Draft Summart Report 12/03/07
-
Upload
petersam67 -
Category
Technology
-
view
394 -
download
3
Transcript of Draft Summart Report 12/03/07
DRAFT
CLIENT
DRAFT SUMMARY REPORT
Prepared by
Mr. Sebestian Roberts (Team Leader)
Mr. Tim Pegg
Mr. Sam Billing
Mr. Nick Petousis
Mr. Iain Hughes
Mr. Danny Thomas
Mr. Carl Young
Mr. Kevin Yong
Directed by
Dr. Phil Purnell
DRAFT
TABLE OF CONTENT
1.0
INTRODUCTION......................................................................................................................1
1.1 Nirex.............................................................................................................................1
1.2 Radioactive Waste.......................................................................................................1
1.3 Nirex’s Phased Disposal Concept...............................................................................2
1.4 Multi-barrier Containment............................................................................................3
1.5 Introduction of PGRC...................................................................................................4
1.5.1 Receipt Facility...................................................................................................4
1.5.2 Inlet Cell.............................................................................................................5
1.5.3 Unshielded ILW Storage Vault...........................................................................5
2.0 PROJECT OBJECTIVES....................................................................................................6
2.1 Inspection.....................................................................................................................6
2.2 Reworking....................................................................................................................6
2.3 Unworkable Packages.................................................................................................6
2.4 General Considerations...............................................................................................6
3.0 CORROSION......................................................................................................................7
3.1 ENVIROMENTS OF EXPOSURE................................................................................7
3.2 STAINLESS STEEL.....................................................................................................7
3.3 FACTORS WHICH CAUSE CORROSION..................................................................7
3.4 CORROSION RESISTANCE.......................................................................................8
3.5 VUNERABLE AREAS..................................................................................................8
3.6 TREATMENT OF MINOR CORROSION.....................................................................8
4.0 WASTE PACKAGE MONITORING....................................................................................9
4.1 Potential Damage........................................................................................................9
4.1.1 Corrosion...........................................................................................................9
4.1.2 Swelling............................................................................................................10
4.1.3Dropping...........................................................................................................10
4.1.4 Cracking...........................................................................................................10
4.2 Monitoring in Vault.....................................................................................................10
4.2.1 ‘Parking Bay’....................................................................................................10
4.2.2 Position of ‘Dummy Packages’ & ‘Sensor Packages’......................................11
4.2.3 Electronic Sensors...........................................................................................12
4.2.4 Active RFID tags..............................................................................................13
4.2.5 Dummy Packages’ & ‘Sensor Packages’.........................................................14
4.2.6 Visual Inspection..............................................................................................14
5.0 INSPECTION CELL..........................................................................................................16
DRAFT
5.1 INSPECTION PROCESSES AND METHODS..........................................................16
5.2 PARAMETERS TO BE INSPECTED.........................................................................16
5.3 METHODS AND EQUIPMENT..................................................................................17
5.3.1 Visual Inspection..............................................................................................17
5.3.2 Direct Viewing..................................................................................................17
5.3.3 Indirect Viewing...............................................................................................18
5.3.4 Radiation..........................................................................................................19
5.3.5 Weight..............................................................................................................19
5.3.6 Dimensions......................................................................................................20
5.3.7 Heat Generation..............................................................................................21
5.3.8 Chloride Levels................................................................................................21
5.3.9 Advanced Methods of Testing.........................................................................21
5.4 COMPARISON BETWEEN THE VARIOUS METHODS...........................................22
5.5 LEVEL OF INSPECTION...........................................................................................22
5.5.1 SCHEME 1.......................................................................................................23
5.5.2 SCHEME 2.......................................................................................................23
5.6 COMPARISON BETWEEN THE INSPECTION SCHEMES.....................................24
6.0 INSPECTION CELL LAYOUT...........................................................................................25
7.0 OVERPACKING CELL………………………………………………………………………….26
7.1 Functional requirements of overpacking cell.............................................................26
7.2 Overpacking cell location...........................................................................................27
7.3 Overpacking, Repackaging and Reworking...............................................................30
7.4 Overpacking damaged packages..............................................................................31
7.5 Overpacking damaged waste package......................................................................32
7.5.1 Stage 1 of overpacking damaged waste package...........................................32
7.5.2 Stage 2 of overpacking damaged waste package...........................................32
7.5.3 Stage 3 of overpacking damaged waste package...........................................33
7.6 Waste package flow diagram.....................................................................................34
7.7 Grouting stage...........................................................................................................35
7.8 Lid manipulation.........................................................................................................35
7.9 Inspection of overpack waste package......................................................................36
7.10 Overpacking cell design layout................................................................................36
8.0 LOGISTICS.......................................................................................................................37
8.1 Emplacement.............................................................................................................37
8.2 Monitoring..................................................................................................................37
8.3 Package Transport.....................................................................................................38
8.4 Maintenance..............................................................................................................39
DRAFT
8.5 Transfer Tunnel..........................................................................................................39
8.6 Ventilation..................................................................................................................40
8.7 Safety features of cell designs...................................................................................41
9.0 RELIABILITY AND RISK ASSESSMENT.........................................................................42
9.1 General Package in vault...........................................................................................42
9.2 Corrosion...................................................................................................................42
9.2.1 Modelling of pit initiation..................................................................................42
9.2.2 Modelling of package failure with no inspection..............................................43
9.2.3 Probability of monitoring system failing...........................................................43
9.3 Mishandling................................................................................................................43
9.3.1 Emplacement Period.......................................................................................43
9.3.2 Monitoring Period.............................................................................................44
9.4 Inspection Cell...........................................................................................................44
9.4.1 Emplacement Period.......................................................................................44
9.4.2 Monitoring Period.............................................................................................44
9.5 Operational Risks.......................................................................................................44
9.5.1 Contaminants Release....................................................................................44
9.5.2 Shielding Malfunction.......................................................................................45
9.5.3 Fire...................................................................................................................45
9.6 Overpacking Cell........................................................................................................45
10.0 CONCLUSION................................................................................................................45
11.0 GLOSSARY....................................................................................................................46
DRAFTSUMMARY REPORT
357976 i
DRAFTSUMMARY REPORT
1 INTRODUCTION
1.1 Nirex
UK Nirex Ltd is a company jointly owned by Defra and the DTI that advises nuclear site
operators on the preparation of safety case submissions to the regulators for the
conditioning and packaging of radioactive waste.[1]
1.2 Radioactive Waste
Nirex had classified wastes into 3 main categories, which are Low Level Wastes (LLW),
Intermediate Level Wastes (ILW) and High Level Wastes (HLW).
LLW Radioactive wastes which releases radiation of not more than 4 GBq/
tonnes of alpha, or 12 GBq/ tonnes of beta/gamma activity.
ILW Radioactive wastes with radioactivity levels exceeding the upper
boundaries of LLW, but do not require heat generation to be taken into
account in the design of storage or disposal facility.
HLW Radioactive waste which generates heat as a result of radioactivity.
This factor needs to be taken into account in designing storage or
disposal facilities.
Table 1: Types of radioactive waste [1]
According to Nirex’s standard specification, ILW is mainly contained in 500L drums, 3m3
boxes, 3m3 drums and 4m3 boxes. The latter designed package incorporates radiation
shielding with thick reinforced concrete walls. This project deals with the three unshielded
ILW packages. Figures 1, 2, and 3 illustrate these waste packages.
