DMS200676 Electricity Distribution Licence Performance Reporting Handbook April 2019

Transcript of Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity...

Page 1: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

DMS200676

Electricity Distribution Licence Performance Reporting Handbook

April 2019

Page 2: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook

Economic Regulation Authority

4th Floor Albert Facey House 469 Wellington Street, Perth

Mail to: Perth BC, PO Box 8469 PERTH WA 6849

T: 08 6557 7900

F: 08 6557 7999

E: [email protected]

W: www.erawa.com.au

National Relay Service TTY: 13 36 77 (to assist people with hearing and voice impairment)

We can deliver this report in an alternative format for those with a vision impairment.

© 2019 Economic Regulation Authority. All rights reserved. This material may be reproduced in whole or in part provided the source is acknowledged

Page 3: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 1

Contents

1. Introduction ..................................................................................... Error! Bookmark not defined.

2. Purpose of this handbook ......................................................................................................... 2

3. Distribution datasheets .............................................................................................................. 3

3.1 Completing the distribution datasheets ......................................................................... 3

3.2 Submission of completed datasheets to the ERA ......................................................... 4

4. Performance reporting indicators ............................................................................................. 5

4.1 Customer connections ................................................................................................... 6

4.2 Network reliability .......................................................................................................... 8

4.3 Complaints ................................................................................................................... 11

4.4 Compensation payments ............................................................................................. 14

4.5 Timely repair of faulty street lights ............................................................................... 15

4.6 Call centre performance .............................................................................................. 16

4.7 Network and asset information .................................................................................... 18

Page 4: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 2

1. Background

The Economic Regulation Authority is responsible for administering the electricity licensing scheme under Part 2 of the Electricity Industry Act 2004.

Electricity licences contain terms and conditions, including a requirement for licensees to provide to the ERA specified information on matters relevant to the licence. Clause 4.5 of electricity distribution licences and electricity integrated regional licences states:

The licensee must provide to the ERA, in the manner and form prescribed by the ERA, specified information on any matter relevant to the operation or enforcement of the licence, the operation of the licensing scheme provided for in Part 2 of the Act, or the performance of the ERA’s functions under that Part.

The obligation to provide performance data only applies to the holders of electricity distribution licences and electricity integrated regional licences who supply electricity to small use customers (customers who consume not more than 160 MWh of electricity per year).

The ERA publishes an annual performance report using the data provided by licensees. Licensees must also publish the data on their website.

2. Purpose of this Handbook

This handbook sets out the non-financial performance data licensees must provide to the ERA, including the date by which it must be submitted.

To be able to interpret and compare the data, there must be a shared understanding amongst stakeholders of the information that must be reported, including the definitions that apply to the performance indicators and how the information should be presented. Accordingly, this handbook informs electricity distribution licensees about:

• the performance indicators that distributors are required to provide data for

• the definitions that apply to the performance indicators

• how to calculate the performance data (where applicable)

• how and when the data must be provided to the ERA.

Licensees should familiarise themselves with the Code of Conduct for the Supply of Electricity to Small Use Customers (Code of Conduct), the Electricity Industry (Network Quality and Reliability of Supply) Code 2005 (NQ&R Code) and the 2017 SCONRRR Report1 to fully understanding the reporting framework.

1 Utility Regulators Forum, Steering Committee on National Regulatory Reporting Requirements – Retail

Working Group, 2007, National Energy Retail Performance Indicators (online) [accessed 17 April 2019]

Page 5: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 3

3. Distribution Datasheets

The ERA has published two Microsoft Excel workbooks: ‘Electricity Reporting Datasheets – Distribution’ and ‘Electricity Reporting Datasheets - Network Quality & Reliability Code’ (together referred to as Distribution Datasheets).

The first workbook covers obligations arising from the Code of Conduct and the second workbook covers obligations arising from the NQ&R Code. The latest version of the Distribution Datasheets can be found on the ERA website.

