Dissertation F M Simba
-
Upload
fungai-martin-simba -
Category
Engineering
-
view
117 -
download
11
Transcript of Dissertation F M Simba
i
AN ANALYSIS OF NEC 3 CONTRACT AS A COST
CONTROL MEASURE ON BUILDING PROJECTS: A
CASE OF PRIVATE SECTOR CONSTRUCTION
INDUSTRY IN ZIMBABWE
BY
FUNGAI MARTIN SIMBA
N01415751L
Supervised by Mr A. Muza
A Dissertation submitted to National University of Science and Technology
in partial fulfillment of the requirements of
Master of Science in Construction Project Management
Department of Quantity Surveying
Faculty of the Built Environment
August 2016
ii
ABSTRACT
The construction industry had been characterized by adversarial relationships between clients
and contractors, and this was partly attributed to risk apportionment in the traditional forms
contracts (Chan, 2006). That relationship resulted in contractors seeking to cushion themselves
from excessive risk by claiming more and pricing exorbitantly. NEC 3 contract was introduced
in the early 90’s in the UK in response to some of those problems. The NEC 3 contract presented
peculiar improved project management principles (Gould, 2007). This research sought to analyse
NEC 3 as a cost control measure and its suitability on the construction industry in Zimbabwe,
particularly in the private sector. The research design was mainly qualitative in nature because
the research sought to obtain underlying information and attitudes. Snow balling technique as a
subset of purposive sampling was used to reach out for information by way of referrals because
the NEC 3 contract was not very popular in Zimbabwe (Redmond. 2009). Literature on related
studies, records and publications were used to collect the secondary data. Questionnaires and
interview guides were used to collect the primary data. The response rate from the questionnaires
was 72% while on the interviews all the respondents participated. The results showed that the
inclusion of the programme of works in the contract and the early warning system on risk
management of costs were particularly highly commended as noble cost control measures. The
time-bar concept on compensation events and target costing were generally accepted as cost
saving mechanisms, but were considered relatively new concepts that needed education and
awareness. Partnering/ collaboration approach as a means to minimising adversity between
parties was considered as a challenge to establish in Zimbabwe due to a depressed economy
where late or non-payments from funders had become commonplace, let alone the rampant
defaulting contractors. However, the role of Project Manager in ‘shouldering’ some of the
responsibilities could go a long way in improving relations and subsequently saving costs.
Further research could explore the time management aspect of the NEC 3 contract on the
Zimbabwean construction industry.
iii
ACKNOWLEDGEMENTS
I would like to acknowledge the supervisory role that Mr A.Muza provided in the entire research.
His wide knowledge on contracts management was very useful. I am also indebted to my
lecturer, Ms Mangore for her guidance on the research methods class. Much appreciation is
extended to my wife, Tapiwa Simba, who gave not only moral support but her academic prowess
on research writing. Furthermore, I am thankful to my brother Farai Simba, mums and friends for
their consistent support. I also acknowledge God’s hand in everything.
iv
Table of Contents
ABSTRACT .................................................................................................................................................. ii
ACKNOWLEDGEMENTS ......................................................................................................................... iii
LIST OF TABLES ....................................................................................................................................... vi
LIST OF FIGURES .................................................................................................................................... vii
LIST OF ACRONYMS ............................................................................................................................. viii
DECLARATION ......................................................................................................................................... ix
CHAPTER 1 ................................................................................................................................................. 1
Introduction ............................................................................................................................................... 1
1.0 Background ............................................................................................................................... 1
1.1 Problem Statement .................................................................................................................... 3
1.2 Main Objective ................................................................................................................................ 4
1.3 Main Research Question ........................................................................................................... 4
1.4 Justification of Research ........................................................................................................... 5
1.5 Scope of Research ..................................................................................................................... 5
CHAPTER 2 ................................................................................................................................................. 7
Literature Review ...................................................................................................................................... 7
2.1 Introduction ............................................................................................................................... 7
2.1.1 Standard forms of contracts ..................................................................................................... 7
2.2 History of NEC 3 contract ........................................................................................................ 7
2.3 NEC 3 contract overview .......................................................................................................... 7
2. 4 Suite of NEC 3 documents ........................................................................................................ 9
2.5 Procurement routes ................................................................................................................. 10
2.6 Criteria used in selecting standard forms of contracts ............................................................ 12
2.7 Discussion on the studies and recommendations of NEC 3 .................................................... 14
2.8 Legal framework of Procurement in Zimbabwe on construction ........................................... 16
2.9 Critical analysis of NEC 3 contract a cost control measure .................................................... 17
2.10 Extent of use of NEC 3 Contract in Zimbabwe ...................................................................... 21
2.11 Conclusion .............................................................................................................................. 21
CHAPTER 3 ............................................................................................................................................... 22
Research Methodology ........................................................................................................................... 22
3.0 Research methodology / strategy ............................................................................................ 22
v
3.1 Description of study area ........................................................................................................ 22
3.2 Target population .................................................................................................................... 22
3.3 Sampling Techniques .............................................................................................................. 23
3.4 Data Collection techniques ..................................................................................................... 23
3.5 Secondary Data ....................................................................................................................... 25
3.6 Results presentation ................................................................................................................ 26
3.7 Data analysis ........................................................................................................................... 26
3.6 Ethical Considerations ............................................................................................................ 26
3.7 Validity of the data .................................................................................................................. 27
CHAPTER 4 ............................................................................................................................................... 28
Results, Analysis and Discussions .......................................................................................................... 28
4.0 Introduction ............................................................................................................................. 28
4.1 Results from Section 1 of the questionnaire ........................................................................... 28
4.2 Results from Section 2 of questionnaire ................................................................................. 30
4.3 Results from Section 3 of the questionnaire ........................................................................... 31
Table 4.4.2 shows the average responses deduced for each cost control measure as follows: ........... 38
4.5 Results from the Interview guide ............................................................................................ 39
4.6 Method of analysis on the interviews...................................................................................... 40
4.6.2 Analysis from the ‘familiarity’ category ............................................................................. 41
4.6.3 Analysis from the ‘economic environment’ category ......................................................... 42
4.7 Discussions ............................................................................................................................. 43
CHAPTER 5 ............................................................................................................................................... 46
Conclusions and Recommendations ....................................................................................................... 46
5.0 Introduction ............................................................................................................................. 46
5.1 Conclusions on the objectives of the study ............................................................................. 46
5.2 Recommendations ................................................................................................................... 48
5.3 Recommendation for future studies ........................................................................................ 49
REFERENCES ........................................................................................................................................... 50
APPENDIX 1 .............................................................................................................................................. 54
QUESTIONNAIRE ................................................................................................................................ 54
APPENDIX 2 .............................................................................................................................................. 58
INTERVIEW GUIDE ............................................................................................................................. 58
vi
LIST OF TABLES
Table 3.4.2: Target Population of Consultants, Clients and Contractors on Questionnaires 24
Table 3.4.3: Classification of the Sample 24
Table 3.4.4: Target population of Consultants, Clients and Contractors on Interview Guide25
Table 3.4.5: Classification of the sample 25
Table 4.4.1: Summary of respondents’ perspective on the NEC 3 contract 37
Table 4.4.2: Average response on cost control measures 38
Table 4.4.3: Average responses on all cost control measures 38
Table 4.6.1.1: Categories / Indexing of results from interviews 41
vii
LIST OF FIGURES
Fig 4.1.1: Respondents Experience – Questionnaires 29
Fig 4.1.2: Professional Respondents 29
Fi g 4.2.1: Procurement Methods 30
Fig 4.2.2: Extent of use of standard forms of contract 31
Fig 4.3.1: Analysis of ‘Time-barring’ for Compensation Events clause 32
Fig 4.3.2: Programme of works to be part of contract 33
Fig 4.3.3: Removal of Provisional Sums 34
Fig 4.3.4: Gain/ Pain share financial gain/ loss 35
Fig 4.3.5: The Project Manager for supervision 35
Fig 4.3.6: Early warning system on risk management 36
Fig 4.5.1: Years of experience for interview respondents 39
Fig 4.5.2: Professionals interviewed 40
viii
LIST OF ACRONYMS
CECCZ - CIVIL ENGINEERING CONDITIONS OF CONTRACT IN ZIMBABWE
CIFOZ - CONSTRUCTION INDUSTRY FEDERATION OF ZIMBABWE
ECC – ENGINEERING AND CONSTRUCTION CONTRACT
FIDIC - FEDERATION INTERNATIONALE DES INGENIEURS-CONSEILS
IAZ - INSTITUTE OF ARCHITECTS ZIMBABWE
ICE - INSTITUTION OF CIVIL ENGINEERS
JCT 80 SBC - JOINT CONTRACTS TRIBUNAL 1980 STANDARD BUILDING CONTRACT
JV – JOINT VENTURE
PM- PROJECT MANAGER
NEC - THE NEW ENGINEERING CONTRACT
ZBCA – ZIMBABWE BUILDING CONTRACTORS ASSOCIATION
ZGCC4 - ZIMBABWE GENERAL CONDITIONS OF CONTRACTS
ZIE - ZIMBABWE INSTITUTE OF ENGINEERS
ZIQS – ZIMBABWE INSTITUTE OF QUANTITY SURVEYORS
ix
DECLARATION
This work has not been previously published to my knowledge or written by another person, and all
literature obtained from other sources was acknowledged.
…………………………………………………. ………………………………………
Signature Date
1
CHAPTER 1
Introduction
1.0 Background
The construction industry has often been viewed as antagonistic, full of disputes and
confrontational in nature (Dickson, 2013). This was partly blamed on the old standard forms of
contracts that were viewed as adversarial between clients and contractors (Chan, 2006).
Adversity primarily stemmed from the risk allocation between two contracting parties
(Frederiksen, 2002). Most traditional contracts had the contractor bearing most of the risk in a
project and that imbalance on risk allocation resulted in most contractors developing a negative
attitude towards costs and claims (Chan, 2006).The introduction of The National Engineering
Council (NEC 3) as a standard form of contract to the construction industry was in response to
the adversity among contracting parties (Dickson, 2013).
