Transcript of Dg Cement Report 12

  • 8/6/2019 Dg Cement Report 12

    1/26

    Acknowledgement II

    Preface III

    Executive Summary IV

    Introduction 1

    Mission Statement 2

    Future Planning of Company 2

    Production Process 4

    Product Process Flow Diagram 8

    Quality Control 9

    Raw Material 11

    Location 17

    Capacity 19

    Distribution 20

    Distribution Requirement Planning 20

    Aggregate Planning 22

    Demand Alternatives (Reactive Alternatives) 22

    Capacity Alternatives (Aggressive Alternatives) 23

    Inventory Management 24

    Purchasing 29

    The Acquisition Process 29

    Supplier Contracts 34

    Appendix

  • 8/6/2019 Dg Cement Report 12

    2/26

    Acknowledgement

    I am highly grateful to Al-mighty Allah who gives me the power to complete

    this report and my respectable teacher

    Dr. Hayat Muhammad Awan

    Who assigned me to write a term report of operations management on the DG

    Khan Cement Factory.

    I also acknowledge the following person who help me to complete my report:

    Mr. Mujahid Hussain Shah

    Shift Engineer

    Mr. Shafi

    Manager Store

    Mr. Sher Khan

    Manager Purchase Department

    Javed Ahmed Bhutta

    Mechanical Engineer

    Muhammad Shahid

    Kiln Operator

    Amin-ud-Din

    Junior officer sales Staff office Multan

    Preface

    Before you read this report one thing you must keep in your mind. Writing a

    report on the real operations is not an easy thing. It is also easy for any student

    of operations management to get all the knowledge of operation of whole

    factory in three trips.

  • 8/6/2019 Dg Cement Report 12

    3/26

    This report is not an academic requirement but also gives students a practical

    vision of operations of company. It provided me an opportunity to perceive

    what is the difference between theoretical studies and activities.

    By the grace of God, I applied all the learning, which was taught to me by my

    honourable teacher Dr. Hayat M. Awan,and the book which I read. Someconcepts and applicable at DG Cement Factory while the others are not.

    Nevertheless, it gives me a greater practical knowledge about operations of

    cement industry. Maximum efforts have been given to make this report easier

    to understand for its readers.

    I hope that the reader will find this report useful and practicable.

    Executive Summary

    DG Khan Cement Factory is one of the computerized cement factories inPakistan. It produces the cement by adopting dry process.

    Production Process

    These are three raw materials of Cement:

    Lime Stone

    Shale and

    Gypsum

    Limestone and shale is taken from quarry with the help of 7-Km long conveyor

    belt. The both raw material and mixed in raw mill, heated in kiln upto 1600 OC

    ground in cement mill along with gypsum almost 5%. The final product cement is prepared.

    Location:

    The company is located at Sattai Khofli, which is about 40 Km from city of

    Dera Ghazi Khan.

    Capacity:

    The company has two plants

    Existing

  • 8/6/2019 Dg Cement Report 12

    4/26

    Expansion

    Both the plants capacity is 2200 ton and 3300 ton clinker per day respectively.

    Quality Control

    The company believes on quality assurance not on quantity inspection. So they

    have got ISO 9002 certification. Following tests are performed at different

    stages of production process.

    Raw Materials

    Test on these material are performed

    Raw Mill

    Following Tests are applied

    Hydraulic Modulus

    Silica Modulus

    Limestone Factor

    Kiln

    Same tests are performed as in raw mill.

    Clinker

    Tests are performed to see the quality of clinker.

    Cement

    Following physical tests are performed:

    Expansion

    Fineness

    Strength

    Loading

  • 8/6/2019 Dg Cement Report 12

    5/26

    Tests are performed after loading.

    Aggregate Planning

    Aggregate planning is done to cope with demand by using both demand and

    capacity alternatives.

