EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and...

37
THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: FOR PROPOSAL B - 1 ESHKOL POWER STATION OFFSHORE PIPELINES SPECIFICATION EM-1510 SPECIFICATION FOR DESIGN SERVICES FOR NEW OFFSHORE FUEL PIPELINES SYSTEM INSTALLATION ANNEXURE "B" Dated: May 2018

Transcript of EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and...

Page 1: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: FOR PROPOSAL

B - 1

ESHKOL POWER STATION

OFFSHORE PIPELINES

SPECIFICATION EM-1510

SPECIFICATION FOR DESIGN SERVICES FOR NEW OFFSHORE

FUEL PIPELINES SYSTEM INSTALLATION

ANNEXURE "B"

Dated: May 2018

Page 2: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 2

ESHKOL POWER STATION

SPECIFICATION FOR SERVICES FOR NEW OFFSHORE FUEL PIPELINES

INSTALLATION

1. PURCHASER: The Israel Electric Corporation Limited (IEC).

2. NAME OF PROJECT: Eshkol Power Station, Offshore Pipelines.

3. LOCATION OF PROJECT: Near Ashdod, On the Mediterranean Sea Shore.

4. SCOPE

Basic scope of work includes the following:

• Conducting Conceptual engineering for two fuel terminals including: complete

three (3) new offshore fuel pipelines system (2x24" and 1x16"), two Multi buoy

mooring berths for 50,000 DWT fuel tankers and related subsea pipeline end

manifolds (PLEM).

Optional scope of work includes the following:

• Conducting detailed design and engineering of the complete three offshore

pipelines systems including the subsea PLEMs and the related two MBM

systems up to an onshore design limit as defined in the supplemented drawings

(Supplements 3 and 4).

• Conducting detail design of concrete conduit (approx. 155 m length) that planned

to be integrated in a new Lee Break water (LBW) of "Hadarom" port which is

under construction. The concrete conduit will encase the fuel pipelines section at

the area along the LBW.

• Preparation a set of technical specifications to purchase and select “Constructor”

of the complete system described above.

Page 3: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 3

4.1 Project description

IEC is the owner and operator of two (2) existing offshore fuel pipelines in

proximity of Eshkol power station. The pipelines supply distillates (light/refined

fuels) and fuel oil (heavy fuels) from two Multi buoy mooring berths (MBM)

located about 1.8 km offshore. Due to proximity to the new Break water (LBW) of

"Hadarom" port, both MBM systems are planned to be relocated, as a results,

the pipelines planned also to be re-routed. Additional fuel oil pipeline will be

designed for future installation.

4.1.1 Following is a short description of the existing pipeline systems:

o Southern MBM connected to a steel pipeline of 16" diameter that used for

loading and unloading tankers of distillates products (refined fuels), hereinafter

called "Southern MBM". The 16” steel pipeline was partially re-routed and a new

pipeline was installed at 2015 as “temporary pipeline”. The southern MBM berth

is located about 300 meters to the north from a new Lee Breakwater (LBW) of

the new "Hadarom" port that is under construction by the Israeli Ports Company

(hereinafter called "IPC").

o Northern MBM connected to a steel pipeline of 24" diameter that used for loading

and unloading tankers of fuel oil (heavy oils), hereinafter called "Northern MBM".

The 24” pipeline was installed at approximately 1959. The northern MBM berth is

located about 1100 meters to the north from the southern MBM.

o Both steel pipelines of the MBMs are terminated onshore in a concrete pit

located inside IEC's Eshkol power station.

o The fuel pipelines at the area near the shore crossing are planned to be covered

under the LBW of the new port.

4.1.2 Following is a short description of the proposed modifications to the existing

systems (MBM berths side and shore crossing side, separately):

4.1.2.1 Relocation of the MBM berths (Berths side):

o As a result of previous nautical risk assessment study performed by IEC, it was

decided that the existing southern MBM berth shall be relocated and shifted by

530m toward the north direction in order to increase the safety distance from the

new LBW. As a result, and in order to save also a safety distance between the

MBM berths, the relocation of the southern MBM berth implied that also the

northern MBM berth location shall be shifted by approximately 750m on the

north-west direction. The sea depth at the new position of the southern MBM will

Page 4: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 4

be approximately 18.5m. The sea depth at the new position of the northern MBM

position will be approximately 22m.

o The new pipelines system will include new MBM systems and subsea manifolds

in the new locations. The Northern MBM will serve the 24" fuel oil pipeline, and

the Southern MBM will serve two pipelines 16" (distillates) and future 24" (fuel

oil).

4.1.2.2 Modifications of the pipelines after MBMs relocation:

The new configuration of the pipelines will contain three pipelines (instead of

existing two pipelines) as following:

o One new steel pipeline for fuel oil of 24" diameter routed from the new location of

the Northern MBM, crossing perpendicularly the LBW and running in a concrete

conduit in the area of the LBW up to the shoreline. The pipeline planned to be

routed onshore up to the power station.

o One new steel pipeline for distillates fuels oil of 16" diameter will be installed

using existing section of the "temporary 16" pipeline" to form complete distillates

pipeline from the new southern MBM up to the LBW. The pipeline will contain

new section of 16" diameter with 530m long routed from the new location of the

Southern MBM up to the existing "temporary" offshore end of the 16" pipeline.

Additional new section will be installed from an existing offshore bend (closest to

the shore line) on the 16" pipeline routed offshore and crossing the LBW in the

same area of the 24" fuel oil pipeline. The pipeline after crossing planned to be

installed in the same concrete conduit in the area of the LBW up to the shoreline,

then running onshore up to the power station.

o One additional steel pipeline for fuel oil of 24" diameter will be completely new

pipeline will be designed and may be installed in future. The pipeline will be

routed from the new Southern MBM, crossing the LBW at the area of the other

pipelines and planned to run in the same concrete conduit in the area of the LBW

up to the shoreline, then running onshore up to the power station.

4.1.3 Considering the above, IEC is seeking to hire engineering services of a

competent and experienced offshore engineering contractor to provide the

engineering works for the new pipelines system and the related changes as

required herein.