Further to addressing adversity, the NEC 3 contract had also been applauded for its project
management principles that Kings (2005) described as effective in achieving a better project
outcome. Gould (2007) stated that NEC 3 contract had features such as early warning system, a
pro-active approach to compensation events, gain/pain share allowances as ways to improve the
management of resources.
In the UK, construction was shifting from a traditional procurement approach where all risks
were transferred to the contractor by considering other standard forms of contracts such as the
NEC 3 (Latham, 1994). The success story of the construction activities for the UK 2012
Olympics was squarely attributed to the use of NEC 3 contracts. It delivered 45 out of its 46
projects (Dhanushkodi, 2012).
2
In the Sultanate of Oman, a study was carried out by Rashdi (2010) to evaluate the use of
standard forms of contract on public sector construction projects and to provide
recommendations to traditional contracts that had not been changed since 1980. Conclusions
made stated that the NEC 3 contract had addressed dispute resolutions and sub-contractor
management in a more contemporary approach in comparison to the dated standard forms that
Sultanate of Oman was using (Rashdi, 2010).
A study on Malaysia’s construction industry by Chan (2006) revealed that its public sector
attempted to adopt NEC 3 contract in a bid to resolve many disputes, claims and litigation on
construction projects. It was however concluded that Malaysia was not ready for total adoption
of NEC 3 contract because of many ‘environmental’ factors and chief among them was that
professionals in the industry were still reluctant to change the role of an Architect. Malaysian
government however, commended NEC 3 for its simplicity on language and favourable contract
adjudication (Chan, 2006).
According to Stiedl (1999), there was need for new forms of contracts in Zimbabwe which could
address the labour issues for workers in the construction industry. He cited that the contract
practice in the civil engineering works had been to amend the existing complex contracts or to
draft some poorly designed bespoke contracts that were seriously lacking on certain fundamental
labour issues (Stiedl, 1999).
According to Gombera and Okorroh (1999), the Zimbabwean economy had made efforts over
years to provide public facilities using traditional procurement approaches to contracts.
However, the ever changing economic environment required improved contracts management in
a construction industry that was lacking goodwill, trust and teamwork between the parties
(Gombera and Okorroh, 1999).
A study by Mukamba (2007) on the indigenous contractors’ requirement to adopt project
management concluded that Zimbabwe was still using the Zimbabwe General Conditions of
Contracts (ZGCC4) and Civil Engineering Conditions of Contract in Zimbabwe (CECCZ) and
those were derived from the JCT and GCC contracts in the 1950s. Further to that, he stated that
3
the indigenous contractors were reluctant to use other forms of contracts such as NEC because
they were familiar with traditional ones that were also upheld by the Government of Zimbabwe
(Mukamba, 2007). However, in a newspaper article of Zimbabwe’s Sunday Mail dated 15
March, 2015, the NEC 3 contract was used on construction projects at Unki Mine in Zimbabwe.
In view of the studies above, NEC 3 contract was generally cited by researchers as a contract that
mightoffer better project management principles. Studies noted its effectiveness on reducing
adversity among contracting parties, contemporary methods to contract management and its
flexibility on language and use. However not so much was said specifically about the NEC 3
contract as a cost control measure on the construction projects. The research would therefore
seek to fill that knowledge gap by zeroing in on the analysis of the cost controls that the NEC 3
contract offered and their suitability on the construction industry in Zimbabwe.
1.1 Problem Statement
The use of NEC 3 contract on projects in Zimbabwe was not very popular according to Redmond
(2009) in a construction industry that was mainly dominated by traditional contracts (Mukamba,
2007). The adversity, cost uncertainties and lack of cost saving mechanisms characterized by
most traditional contracts on projects was criticized by many in the construction industry, hence
the drafting of NEC 3 contract (Chan, 2006). Zimbabwe was no exception to those problems as
stated by Mukamba (2007).
The NEC 3 contract was remarked by Dickson (2013) that it was a cost saving tool. The contract
had features such as compensation events which required pro-activeness from the contractor to
claims by giving a notice within a specified period of becoming aware of the risk, for their claim
to be entertained (Gould, 2007).Most traditional contracts allowed for claims to be attended to
in-retrospect; something that did not encourage risk mitigation and possible cost saving (Gould,
2007). The research would analyse the time-barring approach to claims and how suitable it was
in the Zimbabwean context.
4
Further to that the research would also analyse issues such as the fact that provisional sums were
removed in the NEC 3 contract due to high risk of cost uncertainty on a project (Doig, 2014),
early warning systems, allowed and disallowed costs, target costing and many other features
peculiar to the contract. The study would give a position on the suitability of cost control
measures that the NEC 3 contract offered to the construction industry in Zimbabwe.
1.2 Main Objective
To investigate the suitability of cost control measures in the NEC 3 contract to the construction
industry of Zimbabwe.
1.2.1 Specific Objectives
1.2.1.1To investigate the suitability of using NEC 3 contract with the current Legal framework
on procurement of construction projects in Zimbabwe.
1.2.1.2 To evaluate the suitability of NEC 3 contract as a cost control measure on projects in
Zimbabwe.
1.2.1.3 To investigate the extent of use of NEC 3 contract in the Zimbabwean construction
industry.
1.3 Main Research Question
How suitable are the cost control measures in the NEC 3 contract to the construction industry in
Zimbabwe?
1.3.1 Specific Research Questions
1.3.1.1 How suitable is the use of NEC 3 contract with the current Legal framework on
procurement of construction projects in Zimbabwe?
5
1.3.1.2 How is suitable is the NEC 3 contract as a cost control measure on projects in
Zimbabwe?
1.3.1.3 What is the extent of the use of NEC 3 contract in the Zimbabwean construction
industry?
1.4 Justification of Research
The research sought to analyse the NEC 3 contract cost controls measures and how those could
be applied to the construction industry in Zimbabwe. The exercise would assist in determining
whether the measures could help in ensuring saving of costs on a project and having cost
certainties for budgeting purposes.
The NEC 3 contract was currently administered on private sector projects in Zimbabwe, but
according to Mukamba (2007) the traditional contracts were still dominating on most projects.
The previous studies by Chan (2006) and Rashdi (2010) recommended the need to move away
from traditional contracts which were characterized by lack of good project management
principles. The problems included the confrontational relationship between the contracting
parties, non pro-active approaches to risk management and the subsequent negative attitudes by
contractors to pricing and claiming.
The study might therefore provide information which could help on decision making processes
on cost management issues on construction projects in Zimbabwe. It might also add to the body
of knowledge.
1.5 Scope of Research
The research had the introduction and the background in Chapter 1 which highlighted issues at
hand and the related studies that were done on the topic and the knowledge gap that needed
research. The same chapter provided the statement of the problem which stated that the
traditional contracts had been lacking on project management principles and in particular the cost
controls and how NEC 3 contract was introduced in response to some of those problems.
6
The conceptual framework of the study would be covered under the Literature Review of
Chapter 2. The chapter would define and explain the procurement theories, the overview of the
NEC 3 contract, concepts and discussion on related studies. The chapter would be guided by the
objectives of the study.
As a way of collecting information, a survey would be done through interviews and
questionnaires to collect the data from construction players in Zimbabwe. That should help to
obtain responses to answer the research questions. The results would be analysed, and
conclusions and recommendations drawn from that for the study.
7
CHAPTER 2
Literature Review
2.1 Introduction
The chapter provided in depth the theories and concepts on the subject under study (Baron,
2012). It was important to note that it was guided by the objectives of the study and would reveal
what other authors had written about the subject, the conceptual frameworks that existed and the
discussions about the literature (John, 2007). For the purpose of the study, the form of contract
that would be discussed was the NEC 3 contract.
2.1.1 Standard forms of contracts
The construction activities required terms of reference of who does what and who should bear
what risk (Tate, 2013). A standard form of contract was an agreement between contracting
parties with terms of conditions to achieve the set objectives on a project (Astrup, 2009). The
forms of contracts in the construction activities could be produced by publishing bodies and
standard in nature or they could be bespoke with basic elements of a contract (Tate, 2013).
2.2 History of NEC 3 contract
In the early 90’s the UK Government commissioned a Latham report on the NEC contract with a
view to improve relations between clients and contractors (Gould, 2007). Disputes and litigations
had been rife on construction projects and NEC 3 contract was drafted as a result of that
(Dickson, 2013). It was then adopted in the UK and worldwide as an alternative to traditional
contracts (Chan, 2006).
2.3 NEC 3 contract overview
A standard form of contract is a contract document that has terms and conditions and is prepared
by trade organizations or bodies and is agreed upon between two contracting parties (Chan,
8
2006). NEC 3 contract is one of the many standard forms of contracts in the construction
industry (Heaphy, 2010).
2.3.1 Core Clauses
The NEC 3 contract had 9 core clauses which were synonymous with every suit and should not
be amended as they help to maintain the philosophy of the NEC 3 contract which upholds good
management principles (Kings, 2005). These cover the general principles of the contract and
these include General, Contractor’s main responsibilities, Time, Testing and Defects, Payments,
Compensation Events, Title, Risks and Insurance and Termination (Gould, 2007).
2.3.2 Main Options
The core clauses were followed by the main option clauses. These were basically defining
pricing and payment system. According to Gould (2007), they included Option A-F as follows:
Option A - Priced contract activity schedule
Option B - Price contract - with Bill of Quantities
Option C - Target Cost - with activity schedule
Option D - Target Cost- with Bill of Quantities
Option E - Cost reimbursable
Option F - Management Contracting
These clauses were optional, and one needed to select one depending on the appropriate type of
payment and pricing mechanism for a particular project (Heaphy, 2010).
9
2.3.3 Dispute Resolution
There were two options namely W1 and W2. The option W2 was suitable for UK legislation and
could not be applied elsewhere, while WI could be applied worldwide (Kings, 2005).