Figure 1: 4 500L drums in a stillage [1]
357976 1
DRAFTSUMMARY REPORT
Figure 2: 3m3 box [1]
Figure 3: 3m3 drum [1]
1.3 Nirex’s Phased Disposal Concept
Nirex’s Phased Disposal Concept envisages the following phases.
357976 2
DRAFTSUMMARY REPORT
The latter step would constitute deep disposal of radioactive waste, which is intended to
provide long-term isolation. Each phase will be reversible, and sufficient time will be
available to build confidence at each stage before moving to the next. [1]
1.4 Multi-barrier Containment
Figure 4: Multi-barrier containment system [1]
The multi-barrier containment system is designed so that, after closure, it does not rely on
the actions of future generations to ensure safety. The multi-barrier containment system
is comprises engineered barriers and a natural barrier. [1]
357976 3
Immobilisation and packaging of waste
Interim surface storage
Transport to a repository
Backfilling of the repository
Monitoring of packages
Emplacement in vault
Sealing and closure of the repository
DRAFTSUMMARY REPORT
1.5 Introduction of PGRC
Figure 5: Concept drawings of the Phased Geological Repository Concept (PGRC) [1]
Phased Geological Repository Concept (PGRC) envisages emplacement of radioactive
wastes in a facility constructed at depth within suitable host geology. The concept is
assumed to be generic, rather than site specific. It is envisaged that the PGRC facility will
to be operated as a store initially, where waste would be monitored and readily
retrievable. The concept will undergo a 300 years monitoring period, where waste
packages will be monitored, reworked and overpacked if necessary. The decision of
backfilling, sealing and closure will be left to future generations. [1]
1.5.1 Receipt Facility
Repository receipt facilities would accept packages transported by road and rail. On
arrival, waste packages will be inspected, monitored and decontaminated if necessary.
[1]
357976 4
DRAFTSUMMARY REPORT
1.5.2 Inlet Cell
Figure 6: Concept drawings of the inlet cell [1]
The inlet cell has the function of removing packages from the Reusable Shielded
Transport Container (RSTC) and checking waste packages prior being transferred to the
storage vault. Empty transport containers will be monitored and decontaminated before
returning to the surface facility for reuse.
1.5.3 Unshielded ILW Storage Vault
Figure 7: Concept drawings of an unshielded ILW storage vault [1]
The storage vault will be shielded from radiation to provide safety for both employees and
the general public. The conditions within the storage vault will be monitored and
controlled, in order to prolong the life expectancy of the packages. Every activity within
the vault will be conducted remotely.
357976 5
DRAFTSUMMARY REPORT
2 PROJECT OBJECTIVES
The design brief received from Nirex was to create a concept for the Inspection and
Waste Repackaging Cells for the PGRC. Considering the aforementioned information
concerning the PGRC, and the details in the design brief, the following objectives were
drawn up.
2.1 Inspection
To formulate methods of inspection for the waste packages. The waste packages
themselves would be examined for structural integrity, corrosion, degradation of the
packaged wasteform and any change in the dimensions of the waste package.
2.2 Reworking
If a package were deemed faulty following inspection, it could be ‘reworked’. This would
be affecting slight repairs to the waste package, primarily polishing out pit corrosion and
covering with a protective coating.
2.3 Unworkable Packages
Solutions for damaged packages which are not workable were being devised. This is to
ensure packages are deemed safe to the public and could be managed by the PGRC.
2.4 General Considerations
Whilst working to provide solutions in these three areas, proven technology and simplicity
were to be used where possible. Health and safety of both the public and workers should
also be considered.
The design of the inspection cell and Overpacking cell should also be able to allow
packages to be inspected and overpacked in a satisfactory rate.
357976 6
DRAFTSUMMARY REPORT
3 CORROSION
Waste packages which will be used in the PGRC will be made out of stainless steel.
Stainless steels are iron alloys that have a minimum chromium content of 10.5% which
leads to the formation of the chromium-rich oxide on the surface. This provides the high
corrosion resistance and that is why it is named ‘stainless’ [2].
3.1 ENVIROMENTS OF EXPOSURE
The waste packages will be subjected to various environments from their manufacture to
their placement in the vaults. They will be subjected to atmospheric conditions during
their storage and they will experience alkaline environment during their manufacture and
over-packing stage. In addition, during storage, packages are expected to come in
contact with water coming from ground water flows. Therefore, the packages must be
highly resistant to atmospheric, aqueous and alkaline environments [2].
3.2 STAINLESS STEEL
The reason why stainless steel has such a high resistance to corrosion is because the
high chromium content creates a thin oxide film on exposure to air or water. This film acts
as a shield to the underlying material against further reaction with the surrounding
environment. When this film is damaged it reforms itself and therefore provides long term
protection. However, the stainless steel is vulnerable to localised corrosion when the film
breaks down in small areas. Localised corrosion usually takes the form of small pits (pit
corrosion) which penetrate perpendicularly into the metal or crevices between the mated
surfaces (crevice corrosion) [2].
3.3 FACTORS WHICH CAUSE CORROSION
The main factor which causes corrosion is the presence of aqueous chloride ions. These
ions tend to break the thin protection film and prevent it from reforming. The more
chloride ions are present the higher the risk of corrosion will be. The relationship between
the number of chloride ions and corrosion level follows an exponential relationship [3].
Another factor that causes corrosion is the, surface roughness. The more homogenous
the surface is the lower the active sites for pit initiation are. Therefore, the lower the risk
for corrosion will be [4].
Finally, sulphur tend to cause pitting corrosion. This is due to the fact that the chromium
concentration in the vicinity of the sulphate inclusions is reduced [5].
357976 7
DRAFTSUMMARY REPORT
3.4 CORROSION RESISTANCE
The type of stainless steel which will be mainly used for the container packages will be
304L and 316L. For these types of alloys there is a large amount of previously collected
data [6]. According to this data the lifetime of the packages will be as follow:
Table 2: Estimated lifetime of a package from previous data. [6]
3.5 VUNERABLE AREAS
3.6 TREATMENT OF MINOR CORROSION
357976 8
DRAFTSUMMARY REPORT
4 WASTE PACKAGE MONITORING
The purpose of monitoring waste packages in the vault is to provide a periodic
observations and measurements to determine changes in the physical condition of the
packages over time [7]. By monitoring packages in the vault, the condition of the vault
could also be predicted.
Monitoring of waste packages also had the advantage of increasing the efficiency of
waste package inspection, by identifying damaged packages before being transferred
into the inspection cell.
4.1 Potential Damage
Although the condition of the vault is being monitored and controlled, packages are still
prone to be damaged. The following are types of damages that were predicted to occur to
the packages stored in the vault.
4.1.1 Corrosion
Figure 8: A typical corrosion sensor used in gas pipes [8]
There are mainly two types of corrosion which are pit corrosion and stress corrosion.
Corrosion is difficult to be detected because the sensors only detect corrosion locally.
Pit corrosion is mainly caused when corrosive agents are being deposited in a pit surface.
Pit corrosion happens locally on the package’s surface, and corrodes the package
progressively.
Stress corrosion occurs when a material experienced both tension and corrosion attacks.
Stress corrosion could be detected by measuring strain instead.
357976 9
DRAFTSUMMARY REPORT
4.1.2 Swelling
Figure 9: A typical strain gauge mounted on the wall [9]
Swelling are mainly caused when the venting filter of the package are clogged. Building
up of gasses within the package could cause packages to swell. Swelling of packages will
be detected by a metallic strap around the package together with a strain gauge.