The Electricity Reporting Datasheets – Distribution have five worksheets:

• Customer connections

• Complaints

• Compensation payments

• Timely repair of faulty streetlights

• Call centre performance.

The Electricity Reporting Datasheets - Network Quality & Reliability Code have four worksheets:

• Network reliability

• Complaints

• Compensation payments

• Network and asset information.

3.1 Completing the Distribution Datasheets

The Distribution Datasheets contain tables in the format shown in Error! Reference source not found. below.2

Table 1: Example datasheet format

Indicator No.

Description Basis of Reporting Comments

Number Percentage

CCD 1 Total number of new connections provided

When completing the tables in the Distribution Datasheets the structure of the data entry cell should not be modified by inserting, deleting or re-ordering rows / columns. A number of cells contain values that are calculated from data that has been entered into other cells. These cells have been shaded yellow.

Only enter data into the cells that are not shaded.

2 The ‘Complaints’ (NQ&R Code workbook only) and ‘Compensation payments’ worksheets include a Value

($) column to report dollar amounts paid.

Page 6: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 4

Referring to the example in Table 1:

• The ‘indicator number’ column contains the unique reference number for the indicator.3

• The ‘description’ column provides a short explanation of what the indicator is intended to measure.

• The ‘basis of reporting’ column contains data entry cells for:

− number4

or

− percentage5

In some worksheets, the table includes a value ($) column.6

The data entry cells have been formatted to align with the required degree of accuracy (that is, the number of decimal places) for each indicator.

• The ‘comments’ column allows licensees to add explanatory notes, for example where there has been significant change in values from previous reporting periods, or where the licensee feels that additional information will assist the reader to understand the data.

• This handbook uses the term ‘distribution system’ and ‘network’ to reflect that the Electricity Industry (Metering) Code 2012 (Metering Code) uses the term ‘distribution system’ and the NQ&R Code uses the term ‘network’.

3.2 Submission of completed datasheets to the ERA

The completed Distribution Datasheets for the year ending 30 June must be submitted to the ERA by no later than 30 September. They should be sent by email to: [email protected]

Compliance with clause 4.5 of the licence is only achieved when an electronic copy of the completed Distribution Datasheets has been received by the ERA.

After the ERA has reviewed a licensee’s Distribution Datasheets and the licensee has addressed any comments the ERA may have, the ERA will instruct the licensee to publish the Datasheets on the licensee’s website by a date specified by the ERA, in accordance with clause 13.3 of the Code of Conduct.

3 In this example the indicator is in the ‘Customer Connections’ worksheet. 4 Section 4 provides more information on how to complete the ‘number’ column. 5 This is automatically calculated from numerical data entered into other cells 6 For example, the ‘Compensation payments’ worksheet.

Page 7: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 5

4. Performance reporting indicators

Distributors should complete the ‘number’ column in each worksheet as follows:

• If data is available: enter the data.

• If the activity did not occur: enter ‘0’.

Explanatory note: For example, if the distributor did not provide any new connections on its distribution system, the data for indicator CCD 1 should be ‘0’.

• If the activity is not applicable: enter ‘n/a’.

Explanatory note: For example, if the distributor did not provide any new connections on its distribution system, indicator CCD 2 should be marked ‘n/a’.

• If the data is unavailable: leave the data cell blank and add a comment in the ‘comments’ cell explaining why the data cannot be provided.

If the data shows a change of more than 10% compared to last year’s data, the distributor should include the likely reason(s) for the change in the ‘comments’ column.

Reporting basis: point in time vs whole reporting year

Some indicators are based on a moment in time (i.e. 30 June) whereas others cover the whole reporting year.

Reporting basis: per customer/premises vs per incident

Some indicators require reporting to be on a per customer/premises basis whereas others are on a per incident basis. For example, indicator NQR 1 (Number of premises of small use customers interrupted for more than 12 hours continuously) should be reported on a per customer/premises basis. This means that if a premises of a small use customer is interrupted for more than 12 hours continuously, and more than once during a reporting year, the premises should only be counted once. Indicator CCD 4 (Total number of reconnections provided) should be reported on a per incident basis. This means that if a premises is reconnected more than once during a reporting year, each reconnection should be recorded separately.