    Purchasing

    Purchasing of items is the duty of purchase department. Need is recognized

    when the indentor raises the demand notice. The purchase department identifies

    and selects the supplier and order is placed. Placed order is checked by store

    department and indentor to accept the order.

    Inventory Control

    The store is responsible to manage and control the inventory of inputs. The

    inventory of outputs (cement) kept in silos. The received order is inspected by

    store department. And accepted material is stored in the store.

    Distribution

    The company has four sales offices in the following cities:

    Multan

    Lahore

    Karachi

    D. G. Khan

    These sales offices accumulate demand of their respective regions and send the

    orders to the head office Lahore.

    Introduction

    State Cement Corporation of Pakistan (S. C. C. P) was established in 1984

    managed by the Federal Government. In the beginning, existing plant was

    purchased from U.B. E. industries of Japan. It had installed capacity of 2300-

    ton clinker daily and started its production in April 1986.

  • 8/6/2019 Dg Cement Report 12

    6/26

    The main purpose for the establishment of plant was to fulfil the demand of

    Northern Marketing zone. In 1977 the annual demand for cement in Pakistan

    was about at 3.7 million tons while the production was about 3.1 m. To fulfill

    0.6 million gap, a new plant was required. After a detailed investigation, they

    selected a place D. G. Khan City where large high quality material reserves

    were available at least or 100 years. The location is ideal because it is near to

    market as well as prior to raw material.

    The govt. privatized the SCCOP, first purchased by Segol Group of Industries

    and Nishat Group of Industries combinely. In 1992, the company purchased

    by Nishat Group of Industries solely.After privatization it name changed

    from SCCOP to D. G. Khan Cement Factory. Before the establishment of

    expansion plant (new plant) in 1997.

    The cement was brought to this and either from Maple Leaf Cement Factory

    Mianwali and Zeal Pak Hyderabad and ACC Rohi. The new plant is the relieffor Bhawalpur, Lodhran, Khanewal Muzafargurh, Bhawalnagar, Vehari. It was

    purchased from F. X. Smith of Denmark. Its design capacity of 3300 ton

    clinker per day.

    Types of Cement

    The company has following types of cement:

    Ordinary Portland Cement

    Sulphate Resistance Cement

    Black Cement

    Heat Resistance Cement

    White Cement

    Slag Cement

    Quick Setting Cement

    Under Water Setting Cement

    Acid Resistant Cement

    Mission Statement

  • 8/6/2019 Dg Cement Report 12

    7/26

    The mission statement of D. G. Khan Cement Company is:

    D. G. Khan Cement Company committed to produce and supply high quality

    conforming the local and international standards adopting modern technique

    satisfying the customer requirements the most competitive prices.

    Future Planning of Company

    The company recently did two things:

    Establishment of Expansion Plant

    Getting ISO 9002 Certificate

    Both the measures to reveal the future planning of the company. The future

    planning of the company is to export their high quality cement. The existingplant is unable to cope with the demand of country. With the establishment of

    expansion plant, their supply is more than demand. So, they can easily export

    their high quality cement. The main purpose of ISO 9002 certificate it to get the

    approval from ISO, they can export their high quality cement according to

    international standards and can export after 2000 A. D. when only ISO certified

    companies can export their products.

    Production Process

    D. G. Khan Cement factory adopt true dry production process for themanufacturing of cement. This process consists of following steps.

    Drilling

    Drilling is done in the quarry with the help of drilling machine. They create a

    space for the powder explosive.

    Blasting

    The powder explosive is blasted under a controlled process to get differentsmall segments of limestone. The large segments are also converted into small

    segments which is called crushing process.

    Transportation

  • 8/6/2019 Dg Cement Report 12

    8/26

    The small fragments are loaded on the 7-Km long 3 belts conveyor system

    running over rough terrain. This conveyor takes the new material from quarry

    to the factory site. The limestone and shale to stored in the open space.