4.1.3 Dropping
Dropping of packages are assumed mainly due to mishandling of packages. Dropping of
packages could be detected by placing a load cell on the crane. An unpredictable
decrease in the load on the crane could indicate a drop from happening.
4.1.4 Cracking
Cracking could occur either by corrosive attack or mechanical damage. Cracking is
difficult to be detected as it occurs locally. Cracking is only feasible to be detected by 3D
mapping within the Inspection Cell.
4.2 Monitoring in Vault
Monitoring of packages is being conducted by remote electronic sensors mounted on
‘Dummy Packages’ and ‘Sensor Packages’. These packages will take measurements
periodically and signals will be transferred back to the inspection cell by active RFID tags.
357976 10
The strain gauge on the wall gives a rough estimation of the size of a strain gauge that could be adopted.
DRAFTSUMMARY REPORT
4.2.1 ‘Parking Bay’
‘Parking Bay’ is empty space in a storage vault. Its purpose is to allow extraction of
bottom packages without having to move packages on top of a stack to the end of the
vault.
Figure 10: A drawing of a ‘Parking Bay’ in a vault
4.2.2 Position of ‘Dummy Packages’ & ‘Sensor Packages’
Figure 11: A box in a box layout [10]
The arrangement for unshielded ILW packages within the vault will be 7 stillages across
and 7 stillages in a stack. Assume 7 stillages across by 7 stillages high by 7 stillages
along the vault to be named as a block.
357976 11
Distance = 3 stillages packages apartDistance = 7 stillages
packages apart
Position of ‘Dummy Packages’
DRAFTSUMMARY REPORT
‘Dummy Packages’ will be placed in all 8 corners of each cube, while ‘Sensor Packages’
will be placed at the centre of every face of each cube. Hence, a total of 16 ‘Dummy
Packages’ and 12 ‘Sensor Packages’ in each block.
357976 12
DRAFTSUMMARY REPORT
The following table summarises the statistics of packages in a storage vault.
Type of
Package
‘Real
Packages’
‘Sensor
Packages’
‘Dummy
Packages’
‘Parking
Bay’ (1
every 2
blocks)
Total Space
500L Drums 29464 276 304 336 30380
3m3
drums/boxes
6520 265 292 77 7154
By introducing ‘Dummy Packages’ and ‘Parking Bays’, the effective storage capacity of
the vault is only reduced by 2% for 500L drums and 5% for 3m3 packages. It is also found
that 2% of the 500L drums will be monitored directly and 9% of the 3m3 packages will be
monitored directly. It is arguably that the quality of the sampling methods is the same,
because the distances between ‘Dummy Packages’ and ‘Sensor Packages’ are the
same.
4.2.3 Electronic Sensors
Electronic sensors and active RFID tags require batteries to be replaced. It is assumed
that ‘Dummy Packages’ will have a battery life of 10 years, while ‘Sensor Packages’ will
have a battery life of 5 years.
357976 13
DRAFTSUMMARY REPORT
Figure 12: A typical ‘Sensor Package’
Electronic sensors which are attached in the ‘Sensor Packages’ include corrosion
sensors, strain gauge, humidity and thermometer. It should be noted that strain gauge will
not be equipped in ‘Dummy Packages’ because swelling is not likely to occur.
4.2.4 Active RFID tags
Figure 13: A typical active RFID tag [11]
An active RFID tag will be used to transmit signals to the receiver placed on the crane. By
performing and ‘RFID Sweep’, one could collect readings from ‘Dummy Packages’ and
‘Sensor Packages’ easily and quickly. [12]
Active RFID tag has the advantage of longer range and faster data transfer, compared to
passive RFID tag which only has a range of 3 to 4 feet.
357976 14
Corrosion Sensors
Strain Gauge on metallic strap
Humidity Sensors
Battery, active RFID tag and electronic components
DRAFTSUMMARY REPORT
4.2.5 ‘Dummy Packages’ & ‘Sensor Packages’
‘Dummy Packages’ are packages which contain inert materials. They are being
introduced for easy handling purposes and been used to obtain information of the
condition of a typical ‘Real Package’.
‘Sensor Packages’ are however ‘Real Packages’ which are equipped with electronic
sensors. These packages contain active wastes and hence require strain gauges to
measure swelling of packages.
4.2.6 Visual Inspection
Figure 14: A typical radiation resistant robotic crawler [13]
Visual inspection is only feasible to be carried out by remote CCTVs. Visual inspection
will be the main monitoring method for packages within the vault. It has the advantage of
being reliable, cheap, fast and provide and independent judgement from electronic
sensors.
Figure 15: Corrosion in welded regions [14]
In order to aid visual inspection of corrosion, welded metal coupons will be attached in
every stillages or 3m3 packages. Metal coupons are two metals of the same material
welded together and being attached to the packages. Since welded regions are most
susceptible to be corroded, by just viewing these coupons, one could justify if other
welded regions are corroded.
357976 15
DRAFTSUMMARY REPORT
The following illustrates the sequence of visual inspection to be carried out.
4.3 Waste Package Monitoring Sequence
357976 16
Filter (whether it’s corroded or clogged)
Corrosion in welded areas
Other visible areas
Check for significant deformation
Welded Coupon
RFID
Sweep
Extract + transfer to Inspection Cell
Problem package assessed with mobile CCTV
4 real packages randomly selected. These are taken to Inspection Cell
Real packages randomly selected. These are inspected by mobile CCTV.
All packages confirmed safe.
Problem package(s) identified
DRAFTSUMMARY REPORT
5 INSPECTION CELL
5.1 INSPECTION PROCESSES AND METHODS
5.2 PARAMETERS TO BE INSPECTED
The inspection of a container will consist of two parts.
Part 1: inspection for contamination and structural integrity of the package.
Part 2: inspection of degradation and condition of waste stream.
For both parts of inspection individual data should be saved for each package. This will
give information about the behaviour and degradation of the package. In addition, it will
help to identify packages which show unexpected and dangerous behaviour for more
frequent future inspection
The 1st part of inspection will primarily not include measurement of any parameters since
direct and indirect viewing of the package will be available. Contamination on the
package will be in form of corrosion which will probably occur in the corrosion susceptible
area. [See corrosion technical report]
Inspection for structural integrity will consist of check for swelling, cracks or deformation
of the package which could be caused by dropping or chemical reactions within the
package’s waste stream.
The 2nd part of inspection requires more indirect inspection methods and measurement of
various parameters will be necessary. The parameters that can be measured to indicate
degradation and condition of the waste stream are:
Radiation of the package
Weight
Dimensions
Heat generation
Chloride levels
For more specific information on the density change and degradation of the package
more advanced methods of testing should be provided. These methods of testing should
provide:
Image of the waste stream within the package.
Identification and quantification of the radionuclide within the waste stream.
Check on the fissile content of the waste packages.
357976 17
DRAFTSUMMARY REPORT
5.3 METHODS AND EQUIPMENT
This section presents and discusses various methods and equipment which can be used
to measure each of the parameters introduced in section 1.2.
5.3.1 Visual Inspection
Visual Inspection may be direct, that is, looking at the package through an oil filled
shielded window, or indirect, using cameras. It has been decided that this direct method,
and a further indirect technique will be used. The latter will use a through-wall Endoscope
with built in camera.
Please refer to the Technical Report ‘Visual Inspection and 3D Mapping’ for more details.
Furthermore, ‘Inspection Processes and Methods ’ considers all the methods of
inspection and discusses the preferred processes for an overall inspection routine.
Visual inspection is one of the inspection methods proposed for use in the Inspection
Cell. The pros and cons of the different methods are discussed below.