Page 8: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 6

4.1 Customer connections

4.1.1 Purpose

To report on the number of:

• small use customer connections on each electricity distribution system.

• new customer connections that were not provided on time.

• reconnections that were not provided on time.

4.1.2 Reported indicators

No. Indicator

CCD 1 Total number of new connections provided

CCD 2 Total number of new connections not provided on or before the agreed date

CCD 3 Percentage of new connections not provided on or before the agreed date

CCD 4 Total number of reconnections provided

CCD 5 Total number of reconnections that were not provided within the prescribed timeframe

CCD 6 Percentage of reconnections that were not provided within the prescribed timeframe

CCD 7 Total number of connections on the distribution system(s)7

4.1.3 Definitions

Attach has the same meaning as in the Electricity Industry (Obligation to Connect) Regulations 2005.8

Connection means a customer premises that is attached to the distribution system and energised.

Explanatory note: The total number of customers connected refers to distribution connections rather than customer connections.

Connection provided means the establishment of a new distribution connection on the distribution system during the year ending 30 June.

De-energise means the removal of the supply voltage from the meter at the customer’s premises, while leaving the premises connected to the distribution system.

Disconnection means to de-energise a customer’s supply address.

7 If a distributor operates more than one distribution system, indicator CCD 7 should record the total number

of connections on the systems. Use the ‘Comments’ cell to provide a breakdown of connections by each system.

8 The definition is: “attach” means to do all that is needed to connect premises to a distribution system except energise the premises.

Page 9: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 7

Distribution system has the same meaning as in the Metering Code, which takes its definition from the Act.9

Energise has the same meaning as in the Electricity Industry (Obligation to Connect) Regulations 2005.10

Not provided on or before the agreed date means connections or reconnections not provided within any regulated time limit, or by the date agreed with the customer.

Reconnection means to re-energise a customer premises following disconnection.

Explanatory notes:

• A reconnection does not include when a pre-payment meter is recharged and the supply address goes from de-energised to energised.

• For reporting purposes, reconnections must include all reconnections carried out by the distributor at the request of a retailer (previously, this handbook only required reconnections to be reported when the disconnection occurred because the customer failed to pay a bill).

[This reporting requirement is mandatory from the 2019/20 reporting year onwards. In the 2018/19 reporting year, distributors that are not able to report on all reconnections carried out during the year must use the ‘Comments’ cell for indicator CCD 4 to explain what the reconnections were for].

9 The definition is: “distribution system” means any apparatus, equipment, plant or buildings used, or to be

used, for, or in connection with, the transportation of electricity at nominal voltages of less than 66 kV. 10 The definition is: “energise” means to complete a connection by establishing, at the meter through which

electricity is to be supplied to a customer’s premises, a voltage that is capable of being sustained under the expected load conditions.

Page 10: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 8

4.2 Network reliability

4.2.1 Purpose

To report on the frequency and duration of interruptions to supply experienced by customers on the distribution network during the reporting year.

4.2.2 Reported indicators

No. Indicator

NQR 1 The number of premises of small use customers to which the supply of electricity has been interrupted for more than 12 hours continuously

NQR 2 The number of premises of small use customers to which the supply of electricity has been interrupted more than the permitted number of times, as is defined in section 12(1) {of the NQ&R Code}

NQR 3 For each discrete area, the average length of interruption of supply to customer premises expressed in minutes

NQR 4 For each discrete area, the average number of interruptions of supply to customer premises

NQR 5 For each discrete area, the average percentage of time that electricity has been supplied to customer premises

NQR 6 For each discrete area, the average total length of all interruptions of supply to customer premises expressed in minutes

