMENT powerful methods
![Page 3: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/3.jpg)
HERVE BARON
EPC Contractor management
A. KNOW each Engineering discipline and the overall process
B. UNDERSTAND the critical aspects
C. IMPLEMENT powerful methods
![Page 4: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/4.jpg)
HERVE BARON
EPC Contractor management
Discipline presentation: activities and deliverables
Table of Contents
![Page 5: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/5.jpg)
HERVE BARON
EPC Contractor management
The sequence
and contents of P&ID revisions
![Page 6: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/6.jpg)
HERVE BARON
EPC Contractor management
Ask your
contractor if they work like
this or to advise differences
The sequence
and contents of P&ID revisions
![Page 7: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/7.jpg)
HERVE BARON
Use the sample
documents included to specify to a Contractor
what you want
EPC Contractor management
![Page 8: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/8.jpg)
HERVE BARON
EPC Contractor management
Specify that this is the
level of details you want in the Mechanical data
sheet to be issued by the FEED Contractor
Use the sample
documents included to specify to a Contractor
what you want
![Page 9: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/9.jpg)
HERVE BARON
EPC Contractor management
Make sure your
Contractor performs a proper HAZID
![Page 10: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/10.jpg)
HERVE BARON
EPC Contractor management
A. KNOW each Engineering discipline and the overall process
B. UNDERSTAND the critical aspects
C. IMPLEMENT powerful methods
![Page 11: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/11.jpg)
HERVE BARON
EPC Contractor management
Typical engineering schedule for an EPC
Project
![Page 12: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/12.jpg)
HERVE BARON
EPC Contractor management
Use this to check
the schedule submitted by your
EPC contractor
Typical engineering schedule for an EPC
Project
![Page 13: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/13.jpg)
HERVE BARON
EPC Contractor management
The new 3D
model centered Engineering work
process
![Page 14: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/14.jpg)
HERVE BARON
EPC Contractor management
Ask your contractor
to draw a similar workflow of their
process if different
The new 3D
model centered Engineering work
process
![Page 15: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/15.jpg)
HERVE BARON
EPC Contractor management
A. KNOW each Engineering discipline and the overall process
B. UNDERSTAND the critical aspects
C. IMPLEMENT powerful methods
![Page 16: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/16.jpg)
HERVE BARON
Understand what
makes the duration of a Project
EPC Contractor management
![Page 17: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/17.jpg)
HERVE BARON
Understand what
makes the duration of a Project
2 things make the duration of a Project:
Mechanical Equipment Piping
EPC Contractor management
![Page 18: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/18.jpg)
HERVE BARON
EPC Contractor management
Understand that delay in vendor information is THE most common engineering
show stopper
![Page 19: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/19.jpg)
HERVE BARON
EPC Contractor management
Understand which information from vendors is critical
Understand that delay in
vendor information is THE most common engineering
show stopper
![Page 20: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/20.jpg)
HERVE BARON
EPC Contractor management
Make sure the schedule of submission of these critical
vendor documents is properly defined
![Page 21: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/21.jpg)
HERVE BARON
EPC Contractor management
Check the status of submission of these
critical vendor documents
Make sure the schedule of submission of these critical
vendor documents is properly defined
![Page 22: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/22.jpg)
HERVE BARON
EPC Contractor management
Manual valves have standard dimensions but control valves
do NOT: you need the dimension from the Vendor
?
![Page 23: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/23.jpg)
HERVE BARON
EPC Contractor management
?
Before you get this dimension
the iso is on HOLD
Manual valves have standard dimensions but control valves
do NOT: you need the dimension from the Vendor
![Page 24: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/24.jpg)
HERVE BARON
EPC Contractor management
A. KNOW each Engineering discipline and the overall process
B. UNDERSTAND the critical aspects
C. IMPLEMENT powerful methods
![Page 25: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/25.jpg)
HERVE BARON
EPC Contractor management
The most common measure of progress does not tell you
much...
![Page 26: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/26.jpg)
HERVE BARON
EPC Contractor management
... Without the data on
resources used
The most common measure of progress does not tell you
much...
![Page 27: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/27.jpg)
HERVE BARON
EPC Contractor management
Request this one page
control dashboard from the Contractor
![Page 28: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/28.jpg)
HERVE BARON
EPC Contractor management
With quantities follow-up to make sure construction
resources are adjusted
![Page 29: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/29.jpg)
HERVE BARON
EPC Contractor management
With status of purchase of
Mechanical Equipment
![Page 30: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/30.jpg)
HERVE BARON
EPC Contractor management
Remember that delay in
vendor information is THE Engineering show stopper
With status of purchase of
Mechanical Equipment
![Page 31: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/31.jpg)
HERVE BARON
EPC Contractor management
With status of Piping materials purchase
orders
![Page 32: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/32.jpg)
HERVE BARON
EPC Contractor management
With status of Piping materials purchase
orders
Remember that Piping is always the critical path
![Page 33: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/33.jpg)
HERVE BARON
EPC Contractor management
How do you assess the progress of issue of the
~300 foundation drawings?
![Page 34: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/34.jpg)
HERVE BARON
EPC Contractor management
By means of the workfront curve
How do you assess the progress of issue of the
~300 foundation drawings?
![Page 35: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/35.jpg)
HERVE BARON
EPC Contractor management
How many such work
front curves do you have on your dashboard?
![Page 36: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/36.jpg)
HERVE BARON
EPC Contractor management
How many such work
front curves do you have on your dashboard?
3: foundations, steel structures & piping
![Page 37: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/37.jpg)
HERVE BARON
EPC Contractor management
Use The Oil & Gas Engineering Guide for all what follows:
To help understand and improve Project execution starting by Engineering,
To specify to an Engineering supplier what you want: what deliverables and with what contents,
As a support to the discussion with an Engineering supplier of its work process: design stages/gates, methods to be used, etc.
To show/specify the progress report you want, with the meaningful indicators,
To ask the right questions to assess the true progress,
![Page 38: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/38.jpg)
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
![Page 39: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/39.jpg)
HERVE BARON
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
![Page 40: Epc contractor management](https://reader031.fdocuments.us/reader031/viewer/2022020203/58f9ade1760da3da068b9cdc/html5/thumbnails/40.jpg)
HERVE BARON
The Oil & Gas Engineering Guide 2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html