Visual inspection could be conducted using a variety of methods:
‘Direct Viewing’ - workers looking at packages through shielded windows
‘Indirect Viewing’ – crawler-cam – cameras mounted on robotic crawlers that
move within the ‘hot’ area
‘Indirect Viewing’ with fixed CCTV within the ‘hot’ area
‘Indirect Viewing’ with an through-wall Endoscope
‘Indirect Viewing’ with Master/slave Manipulator held CCTV
5.3.2 Direct Viewing
Workers would view a package through an oil filled shielded window of thickness
approximately 1.2m [15]. needs to be referenced !!!!!!!!!!! Direct Viewing is carried out
by humans so only the maintenance of the window would be required. This would include
cleaning, a monthly inspection of oil reservoir levels and annual light transmissibility
checks. It is felt that a strong point of direct viewing is that independent inspectors would
have the chance to physically see the package which would enhance public confidence in
the PGRC. However, this method would not provide a record with which future
inspections could be compared. Thus, the experience of the viewer would be a critical
factor in the accuracy of this method.
357976 18
DRAFTSUMMARY REPORT
5.3.3 Indirect Viewing
Four methods of indirect viewing are put forward. The two stationary techniques would
use either fixed CCTV cameras located in the ‘hot’ area, or an Endoscope with built in
camera that would be routed from the ‘cold’ to ‘hot’ side through the Inspection Cell wall.
The CCTV cameras are cheaper and can have built in lighting [16]. The more expensive
Endoscope would need external lighting but its internal mechanisms and camera are
always ‘cold’ side. This ensures ease of maintenance as ‘hot’ side equipment would
need to be maintained in the ‘hot’ area using the Master/Slave Manipulators, or, the
equipment would need decontaminating before being repaired/replaced in a ‘cold’
environment.
The two further options for indirect viewing are ‘Crawler-Cams’ and ‘Master/Slave
Manipulator held CCTV’. Crawler-Cams are cameras mounted on radio controlled robotic
crawlers that move around the ‘hot’ cell, sending images to a remote monitor.
Master/Slave Manipulators are mechanical arms that reach into the ‘hot’ area. Workers
on the ‘cold’ side will operate these MSMs. They are already used with great success at
the current waste retrieval facility at Nirex UK, although it is not known whether MSMs
have been used to hold cameras for inspecting a package before.
Through-wall Endoscopes are a proven technology and combined with their
straightforward maintenance make a sensible choice for the indirect Visual Inspection
method.
Figure 16: Schematic of Endoscope [17]
357976 19
DRAFTSUMMARY REPORT
5.3.4 Radiation
Measuring radiation is a relatively straight forward simple process. There is a wide variety
of radiation sensors available in the market. Some radiation sensors are designed and
manufactured to produce data corresponding to radioactive materials therefore a number
of different radiation sensors may be used to measure radiation according to package’s
content. [18]
5.3.5 Weight
The weight of package is also a simple process since it will only consist of a scale of high
accuracy. However, the accuracy level must be very high since it will measure the water
loss from the package surface. Assuming that an average 3m2 box will hold up to 100
grams of water then a reasonable accuracy level would be to measure to the nearest
gram (see Appendix calculations).
The weighting of the packages can either be carried out on the crane during
transportation or on the rump where the package will be place for visual inspection.
Figure 17: Position of the weight scale in the Inspection Cell.
357976 20
DRAFTSUMMARY REPORT
Figure 18: Crane with adjacent weight scale.
5.3.6 Dimensions
Dimensions of the packages can either be measured directly or with the use of more
advanced methods such as three dimensional mapping. High accuracy tapes can be
used to measure the height of the package and adjustable rings to measure the diameter.
This procedure can be carried out on the visual inspection ramp within twenty minutes but
will provide only a limited amount of accuracy.
Three dimensional mapping consist laser scanning which uses the time of flight to record
direct distance. This results in producing a high accuracy image of the scanned package
within a period of seconds. [19] This method can also be carried out on the visual
inspection ramp.
357976 21
DRAFTSUMMARY REPORT
Figure 19: Three Dimensional Mapping in the Inspection Cell.
5.3.7 Heat Generation
Heat generation can be measured in many ways. The most popular ways are using
computer imaging, calorimeters and temperature gauges. [20] Heat generation is an easy
to perform procedure and it will take only a few seconds.
5.3.8 Chloride Levels
Explain briefly the process.
5.3.9 Advanced Methods of Testing
Advanced methods of testing include the use of Real time Radiography, High resolution
segment gamma scanning and Passive Neutron Multiplicity Counting. Real Time
Radiography is an advanced method of X-Ray which can produce images of the waste
stream of the package. [21]High Resolution Segment Gamma will provide information on
the amount of active radionuclide within the waste stream and its elevation within the
package. In addition, it can detect density variations within the waste stream. Passive
Neutron Multiplicity Counting can measure the fissile content within the waste stream for
both encapsulated and un-capsulated waste. [3]
357976 22
DRAFTSUMMARY REPORT
5.4 COMPARISON BETWEEN THE VARIOUS METHODS
Radiation measurement is one of the main parameters that will indicate straight forward
the condition of the waste stream. It is therefore suggested to be included as an
inspection process since it is easy to perform and it is not time consuming.
Weighting of the packages is also an easy and cheap method to measure the water
content change but it will be fairly difficult to obtain accurate results. Frequent calibrations
of the weight scale will be required to obtain reliable results therefore it is decided to
place the weighting scale onto the crane. In this way access for calibration will be easy
and weighting will be included as an inspection process.
Measuring the dimensions of the package is considered as an essential process since it
will indicate whether both the risk for corrosion and will provide information about the
state of the content of the package. Direct measuring with the use of an adjustable ring
and high accuracy tapes will be cheap but will be neither easy to perform nor accurate. It
is therefore decided to use the three dimensional mapping method which provides
accuracy to the nearest millimetre [22].
Chloride level is an important parameter in identifying the risk for corrosion. However,
chloride levels are expected to be controlled and sensors will be provided inside the
vaults. Therefore, it is considered non essential to have a chloride test in the inspection
cell.
For the more advanced methods of testing it is suggested to use only the High Resolution
Segment Gamma. High Resolution Segment Gamma provides higher accuracy than the
Passive Neutron Multiplicity Counting and provides information both on the density
variation and the number of active radionuclide. Real Time Radiography and Passive
Neutron Multiplicity Counting are also useful techniques but the opportunity to over-pack
the defective packages limits the amount of tests that need to be performed
5.5 LEVEL OF INSPECTION
The inspection level of the packages can be carried out in different levels since some of
the packages will be more suspicious due to their content or history record. Two possible
schemes are considered.
357976 23
DRAFTSUMMARY REPORT
5.5.1 SCHEME 1
5.5.2 SCHEME 2
357976 24
Flow Chart of package for Scheme 1
Inspection Cell
Level 1:
Documentation validationWeightVisual Inspection
Level 2:
RadiationHeat generation3D MappingHigh ResolutionSegment Gamma
Level 3
Destructive test
Vault
Duration: 90 min
Duration: 65 min.
