Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission...
Transcript of Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission...
![Page 1: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/1.jpg)
Dispersed Renewable Generation Transmission Study
by Mike MichaudMatrix Energy Solutions
June 27, 2008
![Page 2: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/2.jpg)
STUDY SCOPE
ó Analyze transmission impacts of 1200 MWof new dispersed renewable generation
located statewideó Two phasesó Study Phase I: 600 MW
– Report by OES due June 2008ó Study Phase II: 600 MW
– Report by OES due September 2009
![Page 3: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/3.jpg)
Transmission Modeling
ó MTEP07, 2013 Summer Peak and Off-Peak modelsó Removed Line/Facilities which will not be in-service
before or during 2010.ó Integrated GRE-LRP transmission model detailó Gather additional detail from Minnesota utilitiesó Added Lower Voltage Lines (34.5 kV, 41.6 kV, 46
kV)ó Re-allocated loads from higher voltage to lower
voltage busesó Prior queued generation was not included in the
study model.
![Page 4: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/4.jpg)
Substation InformationóWind Profile Information
Used GIS data & DOC Wind Maps to get capacity factor at substations
ó Distribution Transformer InformationGathered Maximum Load, Minimum Load & Transformer
MVA Ratingó Gathered Data on 2253 Substations at 34.5 kV or
Higher Voltages
![Page 5: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/5.jpg)
Screening Methodology/Criteria
ó Utilized DC Analysis of incremental transfer capability to select DRG Short List sitesó Selected lower-voltage generation study sitesó Screened promising sites further by wind profile
(Minimum of 35 % Capacity Factor)
ó Divided sites equally among planning zonesó Added Biomass site to Short List
![Page 6: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/6.jpg)
![Page 7: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/7.jpg)
First Substation Short List Map
![Page 8: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/8.jpg)
AC AnalysisSingle Site
![Page 9: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/9.jpg)
Dorsey Transformer Issues
![Page 10: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/10.jpg)
![Page 11: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/11.jpg)
RESULTS
The analysis successfully demonstrated a DRG scenario where 600 MW could be sited without significantly affecting any
transmission infrastructure.
![Page 12: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/12.jpg)
RESULTS
The analysis demonstrated that fixing the Dorsey transformer problem will likely
unlock significant opportunity for more dispersed generation
in the Northern half of the state.
![Page 13: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/13.jpg)
RESULTSDORSEY OPTIONS IDENTIFIED
ó Install a third 1200 MVA, 230/500 kV transformer at Dorsey ($41 M)ó Install phase shifters on three northern 230 kV lines
($60M)ó Install a Special Protection Scheme to curtail Minnesota
generationó Communicate and coordinate a DC Runback resolution
with Manitoba Hydro
![Page 14: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/14.jpg)
RESULTS
The utilities have now created a statewide computer model of the lower voltage
transmission system that can be the basis for further study work.
![Page 15: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/15.jpg)
RESULTS
OES plans to convene and facilitate a technical working group in the second half of 2008 to
look into actions necessary, in coordination with the Midwest ISO and with the Minnesota
utilities, to interconnect potential DRG projects with a focus on lower voltage
interconnections.
![Page 16: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/16.jpg)
RESULTS
We now have available an analysis of likely injection potential for generation
installed at virtually every substation in the state with an indication of
likely wind turbine capacity factors.
![Page 17: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/17.jpg)
RESULTSThe analysis found 393 substations
throughout the state that passed all the screening tests.
Only 20 of these were used to create the result that 600 MW of Generation outlet
could be developed with no necessary transmission enhancements.
![Page 18: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/18.jpg)
RESULTS
A team of utility engineers and national experts is convened to continue the
work of examining the potential for dispersed generation and will report
out how to get another increment of 600 MW this way.
![Page 19: Dispersed Renewable Generation Transmission Study - Clean Energy … · 2020-01-07 · Transmission Modeling ŠMTEP07, 2013 Summer Peak and Off-Peak models ŠRemoved Line/Facilities](https://reader034.fdocuments.us/reader034/viewer/2022042018/5e75f9c8085206093e052e67/html5/thumbnails/19.jpg)
TO BE CONTINUED