2.3.4 Contract Data
The contract data included essential specifics for the project with the first part being the
employer’s and the second part is the contractor’s (Heaphy, 2010). The contract data had Works
Information and site information such as specifications and design responsibility between the
two contracting parties (Gould, 2007).
2.3.5 Secondary Options
The secondary options were mainly the inclusion of certain clauses depending on the needs of
the client and how they preferred to customize it (Gould, 2007). Mostly they covered for certain
peculiarities of a project and those could include retention, use of multiple currency,
performance bonds, advance bonds, change of law and so on (Kings, 2005).
2.3.6 Z-Clauses
The z-clauses were an option for amendments depending on what parties to the contract prefer to
be part of the contract (Gould, 2007).
2. 4 Suite of NEC 3 documents
The following list had the suites of different NEC 3 documents according to Rowlinson (2011):
Engineering and Construction
Short contract
Subcontract
Short Subcontract
Framework contract
Term services contract
10
Term services short contract
Professional services contract
Supply contract
Supply short contract
Adjudicators contract
According to Rowlinson (2011), the above suites were used for different scenarios of works and
the names ascribed help to describe that. For example the Engineering contract was used for civil
and building works that were relatively large (ibid). The Supply contract was used to administer
the procurement high valued goods and services such as purchasing a heavy plant or equipment
for construction and so on (Rowlinson, 2011).
The study was confined to the procurement routes which included traditional/ separate system-
both priced contract with activity schedule (re-measurable) and priced contract with Bill of
Quantities (lumpsum), target cost contract, design and build contract and management contract.
Procurement routes were a critical part of project management that ensured successful
implementation of a construction project (Mathonsi et al. 2011).
2.5 Procurement routes
It was advisable that all factors that would help achieve the set goals of a project were attended
to before selecting a procurement route (Ramus et al. 2006).
2.5.1 Traditional System (separated)
This procurement route involved separate preparation of the designs by the designer who could
be architect or engineer appointed by an employer without the involvement of a contractor
(Rashid et al., 2006).The contractor was then asked to tender for a job with already prepared
designs. The contract type was usually lump sum or fixed price, but could have clauses for
fluctuations and variations that could increase or decrease the contract sum (Rashid et al., 2006).
11
There could also be traditional re-measurement procurement route where the actual quantities in
the Bill of Quantities were re-measured post contract to ascertain the actual value of the works.
This was usually often where the extent of works was not known at the initial stages and only
measured when the work had been done (Ramus et al., 2006).
2.5.2 Design and Build
The design and build procurement route involved the contractor participating in the design of the
project as well as its construction. It was usually done to make the contractor a point of
responsibility and best suited when the work was specialized. However the extend of the
contractor’s responsibility on the design was usually stated in the contract (Mathonsi and
Thwala, 2011).
The contractor might be tasked by the employer to take full responsibility of the design and
construction in which case he could have in-house designing team and provided everything to the
completion of the project (Miller et al., 2009). An employer might initially work with a team of
designers who would later transfer to the contractor (novation) to develop a concept. The
contractor would be responsible for that designing team even though the employer carried some
responsibility too (Miller et al., 2009). It was worth noting that novation was viewed as
incompatible with NEC 3 contract (Ramus et al., 2006).
2.5.3 Management Contracting
This procurement route involved an employer engaging a managing contractor to manage the
works (Miller et al., 2009). An employer would employ other consultants for design and Bill of
Quantities preparations (ibid). The managing contractor would then appoint subcontractors who
would do the construction work (Miller et al., 2009). The sub-contractors would however enter
into separate contracts with the employer to commit that they would deliver the work (Ramus et
al., 2006).
12
The managing contractor was responsible for the works to ensure that set objectives were
achieved. The payment of a managing contractor was based on a prime cost of the works plus a
fee of the services which might be fixed or a percentage of a prime cost sum (Ramus et al.,
2006).
2.5.4 Target cost
Target cost contracting could be either with bill of quantities or with only schedule of activities
(Gould, 2007). The principle behind was that the employer and contractor would share the gains
if the project did not reach the target cost or share the pain if there was an overspend (Rashid et
al. 2006). That type of procurement encouraged great cost controlling and was one of the main
options in NEC 3 contract (Gould, 2007).
2.6 Criteria used in selecting standard forms of contracts
The criterion that could be used to select contracts in the construction industry had a number of
factors. The following passages outlined different factors that must be considered:
2.6.1 Procurement route
A procurement route was chosen first before a standard form of contract (Love et al., 1998). A
standard form of contract should only be determined by the procurement route and other
pertinent issues to a project (Love et al., 1998). In principle, certain contracts were only best
suitable for certain procurement routes. For instance, the JCT SBC could only be used under
traditional system of procurement and if one considered design and build, then JCT Design and
build would be more appropriate (Love et al., 1998).
2.6.2 Types of works required and sector
The nature of works should be established in terms of how big or small the works were, the time
period of the works, whether there were civil or building works, whether there were specialist
works or not. All these factors would help in choosing the type of a contract. For instance, the
13
civil works that would be less than $500,000 and taking less than a year could best be
implemented using NEC 3 Short Form contract (Dickson, 2013).
2.6.3 Size, value and complexity of the project
It was worth noting that a project could be huge in terms of size and cost, but relatively easy to
construct (Rowlinson, 2011). There were also cases where a project could be small in size but
had complex designs (ibid). A single factor might not automatically determine the type of
contract (Rowlinson, 2011). NEC3 could best be implemented on relatively large projects, but
has formulated others such as Short contract to cater for small size projects (Dickson, 2013).
2.6.4 The employer’s knowledge about contracts
With most government projects, there were certain contracts that would be commonly used on
their projects (Chan, 2006). In the UK for example, NEC 3 contract was mostly used on public
sector construction projects (Ramus et al., 2006). So sometimes the public sector endorsed
certain type of contracts and that was what would be implemented on every project. The
contractors could resort to hike their rates if there were exposed to unfamiliar contracts to
cushion themselves from unknown risks something that could also discourage many employers
from trying out other forms of contracts. (Ramus et al., 2006).
2.6.5 Risk allocation
The selection of procurement routes hinges on the apportionment of risk (Tate, 2003). For
instance design and build generally apportioned risk of the designs to the contractor (Mathonsi
and Thwala, 2011). However different types of standard forms of contracts could apportion the
extent of responsibility to the contractor and how much the employer could have. Contracts had
traditionally favoured the employer and were adversarial in nature to the contractor who usually
should take the most risk (Dickson, 2013). NEC 3 however had tried to address that issue by
having all the parties to cooperate and acting in good faith (Chan, 2006).
14
2.6.6 Basis of contract sum and payment
The contract type whether it was a lump sum contract with or without quantities or whether it
was a‘re-measurable’ contract also mattered in selection of a contract (Tate, 2003). Lump sum
contract usually favoured the employer and the contractor would have to bear the risk and
usually there would not be room for fluctuations (Ramus et al., 2006). Re-measurement on the
other hand used bill of ‘approximate quantities’ which would mean quantities were subject to re-
measurement when the work had been done; presenting uncertainties to the employer on the total
contract sum (Ramus et al., 2006).
Target cost option in the NEC 3 would benefit all the parties because there were incentives to all
parties (contractor and consultants) for cost savings and also faced penalties for cost overruns
(Kings, 2005).
2.6.7 Sub-contracting
Sub-contractors would either be nominated or domestic (Ramus et al., 2006). Domestic sub-
contractors were chosen by the contractor and had the full liability for their actions, while
nominated sub-contractor was selected by the employer even though they entered into a contract
with the main contractor (Ramus et al., 2006). NEC 3 did not encourage having nominated sub-
contractor/suppliers due to the liability they presented to the client (Gould, 2007).
2.7 Discussion on the studies and recommendations of NEC 3
Arguments had been put forward by Latham (1994) that the use of the same traditional contracts
had resulted in the same kind of disputes being witnessed for decades. Chan (2006) added that
there was need for the standard contracts to move away from a lot of uncertainties and
ambiguous terms to clearer, understandable and fair clauses that would be fair to all the parties.
15
2.7.1 A study by Chan in 2006
According to Chan (2006), construction industry in Malaysia had been using traditional JCT 80
Contracts over the years that many were familiar with and it was difficult to introduce unfamiliar
contracts. The results could be that contractors would increase their charges to guard against
unforeseen risks. The research carried by Chan (2006) out on the adoption of NEC 3 contract
proved that Malaysian construction industry was not ready for it. The cited reasons were that the
industry was not ready to replace the role of an Architect with a Project Manager (Chan, 2006).
Another conclusion made was that variation orders are best attended to as re-measurable when
works had been done rather than prior agreement. That approach however made the costs
uncertain as well and difficult to manage the contract sum. The NEC 3 contract was however
applauded in Malaysia for its simplicity in language and fairness among other benefits (Chan,
2006). The study seemed to highlight so much on the general philosophy of the NEC 3 contract
and not specifically on cost controls.
2.7.2 A study by Rashdi in 2010
A study carried out in the Sultanate of Oman by Rashdi (2010) revealed that their traditional
contracts had become dated and were no longer very suitable to more complex construction of
projects. It is important to note that Rashdi (2010) acknowledged that NEC 3 had brought with
some contemporary approaches to the needs of the contracting parties. The conclusion is
however general and does not give in-depth explanation about these contemporary approaches.
2.7.3 A study by Mukamba in 2007
In Zimbabwe, a study was done by Mukamba (2007) on the need for indigenous contractors to
implement project management practices in their projects. He stated that due to the need to get
most of the government projects, most contractors were still familiar with the traditional
contracts such as ZGCC4 and CIFOZ. He however recommended the adoption of new forms of
contracts such as NEC 3 which had better project management principles (Mukamba, 2007). The
study did not however, acknowledged any cost controls that the NEC 3 contract might offer.