Flow chart for Scheme 2
Inspection Cell
Level 1:
Documentation validationWeightVisual Inspection
Level 2:
RadiationHeat generation3D Mapping
Level 3
High ResolutionSegment Gamma
Vault
Duration: 5 minDuration: 90 min
Duration: 60 min
DRAFTSUMMARY REPORT
5.6 COMPARISON BETWEEN THE INSPECTION SCHEMES
As it can be seen from the flow diagrams the two schemes will take the same time to
perform a full inspection for a package. However, for the main inspection part (Level 1
+Level 2) Scheme 1 requires a total of 135 minutes while Scheme 2 requires only 95
minutes. This is because for Scheme 2 no High Resolution Segment Gamma testing is
included which is one of the most time consuming procedures. In this way less
information and accuracy is achieved for the main inspection part but more packages can
be inspected in the same amount of time. This is preferable because accurate inspection
will be required only to some certain packages and the main aim of the inspection cell is
to investigate whether things go wrong rather than why
In addition, Scheme 2 is preferable because no destructive test is included. Destructive
test would be of use if detailed information about the package degradation was required.
The fact that there is an over packing cell, diminishes the need to understand deeply the
degradation of the packages
357976 25
DRAFTSUMMARY REPORT
6 INSPECTION CELL LAYOUT
7 [WORK IN PROGRESS]
357976 26
DRAFTSUMMARY REPORT
8 OVERPACKING CELL
8.1 Functional requirements of overpacking cell
The primary function of the overpacking cell is to overpack packages that are deemed
unsafe for handling, recovery for inspection, and storage within the PGRC. The damaged
waste packages will come directly from the inspection cell, which through rigorous
inspection techniques has determined the packages to require overpacked. The waste
packages will remain radioactive and hazardous for possibly hundreds and thousands of
years. It is therefore necessary that appropriate measures are put in place for long term
management of these waste packages [23].
There is the potential that the waste packages might not conform to the Nirex waste
package standards [24]. As a consequence small numbers may not adhere to these
specifications either through manufacturing errors, dropping of packages, corrosion, and
degradation of package waste form. If the problems are too extensive to be reworked and
rectified in the inspection cell they will be sent to the overpacking cell to be overpacked.
Multiple corrosion locations to critical parts of the package (Reference waste monitoring
technical report) could have made reworking of the package an unviable option.
Packages could have incurred damage that was deemed unsafe during handling resulting
in overpacking being the only course of action. The package, depending on the size and
nature of the drop, may have undergone deformation that is deemed unsafe to store.
Once the packages are deemed safe for transportation and storage they will be returned
to their respective vaults. Figure 20 show the movement of packages around PGRC.
Figure 20: Movement of damaged waste packages around the PGRC
357976 27
DRAFTSUMMARY REPORT
8.2 Overpacking cell location
Many locations were considered for the overpacking cell (see overpacking cell technical
report for more details). The locations included:
An overpacking cell in each vault
An overpacking cell in every other vault
An centrally located overpacking cell
An overpacking cell at the end of each block of vaults
These locations were scored in a decision matrix against a set of criteria. This set of
criteria comprised of;
Cost – this includes the operational, maintenance, and the initial capital costs
Logistics – this includes how quickly the damaged waste package can be
transferred to the overpacking cell and how quickly the possible congestion this
may cause
Risk – this includes the associated risk of handling the damaged waste package
through to the overpacking cell
Flexibility of design – This includes the ability to upgrade the overpacking cell in
the future and the possibility of adding additional cell if the situation requires
The afore mentioned criteria were marked against the following scale;
The decision matrix is as follows;
Locations Logistics Cost Risk Flexibility Total
Each vault 1 4 4 1 10
Every other vault 2 3 3 1 9
Central 4 2 1 4 11
End of transfer
tunnel
3 2 1 3 9
357976 28
DRAFTSUMMARY REPORT
It was decided that including an overpacking cell in the vaults would cause issues with
the lack of space and the costs involved. It was however decided that a central
overpacking cell will be the preferred location that will service all the overpacking needs
for the PGRC. Figure 21 shows a more detailed location of the overpacking cell drawn on
a schematic plan drawing of the PGRC [25].
357976 29
DRAFTSUMMARY REPORT
Figure 21: Plan view of the PGRC
357976 30
DRAFTSUMMARY REPORT
8.3 Overpacking, Repackaging and Reworking
As noted before, there is the potential that waste packages may need remedial action to
render them safe for handling, recovery for inspection, and storage within the PGRC.
There are certain factors that could attribute to the packages being deemed unsafe.
These factors are [26];
Packages not manufactured with the waste product specification
Inappropriate handling resulting in the package becoming damaged
Certain package components may degrade
Storage conditions may result in package corrosion
All of these deleterious factors could result in remedial action taking place to restore the
package to safe limits. The remedial action taken not only depends on the factors above
but additional factors. The benefits of the remediation process need to be weighed up
against the environmental impact caused, and the associated risks and costs. The three
ways considered as remedial actions are;
Reworking
Repackaging
Overpacking
The first level of action to restore the package to safe limits is by reworking the package.
This will be in the case of minor corrosion and aliments that are able to be rectified within
a 6 hour period in the inspection cell.
If reworking can not make the package safe then another course of action will need to be
undertaken to ensure the package integrity. Repackaging the waste package involves
taking the encapsulated waste out of its damaged package and placing it in new waste
package. This would be a difficult and messy process to undertake remotely and will still
require the damaged package to be disposed. This process is not deemed to be a
practical measure within the PGRC. This method will therefore not be used.
Overpacking of the damaged package is a process in which the damaged waste package
is placed inside a larger waste package and encapsulated in cement. This process is
357976 31
DRAFTSUMMARY REPORT
relatively simple and quick and leaves no mess behind. The damaged container is fully
immobilised in cement and the new package can be transported safely and stored back in
its respective vault. The only disadvantage with this process is the fact the packages will
be larger than they originally were and may be problematic to store within the vault.
8.4 Overpacking damaged packages
The Idea behind the overpacking cell is to encapsulate the damaged package in a larger
package to give sufficient protection and to allow the damaged package to be
manipulated. The package will be encapsulated in cementitious grout.
The packages will be overpacked according to their size;
The larger package will allow a 150mm envelope around the package to allow for a
suitable grout encapsulation layer. Due to this encapsulation layer the overpack
packages will be larger that the standard Nirex waste packages. The new package
dimensions are as follows;
Waste
containerExternal dimensions (m)
Overpack dimensions
(m)
3m3 Box1.72 x 1.72 plan x 1.225
high
2.02 x 2.02 plan x 1.525
high
3m3 Drum 1.72 dia x 1.225 high 2.02 dia x 1.525 high
8.5 Overpacking damaged waste package
8.5.1 Stage 1 of overpacking damaged waste package
The required package will then need to be retrieved from the storage room and be
positioned ready for the damaged package to be placed inside. In order for there to be a
357976 32
Damaged package
3m3 Box 3m3 Drum
Overpacked package
3m3 Box + 150mm Envelope 3m3 Drum + 150mm Envelope
Damaged package
5oo litres drum x 2
Overpacked package
3m3 Box
Figure 22: Overpacking the damaged packages
DRAFTSUMMARY REPORT
150mm grout cover to the bottom, a pre-cast grout unit will first need to be placed on the
bottom of the new package, with the old package then situated on top. This will then allow
sufficient cover to the bottom of the package to the required grout envelope of 150mm.
Figure 23 shows a cross section of the overpack waste package with the pre-cast grout
unit in place.
8.5.2 Stage 2 of overpacking damaged waste package
The next stage is for the damaged package to be placed inside the overpack. For the 500
litre package two damaged packages will be required for the overpack. With the
package(s) in place it is now possible for the encapsulation grout to be pumped into the
overpack waste package. The package will be vibrated as the grout is pumped into the
overpack waste package to ensure the grout is compacted. With the encapsulation
process complete the overpack waste package is left to set of a period of 24 hours.
