Dose Rate Reduction Methods at Shimane Nuclear Power Station Tadashi Kanaoka1, Hiroyasu Kajitani1,...
-
Upload
alyson-cannon -
Category
Documents
-
view
218 -
download
0
Transcript of Dose Rate Reduction Methods at Shimane Nuclear Power Station Tadashi Kanaoka1, Hiroyasu Kajitani1,...
Dose Rate Reduction Methods at Shimane Nuclear Power
Station
Tadashi Kanaoka1, Hiroyasu Kajitani1, Tsuneo Sato1, and Naoshi Usui2
1The Chugoku Electric Power Company, INC2Hitachi-GE Nuclear Energy, Ltd
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 2
0.The location of Shimane NPS and Head office Shimane NPS
Head offie
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 3
1.Introduction
Shimane Nuclear Power Station Unit 1 continues operating smoothly since commercial operation started in 1974.
An increasing trend of the dose rate has been observed since the hydrogen injection was applied at 21st operating cycle (1998) and the dose reduction became the urgent problem.
unit1
unit2
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 4
2(1).Radiation exposure of the outage
0.92 0.90
1.58
2.39
3.00
0.75
1.24
0.0
1.0
2.0
3.0
4.0
21 22 23 24 25 26 27
Number of outage
To
tal
rad
iati
on
ex
po
sure
of
ou
tag
e w
ork
s (p
erso
n・S
v)
Figure 1 Radiation exposure at Shimane Nuclear Power Station Unit 1 after hydrogen injection
Highest level among the total radiation exposure of the outage works in recent Japanese BWR plants.
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 5
2(2).The dose rate of the PLR piping
Figure 2 PLR dose rate trend at Unit 1
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
22-1
22-2 23 24 25 26
27-1
27-2 28
Number of outage
PL
R p
ipin
g do
se r
ate
(mS
v/h)
.
HWC
Before chemicaldecon.
After chemicaldecon.
?
Atmospheric dose rate in the pressure containment vessel are increasing since the hydrogen injection start
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 6
3.Dose rate reduction committee
3WG were settled under the committee.Maintenance staff and headquarter persons were added to the committee .
Superintendent (Station)
Dose rate reduction committeeChief examiner:Deputy
SuperintendentManagers of each section of
stationManagers of headquarter
Chemistry control WG Equipment management WG Radiation control WG
Headquarter staff
General Manager(Nuclear dept.)
ReportReport
Technical support Hitachi-GE Nuclear Energy
Figure 3 Structure of dose rate reduction committee
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 7
4.Examination items of dose rate reduction committeeShort term target is to lessen the dose rate of 28th outage at Unit 1. Middle and long term items aim for permanent dose rate reduction.
ItemChemistry control
WGEquipment
management WGRadiation control WG
Objectives
Dose rate reduction in PCV
Improvement of work methods and work environment
Improvement of radiation control
Matters
NWC pre-oxidation operation,CF bypass operation,Hi-F Coat, etc
Enlargement of chemical decontamination area ,etc
Piping dose rate prediction method,Temporary shielding,Survey of good practice, etcExtension to middle
and long term
Figure 4 Examination items at dose rate reduction committee
Middle and long
term matters
Zinc injection,Improvement of water chemistry control, etc
Adjustment of execution timing of inspection to reduce dose rateChemical decontamination to Valve and PLR-pump impeller , etc
Establishment of piping dose rate prediction method Improvement of mounting method of temporary shielding ,etc
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 8
5(1).Applied countermeasures until 28th outage
Hi-F Coat was applied after chemical decontamination at the 27th outage. NWC pre-oxidation operation of 90 days was conducted at the beginning
of the 28th operating cycle to form a fine oxide structure under NWC conditions.
Pump
CoolerIon exchange column
Catalyst column
Chemical injection system
Filter
Surge tank( with
heater)
Pump
Target( PLR piping etc.)
Figure 5 Outline of Hi-F Coat treatment equipments
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 9
5(2).Results of countermeasures(1) dose rate
Figure 6-1 PLR dose rate trend at Unit 1
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
22-1
22-2 23 24 25 26
27-1
27-2 28
Number of outage
PLR
pip
ing
dose
rat
e (m
Sv/h
)
HWC
The PLR dose rate has decreased to the same level before beginning of HWC.
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 10
5(2).Results of countermeasures(2) dose rate
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
22nd Afterdecon.
23rd 27th Afterdecon.
28th
Number of outage
Dos
e ra
te o
f PL
R
(mSv
/h)
Higher dose rateby rebound
Lower dose rateby countermeasuresto suppress rebound
Figure 6-2 Dose rate change of PLR piping after the 27th outage
Dose rate of PLR piping was about 0.5 mSv/h at the 28th outage at Unit 1 and became much lower than that at the 27th outage
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 11
5(2).Results of countermeasures(3) total radiation exposure
1710
0
500
1,000
1,500
2,0005/
24 6/7
6/21 7/5
7/20 8/2
8/16
8/30
9/13
9/27
End ・ ・ ・
End
Tot
al r
adia
tion
expo
sure
(per
son・m
Sv) Outage work(Prediction)
Outage work(Result)
Reduced to 70 %
Outage shorteningof about 40 days
Figure 7 Trend of total radiation exposure during the 28th outage (Outage works)
Total radiation exposure could be suppressed to about 70% of the planned value. Term of the outage could be cut for about 40 days compared to the original plan
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 12
6.Future activities(1) On-line monitor
Experimental equipments to gather basic data such as energy distribution of gamma ray and atmospheric dose rate in the PCV.
Figure 8 Appearance of experimental equipments
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 13
6.Future activities(2) Zinc injection
Zinc injection is a permanent countermeasure to reduce dose rate to meet the company need to continue hydrogen injection.
DZO
FW pump
FW piping
Figure 9 Image of zinc injection system
Copyright© The Chugoku Electric Power Co.,Inc. All rights reserved. 14
7.Conclusion
■We have decreased the dose to the same level before beginning of HWC.
■We will evaluate the contribution and durability of Hi-F Coat etc..
■We will research the Zinc injection etc. as further countermeasures.