    Driven and

    Bored PilesMADE BY :

    AHMED MOHAMED ZANATY 9103710

    AHMED ABDULLAH NEGM 9104441

    MOHAMED AHMED EL SAEID 9103644

    ABDELRAHMAN MOHAMED 9104286

    AHMED YOUSSEF 9100499

    DEPARTURE: COURSE:

    CONSTRUCTION & BUILDING FOUNDATION

    UNDER SUPERVISION OF:

    PROF. ADEL BELALTo view online:

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    2/39

    What is Deep foundation ?

    A deep foundation is a type of foundation distinguished fromshallow foundations by the depth they are embedded into theground. There are many reasons a geotechnical engineer wouldrecommend a deep foundation over a shallow foundation, but

    some of the common reasons are very large design loads, a poorsoil at shallow depth, or site constraints

    There are different terms used to describe different types of deepfoundations including the pile, the pier, drilled shafts, and caissons.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    3/39

    What are Piles ?

    Piles are generally driven into the ground in situ; other deepfoundations are typically put in place using excavation and drillingThe naming conventions may vary between engineering disciplineand firms. Deep foundations can be made out of timber, steel,reinforced concrete and pre-stressed concrete.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    4/39

    How piles are connected ?

    Foundations relying on driven piles often havegroups of piles connected by a pile cap (a largeconcrete block into which the heads of the pilesare embedded) to distribute loads which arelarger than one pile can bear.

    Pile caps and isolated piles are typicallyconnected with grade beams to tie thefoundation elements together; lighter structuralelements bear on the grade beams, while heavierelements bear directly on the pile cap.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    5/39

    Pile installation

    Pile installation is as important as design. There are two methods ofinstallation :

    a)Installation by Driving

    b)Installation by Boring

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    6/39

    Pile installation

    Before going through pile installation methods understand the following terminology.

    Driven pre-cast pile: The pile is casted in a yard brought to the site anddriven by some mechanism into the soil.

    Driven Cast-in-situ pile: A casing plugged at bottom is driven into the groundand then the pile is casted by removing or retaining the casing.

    Bored Pre-cast pile: A bore is made and the soil inside is removed and then a pilecasted in some yard is put into the bore.

    Bored Cast -in-situ pile: A bore is made the soil is removed and the pile is casted atsite in the bore.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    7/39

    Choosing Pile Type

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    8/39

    Advantage & Disadvantage of DrivenPiles

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    9/39

    Driven Pile installation

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    10/39

    Driven Pile installation

    All pile driving equipment, including the pile driving hammer,hammer cushion, helmet, pile cushion, and other appurtenancesto be furnished by the Contractor shall be approved in advanceby the Engineer before any driving can take place.

    To obtain this approval, the Contractor shall submit a description opile driving equipment to the Engineer before pile driving begin.The description must contain sufficient detail so that the proposeddriving system can be evaluated by the Engineer.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    11/39

    Hammer Types

    Drop hammer / Gravity hammer

    Single acting power driven hammer

    Double Acting Power Driven Hammer Diesel Power Driven Hammers

    Vibratory and Sonic Power DrivenHammers

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    12/39

    Drop hammer / Gravity hammer:This is the original piledriving hammer. It consists of a steel ram that is guided

    within a set of leads. The hammer is raised to a certainheight and allowed to drop on top of the pile, thusproducing the driving reaction.

    Hammer Types

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    13/39

    Hammer Types

    Single acting power driven hammer:Hammers of this type arebasically power gravity hammers. The difference between agravity hammer and a single acting power hammer is that the ram(striking part) is encased in a steel frame work and is raised bysteam or compressed air rather than by the crane load lines. Thefrequency of the blows is also considerably higher than a drophammer. The ram mass is usually greater than a drop hammer andthe vertical travel is usually less than that of a drop hammer. Anytype of power hammer is usually more efficient than a drophammer because there is less time between blows for the soil to seup around the pile.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    14/39

    Hammer Types

    Double Acting Power Driven Hammer:The ram is raisedby steam or compressed air, as in the case of the singleacting power hammer. When the ram approaches thetop of its stroke a valve is opened into a chamber atthe top of the cylinder allowing high pressure air orsteam into the cylinder forcing the ram downward.