Figure 24 illustrates the cross-section of the overpack waste package with grout
encapsulent.
357976 33
Figure 23: Cross-section of overpack waste package with pre-cast grout unit
Figure 24: Cross-section of overpack waste package with grout encapsulent
DRAFTSUMMARY REPORT
8.5.3 Stage 3 of overpacking damaged waste package
After the 24 hour period has elapsed the package is now in the position to be bolted up
and sent to be inspected. All the lids will be bolted rather than welded. Figure 25
illustrates the finished overpack process for a 3m3 box waste package.
The overpack waste package will comply with Nirex’s waste package specification and
will be manipulated in the same way as the other waste packages. The overpack waste
packages will be heavier than the original packages due to the additional weight caused
by the encapsulent material and the overpack container.
357976 34
Figure 25: Overpacking of 3m3 box package
DRAFTSUMMARY REPORT
8.6 Waste package flow diagram
The flow of the damaged waste packages through the overpacking cell is illustrated by
the flow diagram below.
357976 35
Package arrives from inspection cell & placed in buffer store
Sort which package is required for overpack
New package retrieved from storage and placed into position
Cementitious grout mixed and prepared ready to be pumped
New package filled with pre-cast units and damaged package placed on top
Grout pumped into the package and vibrated
Curing takes place to allow the concrete to set and develop early strength
The drum is then lidded and bolted shut
Package is inspected to ensure overpack is satisfactory
DRAFTSUMMARY REPORT
9
9.1 Grouting stage
The encapsulation material must be able to render the radioactive waste package as
passively safe and not affect the performance of other barriers to radionuclide
contamination. Cement based encapsulent materials are easily and quickly formed and
can be designed to resist the expected conditions of intermediate level waste (ILW) forms
[27]. The encapsulent material will be OPC (ordinary Portland cement) based and will
contain cement replacement materials (used to substitute some of the OPC).
To achieve acceptability of the quality of the grout, the following properties are required of
the grout [28];
Sufficient fluidity for up to 2.5 hours from mixing to enable infilling of package
Capable of being pumped and vibrated without segregation
Controlled heat generation during hydration to ensure product temperatures are
within acceptable limits
Setting to occur within 24 hours
9.2 Lid manipulation
There is a need for the packages to be sealed shut after the damaged packages have
been encapsulated in the overpack waste package. There are two possible way in which
this could be achieved;
Welding the lid shut
Bolting the lid shut
It has been decided that the lid will be bolted shut. Welding could present a fire hazard.
357976 36
New identification marks are applied to the package and 3-D mapping of package
Return to respective vault location via transfer tunnel
DRAFTSUMMARY REPORT
9.3 Inspection of overpack waste package
After the overpack waste package has been bolted shut it will come to the inspection
process. This will ensure that the package meets the generic waste package specification
and can be safely transported and stored within its respective vault.
New identification marks are applied to the package at this stage. This will act as the
unique identification mark that will document the history of this package.
In keeping with the process of 3-D mapping of all the packages within the PGRC the new
overpack waste package will undergo this process. This scan will act as the reference
scan of the package and further scans will be compared to the dimensions obtained here
(Waste monitoring technical report).
9.4 Overpacking cell design layout
Will include the final design layout with explanations.
357976 37
DRAFTSUMMARY REPORT
10 LOGISTICS
This document demonstrates the logistics of the integration of inspection cell and
overpacking cell into the PGRC.
Package traffic throughout the whole system is illustrated, and the logistics are broken
down into two key phases. Phase 1 is the emplacement period during which packages
are located in the vaults. Phase 2 is the monitoring period in which the packages are
monitored and cyclic inspection processes are performed.
10.1 Emplacement
Packages initially enter the repository through the inlet cell. Here the package is prepared
for storage in the vault. It is between here and the vault that the first stage of inspection is
performed. The package will be transferred into its designated vault via the transfer
tunnel, however before emplacement it will be transferred from the transfer tunnel to the
inspection cell assigned to that vault via the emplacement crane. Here the package will
be examined, and data of that particular package will be stored for future inspection
comparison (see …). The package will then be transferred into the vault for long term
storage and further monitoring.
Due to the process in which the vaults are filled (one at a time), each inspection cell must
have the capability to deal with 16 packages per day in the case of 4 stillages, or 13
packages per day in the case of 3 stillages and one larger container (it is assumed a
larger container will present greater handling/inspection difficulties) during the
emplacement phase.
During this emplacement phase the inspection cell is unlikely to be used to its full
capabilities (reworking etc). Furthermore the reworking element is likely only to be used in
the case of dropped packages.
10.2 Monitoring
During its time in storage the package will undergo further inspection. This will be carried
out due to scheduled inspection or requested inspection which can arise from vault
monitoring or external party demands. The package will be transferred to the inspection
cell via the emplacement crane. The package is then inspected for defects; if defects are
present the package will require either minor reworking (performed in the inspection cell)
357976 38
DRAFTSUMMARY REPORT
or transfer to the repacking cell. If the defects are easily reparable reworking will be
performed in the inspection cell, the package will then be re-inspected and transferred
back to the vault via the emplacement crane. If the defect is too severe for the rework
capabilities of the inspection cell, it will be transferred to the repacking cell via the
emplacement crane and the transfer tunnel. Once the package is repaired or over-packed
it is returned to the vault via the transfer tunnel and the emplacement crane.
The inspection selection will be a scheduled, cyclic process where the first into the vault
is first inspected. This however is open to review as it is suggested ‘higher threat’
containers should be inspected more frequently.
Figure 26: Flow of packages
10.3 Package Transport
The role of proven technology in the designs of the transport systems is highlighted, with
emphasis on using existing operational designs. Improvements to the transfer tunnel
design are demonstrated to cope with the increased package flow. Existing proven
technology designs will be used for all cranes in the repository. In the vault the overhead
crane has the facility to lift stillages, 3m3 boxes and 3m3 drums. Accurate crane
positioning is of high importance. This is achieved using high precision crane winding and
traversing carriage along with an optical encoding system.
357976 39
vault from inlet
vault from inspection
vault from repacking
repacking from inspection
inspection from vault
DRAFTSUMMARY REPORT
Figure 27: Overhead crane at Sellafield
10.4 Maintenance
Maintenance procedures and frequency for cells and transfer tunnel is considered with
reference to existing Nirex specifications. Maintenance of the following areas will be
required throughout the life of the repository;
- Vaults
- Transfer tunnel
- Inspection cell
- Overpacking cell
Nirex reference case states that vaults will need to be refurbished every 100 years. This
value is used as a rough guide for cell maintenance.
10.5 Transfer Tunnel
The transfer tunnel cannot be replaced without significant construction in all areas;
therefore it is important it is maintained frequently. The current concept design
incorporates two transfer tunnels.
Between transfer tunnels 1 and 2 there is a shield wall. The tunnels are also separately
shielded from the inlet cell and repacking cell. This allows an individual tunnel, or section
of tunnel to be maintained whilst other sections remain in use. Transfer tunnel will be
used most frequently as it is the primary transfer route for packages travelling to the
vaults from the inlet cell. In the case of maintenance of this tunnel, transfer tunnel 2,
357976 40
DRAFTSUMMARY REPORT
which is primarily used for transport of defected packages to the repacking cell, will be
used for inlet – vault transfer.
Figure 28: Transfer tunnel bogie at Sellafiend
10.6 Ventilation
Integration of the inspection cell and overpacking cell with this system is fairly complex.