Page 5: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 5

4.2 Scope of Work

4.2.1 General requirements:

4.2.1.1 The Contractor shall provide the services listed in the following sub-articles as

part of the basic or optional scope of work, at a lump sum rates. All fees such as:

travel, transportation, expenses and accommodation etc. shall be taken into

account.

4.2.1.2 During pricing submission for works required in the current spec., the contractor

shall take into account all expenses for at least five (5) meetings in purchaser

offices (Haifa and Ashdod area, Israel), one meeting shall be conducted

immediately after contract signing (site visit and kick-off meeting), other meetings

will take place for design review.

4.2.1.3 Contractor shall provide, in the required format and form and in a timely manner,

all documentation required by this Specification and/or required by applicable

Standards and Codes and/or as specifically detailed in the Documentation

Submission Schedule (DSS), Annexure "J". A consistent nomenclature shall be

used project-wide in naming all component parts within the Scope of Work. This

shall apply to all drawings, Instruction Books, Bill of Materials, specifications,

special instructions, etc.

4.2.1.4 Engineering design shall commence immediately after contract award.

4.2.1.5 Changes in design already approved by the Purchaser are normally unaccepted.

However, should such changes become necessary on an exceptional basis, the

Contractor shall obtain the Purchaser's approval prior to introducing any such

change. The cost of correcting inconsistent nomenclature shall be borne by the

Contractor.

4.2.2 Basic scope of engineering shall include the following:

4.2.2.1 The Contractor shall perform the conceptual design of the complete new offshore

pipelines system from the MBM systems (including) up to a design limit on the

LBW (including LBW crossing), as will be detailed in § 4.3.1.

4.2.3 Optional scope of engineering shall include the following:

Page 6: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 6

The following optional services may be required by the purchaser to be

conducted in later stage.

4.2.3.1 Detailed design of the complete new offshore pipelines system and onshore

pipelines in concrete conduit (up to purchaser onshore design limit – see

supplements 3-5) based on the conceptual design incorporating all purchaser

requirements and comments, as will be detailed in § 4.3.2.

4.2.3.2 Detailed design (for construction) of the concrete conduit (approx. length is 155

m) for pipelines to be constructed and integrated in the top area of the LBW and

will run along the LBW, as will be detailed in § 4.3.3.

4.2.3.3 Preparation a set of technical specifications to purchase and to allow purchaser

to select a “Constructor” of the complete system (offshore/onshore pipelines,

MBMs, PLEMs, concrete conduit), including specification for purchase,

construction, testing, installation and commissioning of the offshore pipelines

system, as will be detailed in § 4.3.4.

4.3 Detailed Scope of Services

The Contractor shall provide the services listed in the following sub-articles as

part of the Basic Scope of Work and for the Options, all as stated in the

Summary of Prices and Delivery Schedule, Annexure “C1”.

4.3.1 Conceptual design:

As per the documents attached to this specification and site visit followed by

kick-off meeting in IEC's offices with the contractor's project personnel, the

Contractor shall conduct the conceptual design for the complete system of the

offshore pipelines from the MBM systems in the new locations (including) up to a

pipelines design limit on the LBW area (including LBW crossing). The pipelines

after crossing the LBW planned to run in a concrete conduit along the LBW. The

conceptual design limit of the offshore pipelines shall be terminated at point on

the top of LBW before piping entrance to the concrete conduit to be placed along

the LBW.

Upon completion, the contractor shall submit to the purchaser all deliverables of

the conceptual design.

The scope of the conceptual design and the deliverables shall include at

least the following:

Page 7: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 7

4.3.1.1 The Contractor shall develop the system design basis and pipelines cost-efficient

installation method. Contractor shall take into account the following: all existing

and nearby infrastructures, safety distances from existing/operational pipelines,

fluids to be transported, site specific environmental conditions, supplemented

drawings for the new system configuration, a limited available downtime time

during installation/commissioning (10 days maximum), requirements in this

specification, installation method to be applied, and all other aspects required by

the designer.

4.3.1.2 System drawings

After conducting the conceptual design of the system, the Contractor shall submit

the following documents/drawings and any other necessary deliverables:

4.3.1.2.1 Flow drawings covering subsea manifolds and steel pipelines. The flow drawings

shall include the technical information such as design pressures, temperatures,

instrumentations and maximum future flow rates.

4.3.1.2.2 General arrangement drawings and pipelines routes for all new pipelines. A plan

and elevation drawings shall be provided.

4.3.1.2.3 General drawings for connections to the existing 16" pipeline at both ends and

induction bends general drawings. The existing pipeline ends are RTJ type

flanges of #300 rating.

4.3.1.2.4 Detail plan and side drawings for the pipelines crossing in the LBW up to

connection with pipelines that will be planned to run in a concrete conduit at the

LBW area (along LBW).

4.3.1.2.5 Conceptual design for pipelines and their protection near the LBW at sea side

and along the section in the LBW crossing up to a matching point with the

pipelines to be placed the concrete conduit.

4.3.1.2.6 General drawings for the proposed tankers' orientation in the new berths

locations including the pattern of the multi buoy mooring components and marker

buoys for ship anchors. The existing Tankers in both berths mooring at 270°±5°

degree.

4.3.1.2.7 General drawings of offshore manifolds (PLEMs) and MBM systems with

sufficient details including buoy and chain configuration and arrangement. Two

berths shall be designed with MBM systems; the Southern MBM and its PLEM

Page 8: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 8

shall serve two separated types of fuel (distillates/fuel oil) and tankers whereas

the Northern MBM shall serve one fuel oil.

4.3.1.3 The Contractor shall analyze the installation methods and shall develop and

prepare an installation and commissioning plan considering site constrains

(proximity to LBW which is under construction), equipment to be used, the limited

available area onshore for pipelines launching and the possible cost-effective

installation methods/techniques. Required onshore area for installation need to

be marked in the drawings.

4.3.1.4 Material selection list and technical data shall be provided after the conceptual

design, as following:

• Specification of the line pipe material, minimum required thickness, corrosion

coating, and external protection.

• Specification for fittings, subsea valves materials and rating.

• Required components for the subsea PLEMs and MBM systems.

4.3.1.5 Contractor shall recommend and specify the possible leak detection system to be

adopted for the offshore pipelines system.

4.3.1.6 Contractor shall take into account that the 24” pipeline for the Southern MBM will

be installed in future. A plan and methods for the future installation shall be

provided.