NQR 7 Overall SAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 8 Distribution Network (Planned) SAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 9 Distribution Network (Unplanned) SAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 10 Normalised distribution network SAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 11 Overall SAIFI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 12 Distribution Network (Planned) SAIFI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 13 Distribution Network (Unplanned) SAIFI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 14 Normalised distribution network SAIFI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 15 Overall CAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 16 Distribution Network (Planned) CAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

Page 11: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 9

No. Indicator

NQR 17 Distribution Network (Unplanned) CAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

NQR 18 Normalised distribution network CAIDI by Total Network, CBD, Urban, Short Rural and Long Rural

Explanatory note: Indicators NQR 1 to NQR 6 are reporting under the NQ&R Code. The NQ&R Code requires a distributor to report its annual performance and its average performance over the past four years. The values that the distributor puts in NQR 3 to NQR 6 should be the four-year average. Indicators NQR 7 to NQR 18 are for SCONRRR reporting.

4.2.3 Calculations

SAIDI is calculated as:

(∑ Customer interruption durations) / Total number of customers served

SAIFI is calculated as:

(∑ Number of customers interrupted) / Total number of customers served

CAIDI11 is calculated as:

(∑ Customer interruption durations) / Total number of customers interrupted

When calculating SAIDI, SAIFI and CAIDI, apply the data set definitions in Table 2.

Table 2: Reliability data sets for sustained interruptions

Label Data Set

Overall interruptions All sustained planned and unplanned interruptions including those caused by generation outages, transmission outages and directed load shedding

Unplanned and Planned

Excludes generation outages, transmission outages12 and directed load shedding

Normalised All unplanned sustained interruptions with the exclusion of interruptions:

• that are caused by generation outages

• that are caused by transmission outages13

• that are caused by directed load shedding

• where the daily unplanned SAIDI exceeds the Major Event Day boundary14

11 CAIDI is also calculated as the ratio SAIDI / SAIFI. 12 The calculation of unplanned interruptions must include interruptions caused by the failure of transmission

connection assets due to inadequate planning of transmission connections where the responsibility for transmission connection planning lies with the distributor.

13 See the above footnote. 14 The SAIFI and CAIDI associated with the interruption should also be excluded from the calculation of

normalised SAIFI and normalised CAIDI.

Page 12: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 10

4.2.4 Definitions

CAIDI (Customer Average Interruption Duration Index) is the average time to restore supply to a customer when a sustained interruption has occurred.

Directed load shedding means load shedding that has been directed by the Australian Energy Market Operator (AEMO) system management.

Discrete area means the areas defined in Schedule 1, item 2 of the NQ&R Code.

Outage means a state on the network where it is not able to perform its intended function due to an event associated with a network component (Note: an outage may not always result in an interruption of supply to a supply address).

Major Event Day is as defined in the Institute of Electrical and Electronics Engineers (IEEE) standard 1366-2003, IEEE Guide for Electric Power Distribution Reliability Indices. Distributors are required to apply the “2.5-beta method” described in this standard to calculate the major event day boundary (TMED). If four years of interruption data is not available to calculate TMED, then distributors are required to calculate TMED using the maximum available period of time for which interruption data is available.

Planned interruption means a sustained interruption of supply to a supply address that has been caused by scheduled works, for example, preventative maintenance, repairs and network augmentation. Customers are notified in advance of planned interruptions. Planned meter replacements are excluded.

SAIDI (System Average Interruption Duration Index) is the total duration of interruption (minutes without supply) for the average customer as a result of sustained interruptions.

SAIFI (System Average Interruption Frequency Index) is the number of supply interruptions for the average customer as a result of sustained interruptions.

SCADA (Supervisory Control and Data Acquisition) is an industrial computer system that monitors and controls a process. In the case of the transmission and distribution elements of electrical utilities, SCADA will monitor substations, transformers and other electrical assets.

Sustained interruption means a loss of electricity associated with an outage on any part of the network of more than one minute in duration. The interruption starts when it is recorded by equipment (such as a SCADA system) or, where such equipment does not exist, at the time that the first customer call relating to the network outage is received. The interruption ends when supply has been restored to that part of the distribution network affected by the outage, or when the supply is reasonably assumed to have been restored if there is no equipment available to record the time of restoration.