Both cells have facilities involving the use of particulates which could contaminate waste
packages, causing defects. Therefore airflow from these cells should not meet other flows
before the return side, and in the case of the vaults, after the outlet. The inspection cell is
located at the front of each vault; this proves difficult to integrate from a view to optimising
ventilation, therefore it is proposed the inspection cells require a separate ventilation
outlet which bypasses the vault and rejoins the airflow at the end of the vault. This would
be very simple to engineer; ventilation pipes along the vault wall would suffice.
The overpacking cell is located adjacent to the inlet cell. This is very close to the
construction return therefore it is suggested the overpacking return should feed into the
construction return before leaving the repository.
In both cells pressure differentials would be maintained to ensure that any air transfer
was from the inactive to active areas (N/079)
357976 41
DRAFTSUMMARY REPORT
10.7 Safety features of cell designs
Safety features specific to the inspection cell / repacking cell design include;
- Transfer tunnel running through mid section of vault minimising aggressive
features and dropping distances.
- Ventilation systems with pressure differentials to prevent personnel exposure or
vault contamination.
- Use of proven technology in both cells.
1 N/074: Generic Repository Studies: The Nirex Phased Disposal Concept, July 2003
2 Nirex report N/110, “Corrosion Resistance of Stainless Steel Radioactive Waste Packages”, March 2004
3 Henshal, Modelling Pitting Degradation of Corrosion Resistant Alloys (1996)
4 Z. Szklarska-Smialowska, Pitting Corrosion of Metals, NACE, 1986
5 M.P. Ryan, D.E. Williams, R.J. Chater, B.M. Hutton and D.S. McPhail,”Why
Stainless Steel Corrodes”, Nature 415, 770, 2002
6 “Options for Monitoring During Phased Development of a Repository for Radioactive Waste”, Contractor Report to United Kingdom Nirex Limited, June 2002.www.nirex.co.uk Access date: 09/02/07
7 WPS/640: Guidance on monitoring waste packages during storage, September 2005
12 RFID Journal at www.rfidjournal.com/article/articleview/208#Anchor-33869, January 2007
15 What is this reference ???????????
16 Personal correspondence with Peter Gregory. IST Corp. (March 2007).
357976 42
DRAFTSUMMARY REPORT
11 RELIABILITY AND RISK ASSESSMENT
11.1 General Package in vault
Whilst in vault storage the package is subjected to certain risks which are detrimental to
package life. These risks include mishandling and corrosion (localised and uniform).
These risks are minimised by good operating procedures to minimise mechanical
damage, and a monitoring and inspection system to minimise corrosive defects. There is
the possibility of risks being raised if systematic monitoring failure occurs leading to
missed inspection, or if the monitoring system goes offline.
11.2 Corrosion
Package corrosion given no inspection is to be modelled. The mean time to package
failure is 200years [29] under poor conditions (high levels of airborne salts). This value will
18 “Radiation Detectors”, Electronics Manufactures Directoryhttp://www.electronics-manufacturers.com/Safety_and_surveillance_electronics/Radiation_detectors/
Access date: 15/03/07
19 “3D Laser Mapping Technology”, Fujikura Europe Ltdhttp://www.fujikura.co.uk/pdf/spec%20-%203D%20LASER%20MAPPING%20TECHNOLOGY_A4_APRIL06%20_2_.pdf
Access date: 15/03/07
20 “Options for Monitoring During Phased Development of a Repository for Radioactive Waste”, Contractor Report to United Kingdom Nirex Limited, June 2002.www.nirex.co.uk Access date: 09/02/07
21 “Real Time Radiography”, BNFLhttp://www.bilsolutions.co.uk/products_real_time_radiography.php
Access date: 12/02/07
22 “Optical Shape Measurement With Structured light”, Skothei Qystein, March 2006http://www.sintef.no/upload/IKT/OpticalMeasurementSystems/Fact%20sheets/Structured_Light_Factsheet.pdf
Access date: 12/02/07
23 Nirex technical note, Summary note for CoRWN on repackaging of waste, number: 484085, September 2005, pg 2
24 Nirex report N/104, Generic waste package specification: volume 1 – specification, June 2005
25 Nirex Report N/077 – Generic Repository Studies, Generic Repository Design – Volumes 1 & 2
26 Nirex technical note, Summary note for CoRWN on repackaging of waste, number: 484085, September 2005, pg 9
357976 43
DRAFTSUMMARY REPORT
be taken as a reference worst case scenario for modelling purposes. It should be noted
that under controlled environmental conditions as would be present in the repository,
perforation due to pitting would not occur for some 2500 years.
11.2.1 Modelling of pit initiation
Experimental research has shown that the instigation of corrosion pits is a stochastic
process. Shibata and Takeyamad were the first to show that the critical potential
necessary to induce pitting and the “induction” time elapsed before pits become
observable are both statistically distributed quantities.
For example, the graph below presents their data showing the distribution of induction
times for 72 ostensibly identical Type 304 stainless steel specimens subjected to identical
conditions. The data exhibit a wide distribution of induction times, suggesting that pit
initiation occurs stochastically [30].
Graph 1: Distribution of induction time
Therefore pit initiation cannot be accurately predicted as it is a random process; however
the distribution, over time, follows a predictable pattern.
27 Nirex report N/034, why a cementitious repository, 2001, cited in Nirex technical note, Summary note for CoRWN on repackaging of waste, number: 484085, September 2005, pg 6
28 Fairhall & Palmer, The encapsulation of Magnox swarf in cement in the United Kingdom, Cement & Concrete Research, Volume 22, Pg 293-298, 1992
30 Henshal Modelling Pitting Degradation of Corrosion Resistant Alloys (1996)
357976 44
DRAFTSUMMARY REPORT
11.2.2 Modelling of package failure with no inspection
- exponential distribution
- lognormal distribution
- Weibull distribution
Question to Phil: unsure which distribution to use
11.2.3 Probability of monitoring system failing
Unsure if modelling is possible, numerous variables – RFID, power, component, log
computer failure.
Any suggestions Phil??
11.3 Mishandling
General package mishandling frequency in the vault is estimated by Nirex [31];
Reference case - 6.8 dropped packages per year
11.3.1 Emplacement Period
With the integrated design of the inspection cell, the emplacement crane will make twice
as many transportations during the emplacement; hence the risk is effectively doubled.
13.6 dropped packages per year
11.3.2 Monitoring Period
During the monitoring and inspection period all vaults will be operational and movement
of packages will be at a rate of 11 per day (1 per day, 11 vaults). This gives a higher
probability of package damage due to increased risk.
19.2 dropped packages per year
The rate of mishandling is significantly increased due to inspection procedures. This rate,
however, still remains very low. Mechanical damage to packages will be sufficiently
covered by overpacking facilities.
11.4 Inspection Cell
Handling procedures within the inspection cell are comparable with that of the inlet cell.
The Nirex reference case for the inlet cell is;
Reference case - 1.5 dropped packages per year
31 N/079 Part 2: Generic Repository Studies, Generic Operational Safety Assessment Part 2: Fault and Hazard Schedule, July 2003
357976 45
DRAFTSUMMARY REPORT
11.4.1 Emplacement Period
During the emplacement period the inspection cell will handle 16 * 500 litre drums (4
units) per day in a worst case scenario;
6.2 dropped packages (drums) per year
11.4.2 Monitoring Period
During the monitoring period each inspection cell will handle 4 * 500 litre drums (1 unit)
per day in a worst case scenario;
16.9 dropped packages (drums) per year
Dropped packages in the inspection cell are not deemed to be as much of a problem as
in the vault due to reduced dropping distances. Package damage will be minimal under
normal circumstances and package retrieval will be conducted remotely using master
slave manipulators.