4.3.1.7 Based on the conceptual design, the Contractor shall perform detailed cost

estimation (accuracy ±20%) for the complete project including offshore and

onshore pipelines systems and mooring systems.

4.3.1.8 Contractor shall provide detailed schedule for the project including: purchase,

construction, installation and commissioning considering the selected installation

method.

4.3.1.9 Considerations during conceptual design:

4.3.1.9.1 The contractor shall refer to Supplements and shall take into account the existing

and new pipelines configuration and the LBW drawings.

4.3.1.9.2 The design of the pipelines shall take into account all the existing loads that may

occur during the pipeline life cycle and during the installation stage, such as,

erection loads, operational loads, environmental loads and the accidental loads.

4.3.1.9.3 The governing design standards shall be "DNV-OS F101" for pipelines, "DNV

OS-E301" for MBM system design and "OCIMF Guidelines for the Design,

Page 9: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 9

Operation and Maintenance of Multi Buoy Moorings" for subsea PLEMs. Other

standards may be consulted if necessary.

4.3.1.9.4 The offshore pipelines shall be buried and covered below seabed with a cover

depth of at least 2 m.

4.3.1.9.5 The existing 16" pipeline is covered below seabed at a depth of 2m.

4.3.1.9.6 The southern MBM and related subsea manifold shall be designed for two

independent transportation pipelines (16" pipelines for distillates and 24" future

fuel oil pipelines). The subsea cradle shall be designed to be capable to support

a future manifold for the 24" pipeline.

4.3.1.9.7 The design shall take into account all surrounding infrastructures, such as: LBW,

port's entrance channel, subsea distillation pipelines, subsea natural gas

pipelines, existing operational fuel pipelines and moorings.

4.3.1.9.8 The downtime during connections to existing system (especially connections to

the 16" pipeline) and commissioning shall be considered and minimized to

maximum of 10 days.

4.3.2 Detail design of pipelines system (optional scope):

In case that detail design or part of its scope will be required by the purchaser,

the contractor will be notified to conduct a detail design. Upon notified, the

Contractor shall commence the detail design of the system within the scope

specified herein. The detail design boundary limits, are illustrated in the

purchaser supplemented drawings and will include the offshore pipelines and

onshore pipelines section in the concrete conduit at the LBW up to purchaser

design limit.

During the detail design, the designed route shall be optimized taking into

considerations the conceptual design, all existing onshore and offshore

constrains that are in the vicinity of the pipelines and any added construction on-

site.

All drawings and documents related to detail design shall be marked as "For

construction".

The detail design and the deliverables shall include at least the following:

4.3.2.1 Pipelines design:

4.3.2.1.1 Preparation of detailed flow drawings for the new offshore pipelines system

including subsea PLEMs and offshore steel pipelines up to onshore boundary

Page 10: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 10

limit that matching with IEC's onshore pipelines design. The flow drawings shall

contain design pressures, temperatures, maximum allowable flow rates, and any

process instrumentation.

4.3.2.1.2 The contractor shall update and submit complete and detailed set of physical

drawings and isometric drawings for the complete pipelines system including

detail design drawings of LBW crossing. All drawings shall be furnished to

contain all necessary data to allow materials purchase, construction and

installation. Each pipeline shall be clearly defined by at least two (2) views (Plan

and Elevation) and supplemented with sufficient details as much as necessary to

ensure a full understanding of the complete pipelines routes, connections details

to existing 16" pipeline, connections to manifold.

4.3.2.1.3 Pipelines shall be designed and installed taking into account that the existing

moorings will remain operational during new pipelines installation phase. The

commissioning of the new system and disconnection of the existing (especially

connections to the 16" pipeline) will be limited to a maximum of 10 days

downtime.

4.3.2.1.4 The contractor shall update and submit detailed drawings for connections to both

ends of the existing 16" pipeline.

4.3.2.1.5 Detail drawings for all induction bends including specification for material,

thickness, external corrosion coating, external weight and end connections

details.

4.3.2.1.6 Detail plan and side drawings for crossing the LBW for all pipelines with detailed

connection to the onshore pipelines out of the LBW area.

4.3.2.1.7 Detail drawings of pipelines supports in the concrete conduit.

4.3.2.1.8 Detail design and specification for pipelines' protections near the LBW at sea

side and along the crossing of the LBW.

4.3.2.1.9 Detailed stress analysis report for all pipelines considering design standard,

operational parameters, construction and environmental loads. The pipelines

stress analysis shall be terminated at an Anchor located at the matching point

with purchaser onshore design. In case that an Anchor cannot be installed due to

high thermal axial loads, then the stress analysis shall consider and incorporate

the purchaser the onshore pipelines that fall under purchaser scope of design.

4.3.2.1.10 On-bottom stability analysis and free spanning shall be performed according to

DNV-OS-F101 standard (if required).

Page 11: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 11

4.3.2.1.11 Pipelines cathodic protection detail design and specification shall be

implemented for the complete system. The cathodic protection of the pipelines

shall be based on impressed current. Drawings including wiring plan and anodes

locations shall be provided. All system design requirements and performance

shall be extracted from supplement-19.

4.3.2.1.12 Detailed design of leak detection system (if required by purchaser).

4.3.2.2 Pipeline End Manifolds (PLEMs) detail design:

4.3.2.2.1 Data sheet of any equipment to be purchased.

4.3.2.2.2 Detail design drawings of offshore PLEM for each berth with sufficient technical

details to allow construction shall be prepared. All pipes, valves and fittings shall

be completely specified in details considering the fluids to be transported by the

pipelines. All components thicknesses, design standards, materials, construction

requirements, ratings, internal lining, external coating shall be selected and

specified. PLEMs shall allow bi-directional flow operation (Tankers loading and

unloading).

4.3.2.2.3 Detail civil design, static calculations, and drawings of offshore manifolds

foundation/cradles to seabed shall be prepared. Civil design shall be according

comply with Israeli Building Law(s) and Standards, and it shall be approved by

registered Israeli civil engineer.

4.3.2.2.4 PLEMs shall allow internal flushing and shall be designed according to OCIMF

Guidelines for the Design, Operation and Maintenance of Multi Buoy Moorings.