    Grinding

    After storage, the stored limestone and shale are fed to the raw mill with the

    help of two hoppers according to predetermined mixed proportion. The roughly

    crushed material passed through 3 rollers. The mixture is dehydrated, sized, and

    fine particulars are separated.

    The cyclone extracts different gasses, which are emitted in this process. The

    collected separated mixture is called raw meal. It is stored in a silo of 15000

    ton. During the process water is also used with the purpose:

    To lower the gas volume

    To control the variation

    To maintain the temperature

    Clinker

    The raw meal is fed into kiln shell. The kiln shell has following particulars.

    Length of shell 45 m

    Diameter 3.5 to 6.5 m

    Slope 1.5o

    In this kiln shell following reactions take place.

    CaCo3 CaO + O2 (Calcium Oxide)

    CaCo + SI O2

    CaoSio2 (Calcium Silicate)

    CaOSio2 + CaO 2 CaoSio2 (Dicalcium Silicate)

    2CaoSio2 + CaO 3CaoSio2 (Tricalcium Silicate)

    CaO + Al2 O2 CaO Al2 O3

  • 8/6/2019 Dg Cement Report 12

    9/26

    CaO Al2 O3 + CaO 2 CaO Al2 O3

    2 CaO Al2 O3 + CaO 3 CaO Al2 O3

    3 CaO Al2 O3 + CaO + Fe2 O3 C4AF*

    (Tetra Calcium Aluminum Fersite)

    The kiln shell can be divided into four portions.

    Firstly, the incoming raw meal is heated with the help of preheated air which

    comes from the cooler at the terminal end of the kiln. Heat is provided by the

    combustion of the furnace oil. The raw meal is moved on the sloped shell

    which have four zones of temperature.

    Calcination zone 1200 OC

    Transition zone 1250 OC

    Sintering zone 1300 OC

    Burning zone 1400 - 1500 OC

    After the position of burning zone the mixture is cooled down with the help of

    air fans of graze cooler. The heated is omitted which reduce the temperature of

    mixture. This heated air is used to raise the temperature of raw meal enteringinto the kiln. The finished product is called clinker, which is stored in an open

    yard having capacity of 30000 tons.

    Grinding

    Now the clinker enters into Cement Mill. In this mill clinker is ground with

    gypsum. Almost 5% of gypsum is added. The main purpose of addition of

    gypsum is to increase the setting time.

    The final product cement is prepared. It is stored in the silo having capacity of10,000 ton each.

    Packing

    In the packing unit, there are 4 rotary packers and each packer has 8 nozzles.

    The whole packing process is automatic. Cement bags are loaded on the trucks

  • 8/6/2019 Dg Cement Report 12

    10/26

    and heavy trollers automatically. Each cement bag has 50 Kg weight.

    Sometimes heavy users ask for bulk quantity of cement without packing. It is

    loaded into the truck.

    Computerized production process flow is attached at the end of the report.

    Product Process Flow Diagram

    Cement Mill

    Storage Yard

    Cooler

    Kiln

    Preheater

    Silo

    Raw Mill

    Quarry

  • 8/6/2019 Dg Cement Report 12

    11/26

    Quality Control

    Quality a Competitive Priority

    There are four competitive priorities

    cost

    time

    flexibility

    quality

    The product like cement cost priority is not best because of legal consideration

    and suffer heavy losses. Time can be used as competitive priority. On time

    delivery is most important but the sometimes demand is very high the company

    is unable to provided on time delivery. The flexibility is less because cement is

    standardized product. The only one competitive priority is the main base which

    offer the competition. This is achieving the high quality. As it was mentioned

    in the mission statement of the organization. Provide the high quality cement at

    competitive prices. Because the prices of cement are fixed so quality is the only

    competitive weapon through which a company can compete the market.

    Keeping this in its view, D. G. Cement Factory applied for ISO 9000certificate.

    ISO 9002

    D. G. Khan cement factory is providing high quality cement for its beginning.

    After the establishment of expansion department. The company No. 1 in the

    cement industry Pakistan.

