Eng.J.M.Riungu, CEO, Tsavo Power Company, KENYA · EAPIC 2008, 16-18 September, Nairobi, Kenya...
Transcript of Eng.J.M.Riungu, CEO, Tsavo Power Company, KENYA · EAPIC 2008, 16-18 September, Nairobi, Kenya...
EAPIC 2008, 16-18 September, Nairobi, Kenya
2012-TOWARDS EASTERN AFRICA POWER POOL
Eng.J.M.Riungu, CEO, Tsavo Power Company, KENYA
EAPIC 2008, 16-18 September, Nairobi, Kenya
• Introduction
• Africa Electrification and Generation
• Africa’s Natural Resources
• Hydropower Potential In Eastern Africa
• Geothermal resources in E.A
• The Eastern Africa Power Pool
• Proposed Interconnections
• Conclusion
TABLE OF CONTENTS
EAPIC 2008, 16-18 September, Nairobi, Kenya
INTRODUCTION
• Africa is endowed with vast energy resources but our people are still very poor.
• Access rate to electricity very low especially in the sub-Saharan Africa
• African countries individually face scarcity of resources
• There is need to pool resources for the benefit of our people
• The emergence of regional power pools is a step in the right direction.
EAPIC 2008, 16-18 September, Nairobi, Kenya
AFRICA ELECTRIFICATION
6.5%Composite growth rate
1.96mHousehold connections p/yr
39.25mTotal households to be connected
35%Electrification level
20 Year Forecast to 2025
447Total Cons. per capita Kwh/yr)
351Total Electricity Cons. (Twh)
785Population (estimate in millions)
YEAR 2004
EAPIC 2008, 16-18 September, Nairobi, Kenya
AFRICA GENERATING CAPACITY
--Other- Wind, Solar
‹0.1‹0.1Geothermal
3.002.00Nuclear
18.8020.90Hydro
78.1077.10Fossil Fuels
Energy Generated(%)
Installed Capacity(%)
EAPIC 2008, 16-18 September, Nairobi, Kenya
Africa’s Natural Resources-1
• Africa endowed with vast natural power generation resources.
• Central and Eastern Africa have vast hydro resources.
• West and North Africa-natural gas.
• Geothermal energy resources in the African Rift.
EAPIC 2008, 16-18 September, Nairobi, Kenya
HYDRO POTENTIAL IN EASTERN AFRICA-1
1.Democratic Republic of Congo (DRC)
• DRC has a total hydro potential of 100,000 MW of which:-
-56,000 MW are at different sites spread all over the country and
-44,000 MW are concentrated at the Inga Site.
EAPIC 2008, 16-18 September, Nairobi, Kenya
Hydro Power Potential in E.A-2
EAPIC 2008, 16-18 September, Nairobi, Kenya
Hydro Power Potential in E.A-3
EAPIC 2008, 16-18 September, Nairobi, Kenya
HYDRO POTENTIAL IN EASTERN AFRICA-4
2. Ethiopia
• Ethiopia has a hydro potential of 30,000 MW equivalent to annual energy production of 650 TWh.
Currently,
• 670 MW has been developed.
• 1,200 MW is under construction.
• 1,900 MW is committed.
• 2,300 MW is ready for financing and
• 5,145 MW is under feasibility study.
EAPIC 2008, 16-18 September, Nairobi, Kenya
3. Uganda
• Uganda has a hydro potential of 2,750 MW out of which:-
- 380 MW has been developed and
- another250MW (Bujagalihydro project) is under
construction.
HYDRO POTENTIAL IN EASTERN AFRICA-5
EAPIC 2008, 16-18 September, Nairobi, Kenya
HYDRO POTENTIAL IN EASTERN AFRICA-5
4. Kenya
• Kenya’s installed hydro capacity is 736MW.
• An additional capacity of 70MW is currently under construction at various sites.
• There is an unexploited potential of 1,680 MW.
EAPIC 2008, 16-18 September, Nairobi, Kenya
5. Tanzania
•Tanzania has an effective installed hydro capacity of 555 MW.
•There is an unexploited hydro potential of 2,040MW.