4.3.2.2.5 Each PLEM shall allow connection for two hose strings of 12”.

4.3.2.3 MBM systems design

4.3.2.3.1 Detailed drawings with sufficient details shall be issued for each MBM system at

their new locations, showing all system components and coordinates.

4.3.2.3.2 Detailed drawings and specification for the marker buoys of ship anchors.

4.3.2.3.3 Both MBM systems shall be designed in the new locations and analyzed using

proven industry software, according to the design criteria, technical requirements

and applicable standards. The analysis shall take into account all environmental

loads, tankers size and selected Tanker's orientation.

Page 12: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 12

4.3.2.3.4 A design report including all calculations and analysis deliverables, material

selection criteria, operational envelope, details and drawings for each terminal

shall be issued for purchaser review.

4.3.2.3.5 A quasi-static and dynamic analysis for each MBM system with hose string shall

be performed considering all design and environmental loads according to

DNVGL-OS-E301 (Position mooring), latest edition.

4.3.2.3.6 The analysis of MBM system shall be performed by competent and experienced

engineer, and shall be executed using proven industry analysis software

dedicated for mooring analysis.

4.3.2.3.7 Hose strings diameter and length shall be specified by the contractor for each

MBM system. It shall be noted that the existing hosing strings are 12" diameter

and ~70 m long each.

4.3.2.3.8 For Analysis of MBM system, the following standard shall be followed (latest

valid edition):

- DNV OS-E301, Position Mooring, (Precedence standard).

- Other proven industry practices and standards may be accepted.

In addition, the following standards are to be consulted (latest valid editions):

- OCIMF Guidelines for the Design, Operation and Maintenance of Multi Buoy

Moorings.

- BS-6349 Part 6: Maritime structures, Design of inshore moorings and floating.

- API 2SK, Design and Analysis of Station keeping Systems for Floating

Structures.

4.3.2.3.9 Each MBM system shall be designed and analyzed to allow safe mooring of

tankers according to the following data:

- Each MBM system shall include at least 4 mooring legs.

- Tanker maximum tonnage: DWT = 50,000 MT. (Typically 45,000).

- Tankers Minimum length overall (MIN. LOA) is 164 meter.

- Tankers Maximum length overall (MAX. LOA) is 200 meter. (Typical tanker

LOA is 183 m).

4.3.2.3.10 More details on the existing MBM systems will be delivered during detail design.

4.3.2.3.11 Contractor shall take into account that the existing mooring legs (excluding

buoys) will be replaced during the next future. The contractor shall obtain

Purchaser's notice before commencing detail design of MBM systems, and be

Page 13: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 13

informed whether to design completely new MBM systems or designing the MBM

system in the new locations using the existing MBM system components (only

relocation and adjustment of the existing moorings in the new locations - during

system downtime).

4.3.2.4 Bill of Materials:

4.3.2.4.1 After finalizing system detail design, the Contractor shall submit the complete list

of material (BOM) and BOQ including items description, fabrication standards

and quantities.

4.3.2.4.2 The list shall be divided into categories (16” distillates pipeline, 24” fuel oil

pipeline, 24” future fuel oil pipeline, MBM systems, and PLEM systems).

4.3.2.5 Trenching requirements:

For offshore buried pipelines, the Contractor shall submit trenching requirements

and method for excavation surveying the trench before placing pipelines. The

following data and deliverable shall be included and considered:

4.3.2.5.1 The drawings shall include complete details for the configuration of the trenched

sections.

4.3.2.5.2 The trench dimensions shall be specified, the trench survey method during

installation and trench covering method shall be specified.

4.3.2.5.3 The Contractor shall specify the trenching equipment to be used.

4.3.2.5.4 The contractor shall take into account the cover depth requirements specified in

§ 4.3.1.8.3.

4.3.2.6 Risks identification and analyses:

The Contractor shall perform preliminary risks analyses and risks assessment for

the various stages during the installation process, the following are required:

4.3.2.6.1 Identification of the possible risks during all the stages of Project, such as, the

equipment installations, pipelines fabrication, trenching activities and the

pipelines installation.

4.3.2.6.2 Specification of the safety distances from tankers, mooring buoys, subsea

pipelines that are to be adopted during trenching and pipelines installation.

Page 14: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 14

4.3.2.6.3 The Contractor shall propose measures for avoiding potential risks during

installation.

4.3.3 Detail design of concrete conduit on LBW (Optional Scope):

4.3.3.1 Complete detail design and civil engineering for construction shall be

conducted for the concrete conduit planned to be installed and integrated in the

area of the LBW, (refer to concrete conduit general drawing in the supplemented

drawings).

4.3.3.2 The design shall be supplemented by all required plan and side drawings and all

sufficient technical details in order to allow construction.

4.3.3.3 The concrete conduit shall be designed based on the basic configuration

supplemented to the current spec that may be adjusted after the conceptual

design.

4.3.3.4 All necessary technical requirements and coordination of the design shall be

done with IEC, IPC and the LBW designer (HPA engineers inc.).

4.3.3.5 All Civil design documents shall be prepared under the auspices of a structural

engineer registered in Israel, and shall be certified by him.

4.3.3.6 Civil Engineering Documentation Requirements

The sheet sizes to be used for the civil engineering documentation are A0, A1,

A2, A3, and A4.

The scales to be used on the civil engineering drawings are 1:100, 1:50, 1:20,

1:10, 1:5, and 1:2.

Design criteria shall include as minimum the followings:

- General information.

- Nomenclature of foundation components.

- Codes and Standards.

- Materials data (concrete, reinforcement steel, structural steel).

- Loads list and classification.

- Load combinations.

- Structural model.

- Design procedure including description of each design step.

- Design conditions including allowable values for all design parameters.

- Reinforcement details.

Page 15: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 15

- Corrosion protection system.

Concrete Structures / Foundation formwork drawings shall include as minimum the followings:

- Concrete Structures / Foundation plan with all needed dimensions and equipment axes position.

- Concrete Structures / Foundation and equipment axes elevations.

- Concrete Structures and/or Foundation surfaces preparation with all needed tolerances for dimensions.

- Anchoring structures, anchor bolts, inserts and embedded parts layout and elevations. Top of anchor bolts shall consider the use of two nuts.