  • 8/6/2019 Dg Cement Report 12

    12/26

    To cope with the environment they apply for ISO 9002 certificate. The

    company hired Shakeel and Company Lahore as consultant to get ISO 9002

    certificate. A committee is formed under the control of GM of the company Mr.

    Dr. Asif Bashir to be certified as ISO 9002.

    The company get the ISO 9002, certificate in the long run. The main aim to getthe certificate is to provide the customers the quality cement and competitive

    prices.

    After getting the ISO 9002 certificate. The company reduce its inefficiencies in

    management as well as in production. It reduce in rework cost because of clear

    cut responsibilities are awarded to employees. It also increase the reliability of

    employee upon the D. G. Cement.

    Modern equipped laboratory establishment

    Quality to check according to plan at each stage.

    Cement x-ray Spectrometer is used to check the quality of the product at

    different stage. It takes 5 minutes to assess the ingredients of the product. There

    are six tests for the quality assurance at different stages of the production

    process.

    Raw Material

    Raw material of cement can be categorized in three types:

    Limestone

    Shale

    Gypsum

    Lime Stone

    The sampling point of limestone after blasting the rocks. The fragments of therocks are taken and check its chemical composition. Several benches have been

    opened and abandoned if found to be lantern* low grade limestone. The main

    components of limestone is calcium oxide (CaO). The following equation shoes

    the %age of CaO

    Heat

  • 8/6/2019 Dg Cement Report 12

    13/26

    CaCO3 CaO + CO3

    100% 56% 44%

    The production department accept only those limestone having at least 52% of

    CaO.

    Shale or Clay

    Th second component of cement is shale. Shale can be found near the quarry.

    They take different samples of shale at different points to find out which shale

    has high quality. They utilize these shale first and then any other next.

    Gypsum

    Gypsum is another component of cement. It is 5% of the whole cement. It ismostly taken from outside supplier. Its quality is checked at the entering gate. If

    it is according to contsuit* then it is selected otherwise rejected to suppliers.

    Raw Mill

    When the mixture reach in raw mill, three sophisticated chemical tests are

    performed.

    They take different samples having different composition of two raw material

    (limestone & shale). Usually six samples of following composition is taken.

    Sample No. Limestone %age %age of Shale

    1. 77% 23%

    2. 78% 22%

    3. 79% 21%

    Hydraulic Modulus (HM)

    In hydraulic modulus the above taken samples are taken and put the %age

    values of composition of different compound in the following formula.

    HM = = 2.1-/+ 0.2

    CaO

  • 8/6/2019 Dg Cement Report 12

    14/26

    Si2O + Al2O3 + Fe2O3

    The standard values is 2.1 and + 0.2 variation is allowed. The above formula

    tell us by changing the composition CaO we can get the exact result.

    Silica Modulus

    The test is also performed similarly to the above by taking different ingredients.

    The formula is given below

    SM =

    SiO2

    Al2 O3 + Fe2O3

    The SiO2 is the main component of shale. By changing the composition we can

    get the standard result.

    Ume* Saturation Factor (LSF)

    This test is applied to find out the amount of CaO in the mixture. We can

    calculate the LSF factor by the following formula

    LSF = = 90 + 3

    CaO

    28Si2O + 1.2Al2O3 + 0.65FerO3

    90% of lime in mixture is a standard value while + 3 stands for variation.

    Kiln

    When the raw meal is fed to the kiln, it is also checked chemically by taking

    different samples. Some test of hydraulic modulus, silica modulus and lime

    saturation factor is applied to raw meal as well. The main purpose of the raw

    meal test is to find out the temperature required to heating purpose of raw meal.

    Clinker

    When the raw meal passes through kiln shell and take a form of clinker. A

    sample is taken manually at this moment and then it is analyzed chemically

  • 8/6/2019 Dg Cement Report 12

    15/26

    with the help of cement x-ray spectrometer. Clinker is a hasd* granular

    material. They grand into powder form and analyze. If the result is not

    according to standard they dispose it otherwise mixed in high quality clinker.