HYDRO POTENTIAL IN EASTERN AFRICA-6
EAPIC 2008, 16-18 September, Nairobi, Kenya
HYDRO POTENTIAL IN EASTERN AFRICA-7
6. Sudan
• Sudan has a feasible hydro potential of 5,000MW.
• The installed capacity is 338 MW and
• 1,250 MW are under construction.
EAPIC 2008, 16-18 September, Nairobi, Kenya
GEOTHERMAL RESOURCES IN EASTERN AFRICA-8
• There is a huge potential of geothermal energy along the Eastern Africa Rift Valley.
• However, only Kenya has carried out significant exploration work.
• Kenya’s geothermal potential estimated at over 4,000MW.
• Currently only 130 MW has been exploited.
• Additional 70MW under construction.
EAPIC 2008, 16-18 September, Nairobi, Kenya
HARNESSING THE NATURAL RESOURCES
• The most effective way to harness these vast resources to the benefit of the people of Africa is by:-
- regional interconnections of the electricity grid and
- regional developments of the electricity generation resources.
• The formation of the Eastern Africa Power Pool was driven by the need to exploit these resources and regional interconnection.
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE EASTERN AFRICA POWER POOL (EAPP)
• The Power Pool is a framework of power exchanges between utilities in the Eastern Africa region in order to:-
- secure their respective power supply;
- provide mutual assistance in the power sector and
-reduce power supply costs based on an integrated master plan approach and pre-established rules.
EAPIC 2008, 16-18 September, Nairobi, Kenya
OBJECTIVES OF EAPP-1
The main objectives of the EAPP were stated as:-
-Optimize the usage of energy resources available by working out regional investment schemes in Power Generation; Transmission and Distribution areas taking into account the environmental effects.
-Increase the power supply in the region.
-increase the access rate to electricity.
EAPIC 2008, 16-18 September, Nairobi, Kenya
OBJECTIVES OF EAPP-2
• Reduce electricity production cost in the Region, using Power Systems Interconnection and increasing power exchanges between the countries.
• Provide an efficient co-ordination between various initiatives taken in the fields of power production and transmission as well as exchanges in the Region.
• Facilitate the development of competitive electricity market in EAPP Region
EAPIC 2008, 16-18 September, Nairobi, Kenya
EAPP COUNTRIES
1. The Republic of Burundi.
2. The Republic of Rwanda.
3. The Republic of Sudan.
4. The Republic of Uganda.
5. The Republic of Kenya.
6. The United Republic of Tanzania
7. The Democratic Republic of Congo.
8. The Arab Republic of Egypt.
9. The Federal Democratic Republic ofEthiopia
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE EAPP UTILITIES-1
1. ELECTROGAZ of Rwanda
2. Ethiopian Electric Power Corporation (EEPCO) of Ethiopia.
3. The Kenya Power and Lighting Company Limited (KPLC) of Kenya.
4. Kenya Electricity Generating Company Limited (KenGen) of Kenya.
5. The National Electricity Corporation (NEC) of Sudan.
6. REGIDESO of Burundi
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE EAPP UTILITIES-2
7.Societe Rationale d’Electricite’ (SNEL-DR) of Congo.
8.Tanzania Electricity Supply Company Limited (TANESCO) of Tanzania.
9.Uganda Electricity Transmission Company Limited (UETCL) of Uganda.
10.Uganda Electricity Generation Company Limited (UEGCL) of Uganda.
11.Uganda Electricity Distribution Company Limited (UEDCL) of Uganda
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE EAPP UTILITIES-3
12.Egyptian Electricity Holding Company.
13.Societe d’Electricite’ des pays des Grands Lacs (SINELAC)
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE ORGANS OF THE EAPP-1
The EAPP consists of the following organs and bodies:
• The Conference of Ministers which consist of Ministers responsible for electricity in the Region.
• The Steering Committee which consists of the Chief Executive Officers of the public power utilities in member countries.
EAPIC 2008, 16-18 September, Nairobi, Kenya
THE ORGANS OF THE EAPP-2
• The Independent Regulatory Board.
• The Permanent Secretariat headed by an Executive Secretary.
• The Technical Sub-committees on
• Planning
• Operation and
• Environment
• The Coordination Center.