Unplanned interruption means a sustained interruption that is not a planned interruption, or a planned interruption where the required advance notice of the interruption has not been given to the customer.

Page 13: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 11

4.3 Complaints

4.3.1 Purpose

To report on the level of satisfaction with the distributor’s service and the customer complaints it receives.

4.3.2 Reported indicators

No. Indicator

CCD 8 Total number of complaints (excluding complaints under indicator NQR 19) received

CCD 9 Total number of administrative processes or customer service complaints

CCD 10 Total number of other complaints

CCD 11 Number of customer complaints {received in relation to CCD 8} concluded within 15 business days

CCD 12 Percentage of customer complaints {received in relation to CCD 8} concluded within 15 business days

CCD 13 Number of customer complaints {received in relation to CCD 8} concluded within 20 business days

CCD 14 Percentage of customer complaints {received in relation to CCD 8} concluded within 20 business days

CCD 15 Total number of customer complaints {received in relation to CCD 8 and NQR 19 combined} concluded within 15 business days

CCD 16 Percentage of customer complaints {received in relation to CCD 8 and NQR 19 combined} concluded within 15 business days

CCD 17 NOT USED

CCD 18 NOT USED

CCD 19 Total number of complaints relating to the installation and operation of a pre-payment meter at a pre-payment meter customer's supply address

CCD 20 Total number of complaints relating to the installation and operation of a pre-payment meter at a pre-payment meter customer's supply address concluded within 15 business days

CCD 21 Percentage of complaints relating to the installation and operation of a pre-payment meter at a pre-payment meter customer's supply address concluded within 15 business days

NQR 19 Total number of complaints received {that Part 2 or an instrument made under section 14(3) of the NQ&R Code has not been, or is not being, complied with}

NQR 19A Total number of complaints received {that Part 2 or an instrument made under section 14(3) of the NQ&R Code has not been, or is not being, complied with} that were concluded within 15 business days

Page 14: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 12

No. Indicator

NQR 20 Total number of complaints received from customers in each of the discrete areas {that Part 2 or an instrument made under section 14(3) of the NQ&R Code has not been, or is not being, complied with}

NQR 21 Total amount spent in addressing complaints {that Part 2 or an instrument made under section 14(3) of the NQ&R Code has not been, or is not being, complied with} other than by way of payment under sections 18 and 19 {of the NQ&R Code}

NQR 22 Total number of technical QoS complaints

NQR 23 Total number of technical QoS complaints that are low supply voltage complaints

NQR 24 Percentage of technical QoS complaints that are low supply voltage complaints

NQR 25 Total number of technical QoS complaints that are voltage dip complaints

NQR 26 Percentage of technical QoS complaints that are voltage dip complaints

NQR 27 Total number of technical QoS complaints that are voltage swell complaints

NQR 28 Percentage of technical QoS complaints that are voltage swell complaints

NQR 29 Total number of technical QoS complaints that are voltage spike complaints

NQR 30 Percentage of technical QoS complaints that are voltage spike complaints

NQR 31 Total number of technical QoS complaints that are waveform distortion complaints

NQR 32 Percentage of technical QoS complaints that are waveform distortion complaints

NQR 33 Total number of technical QoS complaints that are TV or radio interference complaints

NQR 34 Percentage of technical QoS complaints that are TV or radio interference complaints

NQR 35 Total number of technical QoS complaints that are noise from appliances complaints

NQR 36 Percentage of technical QoS complaints that are noise from appliances complaints

NQR 37 Total number of technical QoS complaints that are other complaints

NQR 38 Percentage of technical QoS complaints that are other complaints

NQR 39 Breakdown of technical QoS complaints into the likely cause of the problem that caused the complaint {by percentage}, separated into:

• Network equipment faulty

• Network interference by NSP equipment

• Network interference by another customer

• Network limitation

• Customer internal problem

• No problem identified

• Environmental

• Other

Page 15: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 13

4.3.3 Calculations

• CCD 12 = 100 x CCD 11/CCD 8

• CCD 16 = 100 x (CCD 11 + NQR 19A)/(CCD 8 + NQR 19)

4.3.4 Definitions

Administrative processes or customer service complaints includes complaints about meter readings, timeliness of correspondence and other customer communications, the complaints handling process, timeliness of response to complaints and any other process of a general administrative nature.