    Cement

    When the 5% gypsum is added to ground clinker, the final product is cement.

    They take the sample of cement to find out the right %age of gypsum in

    cement. As well as the fineness of cement.

    Following tests are performed for quality assurance of cement:

    Expansion

    Setting Time

    Fineness

    Strength

    Expansion

    The expansion test check that upto what extent the cement is expanded after

    addition of water. It is a complex test. According to world standard the

    expansion of cement should not be more that 10-mm. The company mostly test

    shows the expansion of 0.5 to 5.5 mm. Which is obviously excellent.

    Setting Time

    The setting time shows the time taken by cement to become solid.

    There are two types of setting time.

    Initial Setting Time

    Initial setting time is the time when we can penetrate the specific middle exact

    half position of the cement block.

    Final Setting Time

    It is the time when we cant penetrate the specific needle into cement block.

  • 8/6/2019 Dg Cement Report 12

    16/26

    We can compare initial and final setting time of D. G. Cement with the world

    standards.

    Setting time DG Cement World Standard

    Initial Setting Time 150 minutes at least 45 minutes

    Final Setting Time 200 minutes at least 10 hours

    Fineness Test / Blaine Test

    Blaine test measures the small size of the particles in specific weights. The world standard for the fineness test is that the should not be

    less than 2250 cm2/gm while in D G Cement it is 2800 Cm2/gm.

    Strength Test

    The strength test check the strength of cement after passing different number of days.

    The world standard and their standard are given below:

    Strength Unit Company Std. World Standard

    3 days PSI 3800-4400 2200

    7 days PSI 4800-5400 3400

    28 days PSI 6000-7000 5000

    Loading

    The final sample is taken when the packed cement is loaded on the truck. The some four tests are performed as it is performed in cement

    mill. If the cement is not upto the mark dispatch is stopped otherwise no problem.

    Location

    The location of plant is at Sattie Khofli 40 Km away from the Dera Ghazi Khan City. Different factors are considered for the location

    selection of the factory. The plant is located at sattai Khofli 40 Km away from the Dera Ghazi Khan City.

    Cement industry is heavily raw material based industry. Without proper availability of raw material, no one can think of establishment of

    the factory. If we look at the Southern Punjab region. No other place is suitable when limestone and shale is available. So, availability of

    limestone and shale is a dominant factors. If we consume these resources at the present level, it is sufficient for at least 100 years.

    The daily design capacity of both production plants is 56000 tons. So, it requires 9520 tons raw material.

  • 8/6/2019 Dg Cement Report 12

    17/26

    1 ton clinker equals 1.7 ton of raw material. The company is located near to the raw material. It will reduce its transportation cost.

    The one of the secondary factor is prior to market. The market is exclusive plans is located in the heart of the market. Another nearest

    plant is 300 Km away. The dealers can be receive their order within one day.

    The second secondary factor is availability of labor. The factory is located at remote area. Labor is available at cheaper rate without any

    shortage. Higher level managers and technician staff are hired from the whole Punjab.

    The third secondary factor is govt. legislation. The factory location is not contradicted with any rule of the govt. firstly, the govt. want all

    these types of factories outside the city.

    The govt. declared this zone as tax free zone in order to give prosperity to backward area. It was complemented in the beginning but not

    now.

    Capacity

    Capacity is a maximum rate of output for a factory. According to engineers the capacity of both plants is

    Plant Name Capacity Clinker per day

    Existing Plant 2200 tons

    Expansion Plant 3300 tons.

    During peak seasons both the plants are working above their allocated capacity while during off season it works slow their allocated

    capacity. It is harmful for the plant to run it above their recommended capacity.

    Distribution

    For the efficient distribution, the company open his four sales offices in four different cities.