11.5 Operational Risks
11.5.1 Contaminants Release
Many of the processes in the inspection cell create particulates which are potentially
harmful to the packages within the vault. For a release of contaminants into the vault one
of the following would be necessary;
- damage to the ventilation system
- damage to the airlock door
To be concluded with probabilistic analysis.
11.5.2 Shielding Malfunction
The shielding between the inspection cell and personnel area is essential to operations.
Inadequate shielding could be as a result of shield damage due to processes within the
inspection cell or the personnel area.
To be concluded with probabilistic analysis.
11.5.3 Fire
The probability of a fire, hence thermal damage will be of higher probability than that of
the vault due to the type of operations, and close proximity of operations.
To be concluded with probabilistic analysis.
11.6 Overpacking Cell
The frequency of use for the overpacking cell is far lower than the inspection cell or the
vault, therefore rate of dropped packages in the overpacking cell is considered to be
357976 46
DRAFTSUMMARY REPORT
negligible. As is the case with the inspection cell dropped packages will present low risk
due to reduced lifting heights in comparison to the vault. Operational risks will be identical
to that of the inspection cell, with the addition of risk of grout system malfunction – to be
concluded with probabilistic analysis
12 CONCLUSION
It was concluded that the inspection cells and an overpacking cell is feasible to be integrated with the existing PGRC design. The inspection cells and Overpacking cell also proved to operate in an adequate capacity where unshielded ILW waste packages are confident to be safe.
Waste package monitoring in the vault is also feasible to be conducted, and is able to provide a satisfactory sampling result, with the usage of electronic equipments mounted on ‘Dummy Packages’ and ‘Sensor Packages’.
Visual inspection is the prime inspection method, and is being used in monitoring of packages, inspecting packages and also during Overpacking processes.
Overpacking damaged packages is concluded to be easier and more robust compared to repackaging packages.
Health and safety of both workers and the public were also ensured to be safe, by providing adequate shielding and remote handling of packages.
357976 47
DRAFTSUMMARY REPORT
GLOSSARY
500L drum Unshielded cylindrical waste package which has a volume of 500L.
Normally contains ILW.
3m3 drum Unshielded cylindrical waste package which has a volume of 3m3.
Normally contains immobilised radioactive ILW sludge.
3m3 box Unshielded waste package which has a volume of 3m3. Normally contains
solid radioactive ILW waste.
3D Mapping A Non Destructive Testing method which emits waves and receives the
reflected waves. Such method could detect surface cracks and dimensions
of an object
Backfilling Filling the PGRC with concrete. This is envisaged to occur at the end
of the 300 year monitoring period.
Concrete A cementitious based composite which consists of cement, water, coarse
aggregate and fine aggregate.
Cold An environment that contains levels of radiation that are suitable for
humans to work in.
Container An empty stainless steel package which has no grout or any waste forms
in it.
Decontamination The complete or partial removal of contamination by a deliberate
physical, chemical or biological process.
357976 48
DRAFTSUMMARY REPORT
Direct Workers visually inspecting a package with the naked eye. Primarily
Viewing through an oil filled shielded window which provides protection from
radiation.
DPI Dye Penetrant Inspection method is a Non Destructive Testing method. By
allowing dye to seep into cracks, and cleaning the surface, one could
identify the presence of a crack easily.
Encapsulation Immobilisation of solid waste by mixing it with a matrix material
within a container in order to produce a more stable waste form.
GPR Ground Penetrating Radar is a Non Destructive Testing method. By
transmitting radio wave and receiving it, one could determine the
attenuation of concrete. It is being used to monitor the curing of concrete
structures.
Grab Three armed lifting crane to lift/move a 500L drum.
Grout A cementitious based composite used to immobilise waste. It mainly
consists of cement, water and fine aggregate. This will be used in the
Overpacking procedure.
Half-life The time required for half the number of nuclei of a specific radionuclide to
undergo radioactive decay.
Hot An environment that contains levels of radiation that are too high for
humans to work in.
Harwell Current (February 2007) home of Nirex, UK where ILW stored just below
surface’ is being removed, inspected, and stored. This waste will be
transferred to the PGRC when built.
357976 49
DRAFTSUMMARY REPORT
Indirect Visual inspection of a package using indirect means such as cameras.
Viewing
ILW Intermediate Level Waste; wastes with radioactivity levels exceeding the
upper boundaries for Low Level Waste but which do not require heating to
be taken into account in the design of storage or disposal.
Immobilisation Conversion of waste into a less mobile or non-mobile form by, for
example grouting or encapsulating.
Magnox Gas cooled fission reactor using un-enriched uranium as fuel, with
magnesium alloy as cladding, the reactor type used in the UK’s first
generation nuclear power plants.
Master/Slave Tools currently used to inspect and rework waste drums that are being
Manipulator extracted from ‘just below surface’ storage at Harwell.
Nirex UK Nirex Ltd. A company jointly owned by DEFRA and the DTI that
advises nuclear site operators on the preparation of safety case
submissions to the regulator for the conditioning and packaging of
radioactive waste.
Oil filled Allows direct viewing into hot areas of the Inspection and
shielded Overpacking Cells whilst providing protection from the dangerously
window high levels of radiation within the cells.
Overpack- A process which encapsulates damaged packages in a larger package.
357976 50
DRAFTSUMMARY REPORT
PGRC Phased Geological Repository Concept is the concept facility which will
manage radioactive waste in the long term, which includes storage,
monitoring and backfilling in a phased geological disposal method.
Radionuclide A nucleus of an atom that possesses properties of spontaneous
disintegration. Nuclei are distinguished by their mass and atomic number.
Reworking Minor repair work on damaged packages and to prevent further minimise
further degradation from occurring.
Sievert (Sv) The SI unit of radiation dose.
Stillage A container for holding four 500L drums. The drums are only extracted
from a stillage when being individually inspected in the Inspection Cell or
overpacked in the Overpacking Cell.
Storage Vault A facility within the PGRC which is used to store the waste packages.
Transfer Tunnel The tunnel which connects all inspection cells together and with the
overpacking cell. A rack and pinion system will be adopted.
Twist Lock A crane locks into this feature to move/lift a package. A T-Lock is
(T-Lock) used on a 3m3 box, 3m3 drum and stillage.
357976 51
DRAFTSUMMARY REPORT
8 Images from National Energy Technology Laboratory, U.S.A. http://www.netl.doe.gov/publications/press/2003/tl_conformablearray.html, 29th Oct 2003
9 Photographs from Duncan Heron from Duke University , www.env.duke.edu/eos/geo41/mmo.htm, April 1984
10 Images from Donald Bren School of Information and Computer Sciences http://www.ics.uci.edu/~eppstein/junkyard/box-in-box.gif
11 Images from Fujitsu http://www.fujitsu.com/global/news/pr/archives/month/2004/20040927-01.html , September 2004
13 Images from Inuktun, www.inuktun.com, January 2007
14 Images from Corrosion Technology Testbed, Kennedy Space Centre http://corrosion.ksc.nasa.gov/filicor.htm, January 2007
17 IST Corp. (unknown) ONLINE “Radiation Tolerant Thru-Wall/Roof Viewing
System”. [Online]. Last viewed 2007 March 11. Available:
http://www.istcorp.com/documents/ThruWall.pdf
29 N/094, Nirex Document
357976 52