16
2.7.4 A study by Dickson in 2013
A study was also done in Hongkong by Dickson (2013) which sought to analyse if NEC 3
contract would bring any improvement to their construction industry. In his conclusion, he laid
out that it was very flexible, encouraged corporation amongst players and improved management
of projects. He however acknowledged that its implementation in Hongkong was not an easy
task but needed awareness and change of cultures that the industry was used to. It was also stated
that there was need for an initial investment in training resources on unfamiliar procurement
routes such as target cost which was one of the options in the NEC 3 contract (Dickson, 2013).
The study did not also dwell much on the cost control measures that NEC 3 contract offered.
2.8 Legal framework of Procurement in Zimbabwe on construction
2.8.1 The Constitution of Zimbabwe (2013)
The constitution highlights the objectives of public procurement and what the public
procurement system should achieve (Tsabora, 2014). Section 9 states that the government should
‘adopt and implement policies and legislation to develop efficiency, competence, accountability,
transparency, personal integrity and financial probity’ (The Zimbabwe Constitution, 2013:
Section 9). It provides a minimum guide as a regulatory framework to procurement (Tsabora,
2014).
2.8.2 Procurement Act (Chapter 22:14)
It was passed in 1999, and regulates local and central government procurement (Tsabora, 2014).
Procurement act defines the various procurement routes that are available in the construction
industry. It however states categorically the procedure for all public services and goods which is
a traditional procurement procedure (Mukamba, 2007).
2.8.3 Jurisdiction of NEC 3 contract
NEC 3 has an option that makes it have jurisdiction for other countries to implement it by
amending certain clauses to suit a particular environments internationally. It however has its own
17
peculiar core clauses (Chan, 2006). NEC 3 has been in use in countries such as UK, New
Zealand and South Africa (Redmond, 2009).
In view of the above, it was apparent that a legal framework that governed the public sector on
procurement existed but the private sector was not covered by that Procurement Act. However,
all the construction activities should be done within the confines of the constitution which was
the supreme law of the land.
2.9 Critical analysis of NEC 3 contract a cost control measure
2.9.1 Programme of Works
According to Forward (2002), it was important to note that both contracts had a provision for a
programme of works under Clause 31.2. In the NEC 3 contract, a programme of works was a
critical component of the contract (Doig, 2014). It was incorporated into the conditions of
contract, and failure by the contractor to update would result in sanctions on their payments
(Doig, 2014). The programme of works was used to monitor progress, on variations, on early
warnings and when ascertaining compensation events which also considered that the affected
works should be on the critical path for them to be awarded an extension of time (Gould,
2007).Time management was directly proportional to cost management and if it was not well
managed would result in a negative effect on cost (Doig, 2014).The traditional contracts
requested for a programme of works at the beginning of a project and further revision when
extension of time had been granted (Chan, 2006).
2.9.2 Provisional Sums
The Provisional Sums were permissible in the traditional contracts when there was not enough
detail on the designs. According to Doig (2014), the NEC 3 had no provision for Provisional
Sums, which meant the contract required almost complete designs. That might be difficult to
abide by in some cases where time was limited the Works Information would incorporate such
18
an inclusion of a Provisional Sum (Doig, 2014). The feature seemed as though it delayed the
project from commencing, but could help a lot in having certainties on costs.
2.9.3 Nominated sub-contractors and suppliers
The NEC 3 contract did not expressly state the provision for nominated subbies or suppliers
(Doig, 2014). According to Heaphy (2010), Nominated sub-contractors and suppliers constitute
the PC Sums which were provisional and the only true costs were known when the Nominated
subbie or supplier had been selected. Inasmuch as the result could either be an addition or
deduction to the contract sum, the uncertainty of costs was still there. Traditional contracts on the
other hand had the provision of PC Sums, even though some clients had been amending the
contracts not to include such (Heaphy, 2010).
2.9.4 Compensation Events
According to Chan (2006), the NEC 3 contract had compensation events (CEs) under Clause 60.
These were part of the conditions of contracts and made part of the core clauses. The CEs were
events which might result in additional money to the contractor (Gould, 2007). However, the
claim was conditioned upon the pro-activeness of the contractor in raising an early warning upon
them being aware of the event within 8 weeks. Failure on the part of the contractor to give that
warning might result in them not getting compensation in form of money and/or time, unless that
was the mandate of the Project Manager (Gould, 2007). Situations that gave rise to CE included
variations, inclement weather, late instructions, unsafe working conditions and so on. The
approach had to be pro-active (Doig, 2014).Interestingly, that clause is treated differently in
other parts of the world such as the Middle East where the Islamic law is in operation, time
barring is not recognised on compensation claims (Hasan, 2014).
In the traditional contracts the claims for loss and expense did not usually had a time-bar and
could be claimed after the event had occurred without any prior need for early warning and
mitigating measures (Chan, 2006).
19
2.9.5 Early warning – Clause 16
NEC 3 contract used early warning system to identify and attend to risks beforehand, and it was
the responsibility of both project manager and contractor. NEC 3 contract encouraged a pro-
active approach which helped achieve better risk management (Kings, 2005).
2.9.6 Incentives for financial savings
One of the main options of NEC 3 contract was target cost. It was a pricing and payment system
that had mutual gain/ pain share of financial savings or losses at the completion of a project
(Knowles, 2011).It was an approach that motivated parties in a contract to work within a budget
to save costs so that they could share the savings. If the project exceeded the budget, then both
parties should pay for the additional amount (Knowles, 2011).
2.9.7 Core clauses
The NEC 3 contract had the 9 core clauses that helped maintain its philosophy of mutual trust
and cooperation between parties (Gould, 2007). Compensation events, early warning,
programme of works were all found in the main clauses hence Latham (1994) mooted that the
core clauses should not be amended to uphold the philosophy of the NEC 3 contract.
2.9.8 Project Manager
The NEC 3 contract had a project manager representing the employer and that helped to manage
the project better (Gould, 2007). Having an Architect supervising the work that they had
designed might create a conflict of interest and value engineering could also be compromised
(Chan, 2006). Most traditional contracts had a provision for an Architect/ Engineer to design and
supervise their own work unless there was an amendment.
2.9.9 Health and Safety
NEC 3 contract promoted good health and safety principles and these were part of its conditions
of contract. According to Gould (2007), if a contractor violated those principles, they could risk
20
termination of contract. Maintaining health and safety in check was viewed by many as wasting
money, but in actual fact it is a cost saving mechanism (Chan, 2006).
2.9.10 Defined and Disallowed costs
If one used a cost reimbursable approach as a pricing and payment option, there were ways to
manage costs (Gould, 2007). For instance, if there had been excess material purchase after
allowing for waste, that surplus was not paid for. It was considered a disallowed cost because it
was an unnecessary cost incurred by the contractor (Doig, 2014). The cost reimbursable option
generally favoured the contractor and put a higher risk on the employer who might not consider
it (Gould, 2007).
Defined costs generally were costs recoverable by the sub-contractor for the works and including
plant hire, equipment used for the works minus the disallowed costs that arose from contractor’s
inefficiencies (Heaphy, 2010).Traditional contracts were mostly administered by a traditional/
separate method which saw the design preparation by the Architect before the contractor could
execute it.
2.9.11 Variation Orders
An early warning system approach was applied and a budget was established first before the
variation order could be implemented (Chan, 2006). The traditional contracts did not expressly
require that pro-activeness and usually the costs were established after work had been completed.
However, if there were amendments that stipulated a proactive procedure, then that cost
uncertainty could be avoided. Provisional sums for instance should be agreed by the employer
before implementation (Gould, 2007).
2.9.12 Delay Damages
In NEC 3 contract, delay damages were optional and were in the secondary options and should
be part of the contract data if there were included (Heaphy, 2010). However, the NEC 3 had pro-
21
active approach of key dates and sanctions for not submitting or updating the programme of
works (Gould, 2007). In the traditional contracts, there were delay damages known as
Liquidated and Ascertained damages if it was contractor’s fault for late completion and it helped
generally to manage the contractor to work within the programme (Ramus et al., 2006).
2.10 Extent of use of NEC 3 Contract in Zimbabwe
According to Redmond (2009), the NEC contracts publishing house had stated the use of NEC 3
contracts in 16 countries in the world and one of them was Zimbabwe. He however mentioned
that significant use was in South Africa where it was used at a greater scale. The NEC 3
contracts use in Zimbabwe was also confirmed in a Zimbabwean newspaper article of Sunday
Mail 15 March, 2015 at Unki Mine.
2.11 Conclusion
This chapter helped to understand about the overview of the NEC 3 contract, its cost control
measures, what other authors have written and the knowledge gap that exists. It also provided the
institutional framework in Zimbabwe and the judiciary of the NEC 3 contract.
22
CHAPTER 3
Research Methodology
3.0 Research methodology / strategy
This chapter provided the techniques that were used to collect the data. The research used mainly
the qualitative approach due to the underlying information that the researcher sought to obtain of
the underlying attitudes and trends from the respondents through interview guide
(Amaratunga et al, 2001). Quantitative approach was also used to complement the qualitative
approach.
3.1 Description of study area
The study was carried out in Zimbabwe in 3 places namely Harare, Bulawayo and Shurugwi,
Unki Mine. Those areas were selected because of their convenience to access and due to the fact
that NEC 3 contract had been used on those places.
3.2 Target population
The target population for this research was the construction players which included the
consultants, employers and contractors in Zimbabwe.
3.2.1 Sampling Frame
A sample frame was defined as a complete list of all the cases in the population from which
sample was drawn from (Harris and Brown, 2010). The researcher would gather information
from clients, contractors and consultants working in the industry. Contractors registered with
either Zimbabwe Building Contractors Association (ZBCA) or Construction Industry Federation
of Zimbabwe (CIFOZ) categories A to C would be considered for participation in this research.