    Multan

    D. G. Khan

    Lahore

    Karachi

    And dispatch department at the factory site. Mostly sales offices are located near the target market. Dealers are registered called stockists.

    They have to deposit at least Rs. 50000 as security. Before the establishment of expansion plant a quota system is introduced. Each dealer

    has maximum and minimum limit of his quota.

  • 8/6/2019 Dg Cement Report 12

    18/26

    Distribution Requirement Planning

    All the dealers are allotted the dealership number. They booked their orders in one of the sales office. For all orders, dealers have to pay

    the amount in advance. The sales office clerk accumulates all these orders and sends to the head office in two ways. Either he filled

    customer order form or telephone.

    The Head office (Lahore) make the distribution requirement planning. How much amount of dispatch needed for coming days. Usually

    dispatch lot size is dependent on two things.

    Quota imposed in distribution

    Non-quota distribution

    Head office informs the GM for daily dispatch all the dispatch process is done on automatic machines. 40% of excise duty is paid on each

    bag. All the transportation cost paid by dealer.

    Although the lead-time is one day but it takes more than one day because of any disturbance in market and operation.

    Flow Diagram of Distribution Requirement Planning

    Stockist

    Stockist

    Plant

    Head Office

    Lahore

    Sales Offices

    Stockist

    Stockist

    Stockist

    Aggregate Planning

    D. G. Khan Cement Factory has a family of cement types which consists of three cements ordinary port land cement, black cement and

    sulphate resistance cement. They make their aggregate plan keeping in view the demand of cement and capacity of plant. There are two

    types of alternatives:

  • 8/6/2019 Dg Cement Report 12

    19/26

    Demand alternative (Reactive Alternatives)

    Capacity alternative (Aggressive Alternatives)

    D. G. Khan cement factory apply both the alternatives to aggregate planning. We discuss these alternatives one by one.

    Demand Alternatives (Reactive Alternatives)

    This alternative is apply to cope with demand of the cement. In summer, the demand of cement is very high. To cope with this demand,

    they hire extra unskilled and semiskilled labor. They also offer overtime to highly specialized and skilled person. Mostly unskilled labor

    is taken from subcontractors.

    The Company allows vacation schedule in winter, the month of Ramazan and rainy days. The plant is shut for repairing and maintenance

    work.

    The company always keeps the anticipation inventory to meet the unexpected demand e.g. in the peak season both the silo are filled most

    of the time to cope with any mishaps sometimes the bricks of the kiln shell were broken and work was stopped at least 3 days. During

    these 3 days anticipated inventory cope with the demand.

    The company also gives relaxation to their workers during the peak season. Schedules are formed to give the employee more rest.

    Capacity Alternatives (Aggressive Alternatives)

    The company uses these alternatives during the slack. When the demand is less than their capacity. How to utilize their idle capacity? The

    answer is to apply the aggressive or capacity alternatives. Aggressive alternatives allocation that attempt to modify demand and resource

    requirement.

    In the slack season the demand of ordinary postcard cement is low the company change the production OPC to sulphate resistance cement

    and supply into the Karachi.

    Another method is also used to enhance the demand by lowering the prices. When the price of cement will reduce the demand will

    increase.

    Inventory Management

    We can divide inventory management broadly in two ways.

    Inventory Management of Output (Cement)

    Inventory Management of Inputs

    D. G. Cement factory has no inventory in bags. They keep the cement in the 10000 tons capacity silos.

  • 8/6/2019 Dg Cement Report 12

    20/26

    The main problem of inventory management of inputs. Each and every department is responsible for its inventory. Each department has to

    raise the demand notice to the purchase department. The store department provides them the required. In the case of shortage, the

    purchase refer it to purchase department.

    Types of Inventory in Store Department

    The store department provides the inventory of inputs to each department. Its main purpose is to control and manage the inventory.