EAPIC 2008, 16-18 September, Nairobi, Kenya
FORMATION OF THE EAPP-1
• 21st November 2003- The formation of EAPP conceived in Nairobi by CEO’s of utilities in Eastern Africa.
• 24th February 2005- Launch of EAPP by Ministers responsible for electricity and signing of both Intergovermental Memorandum of Understanding and Inter Utilities Memorandum of Understanding. Election of the Chairman of Conference of Ministers
EAPIC 2008, 16-18 September, Nairobi, Kenya
FORMATION OF THE EAPP-2
• 8th May 2005- Election of the Chairman of the steering committee.
• August 2006 -Appointment of the Executive Secretary
• During the period February 2005 and August 2006 EEPCO housed and provided secretarial services.
EAPIC 2008, 16-18 September, Nairobi, Kenya
EAPP CHALLENGES
• Lack of interconnections between the member countries
• Lack of adequate financial resources
• Existence of other parallel organizations-Nile Basin Initiative.
EAPIC 2008, 16-18 September, Nairobi, Kenya
PROPOSED INTERCONNECTIONS-1
A number of transmission power lines in the Eastern Africa Region have been identified and are at various stages.
1. Inga Falls -Sudan-Egypt Line
• Northern Highway- From the proposed Inga Dam to Egypt.
• 5,300 km of 800 kV DC line to deliver 4,000 -10,000MW of power.
EAPIC 2008, 16-18 September, Nairobi, Kenya
NORTHERN HIGHWAY
EAPIC 2008, 16-18 September, Nairobi, Kenya
PROPOSED INTERCONNECTIONS-2
2.Arusha-Nairobi 330 /400kV Interconnector
• 260 km transmission line linking Tanzania and Kenya. Financing being sought. Commissioning Date -2012
3. The Kenya-Ethiopia Interconnector
• 1200 km of 400kV DC transmission line from Gibe III to Nairobi. Commissioning Date-2012
EAPIC 2008, 16-18 September, Nairobi, Kenya
PROPOSED INTERCONNECTIONS-4
4. Sudan-Ethiopia Interconnector
A 321 km ,240 kV Sudan to Ethiopia interconnector is due for construction. Commissioning Date-2011
5. Behr Eljebel (South Sudan)-Equatorial Lake Regions Interconnector
Proposed interconnector between S. Sudan and the Equatorial Lake Regions with a capacity of 1000 MW.
EAPIC 2008, 16-18 September, Nairobi, Kenya
PROPOSED INTERCONNECTIONS-5
EAPIC 2008, 16-18 September, Nairobi, Kenya
PROPOSED INTERCONNECTIONS-6
6.Lessos-Tororo–Bujagali 220kV line to strengthen the Kenya-Uganda link. Commissioning Date-2012
7.103 km of Burundi-Ruanda Interconnector. Commissioning Date-2012.
8.A total of 341km of 11kV lines for strengthening the interconnection between Burundi, DRC and Rwanda.
Commissioning Date-2012
EAPIC 2008, 16-18 September, Nairobi, Kenya
YEAR 2012-1
• By year 2012:
-Tanzania-Kenya interconnector will be commissioned
-Kenya-Ethiopia interconnector will be commissioned
-Ethiopia-Sudan Interconnector will be commissioned
-Sudan-Equatorial Lakes interconnector will be commissioned
EAPIC 2008, 16-18 September, Nairobi, Kenya
YEAR 2012-2
• Kenya-Uganda Interconnector will be strengthened
• Tanzania-Zambia interconnector will be commissioned
As a result, the Eastern Africa Power Pool will become fully operational
EAPIC 2008, 16-18 September, Nairobi, Kenya
CONCLUSION
• The coming into full operations of the EAPP in year 2012 will speed up the exploitation of the vast natural resources resident in the region.
• Political goodwill among Governments of member countries is essential.
• EAPP should lead other institutions in the efforts of harmonizing the exploitation of resources and power trade.
• Avoid duplication of efforts. It wastes resources which are very scarce.
EAPIC 2008, 16-18 September, Nairobi, Kenya
END
THANK YOU
FOR YOUR
ATTENTION