In addition to that registered consultants from Institute of Architects Zimbabwe (IAZ),
Zimbabwe Institute of Engineers (ZIE) and Zimbabwe Institute of Quantity Surveyors (ZIQS)
23
and Private Sector Clients such as Mines, NGOs and other privately owned entities would also
be considered for this study.
3.3 Sampling Techniques
A non-probabilistic approach of purposive sampling was used on the 3 strata to target specific
group that had utilized NEC 3 contract on their projects. Snow-ball sampling technique was a
subset of purposive sampling was applied since the use of NEC 3 contract was still new in
Zimbabwe and referrals would help a lot to collect data.
3.4 Data Collection techniques
3.4.1 Primary Data
Primary data was gathered using two sources of collecting data, which were interviews and
questionnaires. Questionnaires were used to maximize the proportion of respondents answering
questionnaires and to obtain accurate relevant information. They were distributed by means
emails and physically. The only problem associated with the approach was that respondent might
not be able to obtain clarity on the questions in case there was need for some information outside
the structured questions may not be obtained. Questionnaires were also a stated as a good source
of obtaining information by Harris and Brown (2010) as one might express themselves without
feeling any obligation to impress.
The questionnaire was divided into three categories namely; General Information of respondents,
extend of use of different procurement routes and standard forms of contracts and analysis of the
NEC 3 contract and its suitability as a cost control measure. Purposive sampling was applied
using snowballing approach and it was assisted in acquiring information from those construction
players who have used NEC 3 contract on their projects. According to Creswell (2007) a
representative sample frame should have a minimum of 10% of the total population. For this
research a sample size of 50% was used for each category.
24
A certain number of participants were drawn from the target population of contractors, clients
and consultants to make up a sample size. The composition of the sample size is as shown in
Table 3.4.2
Table 3.4.2: Target Population of Consultants, Clients and Contractors
Respondents Targeted respondents
Quantity Surveyors 12
Engineers 12
Architects 12
Clients 12
Contractors/ Contracts Mgr. 16
Total 64
A representative sample was drawn from the population as shown in Table 3.4.3
Table 3.4.3: Classification of the Sample
Construction
Professionals
Number of Construction
Professionals
50% sample size
Quantity Surveying 12 6
Architects 12 6
Engineers 12 6
Contractors/ Contracts
Mgr.
16 8
Clients 12 6
Total 32
Interviews were be done using a carefully prepared structured interview guide to collect data face
to face, by telephone and through Skype. Clarity on certain questions and any other information
required was obtained through this approach. However, with interviews, appointments were
necessary due to busy schedules.
25
Table 3.4.4: Target Population of Consultants, Clients and Contractors on the interview
guide
Respondents Targeted respondents
Quantity Surveyors 10
Engineers 10
Architects 10
Clients 10
Contractors/Contracts Mgr. 10
Total 50
A representative sample was drawn from the population as shown in Table 3.4.5
Table 3.4.5: Classification of the sample
Construction
Professionals
Number of Construction
Professionals
50% sample size
Quantity Surveying 10 5
Architects 10 5
Engineers 10 5
Contractors/Contracts Mgr. 10 5
Clients 10 5
Total 50 25
3.5 Secondary Data
Secondary Data was gathered from the literature that was published regarding the topic.
Secondary data helped in collecting statistics of the past trend on construction projects and this
was important in identifying the knowledge gap of the study.
26
3.6 Results presentation
In the results section, the researcher would use the visual aid such as pie charts and graphs to
present data (Baron, 2012). The results or findings would be aided by short objective
interpretations to give meaning to the visual aids. The results would be in direct response to the
research questions of the study.
3.7 Data analysis
To analyse data from the questionnaires, a Likert scale was used measure the attitudes and
perspectives because of the qualitative nature of the study into quantitative data as recommended
by Boon (2012). According to Kendall (2008), the questionnaire analysis should help bring out
the trends/patterns amongst respondents. The main objective of the study was to investigate the
suitability of the cost control measures in the NEC 3 contract on the private sector construction
industry in Zimbabwe. The analysis should bring out the perspective of the construction players
on the cost control measures.
To complement the questionnaires Kendall (2008) stated that the interviews would give in-depth
information about the respondents’ opinions. A qualitative research could be interpreted by
coding of selected common phrases or outstanding information from the study, even though
sometimes the process could lack objectivity (Bryman, 2008). The process should include
categorizing data based on codes and interpreting the significance of those categories in
answering the research questions (ibid).
3.6 Ethical Considerations
The research considered ethical norms before and during field research in order to create rapport
between the researcher and the respondents. This was important to the respondent’s interest in
sharing data with the researcher. There were no incentives or gifts that were offered when
obtaining information. Furthermore, to counteract the issue of plagiarism, various sources were
acknowledged. The information gathered was strictly confidential.
27
3.7 Validity of the data
As a way of establishing the truthfulness of the data collected, there would be need to use more
than one technique of data collection to increase objectivity in the results (Golafshani, 2003).
Since the research was mainly qualitative, multiple ways of obtaining the truth such as
questionnaires, interviews and records from literature would be used to reduce subjectivity.
According to Noble and Smith (2015), there were strategies to help improve the credibility of the
qualitative results collected as follows:
Acknowledging the level of bias on the researcher that could have manipulated the results
Acknowledging the limitations of the research
Keeping of records and showing of calculations of all the analysis for easy reference.
Acknowledging authors for their sources of information
Triangulation that is making use of multiple ways to obtain and analyse the results.
28
CHAPTER 4
Results, Analysis and Discussions
4.0 Introduction
The results and analysis of the study would be presented and discussed in this chapter. The
chapter was critical because it would provide the findings of the study and their meaning (Baron,
2012).
The research was qualitative in nature on most parts because the research sought to find answers
about the attitudes and coming up with conclusion that could reveal whether the NEC 3 contract
was a cost control measure that could be suitable for construction projects in Zimbabwe. It was a
research where not all the ideas were available but the researcher was also looking for ideas,
concepts and general expert advice from people in the field.
A total of 32 questionnaires were administered on consulting companies, clients and contractors
and responses were 23, meaning the response rate was 72%. The respondents were from
construction professionals in the construction industry. They were selected using both random
sampling and purposive sampling.
The questionnaire was mostly structured. It was a quick and easy way of collecting data from
respondents; however it had its limitations as it confined respondents to choosing responses from
given answers rather than freely expressing themselves.
4.1 Results from Section 1 of the questionnaire
Section 1 of the questionnaire was a respondent’s profile and the researcher was seeking to
establish the experience of the respondents as well as their field. Below is a presentation of the
results obtained:
29
Fig 4.1.1: Respondents Experience
n=23
From the presentation in Fig 4.1.1, the largest number of respondents was in the experience
range of 6-10 years, while the other ranges had relatively lower numbers. Most respondents had
acceptable experience level which makes the results of the study more credible.
The distribution of professionals who responded to the questionnaire was as shown in Fig 2
Fig 4.1.2 – Professionals Respondents
0
2
4
6
8
10
12
0-5yrs 6-10yrs 10-20yrs Over 20yrs
No
. of
resp
on
de
nts
Years of experience
0
1
2
3
4
5
6
7
Architect QuantitySurveyor
Engineer-Civil Client expert ContractsManager
No
. of
pro
fess
ion
als
Professionals
30
The distribution of professional respondents had the Quantity Surveyors with the highest number
of respondents and the Architects with the lowest. However the distribution was fairly
represented for the data that the research required.
4.2 Results from Section 2 of questionnaire
Section 2 of the questionnaire was on the extent of use procurement routes and standard forms of
contracts in Zimbabwe. The question was seeking to answer the research question on the extend
of the use of NEC 3 contract and to do so, one needs to understand the types of procurement
routes in use as shown in Fig 4.2.1.
Fig 4.2.1: Procurement methods
The results showed that the traditional route was extensively in use in Zimbabwe with 62%,
Design and Build had 19%, while Management contracting had 13% and collaborative and
Target Cost each had 3%.
Traditional62%
Design and Build19%
Management Contracting
13%
Collaborative3%
Target Cost3%
31
Fig 4.2.2 shows results indicated the extent of use of NEC 3 contract in Zimbabwe by having a
comparison with other standard forms of contracts:
Fig 4.2.2 Extent of use of NEC 3 contract in Zimbabwe
The respondents indicated that the FIDIC contracts were mostly used in the private sector with
26%, followed by ZGCC4 with 19% and CECCZ with 18%, followed by CIFOZ and JCT
contracts with 13% each and lastly NEC contracts with 11%. It is worth noting that JCT
contracts were not in use in Zimbabwe, and that perhaps indicated the lack of knowledge in the
area by some respondents. The results clearly showed that the use of NEC contracts was still
very low and mainly traditional contracts dominated the private sector.
4.3 Results from Section 3 of the questionnaire
Section 3 sought to answer the main research question on the investigation of the suitability of
the cost control measures in the NEC 3 contract on the private sector construction industry in
Zimbabwe.
NEC contracts
11%
FIDIC contracts26%
JCT contracts
13%
ZGCC419%
CECCZ18%
CIFOZ13%
32
Fig 4.3.1 shows the analysis of ‘Time-barring’ on Compensation Events clause as follows:
Fig 4.3.1 Time barring on CEs
According to the results obtained, 9 of the respondents did not know the time barring clause on
compensation events, while 5 disagreed, 5 agreed and 4 strongly agreed that it was a cost control
feature.
0
1
2
3
4
5
6
7
8
9
10
Stronglydisagree
Disagree Don’t Know Agree Strongly Agree
No
. of
resp
on
de
nts
33
Fig 4.3.2 has the results on the analysis of a programme of works being part of the contract:
Fig 4.3.2 Programme of Works to be part of contract
According to the responses, the idea of having the programme of works in the contract as a cost
control measure had highest respondents about who strongly agreed and shared that number with
those who agreed, while 5 of them did not know and 4 disagreed.