    The store department categorizes its inventory of two types as:

    Immediately consumable goods (Fast Moving Goods)

    Non-consumable goods (Slow Moving Goods)

    Immediately Consumable Goods

    Immediately consumable goods are those goods which lose their quality and quality with the usage of items e.g. explosive, stationary,

    soap, towel, oil etc.

    Non-consumable Goods

    Non consumable goods are those goods which do not lose their quantity and quality with the usage and time. These are everlasting items

    e.g. spare parts, machinery, either moving equipment or plant assets.

    Functions of Store Department

    The store department performs two basic functions:

    Management of Inventory

    Controlling of Inventory

    Management of Inventory

    The store department perform follwing functions for management of inventory.

    the inward card is issued when the truck passes through factory gate.

    Inspection of quantity of material done on the gate. Inspection note is sent to the concerning

    department. The manager or incharge who raise the order called indentor write the remarks

    upon it after checking the quality. It is the duty of indentor to write the acceptance and

    rejection note upon it.

  • 8/6/2019 Dg Cement Report 12

    21/26

    All accepted material is stored by store department and write material receiving report.

    One of copy of material receiving report is sent to following departments.

    Finance department

    Store department

    Purchase department

    MIS department

    Supplier

    All the received items are written in the records books.

    Control of Inventory

    The store department controls the inventory both manually and by computer. Two systems are introduced for physical control of

    inventory.

    Cardex Card or Bin System

    In the Cardex card system, all the materials for which store department issued the material receiving report entered in the Cardex cards.

    Different pieces of information is written on these Cardex cards. Different pieces of information is written on these Cardex cards.

    1. Category 2. Code no.

    3. Part No. 4. Description

    5. Maximum Level 6. Re-ordering Level

    7. Location

    All the work done manually and balance the card when the inventory coming or going out of department.

    Computer Records

    The second system for controlling of inventory is computer records. All the transactions are updated in the computer.

    The store department manages and controls 22000 inventory items for all the departments. In any of stock out (the inventory level down

    the minimum level) store department is responsible for the replenishment. He order to the purchasing department for purchasing of goods.

  • 8/6/2019 Dg Cement Report 12

    22/26

    Matching the tow systems

    Both the systems records are matched at the end of accounting period in order to check the correctness of records.

    In any disturbance in the records the physical inspection is also done.

    The possible causes for disturbance of balance for an item may be the following.

    Misplacement of inventory

    Mistake in records calculating

    Due to theft

    In order to reduce the theft, the department due the physical inspection after every these months. It also reveals some other problems with

    the inventory.

    Purchasing

    The purchasing of or different items done by the purchase department of the D. G. Khan Cement Factory. The purchase department not

    only purchase for the factory as well as for the sales offices. Usually the department purchases machinery furnace oil, office equipment,

    supplies, paper sacks, explosive etc:

    The purchase department acquire the things through the acquisition process.

    The Acquisition Process

    The acquisition process consist of following steps.

    Need Recognition

    Need for the acquisition of raw material arises when the production department asks to the store department of some particular item. The

    store department is unable to fulfil the need. So he recommends to the purchase department.

    Production Department

    Needs a calculator

    Store Department

    Calculator is not

    available

  • 8/6/2019 Dg Cement Report 12

    23/26

    Purchase Department

    Need to Purchase

    calculator

    Supplier Selection

    In the supplier selection stage, Different suppliers are identified. Suppliers are of two types.

    Permanent Suppliers

    Random Supplier

    The company has permanent contractor to the different items. Contracts are of long term in nature. So they dont need any frequently

    selection of random supplier. The company selected the supplier do to following characteristics.

    Past experience

    Past performance

    Financial strength

    Quality of material supplied

    Price charges

    Nature of relationship with the supplier

    One of these factors can change the decision.

