Entrega Project Update
description
Transcript of Entrega Project Update
![Page 1: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/1.jpg)
Entrega Project UpdateEntrega Project Update
Wyoming Natural Gas Pipeline Authority – August 30, 2005Wyoming Natural Gas Pipeline Authority – August 30, 2005
EntregEntregaaGas Pipeline Gas Pipeline Inc.Inc.
www.entregapipeline.comwww.entregapipeline.com
![Page 2: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/2.jpg)
Agenda
Entrega Project Update
Project and Facilities
Milestones and Schedule
Interconnects and Capacity
Access to Markets
Wrap-up
![Page 3: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/3.jpg)
Segment 1
Meeker to Wamsutter
136 miles of 36-inch pipe
Segment 2
Wamsutter to Cheyenne Hub
191 miles of 42-inch pipe
Big Hole Compressor Station
Wamsutter
Compressor Station
Meeker Compressor Station
![Page 4: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/4.jpg)
Project Description
Entrega is a new open access natural gas pipeline developed to move Rocky Mountain gas production to Midwest markets
FERC regulated interstate pipeline; developed with cooperation of Bureau of Land Management and other Federal and State Agencies
Runs from Meeker Hub in Rio Blanco County, CO through Wamsutter, WY to the Cheyenne Hub near Rockport, CO
FERC certificate includes capacity of 1,500 MMcf/d, developed in 2 phases
– Phase 1 approximately 750 MMcf/d (free flow)
– Phase 2 incremental 750 MMcf/d (compression)
![Page 5: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/5.jpg)
Description of Facilities
Project includes 136 miles of 36-inch pipeline and 191 miles of 42-inch pipeline
Maximum Allowable Operating Pressure (MAOP) of the system is 1,480 psig
Route chosen to minimize environmental impact; 94% is adjacent to existing pipeline and utility right-of-way
Phase 2 will include 3 compressor stations; Meeker (11,000 HP), Big Hole (22,000 HP), and Wamsutter (14,000 HP)
Eight delivery/receipt meter stations at interconnects with existing pipelines, two at Meeker, two at Wamsutter, and four at Cheyenne Hub
![Page 6: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/6.jpg)
Recent Significant Milestones
FERC Certificate Granted – August 9, 2005
Construction contract awarded to US Pipeline Company
Operating contract awarded to Kinder Morgan NatGas Operator LLC
Agreement to interconnect with TransColorado
![Page 7: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/7.jpg)
Project Concept
Developed
Timeline of Major Milestones Achieved
9/03 12/03 1/04 12/04 1/05
Pre-Filing Docket
Assigned3/19/04
Applied for FERC
Certificate9/17/04
Open Season
6/4/04 – 6/25/04
Agmt Signed with Pipeline
Operator6/2/05
Environmental Impact Stmt
Issued7/1/05
FERC Certificate Granted
8/9/05
FERC Certificate Accepted
8/12/05
![Page 8: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/8.jpg)
Project Timeline (most recent update)
1/05 12/05 1/06 12/06 1/07
Phase 1 Segment 1
ConstructionSep 05 – Dec 05
Phase 2 Construction of FacilitiesApr 07 – Jun 07
Phase 1 Segment 2
ConstructionJul 06 – Nov 06
FERC Notice to Proceed
Expected 9/5/05
Note: All dates referenced above are approximate and differ from the FERC filing
Meeker to
Wamsutter
Wamsutter to
Cheyenne
Compressor
Expansion to 1.5 Bcf/d
![Page 9: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/9.jpg)
Proposed Pipeline Interconnects
Denver
Salt Lake City
Cheyenne Hub
Meeker Hub
Wamsutter
Opal
Denver
Salt Lake City
Cheyenne Hub
Meeker Hub
Wamsutter
Opal
Receipt Interconnects
EnCana GatheringTransColorado
Bi-directional Interconnects
CIG WIC
Delivery Interconnects
CIG Cheyenne Plains
XCEL Trailblazer
CIGCIGCheyenne PlainsCheyenne PlainsPSCOPSCOTrailblazerTrailblazerWICWICTransColoradoTransColorado
Entrega Gas PipelineEntrega Gas Pipeline
![Page 10: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/10.jpg)
Entrega Pipeline Capacity
Phase
Meeker to Wamsutter (MMCFD)
Wamsutter to Cheyenne (MMCFD)
Approximate In-Service
Date
Interim Up to 800 0 Dec 2005
Phase I 750 750 Nov 2006
Phase 2 1,500 1,500 Jul 2007
Phase 3 (Optional) 1,500 2,000 TBD
Ultimate (Optional) 1,800 2,300 TBD
Included in FERC Certificate dated 8/9/05
New FERC Application and open season required
![Page 11: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/11.jpg)
Market Pipeline Access
Denver
Salt Lake City
Greensburg
Cheyenne Hub
Meeker Hub
Wamsutter
Opal
ANRANRNNGNNGNGPLNGPLPEPLPEPLSSCSSCTrailblazerTrailblazer
Midwest Market PipelinesMidwest Market Pipelines
NWPLNWPLKern RiverKern River
Western Market PipelinesWestern Market Pipelines
TransColoradoTransColoradoCIGCIGWICWICCheyenne Cheyenne PlainsPlains
EntregaEntrega
Regional PipelinesRegional Pipelines
![Page 12: Entrega Project Update](https://reader034.fdocuments.us/reader034/viewer/2022051401/568150a5550346895dbeaa4c/html5/thumbnails/12.jpg)
Wrap-up
Review of Project Timeline– Segment 1 (Meeker to Wamsutter) – In Service December 2005
– Segment 2 (Wamsutter to Cheyenne) – In Service November 2006
– Phase 2 (Compressor Expansion) – In Service July 2007
We appreciate your continued support