- All needed sections and details.

Foundation anchoring structures, anchor bolts, inserts and embedded parts lists

and drawings shall include information about item number, quantity, dimensions,

tolerances, materials, corrosion protection and fabrication details.

Center to center bar dimensions shall be used on the Concrete Structures/

Foundation reinforcement drawings and schedules. Adequate remark as well as

information about reinforcement steel properties, concrete cover, diameters of

bending roll shall be presented on the drawings. Stirrups shall be shown on both

transversal and axial sections of the beams.

Erection drawings shall show in details how different parts are to be assembled

and inspected on-site.

Detailed execution of work directives and assembly instructions shall permit the

Purchaser to organize construction work, erection and assembling of the

foundation and all supplied equipment.

Detailed instructions to maintain and keep safe every part of the equipment

during construction and erection, complete list of erection tools and separate

complete list of maintenance equipment and tools shall be provided by

Contractor.

4.3.4 Project Construction, Installation, Testing and Quality Control Specifications

(Optional Scope):

The Contractor shall provide complete specifications in order to perform a bid for

selecting the Constructor to construct and install the new pipelines and the

Page 16: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 16

onshore concrete conduit. At least the following specifications, plans and

procedures shall be provided and submitted:

4.3.4.1 Technical specification includes all the requirements for the tender of selecting

the Constructor. The Contractor shall specify all the technical requirements and

the quality requirements from the Constructor during all pipelines under scope of

detail design, concrete conduit and equipment installation.

4.3.4.2 Pipeline, PLEMs and MBMs fabrication specifications.

4.3.4.3 Specifications for the offshore trenching process, surveying and covering.

4.3.4.4 Complete pipelines installation plan (Basics, work plan, method statement).

4.3.4.5 Specification for pipelines field joint coating process and coating testing.

4.3.4.6 Specification and procedures of welding process, welders' qualifications and

Heat Treatment process.

4.3.4.7 Specification and procedure of N.D.E. examinations and N.D.E. Inspector's

qualifications.

4.3.4.8 Examination and testing requirements during the pipelines, manifolds and MBM

components fabrication.

4.3.4.9 Inspection and testing plan (I&TP) during the pipelines, manifolds, MBM

components installation and commissioning.

4.3.4.10 Specification of procedures to be prepared by the Constructor for pipelines

installations, testing and commissioning.

4.3.4.11 Complete procedure to be applied for the abandonment of the existing pipelines

after the commissioning of the new pipelines.

4.3.4.12 Construction and installation Safety requirements and instructions based on risks

identification.

4.3.4.13 Any additional required Special processes or procedures in order to allow

successful installation.

4.3.4.14 All above data and other essential data shall be formed and organized by the

Contractor in single and complete technical specification booklet in order to

allow purchaser to select Constructor for the offshore system.

4.4 Submitted documents:

4.4.1 At the end of the each engineering phase, all drawings, calculations, reports,

procedures, plans, specifications and bill of material shall be issued in the

required schedule and submitted for IEC's approval (Refer to Annex. J).

Page 17: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 17

5. TERMINAL POINTS AND TERMINAL CONNECTIONS

5.1 The battery limits of the conceptual design shall include the complete system of

the offshore pipelines from the MBM systems in the new their locations

(including) up to the crossing of the LBW (including), the conceptual design shall

be terminated at point on the top of LBW before piping entrance to the concrete

conduit to be placed along the LBW.

5.2 The battery limits of the pipelines system detail design, shall include the

complete system of the offshore pipelines from the MBM systems (including) at

the new locations up to the crossing of the LBW (including), and shall include the

pipelines in concrete conduit up to matching point with Purchaser onshore

pipelines design (refer to the supplemented drawings).

5.3 The battery limits of the concrete conduit detail design shall include its entire

length (approximately 155 meter length).

6. CYBER SECURITY SAFEGUARD REQUIREMENTS FOR CONTROL AND

DATA ACQUISITION SYSTEMS IN IEC FACILITIES.

NA

7. QUALITY ASSURANCE AND QUALITY CONTROL

7.1 The Contractor and the main subcontractors shall be valid certified to ISO-9001

for the herein scope of services.

7.2 The Contractor shall submit upon request a copy of its Quality Assurance Manual

including Quality Procedures.

8. STANDARDS AND SUPPLEMENTS

8.1 Standards and Codes referenced in this Specification and in the Supplements to

this Specification form an integral part of this Specification - to the extent their

requirements are consistent and conform to the requirements specifically set

forth herein. All such Standards and Codes are to the issue, including all

amendments, supplements, etc., current as of the date of the Contract, unless

indicated otherwise. In the event of a variance between the requirements of the

Standards and Codes and the particular requirements set forth in the

Page 18: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 18

Specification, the requirements specifically set forth in the Specification shall take

precedence.

8.2 The Contractor may propose Standards and Codes as alternates for, or additions

to those specified herein. A copy of each proposed Standard and code, if any,

shall be submitted (in English) for Purchaser's approval. In case Purchaser's

approval is granted, the Contractor shall remain responsible for the compatibility

of the design and the physical interfaces between the supplied Equipment and

the equipment supplied by others.

8.3 The Purchaser shall assist Contractor in identification of Israeli codes and

standards applicable to the Work. In all cases Contractor shall adhere to and

comply with the requirements of Israeli official standards found to be more

restrictive than those specified herein.

8.4 Subject to the provisions stated above, the pipelines shall be designed,

manufactured, erected, tested operated and maintained in accordance with the

standards, regulations, directives and publications of the following agencies and

organizations:

ANSI: American National Standards Institute, Inc.

ASME: American Society of Mechanical Engineers.

ASTM: American Society for Testing and Materials.

AWS: American Welding Society.

API: American Petroleum Institute.

DVN: Design according to Det Norske Veritas.

ISO: International organization for standardization.