0
1
2
3
4
5
6
7
8
Stronglydisagree
Disagree Don’t Know Agree Strongly Agree
No
. of
Re
spo
nd
en
ts
34
Fig 4.3.3 showed results on people’s perspective on the absence of provisional sums as a cost
control measure.
Fig 4.3.3 Removal of Provisional Sums
The cost control measure of removing the provisional sums in the contract had the 9 respondents
disagreed, followed by 8 who did not know, 3 respondents strongly agreed, 2 agreed while 1
respondent strongly disagreed.
0
1
2
3
4
5
6
7
8
9
10
Stronglydisagree
Disagree Don’t Know Agree Strongly Agree
No
. of
Re
spo
nd
en
ts
35
Fig 4.3.4 shows results on respondent’s view about the Gain/Pain share of financial gain/loss in
Target cost procurement route found in the contract’s main clauses of the as an option
Fig 4.3.4 Gain/ Pain share of financial savings/losses
The responses from the questionnaire indicated that 10 respondents agreed, 5 strongly agreed,
while 5 did not know and three disagreed to the effectiveness of the cost control feature.
Fig 4.3.5 The Project Manager for supervision
0
2
4
6
8
10
12
Stronglydisagree
Disagree Don’t Know Agree StronglyAgree
No
of
Re
spo
nd
en
ts
0
1
2
3
4
5
6
7
StronglyDisagree
Disagree Don't know Agree Strongly Agree
No
. of
Re
spo
nd
en
ts
36
The questionnaire responses indicated that the idea of having a project manager for supervision
had highest responses under those who agreed (6). That was also equal to the number of those
who did who did not know, while 5 strongly agreed, 4 respondents disagreed and 2 strongly
disagreed to its effectiveness as a cost control measure.
Fig 4.3.6 Early warning system on risk management
The questionnaire results obtained showed that the early warning system had the 9 respondents
strongly agreeing, 7 agreeing, while 4 did not know and 4 disagreed on its effectiveness as a cost
control measure.
0
1
2
3
4
5
6
7
8
9
Stronglydisagree
Disagree Don’t Know Agree Strongly Agree
No
. of
Re
spo
nd
en
ts
37
4.4 Analysis of the results from Questionnaire
A comparison on respondents’ perspectives about the suitability of each NEC 3 cost control
measure on the Zimbabwean private sector construction industry:
Table 4.4.1 Summary of respondents’ perspective on the NEC 3 contract
Cost Control
Strongly
disagree Disagree
Don't
know Agree
Strongly
agree
Time bar on C.E 0 5 9 5 4
Prog. of works on contract 0 4 5 7 7
No Provisional Sums 1 9 8 2 3
Gain/Pain share 0 3 5 10 5
P.M for supervision 2 4 6 6 5
Early warning 0 4 4 7 8
From the Table 4.4.1, the numbers represent the number of respondents who answered a
particular cost control.
To draw comparisons and contracts, the researcher assigned values to the Likert scale as follows:
Strongly disagree 5 points
Disagree 4 points
Don't know 3 points
Agree 2 points
Strongly agree 1 points
38
Table 4.4.2 shows the average responses deduced for each cost control measure as follows:
Table 4.4.2 Average response for cost control measure
Time bar on C.E Strongly agree 5 x4 =20
Agree 4 x5 =20
Don't know 3 x9 =27
Disagree 2 x5 =10
Strongly agree 1 x0 =0
Total points 77
The same approach shown in Table 4.4.2 was applied to all cost control measures as shown in the Table
4.4.3
Table 4.4.3: Average responses for all cost controls
Cost Control Average
Time bar on C.E 3.3
Prog. of works on contract 3.74
No Provisional Sums 2.86
Gain/Pain share 3.74
P.M for supervision 3.3
Early warning 3.83
The data in Table 4.4.3 showed that Early Warning System was regarded by respondents as the most
suitable cost control measure with an average of 3.83. It was followed by Program of works in the
contract and the Gain /Pain share on savings/ losses both with an average of 3.74. On the third position
was Time barring of Compensation Events sharing the same position with having the Project Manager for
supervision with an average of 3.3. The least averaged cost control measure of 2.86 allocated to the
removal of Provisional Sums from the contract. The degree of differences was not much but significant
enough to show a pattern on the respondent’s perspective of the cost control measures in the NEC 3
contract.
39
4.5 Results from the Interview guide
The interviews were mostly carried on Skype with a few on one on one due to limited resources
to travel from one point to another. The sample was relatively smaller than for questionnaires as
respondents needed appointments for interviews. Out of the 25 appointments on interviews, a
total of 15 were able to avail themselves for interviews. That meant a total of 60% response to
the interview guide. The guide had a section of respondents’ profile that included their years of
experience and professions.
The distribution of the respondents who answered the interview guide was as shown in Fig 4.5.1:
Fig 4.5.1 – Years of experience for interview respondents
n=15
The interview respondents were mostly in the range of 6-10years of years of experience. It is a
fairly reliable range of experience to obtain most of the answers from.
0
1
2
3
4
5
6
7
8
1-5yrs 6-10yrs 11-20yrs Over 20yrs
No
. of
resp
on
de
nts
Range of Years
Years of experience
40
Fig 4.5.2– Professionals Interviewed
n=15
The interviews had the Civil Engineers with the highest number of respondents (5) and the
Contracts Manager had the lowest figure. It is also a fair presentation by different professionals
on the study.
Section B of the interview guide focused on the analysis of the NEC 3 as a cost control measure.
The advantage of the interviews was that questions could be clarified and obtaining more
information from the respondents.
4.6 Method of analysis on the interviews
The data collected was mainly qualitative and for a method of analysis, the researcher used an
open minded approach with no bias of pre-conceived ideas. The coding of the responses was
derived from the following observations that were noted as recommended by Kent (2012):
statements that were repeated by many respondents
statements that were conceptual
statements were also similar to other conclusions made by other authors
0
1
2
3
4
5
6
Architect QuantitySurveyor
Engineer-Civil Client expert ContractsManager
No
. of
pro
fess
ion
als
Professionals
Professionals Interviewed
41
4.6.1 Categories that were derived from the above codes
There were two categories that were derived from the responses that were collected and these
were classified as ‘economic environment’ and ‘familiarity’ as shown in Table 4.6.1.1. The
economic environment was referred to by many in their responses, while issues of familiarity
were also coming out quite often from many respondents.
Table: 4.6.1.1 – Categories/indexing of results from interviews
Familiarity Category Time barring in Compensation Events
Early warning system
Removal of Provisional Sums
Z-Clauses
Economic Category Defined and disallowed costs
Programme of works as part of the contract
The Project Manager for Supervision
Collaboration / Partnering
Gain / Pain sharing of savings/losses
4.6.2 Analysis from the ‘familiarity’ category
4.6.2.1‘Time-barring’on compensation events clause
Many respondents stated that there were not familiar with ‘time barring’ concept. However, they
said it was a good approach to claims even though it would cause a lot of disputes with
contractor’s who were not used to such.
4.6.2.2 Early warning system on risk management
From the interviews carried, the view of the respondents was that early warning system was a
good mitigating measure to cost overruns even though it was a new concept and needed more
education.
4.6.2.3 No provisional sums
The removal of provisional sums in the NEC 3 contract was not viewed as anything that helped
to control costs. The general understanding that many respondents stated was that provisional
sums helped to provide a better estimate of a project and would increase or reduce the final cost
when scope was fully defined.
42
4.6.2.4 Z-clauses
The option of Z-clauses was considered as a good option that provided room for flexibility to
amend the contract with more familiar clauses.
4.6.3 Analysis from the ‘economic environment’ category
4.6.3.1 Defined and disallowed costs
Most respondents welcomed the idea stating that the even though cost reimbursable contracts
were not very ideal on the clients’ side due to high risk, having defined and disallowed costs was
necessary to manage what was due to the contractor and avoid unnecessary payments. They
stated the economic environment needed such diligence.
4.6.3.2 Programme of works to be part of the contract
The explanation from the interviews indicated that respondents were generally for the idea of
having the programme of works as part of the contract as a way of improving time and cost
management.
4.6.3.3 The Project Manager for supervision
The interviews on the subject matter revealed that many respondents did not appreciate much the
value of having a project manager. Some viewed it as an extra cost that could be avoided by the
usual services of an architect/ engineer who designed and supervise works.
4.6.3.4 Collaboration/ Partnering
Respondents appreciated the concept of ‘partnering’ as a way of removing adversity, but stated
that it was not very feasible in an environment where many disputes arose from late or non-
payments from the clients and contractor’s defaulting due to the difficult economic environment.
4.6.3.5 Gain/Pain share financial saving/loss
From the interviews carried out, the concept of gain/ pain share of financial saving/ losses was
foreign to respondents. Respondents needed further explanation and some were skeptical about
its feasibility in Zimbabwe where in most cases projects would have cost overruns due to late
payments and a lot of variations due to design changes.
43
4.7 Discussions
The main purpose of the research was to investigate the NEC 3 contract as a cost control
measure and how suitable it was to the construction industry in Zimbabwe. The following
passages discuss those measures as well the responses that came out of the questionnaires and
interviews.
4.7.1 Time barring on compensation events clause
The compensation event clause 6 called for a pro-active approach on the part of the contractor to
give notice within 8 weeks of becoming aware of risk that would result in additional cost before
their for their claim could be entertained. As shown in the results that many respondents were not
really in support of this stance stating that it might be a source of disputes. Many stated that even
without a notice given, the contractor should be entitled as was the case with other contracts. It
was probably because of the absence of such an approach in most traditional contracts that
Zimbabwe used. However, in FIDIC (red book) 1999 for example, that approach was found and
had even a lesser period of 28days to give a notice on a loss and expense claim. From a due
diligence point of view, being pro-active in giving a notice to a risk could help to mitigating risks
and perhaps realizing a cost saving. Giving a notice could also assist to the reconciling the period
when the additional costs started and supporting documents incurred for the processing of
payments. Given that the concept was relatively new to the construction players, making
everyone aware of such clauses would assist for the good of the project.