    Placing the order

    The purchase department has authority to buy the items. The purchase is done once the particulars given by the store department. The

    following particulars are given in the indent form:

    Name of the department

    Description of the item needed

    Last purchase date

    Quality of item

  • 8/6/2019 Dg Cement Report 12

    24/26

    Quantity of item

    The order placement is dependent upon the requirement of item. Different purchases procedure are adopted depending upon

    Urgency

    Availability

    Importance

    There are three types of purchase processes:

    Regular Purchase

    Spot Purchase

    Importance

    Regular Purchase

    Regular purchase is the purchase of those items which they are required after the certain period with regularity. It exhibits the follwing

    characteristics.

    Such items are very expensive

    Such items are not needed urgently

    These are consumable goods.

    The order is placed in the newspaper in the form of tender notice. The terms and condition are mentioned in the tender notice. The

    supplier get the tender form from the nearest sales office (mentioned in the newspaper) on submission of fee. In this tender notice all the

    description of item is mentioned. The supplier fills the form and submits to department with a security fee. The supplier is selected on the

    basis of low bid of the supplier. In case, the company accepts the tender notice of supplier who give maximum discount.

    Sometimes the indentor is also considered for the selection of supplier which negotiate with the supplier in term of quality of item.

    After the supplier has been identified and selected the company will issue purchase order to the supplier.

    Spot Purchase

    Sometimes, different items are purchased on the spot. These items are urgently needed, having more alternative and payment made in

    cash e.g. towels, tube lights, stationary, bullets, bed sheets and spoons, dishes etc. Spot purchase is done through spot purchase committee

    which is consists of

  • 8/6/2019 Dg Cement Report 12

    25/26

    Indentor or end user

    Purchase department representative

    Commercial

    The spot committee visits different suppliers evaluate the items in terms of price, quality and delivery date. The committee make the

    payment to the supplier on the spot. One month is needed for the spot purchase to be completed.

    Import

    The company imports those items which are not available here or having low quality. Import is a long and complex process, it takes six

    months for an import purchase to be completed mostly earth moving machinery, fire bricks and spare parts are imported.

    Track the order

    Track the order means routine follow ups of orders to anticipate late deliveries or probable deviations from requested order quantities.

    Different modes are used or tracking the orders e.g. telephone, letter, fax. The company usually tracks the order when some delay will

    stop the production.

    Receiving the order

    When the order is received from the supplier, the indentor checks the quality of the incoming materials. The indentor writes the remarks

    about items either it is accepted or rejected. Acceptance or rejection note is issued by the store department. If the materials are accepted

    the store department issues material receiving report. One copy of the material receiving report is issued to each of the following

    department.

    Supplier

    Finance Department

    MIS Department

    Store Department

    Purchase Department

    The rejection of items is informed to the purchase department and they return to the supplier. The purchase department also maintain and

    updates their records of different supplier on punctuality, quality, quantity deviations and price. All these information help for future

    evaluation of supplier.

    When the finance department has received the material receiving report from the store department supplier as paid and entries are passed

    in their records.

  • 8/6/2019 Dg Cement Report 12

    26/26

    Supplier Contracts

    The purchase department of D. G. Khan Cement company has identified and registered different suppliers for the materials, which have

    vital importance such as furnace oil, paper sacks and explosive.

    Furnace Oil

    90% of furnace oil is purchased from Pakistan State Oil

    10% of the required furnace oil is purchased from Shell

    Paper Sacks

    The company usually makes a contract of six months duration for the supply of paper sacks. Generally, the company awards contract to

    any of the following companies.

    Pakistan Paper Sack Corporation Karachi

    Khyber Papers Private Ltd. Gadoon.

    Cherat Paper Sack Gadoon.

    Supplier of Stationary

    Following printing agencies are the suppliers of stationary to the D. G. Khan Cement Company:

    Dera Press

    Freedom Art Press

    Top Signs

    All located in Dera Ghazi Khan City.

    Explosive

    There is only one supplier of explosive in the whole country. So the company also makes purchase of explosive from that very company

    i.e. Pakistan Ordinance Factories Wah Cantt.