8.5 Furthermore, without derogating from the technical requirements stipulated in

this specification, the items listed below shall be designed in accordance with the

latest editions of standards specified herein or their equivalents:

8.5.1 General and Civil design codes and Standards:

a. SI 109: Israeli Standard – Weights of building materials and structural parts

Page 19: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 19

b. SI 412: Israeli Standard – Loads on structures: Characteristic Loads

c. SI 413: Israeli Standard – Design provisions for earthquake resistance of

structures

[Combined Edition 5 (2013) and Amendments 6 (2016), 7 (2017) and 8 (2018) are

currently in force].

d. SI 413 part 2.4: Israeli Standard – Design provisions for earthquake

resistance: Non-building structures – Above-ground pipelines in industrial

facilities.

e. SI 414: Israeli Standard – Characteristic Loads on Structures: Wind Loads

f. EN 206-1: Concrete – part 1: Specification, performance, production and

conformity

g. SI 118: Israeli Standard – Concrete: Specifications, performance and

production

h. SI 466 part 1: Israeli Standard - Concrete code: General principles

i. SI 466 part 2: Israeli Standard - Concrete code: Elements

j. SI 4466 part 3: Israeli Standard - Steel for the reinforcement of concrete:

Ribbed bars

k. SI 4466 part 4: Israeli Standard - Steel for the reinforcement of concrete:

Welded fabric

l. SI 940 part 1: Geotechnical design: Geotechnics and foundation for civil

engineering

8.5.2 Primary design codes for fuel pipelines:

a. DNV-OS-F101: Submarine Pipeline Systems.

b. ISO 13623: Petroleum And Natural Gas Industries – Pipeline

Transportation Systems

8.5.3 Line Pipe materials:

a. The pipelines material standard shall conform to the latest edition of API-5L

for offshore pipelines, or

b. ISO 3183: Petroleum and natural gas industries - Steel pipe for pipeline

transportation systems

8.5.4 Valves and Flanges:

Page 20: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 20

a. ASME B16.34-2013: “Valves Flanged, Threaded, and Welding End”.

b. ASME B16.5-2009 or later: "Pipe Flanges and Flanged Fittings".

c. ASME B16.47: Large Diameter Steel Flanges.

d. API 6D: Specification for Pipeline Valves.

e. API 598: Valve Inspection and Testing.

f. API 594: Check Valves: Wafer, Wafer-lug, and Double Flanged type.

g. ISO 14313: Petroleum and natural gas industries - Pipeline transportation

systems - Pipelines valves.

h. ISO 14723: Petroleum and natural gas industries - Pipeline transportation

systems - Subsea pipelines valves.

8.5.5 Fire detection and protection:

a. National Fire Protection Association Standards (NFPA) or

b. British Standards (Great Britain)

c. Local industry standards

8.6 Supplement

The following supplements are attached hereto and their requirements form an

integral part of this specification - to the extent they are consistent and conform

to the requirements specifically set forth herein. In the event of a variance

between the requirements of the Supplements and the particular requirements

set forth in the Specification, the requirements specifically set forth in the

Specification shall take precedence.

8.6.1 Threshold Conditions, Purchaser's general documentation:

8.6.1.1 Supplement-1: Reserved.

8.6.1.2 Supplement-2: Standard 01-1E Standard Specification for Contractor’s Drawing

and Data Transmittal.

8.6.1.3 Supplement-3: General offshore pipelines plan.

8.6.1.4 Supplement-4: Proposed General arrangement in LBW area.

8.6.1.5 Supplement-5: Proposed concrete conduit section.

Page 21: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 21

8.6.1.6 Supplement-6: LBW sections (Under preparation at IPC/HPA, Will be delivered

after contract award).

8.6.1.7 Supplement-7: Pipeline existing subsea manifold drawing (for 24").

8.6.1.8 Supplement-8: deleted.

8.6.1.9 Supplement-9: Existing Boreholes Locations Drawing.

8.6.1.10 Supplement-10: Existing Boreholes logs.

8.6.1.11 Supplement-11: List of fluids to be transported by the pipelines.

8.6.1.12 Supplement-12: New distillates pipelines Flow drawing.

8.6.1.13 Supplement-13: New fuel oil pipelines Flow drawing.

8.6.1.14 Supplement-14: Eshkol-24-Terminal GA.

8.6.1.15 Supplement-15: Eshkol-16-Terminal GA.

8.6.1.16 Supplement-16: Report P.N. 736/11, "Processing of Hydrographic Data for

Ashdod Region". (Will be delivered after contract award).

8.6.1.17 Supplement-17: Site specific design response spectrum.

8.6.1.18 Supplement-18: Minimum tankers design wind Speeds requirements.

8.6.1.19 Supplement-19: Cathodic protection-SRL-366-Rev-A.

9. TECHNICAL DOCUMENTATION

The Contractor shall submit technical documentation in accordance with the

provisions of Annexure "J" – Documentation Submission Schedule.

9.1 Documentation Submission Schedule-General

9.1.1 Without derogating from Contractor's obligation to provide any other document

called for by the Contract, the Contractor shall provide the following

documentation in accordance with the general requirements set forth above and

the schedule as listed in annexure JA & JB (attached herein).

Annexure JA: A table that summarizes all required technical documentation

that will accompany the proposal.

Page 22: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 22

Annexure JB: A table that summarizes all required technical documentation

that will be submitted after notification of award.

9.1.2 The table of annexure JB shall form the basis for a monthly report to be

submitted following Contract award showing the actual submission dates and the

respective Approval Status, and upon Purchaser's and Contractor's mutual

written consent shall be updated to account for any additional documents called

for by the Contract in the course of detail design or additional documents called

for by Change Orders.

10. TECHNICAL REQUIREMENTS

10.1 General requirements

10.1.1 Basic Pipelines data:

10.1.1.1 Existing maximum operating internal pressure (MOP): 15 barg (Dictated by tanker

pumps).

10.1.1.2 New pipelines design Pressure: All pipelines design pressure shall be at least 19

bar.

10.1.1.3 Design temperature of the 16" distillates pipeline shall be 35 °C, and 70°C for the

24" fuel oil pipelines.

10.1.1.4 Flow Rate: The maximum flow rates in the new system shall be calculated by the

contractor for each pipeline.

10.1.1.5 Design life time: 50 years for pipelines/Manifolds, 30 years for MBM systems.

10.1.1.6 Following are basic existing future pipelines information:

Description

Existing

Dia.

(inch)

New

Dia.