4.7.2 The role of Project Manager
The respondents indicated less enthusiasm about having a project manager on a project and they
mostly recommended that it was appropriate on large projects. Some viewed as an additional and
recommended the designer to manage. However others welcomed the idea as refreshing since the
person would be having any conflict of interest. The traditional contracts such as the ZGCC4
recognised the services of the Architect for designing and supervision. It is important to note that
the notion that Project Manager meant additional cost to the project might not be true, because
even when the Architect designs and supervises their statutory charges are generally 4.5% on
design and 1.5% on supervision of the contract sum. Project Managers charges were about 1% of
the contract sum and that might make them even cheaper. It might actually benefit the client to
have a more neutral person who has no conflict of interests to represent them on the supervision
of works and may help in objective value engineering. A study done in Malaysia by Chan (2006)
on the NEC 3 also indicated that the Architects in that country were not ready to ‘relinquish’
their supervision services to a Project Manager.
44
4.7.3 Removal of Provisional Sums
Some respondents felt the removal of provisional sums was not necessary as having them was
just a measure that helped to estimate works when they were not fully designed. Having no
provisional sums in the NEC 3 contract was done specifically reduce the risk of costs
uncertainties (Doig, 2014). The absence of the provisional sums in the NEC 3 contract would
mean having complete designs before a project commenced. The risk of consultants treating a
provisional sum as a ‘contingency’ that could easily be exploited was not really a significant
issue to many, yet in reality that could cause escalations costs on many projects. However, the
fact that designs should be completed might not always be practical due to limited time before a
project commenced and having provisional sums might be inevitable. Furthermore the issue that
traditional procurement route with a single stage tendering procedure was more popular, the
contractor involvement at design stage was absent and that might result in having provisional
sums to the client.
4.7.4 Early Warning System
This feature was embraced by many respondents as a way of helping to attend to risks and
mitigate possible losses. They stated that it was one exercise that should take place to manage
risk and complementary to compensation events. Early warning should come from both the
Project Manager and the contractor and that made the approach less punitive and everyone
responsible (Hasan, 2014).
4.7.5 Gain/Pain share of financial savings/losses on Target Cost
The respondents indicated that they were not really familiar with this procurement route and
would need education on it. It was noted however that it could be a good cost saving tool. A
study by Dickson (2013) also stated that this procurement route needed initial injection of costs
on training resources to contractors tendering using target cost. The concept of incentivizing both
parties for savings and bearing costs on losses was a noble cost saving idea that could help with
effective cost controls.
4.7.6 Z-Clauses
The Z-Clauses in the NEC 3 contract allowed for amendments to the contract. According to a
study by Chan (2006), that was considered as a cause for concern the philosophies of NEC 3
contract which was generally considered a departure from the traditional contracts. The
respondents however noted that it gave room for flexibility to different countries with peculiar
environments. Care cited that care should therefore be necessary on amendments so that the
amended contracts maintained cost control features as stated in the NEC 3 contract.
45
4.7.7 Defined and disallowed costs on Cost Reimbursable
This feature of controlling costs under cost reimbursable procurement route was considered by
respondents as a noble way to pay for actual costs and to ‘disallow’ costs associated with
contractor’s incompetence. Again cost reimbursable procurement route was not a popular
procurement route to many and respondents stated that they would prefer approaches that they
were familiar with.
4.7.8 Partnering/ Collaboration
The NEC 3 contract was introduced partly to deal with adversity between client and contractor,
and to bring corporation and sort of partnering arrangement with mutual understanding or mutual
trust between parties (Stiedl, 1999). The respondents acknowledged its rationale in controlling
costs, but indicated that the economic environment in Zimbabwe was marred with late payments
or non-payments and disputes were rife. Others referred to problems by indigenous contractors
who were defaulting on projects and the idea of ‘partnering’ was not likely an option. The role of
Project Manager as a pro-active supervisor who took some of the responsibilities could assist in
improving the relations and in turn help on reducing claims.
46
CHAPTER 5
Conclusions and Recommendations
5.0 Introduction
The overall aim of this project was to investigate the suitability of cost control measures in the
NEC 3 contract to the construction industry of Zimbabwe. This was discussed together with
objectives in Chapter 1 and the conclusions and recommendations that this study has contributed
to the body of knowledge.
5.1 Conclusions on the objectives of the study
Objective 1: To investigate the suitability of using NEC 3 contract with the current Legal
framework on procurement of construction projects in Zimbabwe.
According to Tsabora (2014), the Constitution of Zimbabwe published in 2013 indicated that it
was not very explicit about the standard forms of contracts or procurement routes, but its Section
9 states that the government should ‘adopt and implement policies and legislation to develop
efficiency, competence, accountability, transparency, personal integrity and financial probity’. In
that regard, the Constitution was in a way encouraging for the establishment of frameworks that
promoted efficiencies in the administration of procurement even though it was in reference to the
Public Sector. It is worth noting however that the Constitution is the ‘supreme law’ and therefore
governs every activity or undertaking in a country.
The Zimbabwe Procurement Act (Chapter 22:14) provides a legal framework for public
procurement but not on the private sector. It was in the private sector that other forms of
contracts such as the NEC 3 contract were used. According to the results, it was clear though that
both public and private sectors were still dominated by traditional contracts. In conclusion, the
use of other forms of contracts in the private sector was not limited by the Procurement Act and
construction players could use other new forms.
The jurisdiction of the NEC 3 contract as indicated in the literature review went beyond UK
where it was originally drafted. The Z – clauses in the NEC 3 contract enabled for amendments
in the contract to suit particular project environments.
47
Objective 2: To evaluate the suitability of NEC 3 contract as a cost control measure on
projects in Zimbabwe.
By and large, there was significant information from the results collected that confirmed the
NEC 3 contract as a cost control measure that could be adopted by the construction industry in
Zimbabwe. However, as discussed there were some areas which required attention for the
appropriate implementation of those measures.
NEC 3 contract was commended by many respondents as a cost control measure with many
peculiar features that were in direct response to some ‘flaws’ found in traditional contracts. From
the results, many applauded having the programme of works as part of the conditions of contract
as a way of managing time and cost, and the early warning system to risks which was viewed as
a noble mechanism to managing additional cost related risks.
Many respondents stated that partnering/ collaboration approach on contracts could be a
challenge to instill between parties due to the depressed state of economy in Zimbabwe which
was characterized by delayed payments, suspensions and defaulting contractors. Some
indigenous contractors were cited as a challenge to build ‘good faith’ and trust due to their
inconsistences on delivering projects and profiteering through cutting corners.
Target costing as a procurement route and the time bar approach to compensation events were
described as refreshing ideas that could help saving costs on site and encouraging parties to be
more pro-active. Change management, extension of time claims and any other risk that could
result in additional cost, time or affect progress required every party to be pro-active in
mitigation before assessing the need for compensation. However, lack of familiarity of some
respondents with these ‘concepts’ required awareness and training to avoid disputes that could
arise if those procedures were not followed.
Most respondents did not agree to the idea removal of provisional sums from the contracts as
was the case in the NEC 3 contract. They stated that provisional sums assisted with estimation of
works that had not been defined at the time of tender and should not be seen as a risk factor.
48
They argued that the abuse of provisional sums could be avoided because it was incumbent upon
the client whether they wanted to utilise it or not depending on their budget.
Objective 3: To investigate the extend of the use of NEC 3 contract in the construction
industry in Zimbabwe
According to results obtained from the questionnaires, the NEC 3 contract was used in the
private sector and only 12% of the respondents had used it on projects. This entailed that it was
relatively new in the industry. According to the literature review, a newspaper article in the
Zimbabwean Sunday Mail of 15 March, 2016 confirmed its use at Unki Mine in Zimbabwe.
According to Redmond (2009), the use of NEC 3 contract had been registered in 16 countries
including Zimbabwe even though he stated that it was not as significant as was the case in South
Africa.
5.2 Recommendations
5.2.1 Consultants should do a better job of acquainting clients they represented on the forms of
contracts. A classic example of why education on contracts administration was needed on
contracts was more than half of the respondents indicated that the JCT contract was used
in Zimbabwe, something that was not true and probably, an indication that knowledge
was probably lacking in that area.
5.2.2 The NEC 3 contract was relatively new in Zimbabwe and naturally construction players
were a little apprehensive in their responses on adopting the cost control measures
offered by NEC 3 contract. Seminars on the awareness of NEC 3 contract by construction
stakeholders for both private and public sectors would be necessary. Government of
Zimbabwe had not used the NEC 3 contract on its projects and such seminars could be an
eye opener.
5.2.3 The bias towards traditional contracts was still there even though they were some cost
control measures in the NEC 3 contract that were commended. As a recommendation, the
construction players could introduce some of these clauses amendments to their contracts
on some of the projects and evaluate their effectiveness. In Zimbabwe where concepts
such as ‘time barring’ on claims were not common, parties should be made aware of such
clauses in the contract beforehand to avoid unnecessary disputes.
49
5.2.4 The change of mindset on subjective risk allocation to the contractor which the NEC 3
contract addressed should be emphasised across the construction industry. Clients should
also engage on projects that they could fund to avoid late or no payments, and on the
other hand a thorough scrutiny of contractors on their financial statements and reputation
was necessary before tender award to avoid selecting contractors who had no capacity to
deliver projects. That would go a long way in avoiding disputes and promoting ‘good
faith’ between parties.
5.2.5 The concept of defined and disallowed costs were considered as affective resource
management to a project as payments could be done for actual cost and not on
unnecessary costs incurred by the contractor. However the cost-reimbursable route
generally had a higher risk to the client, and as a recommendation it could be combined
with the concept of target cost so that cost savings could be realised.
5.2.6 It was worth noting that NEC 3 contract was in use in Zimbabwe even though not on
many projects. Objective thinking by the construction players on such new forms of
contracts, willingness to change and pursuance of informed decisions could go a long
way in improving practices on projects.