Complaint means an expression of dissatisfaction made to or about an organisation, related to its products, services, staff or the handling of a complaint, where a response or resolution is explicitly or implicitly expected or legally required.15

Explanatory notes:

• Complaints may be received via a variety of media, including telephone, mail, facsimile, email or in person.

• More than one complaint can be made per customer contact. If a customer makes a complaint about a billing matter and a transfer matter in the same communication, then two complaints should be recorded.

• For reporting purposes, complaints do not include complaints made internally by the distributor’s staff about the matters specified in the complaint categories.

• For reporting purposes, complaints must include complaints resolved at the first point of contact. [This reporting requirement is mandatory from the 2019/20 reporting year onwards. In the 2018/19 reporting year, distributors that have not recorded complaints resolved at the first point of contact during the year must use the ‘Comments’ cell for indicators CCD 8 and NQR 19 to explain that the total number of complaints does not include complaints resolved at the first point of contact].

Discrete area means the areas defined in Schedule 1, item 2 of the NQ&R Code.

Other complaints include poor service, privacy considerations, failure to respond to complaints, health and safety issues, and any other matter that is not covered by the NQ&R Code.

Technical QoS complaints includes complaints about electricity supply quality.

15 A detailed discussion of complaints, with examples, is in Appendix 1 of the 2007 SCONRRR Report.

Page 16: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 14

4.4 Compensation payments

4.4.1 Purpose

To report on the number of payments and the amounts paid by distributors for failing to meet specified standards of service to customers.

4.4.2 Reported indicators

No. Indicator

CCD 22 Total number of payments made, and the total amount paid under clause 14.4 of the Code of Conduct

CCD 23 Total number of payments made, and the total amount paid under clause 14.5 of the Code of Conduct

NQR 40 The number of payments made, and the total amount paid under section 18 of the NQ&R Code

NQR 41 The number of payments made, and the total amount paid under section 19 of the NQ&R Code

Explanatory note: the distributor should only include the payment of the statutory amount required by each section of the NQ&R Code, or the Code of Conduct, as applicable. The payment of ex-gratia sums over and above these amounts should be included in indicator NQR 21.

Payments that have been claimed by customers during the reporting year, but have not been paid as at 30 June, should be excluded.

Page 17: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 15

4.5 Timely repair of faulty street lights

4.5.1 Purpose

To report on the timeliness of repairs to faulty street lights.

4.5.2 Reported indicators

No. Indicator

CCD 24 Total number of street lights reported faulty in the metropolitan area

CCD 25 Total number of street lights reported faulty in the regional area

CCD 26 Total number of street lights not repaired within five (5) business days in the metropolitan area

CCD 27 Percentage of street lights not repaired within five (5) business days in the metropolitan area

CCD 28 Total number of street lights not repaired within nine (9) business days in the regional area

CCD 29 Percentage of street lights not repaired within nine (9) business days in the regional area

CCD 30 Total number of street lights in the metropolitan area

CCD 31 Total number of street lights in the regional area

CCD 32 Average number of business days to repair faulty street lights in the metropolitan area

CCD 33 Average number of business days to repair faulty street lights in the regional area

4.5.3 Calculations

The “average number of business days to repair faulty street lights” is calculated by:

∑(number of business days to repair each faulty streetlight) / total number of faulty streetlights

4.5.4 Definitions

Metropolitan area means the areas of the State defined in Part 1.5 of the Code of Conduct.