(inch)

Existing

length

(meter)

New

length

(meter)

Fluids (1)

Existing

Flow rates

m³/hr

Operational

temperature

(ºC)

Southern

MBM 16" 16" 1300 *

Distillates

(Refined

fuels)

750~1000 35

(non heated)

Page 23: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 23

Southern

MBM NA 24" 1500 * Fuels oil NA

65

(heated)

Northern

MBM 24" 24" 1794 * Fuels oil 1000~1500

65

(heated)

(1) Refer to Supplement-11 - fluids list.

10.1.2 The pipelines design shall insure future piggablility of the pipelines. The

Contractor shall provide all the drawings for the intelligent pigs' launchers and

receivers at both ends of the pipelines.

10.1.3 The design of the pipelines shall take into account all the existing loads that may

occur during the life of the pipeline, standard required loads, erection loads,

environmental loads, accidental loads, occasional loads (Wind/Seismic) and

operational loads.

10.2 MBM System requirements:

10.2.1.1 As minimum, each MBM system shall be capable to withstand the standard load

combinations of the following: Minimum Wind velocity according "Supplement

18", current velocities as specified in paragraph 10.3 and a wave significant

height of at least 2m.

10.2.1.2 The design life of each system shall be at least 30 years.

10.2.1.3 The criteria and safety factors to be adopted for selecting the capacity of mooring

components shall be not less than those specified in "Table 4 — Suggested

criteria for selecting the capacity of mooring components" of BS-6349 part 6

standard.

10.2.1.4 Considering that the connections of mooring legs to tanker are by steel cables

connected to tanker's winches. A wind limitations envelope (operational

envelope) shall be developed after analysis for each MBM considering winch

braking loads (30 Ton) combined with maximum wave height and maximum

current speed.

10.2.1.5 The MBM analysis shall take into account both ballast draft and fully laden

conditions.

10.2.1.6 The MBM shall be designed to allow survival condition for berth occupied and

unoccupied.

Page 24: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 24

10.2.1.7 Wear and corrosion rates in allowances [mm] per year of service life for chain

sections, shall not be less than:

• For splash zone, 0.4 mm/year.

• For Intermediary zone (catenary), 0.2 mm/year

• For touch down zone and bottom, 0.4 mm/year.

10.2.1.8 After analysis and material selection, the contractor shall specify the minimum

free maintenance/inspection period in years for the each chain section (Splash

zone, Intermediary (catenary) zone, touch down and bottom zones). The period in

any case shall not be less than 5 years. as following sections:

10.2.1.9 A quasi-static and dynamic analysis for each MBM system shall be performed

considering all design and environmental loads according to DNVGL-OS-E301

(Position mooring), latest edition.

10.2.1.10 The analysis of MBM system shall be performed by competent and experienced

engineer, and shall be executed using proven industry analysis software

dedicated for mooring analysis.

10.2.1.11 The tankers in all berths are mooring in a direction of 270°±5° degree.

10.2.2 Selection of MBM components:

10.2.3 The proposed MBM's design shall assure that the buoys will remain at their

positions without excessive movements during storms according to the

supplemented environmental conditions. To avoid excessive buoy movements,

or in order to shorten chains of mooring legs, the designer shall offer measures

to limit buoy movements such as adding sinkers.

10.2.4 The use of intermediate shackles for chains joining shall be avoided, i.e. the

mooring leg shall be made of one piece of chains without intermediate shackles

or connecting elements.

10.2.5 Anchors shall be selected to hold at least the most severe calculated

combination of analyzed load.

10.3 Environmental considerations, Site Conditions and Hydrographic

Conditions

The following hydrographic conditions may be taken into account during

proposal, complete historical hydrographic information (Supplement-16) will be

provided after contract award

Page 25: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 25

10.3.1 Waves:

The statistical analysis of waves at Ashdod during the considered 19

hydrographic years (01.04.1992 – 31.03.2011) shows that:

• The dominant direction is WNW. Approximately 51% of the annual waves come

from this direction.

• At the recording buoy location the extreme wave height with 50 years return

period is about 7.2 m, with 100 years return period is about 7.6 m, with 200 years

return period is about 8.0 m.

• In deep water, the extreme wave height with 50 years return period is about 8.1

m, with 100 years return period is about 8.7 m, with 200 years return period is

about 9.2 m.

• The total number of storms was 91.

• The average number of storms per year is ~5, the minimum is 2 storms per year

and the maximum is 9 storms per year.

• Three major storms with Hm0>6.5 m occurred on December 2002, January 2008,

and December 2010. The highest significant wave in deep water was Hm0 =6.93

m (20.12.2002). The highest waves propagate from the dominant direction

WNW.

• The average storm duration is about 47 hr.

• The longest storm duration was approximately 100 hr and the shortest storm

duration was 18 hr.

• Refer to the following figures:

Page 26: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 26

Page 27: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 27

Page 28: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 28

Page 29: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 29

Page 30: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 30

Page 31: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 31

Page 32: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 32

10.3.2 Winds data to be considered for the design:

It should be noted that the statistical analysis is based on 10min wind time

series, thus, could not be applied for analysis of wind gusts. The statistical

analysis of winds in Ashdod area shows that:

• Approximately 90% of annual winds, 86% of winter winds and 93% of summer

winds are light (Wind speed less than 6 m/s). About 9% of annual winds, 12% of

winter winds and 7% of summer winds are fresh (Wind speed between 6 m/s

and 10 m/s). In general, only 1.2% of annual winds, 2.7% of winter winds and

0.26% of summer winds are strong and exceed 10 m/s.

• The direction of significant winds (wind speed larger than 6 m/s) is NNW with

1.64% occurrence. The dominant direction of strong winds (wind speed larger

than 10 m/s) able to generate wave storms and strong currents is SW with

0.30% occurrence.

• The strongest winds are in reasonable agreement with wave storm events in

deep water. The maximum wind speed 21.8 m/s was recorded during the winter

storm event on 12.12.2010. In that storm the wave significant height at the

Ashdod buoy location larger than 6m. The corresponding wind direction was

SSW.