5.3 Recommendation for future studies
Further research could explore the analysis of NEC 3 contract on time management. It was an
area that needed thorough research. Most research work on the NEC 3 contract focused on its
general overview but not the specifics of project management principles.
50
REFERENCES
• Amaratunga, D., Baldry, D., Sarshar, M. and Newton, R. (2001) Quantitative and
qualitative research in the built environment: application of ‘mixed’ research approach
• Ashworth A (1983), Building Economics and cost control- Worked solutions
• Astrup, J (1999), Standard form construction contracts
• Bahaudin, A.Y, Elias, E.M, Dahalan, H, Jamaluddin, R (2012), Construction Cost
Control: A Review of Practices in Malaysia
• Baron, M A (2012), Guidelines for writing proposals and dissertations
• Boon, H.N (Jnr) (2012). Analysing Likert data. http.//www.joe.org2012April .Accessed
10:00pm, 8/20/16
• Bryman, A. (2008). Social research methods. Oxford University Press.
• Burrows J (2002): Principles of the law of contract in New Zealand,
(http://www.observationalmethod.com/media/Contracts), Accessed at 12:17, 4/16/2016
• Chan,M (2006) , New Engineering Contract (NEC), 1993 as radicals to the Malaysian
standard forms of contracts
• Conlin, J T, Langford, D A, and Kennedy, P (2012): The relationship between
construction procurement strategies and construction contract disputes. Organization and
Management of Construction, 360-371.
• Creswell, J.W(2007), Qualitative inquiry and research design: Choosing among five
approaches.
• Dickson R.N (2013), An analysis of the use and implementation of NEC vs. Traditional forms of
contract in the HK construction industry.
51
• Diether B (1977): Writing Chapter 5, conclusions and recommendations
http://dissertationwriting.com/thesis-dissertation-conclusion-chapter.shtml. Accessed at
9:04, 4/20/2016
• Doig D (2014), NEC 3 – A model for best practice project control
• Forward, F (2002), NEC 3 Compared and Contrasted
• Frederiksen R (2002), Adversity challenges contractors, clients,
http://djcoregon.com/news/2002/07/24/opinion-adversity-challenges-contractors-clients/
Accessed at 22:55, 13/7/2016
• Golafshan, N (2003), Understanding reliability and validity in Qualitative Research
• Gould, N (2007), NEC 3 – The contract of the future
• Harris L.R and Brown G.T.L (2010), Mixing interview and questionnaire methods: Practical
problems in aligning data
• Hasan K.T (2014) , FIDIC for Middle East User’s: Pursuing or defending claims under FIDIC
Contracts-Regionally and Internationally
• Heaphy, I (2010), NEC v FIDIC, Society of Construction Law, Hong Kong, International
Construction Law Conference
• John W. C (2007) Research Design, Qualitative, Quantitative, Mixed Method
Approaches: Fourth Edition
• Kendall, L. (2008). The conduct of qualitative interview: Research questions,
methodological issues, and researching online.
• Kent, L (2012), Visualising and exploring qualitative research: Interview transcripts
• Kings, S (2005), Using the NEC 3 Contracts effectively,
www.cips.org/documents/membership/.../nec3, Accessed at 21:47, 5/4/2016
• Knowles , R (2011)-Target Cost Contracts
52
• Latham, Sir Michael (1994). Constructing the team. Final Report of the Joint Review of
contractual and procurement arrangements in the United Kingdom Construction Industry.
• Love, P.E.D., Skitmore, R.M., and Earl, G. (1998). Selecting a suitable procurement
method for a building project. Construction Management and Economics, 16(2), pp.221-
233.
• Mathonsi, M. D. and Thwala, W. D (2011): Factors influencing the selection of
procurement systems in the South African construction industry.
• Mukamba E (2007) Project Management: A requirement for Zimbabwean Indigenous
Contractors
• Noble, H and Smith J (2015), Issues of validity and reliability in qualitative research
• Project Administration, Procedure No: 1 PROJECT COST CONTROL
,http://www.caldenergine.com/Project%20Cost%20Control%20Procedure, Accessed at
20:56, 4/23/2016
• Ramus J, Birchall S, Griffiths P (2006) Contract Practice for Surveyors, Fourth Edition
Rashdi A, A (2010), Evaluation of the Standardized form of contract at Sultanate of
Oman
• Redmond, J (2009), International disputes under NEC, http://www.nec-
adjudicators.org/articles/john-redmond/77-international-disputes-under-nec. Accessed at
22:46, 7/22/2016
• Rowlinson, M (2011), A practical guide to the NEC 3 engineering and construction
contract
• Stiedl, D (1999), Contract documents for small contracts in the road sector
• Sweet, J (1994) Judging contracts: Some reflection on the Third International Law
Conference
• Tate, R (2003): A guide to standard forms of contract
53
• The Constitution of Zimbabwe 2013:
https://www.constituteproject.org/constitution/Zimbabwe_2013. Accessed at 20:57,
4/16/2016
• The Sunday Mail, March 22, 2015, http://www.sundaymail.co.zw/unki-mine-loses-
contract-case/ Accessed at 22:00, 6/9/2016
• Tsabora J (2014): Public procurement in Zimbabwe: Law, policy and practice
• Watermayer, R (2009), Getting to grips with the NEC 3 ECC Target Contract with
activity schedule
54
APPENDIX 1
QUESTIONNAIRE
The researcher is a student currently studying a Master of Science Degree in Construction
Project Management at National University of Science and Technology. In partial fulfillment of
the Degree, a questionnaire has been prepared to address the dissertation topic titled ‘An
analysis of NEC 3 contract as a cost control measure on building projects: A case of private
sector construction industry in Zimbabwe’. You are kindly requested to answer the questions
below. Some questions are closed-ended and will require ticking inside a box provided, while
others are open- ended. Your responses to this questionnaire will be strictly confidential and
shall be used solely for academic purposes.
SECTION 1: RESPONDEND PROFILE
1.1 Profession: A. Architect B. Q .S C. Engineer D. Client Expert
E. Contractor F. Other: Please specify……………………
1.2 Indicate the level of experience in the construction industry:
A.1-5years B. 6-10years C. 11-20 years D. Over 20years
55
SECTION 2: EXTENT OF USE OF NEC 3 CONTRACT IN ZIMBABWE
2.1 Indicate the extent of use of the following procurement routes in Zimbabwe:
0-Not used 1-Very limited 2-Limited 3-Extensive 4-Very extensive
0 1 2 3 4
Traditional Method/
Separated
Design and
Build/Integrated
Management
Contracting/Packaged
Method
Collaborative/
Relational Method
Target cost
2.2 Indicate the level of use of the following Standard Forms of Contracts in the private
sector of Zimbabwe:
0-Not used 1-Very limited 2-Limited 3-Extensive 4-Very extensive
0 1 2 3 4
NEC 3
FIDIC
Contracts
JCT 80
ZGCC4
CECCZ
CIFOZ
56
2.3 Indicate the level of use of the following Standard Forms of Contracts in the public
sector of Zimbabwe:
0-Not used 1-Very limited 2-Limited 3-Extensive 4-Very extensive
0 1 2 3 4
NEC 3
FIDIC
Contracts
JCT 80
ZGCC4
CECCZ
CIFOZ
SECTION 3: ANALYSIS OF THE NEC 3 CONTRACT COST CONTROL MEASURES
3.1 NEC 3 contract has cost control measures that it provides. Please indicate your perspective on the
suitability of each on Zimbabwean private sector construction industry in the appropriate box.
1-Strongly disagree 2-Disagree 3-Don’t Know 4-Agree 5-Strongly Agree
Cost Control
Measures
1 2 3 4 5
Time-barring of
compensation events
Programme of works
to be part of contract
No Provisional Sums
Gain/Pain share of
financial
savings/losses
Project Manager for
supervision
Early warning
system
57
3.2 Considering the general culture of the construction industry in Zimbabwe, what is your
view on the adoption of cost control measures of the NEC 3 contract?
……………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………………………………
Thank you for taking time to answer this questionnaire. It is much appreciated!
58
APPENDIX 2
INTERVIEW GUIDE
SECTION 1: RESPONDENT’S PROFILE
1.1What is your profession?
1.2How many years of experience do you have in the construction industry?
SECTION 2: ANALYSIS OF NEC 3 CONTRACT AS A COST CONTROL MEASURE
2.1NEC 3 contract has a provision for a Project Manager as a client’s representative to supervise
the works, and not necessarily the designer (Architect/Engineer). How feasible is this aspect
considering the status quo in Zimbabwe which usually has Architect/ Engineer at the helm?
2.2 NEC 3 contract does not have a provision for Provisional Sums. What is your analysis on the
applicability of this cost control feature on a project?
2.3 Programme of works is made part of the contract in the NEC 3 contract as a way of
managing time. A contractor is sanctioned if they default in submitting or updating a programme
of works. How feasible is this approach on construction projects in Zimbabwe?
2.4 NEC 3 contract has an option of Z-clauses that allow for amendments to be included in a
contract. What do you think can be the effect of Z-clauses on the general cost controls and what
is your recommendation, if any?
2.5 In the NEC 3 contract, compensation events come with a time-bar clause that states a
contractor should give notice within 8 weeks of becoming aware (or should have become aware)
of an event that will increase time/cost of a project. Failure to give such a notice within stipulated
period may result in the contractor’s claim not being entertained. What is your view with regards
to cost savings and the feasibility of such a stance in Zimbabwe?
2.6 The NEC 3 contract has defined and disallowed costs under cost reimbursable procurement
route. By definition, these are actual costs and costs incurred by the contractor as a result of
incompetence respectively. The procurement route promotes the payment of defined costs while
it does not entertain costs that are borne from the contractor’s incompetence. What is your view
on this cost control feature and how can it be applied in the construction industry in Zimbabwe?
2.7 What is your opinion about partnering and collaboration relationship between contractor and
the client in light of cost controls?