    Some double acting hammers utilize a light ram,operating at a high frequency, to develop the energyblows comparable to those developed by heavier,slower acting hammers. The advantage of the lighterram hammer is that there is less time between blows forsoil to re-settle against the pile, thus increasing thedriving efficiency and decreasing the drive time.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    15/39

    Hammer Types

    Diesel Power Driven Hammers:They are simply a onecylinder diesel engine consisting of a steel cylindercontaining a ram and an anvil. The ram is raised initially byan outside power source (crane) and dropped. As the ramdrops, it activates a fuel pump, which injects fuel into a cupin the top of the anvil. The ram continues down blocking theexhaust ports and compressing the air in the combustionchamber. A ball on the end of the ram, mating closely withthe cup in the anvil, forces the fuel into the hot compressedair between the ram and the anvil. The fuel then explodesforcing the ram up and forcing the anvil, and in turn, thepile down.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    16/39

    Hammer Types

    Vibratory and Sonic Power Driven Hammers: These are themost recent developments in pile hammer technology.They are comparatively heavy, requiring handlingequipment of greater capacity than required for

    conventional pile hammers. The Vibratory Hammer vibratesthe pile at frequencies and amplitudes which tend to breakthe bond between the pile surface and the adjacent soils,thus delivering more of the developed energy to the tip ofthe pile.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    17/39

    Driven Pile installation

    1. Raising the piston (starting)

    2. Injection of diesel fuel andcompression

    3. Impact and atomization.4. Exhaust

    5. Scavenging

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    18/39

    Driven Pile installation

    1.Raising the piston (starting): For starting the diesel hammer, thepiston (ram) is raised by means of a mechanical tripping device and iautomatically released at a given height.

    2. Injection of diesel fuel and compression:As the piston falls throughthe cylinders, it activates a lever on the back of the fuel pump, whichinjects a measured amount of diesel fuel on to the top of the impactblock. Shortly after this, the exhaust ports are closed.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    19/39

    Driven Pile installation

    3. Impact and atomization: Compressing all the air /fuel between theexhaust ports and the top Of the impact block, the piston continuesfalling until it strikes the top of the impact block. The heat generated

    by the compression of air, in the presence of atomized fuel, causesthe explosion of the fuel, throwing the piston upward and forcing theimpact block downward against the pile.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    20/39

    Driven Pile installation

    4. Exhaust:While moving upwards, the piston will pass and open theexhaust ports. Exhaust gases will escape and the pressure in thecylinder will equalize.

    5. Scavenging:The piston continues its upward momentum, whichdraws in fresh air for the nextcycle, cools the cylinders, and releasesthe pump lever. The pump lever returns to its startingposition, so thatthe pump will again be charged with fuel. Gravity stops the upwardmotion of thepiston and it starts falling through the cylinders onceagain.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    21/39

    Driven Pile installation

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    22/39

    Driven Pile installation

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    23/39

    Design of driven pile in sandy soil

    Using static formula:

    Length of pile = 25 m , Diameter of pile = 50 cm , = 18 /, = 30

    Qult = q Nq + KHcPo tan . 2 R H

    q = 18 25 = 450 /

    = 30 + 40/2 = 35, Nq = 75

    Qb = .5

    7 5 4 5 0 4= 6627 P = 18 20 0.5 = 180 /

    QS = KHc Po tan . 2 R

    QS = Q1 + Q2

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    24/39

    Design of driven pile in sandy soil

    (Cont.)Design of driven pile in sandy soil

    Q2= 180 1.25 0.75 30 ( 0.5 15) = 2196

    QS1= 180 2 1.25 0.75 30 ( 0.5 10) = 732

    QS Total = 2196 + 732 = 2927 KN

    QU = 6627 + 2928 = 9555 KN

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    25/39

    Design of driven pile in clay soil

    Use static formula:

    Length of pile = 25m, Diameter of pile = 50cm, =18 , = 30 , c = 3.8 t/Ca =3t/

    Qb = Ab Cnc

    Qb = .5

    38 5.7 4 = 42.529KNQS= f = CaDL

    Qs=30 .5 25 = 1178

    QU=42.529+1178=1220.6KN

    Qall=1220.6 3 = 406.8

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    26/39

    BORED PILES

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    27/39

    Pile installation

    Pile installation is as important as design. There are two methods ofinstallation :

    a)Installation by Driving

    b)Installation by Boring

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    28/39

    Bored Piles

    Bored piles is another type of reinforced concrete pileswhich isused to support high building which has heavy vertical load. Bored

    pile is a cast-in-place concrete pile where the bored piles have tobe cast on construction site.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    29/39

    Bored Piles

    Normally bored piling has be to carried on those tallbuildings or massive industrial complexes, which requirefoundations which can bear the load of thousands oftons, most probably in unstable or difficult soilconditions. Bored piling is cast by using bored piling

    machine which has specially designed drilling tools,buckets and grabs, its used to remove the soil androck. Normally it can be drilling into 50metres depth ofsoil.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    30/39

    Advantage & Disadvantage of BoredPiles

    Advantage Disadvantage

    Absence of vibration will not disturb adjacentpiles or structures.

    Susceptible to "wasting" or "necking" in"squeezing" ground.

    Extremely high capacity caissons can beobtained by expanding the base of the shaft upto three times the shaft diameter, thus

    eliminating construction of caps over multiplepile groups.

    Concrete is not placed under ideal conditioand cannot be subsequently inspected.

    For many design situations bored pilesoffer higher capacities with potentially bettereconomics than driven piles.

    Water under artesian pressure may pipe upshaft washing out cement.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    31/39

    Bored Pile installation

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    32/39

    Bored Pile installation

    To install a pile you should drill a borehole of a specified diameterand depth. Next the borehole should be filled by fine-aggregatedconcrete and reinforced with a metal frame of a required cut. So,the bored piles are installed and concreted directly on a site. Thediameter varies up to 1500mm and depth - up to 10m or 30 m and

    more. To increase bearing capacity the piles should be installedwith a widening at the bottom of the borehole (a foot of pile).Mostly such types of bored piles are used in situations when thereare heavy loads to a foundation and the few compressible soils aredeep-seated.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    33/39

    Bored Pile installation

    The installation of bored piles is free of dynamic effects to soils andfoundations of existing buildings. This main advantage of boredpiles is more appreciable during a construction within the urbanzone. Moreover this type of foundations allows installing of a pile inany soil; even there are construction waste, remains from theprevious structures and boulder and cobble deposits.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    34/39

    Bored Pile installation

    Quality control is very important during installation of bored piles. Arigs are equipped with a special computer system to control a pile

    concreting process. The monitoring piles parameters are depth,pressure of concrete mix, concrete volume and shape of piles.

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    35/39

    Design of Bored Piles in sandy soil

    =1.8 t/m, = 25 , D = 50 cm , L = 18 m

    Q = 1.8 x 18 = 32.4 t/

    = 253= 22 = 20.27

    Bored piles: KH=0.7-1.5 , taken =1.1

    Concrete material = 0.75 , = 18.75

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    36/39

    Design of Bored Piles in sandy soil

    Qu= 32.4 20.27 0.25 + 1.1Tan 18.75 (2x0.25)

    18

    2 10 + 18 (8)

    =266.2 TON

    =

    .=

    .

    = 88.73 TON

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    37/39

    Design of Bored Piles in clay soil

    = 1.9t/m, C = 3.8 T/m, D= 50 cm , L=25m

    Medium soil C=2.5-5 taken =3t/m

    = 0 Nc=5.7

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    38/39

    Design of Bored Piles in clay soil

    Qu= 3.8 5.7 0.25 + 3(2x0.25) (25)

    Qu=122.06 Ton

    Qll=

    f.s=

    .

    =40.69 Ton

  • 8/13/2019 drivenpiles-130527182218-phpapp01

    39/39

    THANK YOU

    Made by :

    Ahmed Mohamed Zanaty 9103710

    2. Ahmed Abdullah Negm 9104441

    3. Mohamed Ahmed El Saeid 9103644

    4. Abdelrahman Mohamed 9104286

    5. Ahmed Youssef 9100499

    Departure:Construction

    CourseFoundation

    Under supervision oProf. Adel Be