Number of street lights reported faulty each month includes all fault reports that have been recorded during each calendar month. If a faulty street light is the subject of more than one fault report for the same fault, then only one fault is recorded.

Regional area means all areas in the State other than the metropolitan area.

Page 18: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 16

4.6 Call centre performance

4.6.1 Purpose

To report on the level of service provided to customers who contact the distributor by telephone.16

4.6.2 Reported indicators

No. Indicator

CCD 34 Total number of telephone calls to a call centre of the distributor

CCD 35 Total number of telephone calls to a call centre answered by a call centre operator within 30 seconds

CCD 36 Percentage of telephone calls to a call centre answered by a call centre operator within 30 seconds

CCD 37 Average duration (in seconds) before a is call answered by a call centre operator

CCD 38 Number of the calls that are unanswered

CCD 39 Percentage of the calls that are unanswered

4.6.3 Calculations

The “average duration before call answered by operator” is calculated as:

∑(answer wait times) / total number of calls answered by an operator

Explanatory note:

• This measure only includes calls that are answered by call centre staff.

• For IVR systems, the measurement period commences at the time that the customer selects an option indicating they wish to speak to a call centre operator.

• For non-IVR systems, the measurement period commences when the call is received by the switchboard.

• Calls that are unanswered are excluded from the calculation of this indicator.

16 Reporting against these indicators is mandatory for distributors who operate a call centre that is capable of

automatically recording some or all of the responsiveness indicators. Distributors who have other systems to handle customer calls may report on a voluntary basis those responsiveness indicators that they record.

Page 19: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 17

Worked example

Distributor A operates a single call centre with integrated IVR technology with a single 13 number for customers to call. During the reporting year the following call data was recorded:

Total calls to the 13 number = 467,450

Number of calls to the call centre = 265,328

Number of calls answered within 30 seconds = 221,846

Number of calls that were unanswered = 4,921

Sum of wait times for answered calls = 217,006 minutes

Calculation of indicators:

• CCD 34 = 265,328

• CCD 35 = 221,846

• CCD 36 = 100x221,846/265,328 = 83.6%

• CCD 37 = 60x217,006/(265,328-4,921) seconds = 50 seconds

• CCD 38 = 4,921

• CCD 39 = 100x4,921/265,328 = 1.9%

4.6.4 Definitions

Call centre means a dedicated facility that has the purpose of receiving and transmitting telephone calls in relation to customer service operations of the distributor, consisting of call centre staff (operators) and one or more information technology and communications systems that are designed to handle customer service calls and record call centre performance information.

Call that is unanswered means where the customer has terminated the call before it was answered by a call centre operator (in the case of IVR system calls that are terminated by the customer prior to selecting an option indicating they wish to speak with a call centre operator are not included).

Telephone calls to a call centre answered by a call centre operator within 30 seconds means the number of calls to call centre operators that were answered within 30 seconds (in the case of an IVR17 system the measurement period commences at the time that the customer selects an option indicating they wish to speak with a call centre operator).

Total number of telephone calls to a call centre means the total number of calls received by the call centre operators (in the case of an IVR system the measurement only includes the calls where the customer has selected an option indicating they wish to speak with a call centre operator).18 19

17 Interactive Voice Response – equipment that allows a call centre telephone system to detect voice and

keypad tone signals and then respond with pre-recorded or dynamically generated audio to further direct callers to the service they require.

18 This indicator excludes calls that do not require operator attention, including IVR calls where the customer does not select an option indicating they wish to speak with a call centre operator, and calls that were terminated before an option to speak with a call centre operator was selected.

19 Do not include calls to third parties, such as contractors acting on behalf of the distributor. However, do include calls received by a contractor that is providing all or part of the distributor’s customer service operations, i.e., an outsourced call centre.

Page 20: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 18

4.7 Network and asset information

4.7.1 Purpose

To report on the assets employed by the distributor to provide the distribution service, and the amount of energy supplied at the time of peak demand.