• Refer to the following figures:

Page 33: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 33

10.3.2.1 Currents:

The statistical analysis of currents in the, according to measurement stations

Asd1-Asd3 (most relevant stations) and CM1-CM3, in Ashdod area shows that:

• Most of the time (90%), the speed of near-surface current does not exceed 35

cm/s at Asd1, Asd2 and Asd3 stations, 25 cm/s at CM1 station and 15 cm/s at CM3

station; and the speed of the near-bottom current does not exceed 25 cm/s at

Asd1, Asd2 and Asd3 stations, 20 cm/s at CM1 station and 10 cm/s at CM3 station.

• The larger velocities were recorded close to the water surface. The largest near-

surface and near-bottom speeds recorded were: at Asd1, Asd2 and Asd3

stations (10 years of measurements) ~ 120 cm/s and 85.0 cm/s respectively; (b) at

Cm1 station for every short time of records (1 year of measurements only) ~ 61

cm/s and 60 cm/s, respectively; (c) at Cm3 station for every short time of records (1

year of measurements only) ~ 41 cm/s and 32 cm/s, respectively.

• The predominant direction of currents is from south to north along shore.

• Refer to the following figures:

Page 34: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 34

10.3.2.2 Seawater Temperature:

The statistical analysis of seawater temperature in the Ashdod area shows that:

• Seawater temperature range from 12.5 ºC in winter to 32.8 ºC in summer. The

average temperatures in winter are 19.6 ºC, 26.2 ºC in summer and 23.4 ºC on

a yearly basis.

• Seawater temperatures are larger than 19.0 ºC for 50% of winter records, 27.5

ºC for 50% of summer records and 23.0 ºC for 50% of annual records.

• Only 10% of winter records show temperature lower than 17.0 ºC, only 10% of

summer records show temperatures lower than 20.0 ºC and only 10% of annual

records show temperature lower than 17.5 ºC.

• Only 10% of winter records show temperature larger than 24.0 ºC, only 10% of

summer records show temperatures larger than 30.5 ºC and only 10% of annual

records show temperature larger than 30.0 ºC.

10.3.2.3 Air Temperature:

Records at the "Negba" meteorological station (Nearest one to Ashdod) during

1981-2000 show that:

• The daily mean maximum and minimum air temperature measured by Israeli

meteorological services "IMS" are +31.1 ºC in August and +8 ºC in February.

Page 35: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 35

• The highest daily maximum and the lowest daily minimum air temperature are

+42.4 ºC in September and -0.7 ºC in February.

10.3.3 Wind Load to be considered for the design of Onshore above ground structures:

The calculation of wind loads on above ground structures in Israel is governed by

the provisions of the Israeli Standard SI 414 (latest edition at contract signing)

“Characteristic Loads in building: Wind Load”.

The calculation shall be accomplished using the basic design wind velocity,

defined below.

According to this Israeli Standard, the basic design wind velocity is defined as

the average velocity for ten (10) minutes, with an average return period of fifty

(50) years, at an altitude of ten (10) meters above ground level, and in a flat open

country terrain with only a few obstacles (Roughness Category II)".

The maximum upper gust velocity (three (3) seconds average) can be calculated

by multiplying the fundamental basic design wind velocity (ten (10) minute

average) by a factor of 1.50.

The fundamental basic design shall be taken from the velocity map which forms

an integral part of the standard.

For the site of the project, the fundamental basic design wind velocity indicated

by this Standard is 30 m/sec.

Roughness Category 0 shall be assumed at the project site.

Note:

For the full Hydrographic data of Ashdod region, refer to Supplement-16,

"Processing of Hydrographic Data for Ashdod Region.

10.3.4 Earthquake Loads to be considered for the design of above ground structures

(Onshore):

The seismic design of buildings and structures in Israel is governed by the

provisions of the Israeli Standard SI 413 “Design Provisions for the Earthquake

Page 36: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 36

Resistance of Structures” (Combined Edition 5 (2013) and Amendments 6

(2016), 7 (2017) and 8 (2018) are currently in force).

According to this Standard, the seismicity of the site is expressed by the

expected horizontal ground acceleration coefficient Z and corresponding mapped

horizontal spectral response acceleration parameters Ss and S1.

The expected horizontal ground acceleration coefficient Z expressed as:

Z = ah,max/g.

The expected ground acceleration is a forecast of the peak of the horizontal

ground acceleration due to an earthquake, ah,max, expressed in m/sec², for which

there is a given probability (10%, 5%, 2%) that a stronger acceleration will occur

at least once within a period of 50 years. The gravity acceleration g = 9.81

m/sec2.

For Plant site the following parameters shall be assumed.

For 10% probability (475 years return period):

Z = 0.06, Ss = 0.15, S1 = 0.04

For 2% probability (2475 years return period):

Z = 0.11, Ss = 0.28, S1 = 0.07

Site Class by soil profile type shall be determined by Geotechnical Consultant.

Site Class D is assumed.

Power Plant is included in Group A with importance factor I=1.4.

Site specific response spectrum shall be taken into consideration.

10.3.5 Exposure Classes for concrete structures

Exposure classes related to environmental conditions in accordance with Israeli

Standards SI 118 and SI 466 will be at least as follows:

10.3.5.1 Concrete structures above ground level – Exposure Class 8;

10.3.5.2 Concrete structures below ground and Foundations – Exposure Class 9;

10.2 Safety

The services supplied under this Specification shall meet the U.S.

"OCCUPATION, SAFETY, AND HAZARD ADMINISTRATION" (OSHA)

requirements or equivalent.

Page 37: EM-1510-ANN-B-Eshkol New offshore pipelines - iec.co.il New offshore... · offices (Haifa and Ashdod area, Israel), one meeting shall be conducted immediately after contract signing

THE ISRAEL ELECTRIC CORPORATION LTD. ANNEXURE "B" Engineering Division SPEC.: EM-1510 ISSUE: for Proposal

B - 37

11. TEST AND INSPECTIONS

NA

12. PACKAGING & DELIVERY

NA

13. STORAGE & HANDLING

NA

14. NAMEPLATE / MARKING

NA

15. NOTES

Subcontracting of any services provided herein, shall only be allowed with the

written approval of the Purchaser, prior to any such activity.

16. SPECIAL REQUIREMENT

All “for construction” Civil design such as subsea foundations, PLEM’s cradle,

concrete conduit or other) under the current spec, shall be prepared under the

auspices of a structural engineer registered in Israel, and shall be certified by

him.

– F I N A L –