4.7.2 Reported Indicators

No. Indicator

NQR 42 Number of metered supply points by feeder category (CBD, urban, short rural and long rural), reported against the categories of residential and non-residential customers and sub-transmission, high voltage and low voltage

NQR 43 Number of unmetered supply points, by type of feeder (CBD, urban, long rural and short rural)

NQR 44 Energy delivered (GWh) by type of feeder (CBD, urban, long rural and short rural) reported against the categories of residential and non-residential customers and sub-transmission, high voltage and low voltage

NQR 45 Line lengths by type of feeder (CBD, urban, long rural and short rural) reported against the categories of underground and overhead line categories and sub-transmission, high voltage and low voltage

NQR 46 Number and total capacity of transformers, separated into sub-transmission and distribution

NQR 47 Total distribution losses (%)

NQR 48 Size of network service area (sq km)

NQR 49 Number of poles

NQR 50 Peak demand (MW)

4.7.3 Calculations

Distribution losses (%) is calculated as:

100 x (electricity supplied – electricity delivered) / electricity supplied

Peak demand is calculated as the maximum coincident demand on each network type at the terminal stations feeding the sub-transmission network, and at the zone substations feeding the high voltage network. Total peak demand is the maximum coincident demand in each of the network types. The total network peak demand is the maximum coincident demand of the distributor’s network.

Explanatory note: Peak demand should be stated in MW at the time of maximum MVA demand. A distributor’s network peak demand does not necessarily coincide with system maximum demand.

Page 21: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 19

4.7.4 Definitions

Feeders

CBD feeder means the area supplied with electricity by the Milligan Street Zone Substation, or Hay Street Zone Substation.20

Long rural feeder means a feeder that is not a CBD or urban feeder, with a total feeder route length greater than 200 km.

Short rural feeder means a feeder that is not a CBD or urban feeder, with a total feeder route length less than 200 km. Rural short feeders may include feeders in urban areas with low load densities.

Urban feeder means:

• a feeder, which is not a CBD feeder, with actual maximum demand greater than 0.3MVA/km over the reporting period; and

• the feeder is located in the areas of the State defined under “metropolitan area” in Part 1.5 of the Code of Conduct.

Explanatory note: Back-up feeders should be given the same classification as the normal supply feeder they are providing back up for.

Network and Lines

High voltage (HV) line means a line used to distribute electricity from a (zone) substation, generally operating at a nominal voltage between 1 kV and 33 kV.

Line length means the route length in kilometres of lines in service, including overhead lines, underground cables or a combination of the two. Line length does not include low voltage service connections.

Explanatory note: a double-circuit line counts as two lines, and each three-phase line, single-phase line or single-wire earth return (SWER) line counts as one line.

Low voltage (LV) line means a line that operates at a nominal voltage of 1 kV or below.

Network means distribution works that are used to convey electricity under a distribution licence.

Sub-transmission (ST) line means a line generally 22 kV or above, used to distribute electricity from a transmission connection point to one or more (zone) substations.

Total capacity of transformers means the total rated MVA capacity of the transformers installed in the distribution network.

General

Energy delivered means the electricity consumed by end-customers of the distribution network. This includes energy produced by embedded generators and consumed within the

20 See clause 3(1) of the NQ&R Code. These feeders are operated by the Electricity Networks Corporation

(trading as Western Power).

Page 22: Electricity Distribution Licence Performance Reporting Handbook · 2019-04-30 · Electricity Distribution Licence Performance Reporting Handbook 7 Distribution system has the same

Economic Regulation Authority

Electricity Distribution Licence Performance Reporting Handbook 20

distribution area through the distribution network, unread meters and un-metered consumption (including estimated theft).

Network service area means the area in square kilometres covered by the licensee’s distribution network. Areas within the network service area that are not provided with a service by the distributor (e.g. national parks, inset areas) are included in the service area.

Non-residential customer means a customer who is not a residential customer.

Residential customer means a customer who receives a residential tariff for the electricity that is supplied to them, or who is otherwise identified as consuming electricity for residential purposes.